Urban Stuff Breakout Session # 3€¦ · Urban Stuff Breakout Session # 3 ... •Included in...
Transcript of Urban Stuff Breakout Session # 3€¦ · Urban Stuff Breakout Session # 3 ... •Included in...
Urban Stuff
Breakout Session # 3
September 19, 2018
Moderator – Michael Fulcher
Program Manager, VDOT Staunton District
Urban Program Overview
Urban Maintenance Program
Weldon Cooper Center
Eligible Maintenance Activities
Yolanda Newton
Local Systems Policy Manager
Local Assistance Division
VDOT Urban Program – Overview
•The individuality of the municipalities of the Commonwealth of
Virginia have long been recognized. The relationship between
certain cities and towns and the Department of Transportation is one
of mutual responsibility and cooperation in regard to street
maintenance and construction.
•The Code of Virginia establishes the eligibility criteria of localities for
receiving funds for street maintenance payments and
apportionments for highway construction work.
•These localities are responsible for maintenance and operation of
their highway systems.
•The Code also provides for the Commonwealth Transportation
Board to allocate such funds to the municipalities for construction
projects.
3
VDOT Urban Program – Overview (continued)
There are currently 84 municipalities in the urban system as defined
under Sections 33.2-362 and 33.2-319 of the Code of Virginia.
A municipality qualifies for the urban program by satisfying any of the
following requirements:
•All cities regardless of population;
•All incorporated towns of more than 3,500 population according to the
latest U.S. Census or by evidence of population;
•Six incorporated towns (Chase City, Elkton, Grottoes, Narrows,
Pearisburg, and Saltville) which maintained streets under (repealed)
Section 33.1-80
•The towns of Wise, Lebanon, and Altavista pursuant to Section 33.2-358
4
•Urban (84 Cities and Towns) FY19 Overall Urban Budget ≈ $ 386 M
Payment Rates:
•Principal and Minor Arterial Roads = $ 21,690 per lane mile
•Collector Roads and Local Streets = $ 12,735 per lane mile
Arterial Lane Miles: 5,954
Collector/ Local Miles: 20,119
•Overweight Permit Fee Revenue FY18 Urban Distribution ≈ $ 177,237
‒Equivalent to $6.79 per lane mile
• Continue $1M to Chesapeake to address additional costs
associated with movable bridges (payments began 2005)
Urban Maintenance Program (continued)
5
Urban Maintenance Program
Eligibility Requirements for Maintenance Payments:
– Urban street acceptance criteria established in Code Section 33.2-319
– CTB approves mileage additions/ deletions
Payment - General – Payments based on moving lane miles (available to peak-hour
traffic)
– CTB approves payment amounts to localities
– Localities annual growth rate is based upon the base rate of growth for VDOT’s maintenance program
– Payments to localities made quarterly
6
Urban Maintenance Program (Continued)
Weldon Cooper Center Financial Summary
Financial Accountability:
•Required annual reporting to Commonwealth Transportation Board (CTB)
•In 2004, the CTB adopted Weldon Cooper Center Financial Survey as reporting mechanism
•Report all expenditures for Maintenance and Construction activities
•Included in locality’s annual CPA audit
•Surveys are required to be completed on Weldon Cooper Center website by March 15th each year
•The Survey information is utilized to meet both state and federal data reporting requirements
•Survey shows that on average, localities are expending 40% more than their annual state maintenance payment
7
Weldon Cooper Center Financial Summary (continued)
Expenditure Categories
Maintenance
Pavement
Drainage
Structures & Bridges
Traffic Control Devices
Other
Road, Street and Other Highway Services Traffic Control Operations
Emergency Snow/Ice Removal
Other Emergency Services
Engineering
Other Traffic Services
General Admin and Misc
Capital Outlay Right of Way
Engineering (Where Separable)
Construction
Eligible Maintenance Activities – Legal Requirements
•Section 33.2-100 defines the term “maintenance” as ordinary
maintenance, maintenance replacement, and any other
categories of maintenance designated by Commissioner
•Chapter 2.6 and Appendix E of VDOT’s Urban Manual further
defines what is eligible for maintenance payments, link: •http://www.virginiadot.org/business/resources/local_assistance/Ur
ban_Construction_and_Maintenance_Program_Guidance.pdf
•Acceptable items include: •Activities pertaining to preservation of each type of roadway structure and
facility as near as possible in its condition as constructed,
•Replacement activities pertain to the function of restoring each type of
roadway structure and facility as near as possible to as constructed,
•Replacements in-kind are acceptable charges,
•Betterments are not acceptable charges
9
Eligible Maintenance Activities – Traffic Services & Operations
I. MAINTENANCE ACTIVITIES
ACTIVITIES DESCRIPTION
Signs and Traffic Control
Signs Cleaning, repairing, replacing, and resetting signs
Traffic Signals Replacement, maintenance and energy costs
Railroad Protection Devices Payments to railroads for maintenance and operation to
grade crossing protection
Traffic Services and Operations
Traffic Counts Arterial Roads and Collector/Road Streets
Highway Lighting Maintenance and energy costs
Operation and Maintenance of Fog Warning System General maintenance
Maintenance of Impact Attenuators General maintenance
10
Eligible Maintenance Activities – Traffic Services & Operations
(Continued)
I. MAINTENANCE ACTIVITIES
ACTIVITIES DESCRIPTION
Snow and Ice Control
Deicing Chemicals and Abrasives
Snow Removal Expendable Equipment Cost of spreaders, plows, or other snow removal
equipment
Snow Fence Cost of fence, erection and removal
Snow and Ice Control Support Cleaning and servicing of snow removal
equipment, and cleaning and washing bridges after
storms
Snow Removal and Ice Control Availability Fee Paid to hired equipment owners for making their
equipment available for snow removal
11
Eligible Maintenance Activities – Traffic Services & Operations
(Continued)
I. MAINTENANCE REPLACEMENT ACTIVITIES
ACTIVITIES DESCRIPTION
Signs
Signs Replacing sign structures, refurbishing major signs
Traffic Signals Replacing traffic signals and equipment
Pavement Marking Painting centerlines, edge lines and messages
Reflection Pavement Markers Replace raised pavement markers
12
Eligible Maintenance Activities – General
Acceptable items: 1. Costs to implement and continue these procedures.
2. Payroll additives and applicable overhead charges.
3. Expenditures for training in maintenance or bridge inspection work.
4. Bridge inspection costs for bridges on all public streets.
5. Replacement, maintenance and energy costs for traffic signals.
6. Maintenance and energy costs for roadway lighting.
7. Cost to maintain features within right-of-way such as sidewalks,
bikeways etc.
8. Use of municipal prison labor as long as there is a work order system
sufficient to document the work is an eligible activity on an eligible
street.
9. Operation of intelligent and other traffic control and surveillance systems
to monitor and control traffic.
10. Traffic calming devices which meets VDOT standards.
11. Storm drainage replacement for undersized culverts.
12. Minor pavement widening where tractor trailers run off the pavement or
intersection radii need to be increased to accommodate turning
movements.
13
Eligible Maintenance Activities – General (Continued)
Acceptable items (Continued): 13. Reconstruction or replacement of roadbeds or sidewalks where
deteriorated beyond repair.
14. Plant mix overlays for streets previously only surface treated.
15. Higher grade materials, such as traffic signs and paint, than originally
used.
16. High intensity pavement marking devices on roadways.
17. Traffic control devices upgrading and replacement.
18. Barriers or guardrails to protect traffic control cabinets when the barrier
or guardrail is immediately adjacent to the cabinet.
Unacceptable items: 1. Parking meter costs.
2. All costs on ineligible streets, except for bridge inspection costs.
3. Follow-up repairs to utility cuts.
4. All non-highway related items.
5. Municipality's share (contribution) on construction projects.
14
QUESTIONS?
Bike/Transit Lanes
Urban Manual Updates
Urban Formula Funds
Todd Halacy, P.E.
Assistant Division Administrator
Local Assistance Division
Bike/Transit Lanes
HB2023 - Bicycle-Lane Conversions for Urban Municipalities
• Code of Virginia, Section 33.2-319 per the 2017 General Assembly
• D. Any city converting an existing moving-lane that qualifies for payments
under this section to a transit-only lane after July 1, 2014, shall remain eligible
for such payments but shall not receive additional funds as a result of such
conversion. Any city or town converting an existing moving-lane that qualifies
for payments under this section to a bicycle-only lane after July 1, 2014, shall
remain eligible for such payments, provided that (i) the number of moving-
lane-miles converted is not more than 50 moving-lane-miles or three percent
of the city's or town's total number of moving-lane-miles on July 1, 2014,
whichever is less, and (ii) prior to any such conversion, the city or town
certifies that the conversion design has been assessed by a professional
engineer licensed in the Commonwealth
17
Bike/Transit Lanes
• Conversion of streets must meet the eligibility criteria in Chapter 2.2 of
the Urban Manual . When conversion of streets meet these criteria, the
municipality may request that the Department accept the conversion and
update the Urban Highway System Inventory
• Chapter 2.5.3.2 of the Urban Manual outlines procedures for moving lane
conversions
• Bike Lanes Only - The conversion has been designed in accordance with
the National Association of City Transportation Officials' Urban Bikeway
Design Guide
• Urban Manual Appendix D – Sample Resolution for street conversion
18
Eligibility Requirements for Maintenance Payments
(Example 1)
19
Eligibility Requirements for Maintenance Payments
(Example 2)
Eligibility Requirements for Maintenance Payments
(Example 3)
Urban Manual Updates
Urban Manual Updated in 2017
• Updates for the Urban Maintenance Program
• Added Bike/Transit Lane Legislation
• Modified U-1 Form to include eligibility codes
• Provides a Sample Resolution for bicycle and transit-only lane
conversions
• Added Section to Address Functional Classification changes in
urban municipalities
22
Urban Manual Updates (continued)
• Updates for the Urban Construction Program
• Added Six Year Improvement Program Prioritization Process
• Incorporated changes to the Urban Formula Funding
• Added Smart Scale and State of Good Repair Information
• Incorporated the UCI Manual (Chapter 5)
• Updated Appendices
23
• 2016 Appropriations Act - Consolidating Formula Funding
• Worked with localities and District management to
determine: •If the project(s) can be fully funded and advanced to
construction
•If the project scope can be revised to reduce costs (while still
meeting “purpose and need”) and advance to construction
•
•If formula funding on a project (surplus or not) should be
transferred to advance a project within the jurisdiction or
district
Urban Formula Funds
24
Urban Formula Funds (continued)
•All unspent formula funds was utilized in one of the
following manners: •Fund deficits on completed projects
•Cover non-participating charges on projects eligible to
receive the respective formula funding (state formula only)
•Fully fund active projects that will remain in the SYIP
•Help fund active projects that will remain in the SYIP AND
will be seeking additional funds through other programs in
order to fully fund the project
•Remaining funds should be transferred to the District
Formula Fund Balance Entry (list provided on separate page)
25
QUESTIONS?
RIMS/UMIS Geo-referencing
John Leonard Local Finance Manager
VDOT – Local Assistance Division
Urban Maintenance Payments
• Eligibility Requirements for Maintenance Payments: – Urban street acceptance criteria established in Code Section 33.1-41.1
– CTB approves mileage additions/ deletions
• Payment - General
– Payments based on moving lane miles (available to peak-hour traffic)
– CTB approves payment amounts to localities
– Localities annual growth rate is based upon the base rate of growth for VDOT’s maintenance program
– Payments to localities made quarterly
• Payment Categories/ FY19 Rates – Functional Classifications
1. Principal and Minor Arterial Roads: $21,689 per lane mile
2. Collector Roads and Local Streets: $12,734 per lane mile
• Overall FY19 Urban Maintenance Budget ≈ $386M
28
RIMS/UMIS Geo-referencing Project
• A project was initiated in 2008, referred to as the Urban Conversion Project
(UCP). This project was intended to replace a manual Urban Maintenance
Inventory System (UMIS) and allow the urban street data to be
georeferenced. Combining the VDOT Urban Maintenance Inventory System
(UMIS) into a geospatial layer with a centerline dataset on the Roadway
Network System.
• We are now reaching the final stages of this effort. The remaining effort is
focused on hammering out a few bugs and placing the final segments. We
will then clean up some data issues, and place incorrectly mapped
segments.
29
30
UMIS Legacy System
• The Current UMIS system is a collection of street segments which can
be exported to a pdf for each locality.
RIMS System
31
Public UMIS Map
32
Public UMIS Map
33
Moving Forward
• The hardest part of this project has been building the centerlines.
• Centerlines benefit VDOT as a whole. They help VDOT place crash
data, structure locations, etc.
• Localities will be able to see what streets are in the system, as well
as what streets are excluded.
34
QUESTIONS?
Urban Information Table
Crystal Court
September 20th
8:00am – 12:00pm
Urban Questions
Weldon Cooper
Maintenance Payments
Eligible Maintenance Activities
Urban Construction Initiative
Primary Extensions
Urban Construction Initiative
CONTACTS
Todd Halacy, P.E.
Assistant Division Administrator
Phone: 804-786-3438
Yolanda Newton
Local Systems Policy Manager
Phone: 804-786-0334
John Leonard
Local Finance Manager
Phone: 804-225-4466
Pros of Becoming a UCI Locality
David S. Jarman, P.E.
Transportation Project Management Supervisor
City of Virginia Beach
39
Project Delivery Options Available
UCI Member
(Certified)
Locality administers
Urban Program
using Streamlined
Project Delivery
Process –
Reference VDOT’s
UCI Guide
Locally
Administered
Project
Locality administers
individual Project –
Reference VDOT’s
LAP Manual
UCI Member
(Non-
Certified)
Locality
administers
Urban Program
– Reference
VDOT’s UCI
Guide
Approved on a project by project basis
Programmatic Approval
Programmatic approval with Streamlined Process
VDOT
Administered
Project
VDOT administers
individual Project
on behalf of locality
– Reference VDOT
Road & Design
Manual
Project Delivery Options Available
Locally
Administered
Project
Locality administers
individual Project –
Reference VDOT’s
LAP Manual
UCI Member
(Non-
Certified)
Locality
administers
Urban Program
– Reference
VDOT’s UCI
Guide
UCI Member
(Certified)
Locality administers
Urban Program
using Streamlined
Project Delivery
Process –
Reference VDOT’s
UCI Guide
Approved on a project by project basis
Programmatic Approval
Programmatic approval with Streamlined Process
VDOT
Administered
Project
VDOT administers
individual Project
on behalf of locality
– Reference VDOT
Road & Design
Manual
40
Project Delivery Options Available
Locally
Administered
Project
Locality administers
individual Project –
Reference VDOT’s
LAP Manual
UCI Member
(Non-
Certified)
Locality
administers
Urban Program
– Reference
VDOT’s UCI
Guide
UCI Member
(Certified)
Locality administers
Urban Program
using Streamlined
Project Delivery
Process –
Reference VDOT’s
UCI Guide
Approved on a project by project basis
Programmatic Approval
Programmatic approval with Streamlined Process
VDOT
Administered
Project
VDOT administers
individual Project
on behalf of locality
– Reference VDOT
Road & Design
Manual
?
41
Why Manage Your Own Projects?
• Public Relations
42
Why Manage Your Own Projects?
• Maintenance of Traffic Issues
43
Why Manage Your Own Projects?
Utility Relocations
44
Why Manage Your Own Projects?
• Storm Water & Grading Issues
45
Why Manage Your Own Projects?
• Storm Water & Grading Issues (con’t)
46
Urban Construction Initiative
• Why manage your own projects?
–Better understanding of local issues • Stormwater, sea level rise, lighting, streetscaping, access
management, bike lanes, multi-use path
–Better understanding of stakeholder concerns • Neighborhoods, civic organizations, business owners,
commuters, property owners….
–Better control of the end product • Processes must be followed, dates must be met, but no one
understands the project needs better than the locality
47
Project Delivery Options Available
Locally
Administered
Project
Locality administers
individual Project -
Reference VDOT’s
LAP Manual
UCI Member
(Non-Certified)
Locality administers
Urban Program –
Reference VDOT’s
UCI Guide
UCI Member
(Certified)
Locality administers
Urban Program
using Streamlined
Project Delivery
Process –
Reference VDOT’s
UCI Guide
Approved on a project by project basis
Programmatic Approval
Programmatic approval with Streamlined Process
48
49
Urban Construction Initiative Localities
• UCI Municipalities (Currently 15 Cities/Towns): – FY 2005: Hampton, Richmond, Virginia Beach
– FY 2006: Charlottesville
– FY 2007: Harrisonburg, Bridgewater
– FY 2008: Lynchburg
– FY 2009: Blacksburg, Dumfries
– FY 2010: Colonial Heights
– FY 2011: Newport News
– FY 2012: Chesapeake, Purcellville
– FY 2013: Danville
– FY 2015: Suffolk
• UCI Certified Municipalities
• FY2012: Virginia Beach
• Who is Eligible? – The Code of Virginia in Section 33.2-362 provides that interested
municipalities may assume responsibility for their urban highway construction program.
Urban Construction Initiative
• What the program is… • Local control of Program/Project
• Integrating land use and transportation projects
• Keep decision-making close to the “customer”
• Streamline and expedite project delivery
• Financial advantages from efficiencies
• Partnership with VDOT
• Prerequisite to UCI Certification
• What the program is not… • Replacement for VDOT/FHWA requirements
• Avoiding local project and citizen concerns
• Complete autonomy from VDOT
50
Task LAP UCI
Project Agreements Yes Yes
State Funded Projects Certify/Reimburse No
Phase Authorization Yes Yes (Certification Letters)
NEPA/ Reevaluation Yes Yes
Plan Reviews (L/M/H) Yes Yes
Value Engineering Yes No
Title Sheet Signatures Yes No
PS&E Yes Yes
Bid Packages Certified by
District Yes Yes
Pre-Award Audit (ECAD)/
FAR Yes Yes
Civil Rights Yes Yes
Construction Award Yes Awarded by Localities*
Reimbursement of Federal
Funds Yes Yes
Urban Construction Initiative
VDOT Involvement?
*After VDOT award concurrence
51
Urban Construction Initiative
What are the benefits of being a UCI member?
• Flexibility in project delivery • Localities understand local issues better than VDOT
• Traffic impacts, drainage concerns, property impacts, public relations, political issues
• Networking with other localities • Sharing project/program experiences & lessons learned
• Ensure that VDOT is interpreting policies consistently across the state
• Access to VDOT resources through Local Assistance • Knowing who to talk to
• Better understanding of internal VDOT policies and processes
52
Urban Construction Initiative
What are the benefits of being a UCI member (con’t)?
•More accountability and responsibility for program/project delivery • We learn more when we actually go through the process
•Decision making on programmatic priorities • More flexibility with establishing federal strategy plan and funding schedule
• Financial advantages • Less VDOT oversight and more streamlined processes
• Demonstrating project delivery proficiency can help when seeking grant funding
•Experience for UCI Certification • Provides better understanding of programmatic needs
53
Project Delivery Options Available
Locally
Administered
Project
Locality administers
individual Project -
Reference VDOT’s
LAP Manual
UCI Member
(Non-Certified)
Locality administers
Urban Program –
Reference VDOT’s
UCI Guide
UCI Member
(Certified)
Locality administers
Urban Program
using Streamlined
Project Delivery
Process –
Reference VDOT’s
UCI Guide
Approved on a project by project basis
Programmatic Approval
Programmatic approval with Streamlined Process
54
What is UCI Certification?
Opportunity for UCI qualified members to receive delegated
authority from VDOT for project administration:
• Modeled after FHWA/VDOT relationship outlined in their Joint
Efficiencies Agreement
• Minimal VDOT oversight
• Does Not take away any Project Development Requirements
• Applicable to State and Federally Funded Projects
• Does not apply to projects on NHS; Project of Division Interest
(PODI); and projects identified as VDOT Central Office Oversight
• Locality subject to project and program audit
55
Eligibility Requirements
• Locality has demonstrated their ability to administer and deliver a
federally funded project
• Locality has participated in the UCI program for a minimum of one
(1) year and demonstrated programmatic responsibilities
• Locality has no unresolved compliance issues with VDOT or
FHWA
56
Project Development Concurrent Engineering Process—January 13, 2010 (Total & Partial R/W Takes)
57
UCI Certification - Advantages
58
UCI Certification - Advantages
Construction Phase Authorizati on Administer Construction Contracts Project Completion
Traffic Safety
in Highway
and Street
Work Zone
Construction Records and
Procedures
Project Files
Contract
Claims
Daily Reports
Quality
Assurance
Program
Subcontractors Final DBE
Utilizat ion Report
Development)
Contract Time Equal
Employment
Opportunity
Labor
Compliance Pre -
Construction
Meeting and Partnering
Safety
Provisions
Project
Supervision
and Inspection
6 . VDOT Final
Voucher and
Acceptance
Report of Expenditures
As Built P lans
Acceptance
Procedures Project
Advertisement
Contract Bid Opening
Contract
Awarded
Contractor
Value
Engineering
Owner Force
Account Work
Cost Control
KEY Local Government Activity
VDOT Activity
59
Task LAP UCI UCI Certified
Project Agreements Yes Yes Yes
State Funded
Projects Certify/Reimburse No No
Phase Authorization Yes Yes (Certification Letters) Yes (Locality Certifies)
NEPA/ Reevaluation Yes Yes Yes (Reevaluated by Locality)
Plan Reviews
(L/M/H) Yes Yes No
Value Engineering Yes No No
Title Sheet
Signatures Yes No No
PS&E Yes Yes Certified by Locality
Bid Packages
Certified by District Yes Yes Certified by Locality
Pre-Award Audit
(ECAD)/ FAR Yes Yes Certified by Locality
Civil Rights* Yes Yes Transitioned to Locality
Construction Award Yes Awarded by Localities* Awarded by Localities*
Reimbursement of
Federal Funds Yes Submit 1-pg invoice to VDOT Submit 1-pg invoice to VDOT
UCI Certification
VDOT Involvement?
*After VDOT award concurrence 60
–Major Advantages
• No plan reviews—largest time savings on project delivery
• Pre-award evaluation—generally completed in ~2-3
weeks
• Phase authorizations (RW, CN) are processed with a
certification letter and a few forms—no plans are
submitted
• Overall time savings from being able to avoid stop/start in
the project development process
UCI Certification
61
No Locality is
Perfect…Mistakes Do Happen!
• How did this happen?
• A lot of people were doing the right things, but it still happened
•How do we correct it?
•How do we prevent it from happening in the future?
62
• UCI Municipalities (Currently 15 Cities/Towns): − FY 2005: Hampton, Richmond, Virginia Beach
− FY 2006: Charlottesville
− FY 2007: Harrisonburg, Bridgewater
− FY 2008: Lynchburg
− FY 2009: Blacksburg, Dumfries
− FY 2010: Colonial Heights
− FY 2011: Newport News
− FY 2012: Chesapeake, Purcellville
− FY 2013: Danville
− FY 2015: Suffolk
− FY 2019: ????
• UCI Certified Municipalities − FY2012: Virginia Beach
− FY2019: ????
63
UCI Localities
Support and Resources
• Local Assistance Division Website http://www.virginiadot.org/business/local-assistance.asp
• Locally Administered Projects Manual http://www.virginiadot.org/business/locally_administered_projects_manual.asp
• Urban Construction Initiative http://www.virginiadot.org/business/local-assistance-firstCities.asp
• Local Assistance Division Staff
–
–
64
Contact Information
Yolanda Newton
Local Systems Policy Manager
VDOT Local Assistance Division
804-786-0334
David Jarman, P.E.
Transportation Project Management Supervisor
City of Virginia Beach
757-385-4144
65