Upgrade week Apr10 AB CMS assembly lab areas: future External constraints : entire 3000m 2 CMS area...

7
Upgrade week Apr10 AB CMS assembly & lab areas: future s : entire 3000m 2 CMS area in ISR destined for rad material treatme entire 1500m 2 CMS area in 867 destined for machine y (discussed with SC): equipment exposed to beam in UXC (including activated material) 1 ivity at LHC Point 5, Cessy. non-activated equipment NOT exposed to beam in UXC or elsewhere, ….and for upgrade. e activity in 186 (Meyrin) & 904 (Prevessin) es that CERN staff TSO and support technicians can be assigned to infrastructure will be included in CCC monitoring task. common specialist ra electronic workshops which are planned for a workshop if higher than class C needed)

description

Upgrade week Apr10 AB Temp & RH stability at the ISR: ideal for RPC From Stefano Colafranceschi Need to duplicate conditions in 904. Local environment enclosures feasible (eg around cosmic ray stand) but only as a refinement of generally stable conditions in the building. Request to CERN as host lab to consolidate Building 904 so that such conditions are Possible.

Transcript of Upgrade week Apr10 AB CMS assembly lab areas: future External constraints : entire 3000m 2 CMS area...

Page 1: Upgrade week Apr10 AB CMS assembly  lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.

Upgrade week Apr10 AB

CMS assembly & lab areas: future

External constraints : entire 3000m2 CMS area in ISR destined for rad material treatment entire 1500m2 CMS area in 867 destined for machine ra material handling.

Basic CMS philosophy (discussed with SC):

For maintenance of equipment exposed to beam in UXC (including activated material)1 Concentrate activity at LHC Point 5, Cessy.

For maintenance of non-activated equipment NOT exposed to beam in UXC or elsewhere, ….and for upgrade.

Concentrate activity in 186 (Meyrin) & 904 (Prevessin)

Concentration ensures that CERN staff TSO and support technicians can be assigned to each of these sites. Key infrastructure will be included in CCC monitoring task. 1 Will still need access to common specialist ra electronic workshops which are planned for Meyrin. ( plus mechanical ra workshop if higher than class C needed)

Page 2: Upgrade week Apr10 AB CMS assembly  lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.

Upgrade week Apr10 AB

From Guy Duthion 22.04.2010

Page 3: Upgrade week Apr10 AB CMS assembly  lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.

Upgrade week Apr10 AB

Temp & RH stability at the ISR: ideal for RPC

From Stefano Colafranceschi 22.04.2010 Need to duplicate conditions in 904.

Local environment enclosures feasible(eg around cosmic ray stand) but only as a refinement of generally stable conditions in the building.

Request to CERN as host lab to consolidateBuilding 904 so that such conditions are Possible.

Page 4: Upgrade week Apr10 AB CMS assembly  lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.

Upgrade week Apr10 ABCMS Gas Detector Labs - 904Preparation of RE and CSC upgrade production sites

Cooling:

Total cooling power for the 904 estimated at 300kw

- 200 kw to supply the racks - 100 kw for the remainder of 904 to include the HVAC, CSC and RPC production lines - Minimum cooling plant, 2 groups in parallel. - Preference 3 groups in parallel 2 operational + 1 spare for redundancy facilitating maintenance and guaranteed cooling supplies. - Incorporate supervision and control circuits.

Recuperation from P5 being looked at

From D.Hay, A.GaddiC.Martel 22.04.2010

Page 5: Upgrade week Apr10 AB CMS assembly  lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.

Upgrade week Apr10 AB

Budget estimates:building & lab infrastructure

Building 904: cost estimate: last changes 28 April 10 AB needed(exclude ELIC, EnIC or prod lines) Item who pays? status

2010 2011 2012 TOTALEmpty hall 1 June 2010 CERN-PH done ex lead glassRoof repair skydomes 1 July 2010 30 CERN-GS awaiting quote/ CMS loanClosing inspection pits 1 July 2010 26 CERN-PH? design review/ CMS loanClean and seal floor 1 September 2010 30 CERN-PH? users to fix requirements

Roof insulation 31 March 2011 470 CERN-GS 1'st quoteWall insulation 1 July 2012 500 500 CERN-GS 1'st quoteWindows May 2011/May 2012 200 100 CERN-GS 1'st quoteSmoke detection 1 September 2010 75 CERN-GS 1'st quoteAccess, evac and surveillance 1 November 2010 50 18 CERN-PH 1'st quoteStorage platform 1 June 2010 50 CERN-PH complete

Packing/Transport from ISR/867 45 25 CERN-PH? checkNetwork 1 September 2010 30 CERN-PH checkPower distribution 1 September 2010 20 CERN-PH checkHVAC 31 March 2011 250 CERN-CV 1'st quote

Rack cooling 1 January 2011 50 CMS-MandO-A OKDetector cooling 1 January 2011 200 CMS-upgrade 200 kW det + racksEntry SAS 1 January 2011 30 CMS-upgrade exchange with skydomes?CSC/RPC Gas distribution 1 January 2011 100 CMS-upgrade PH-DT quoteLocal environments 1 January 2011 50 CMS-upgrade new CR, not ISR?

1506 743 600 2849

kCHF

Page 6: Upgrade week Apr10 AB CMS assembly  lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.

Upgrade week Apr10 AB

SX5: OSC intended layout

ECAL/HCAL/CASTORTOTEM20 x 17mClass C ra

Pixel & BCM(lower)Vis centre (upper)

Workshop(incl users)

HCAL (upper)Workshop (ra)

Class C

CSC/DT/RPC3 areas 10 x 15m flexible

Cranestaging

Green BarrackDAQ,TK & MU

TOTEM

Infra & Logistics

25m x 20m

Ready-use tooling Gas

E-mech w/sbeampipePM56 shaft

Future Offices

Access controlled area

basic infrastructure, offices: CERN : 2000k (update for GS SX5/SHL project) common systems and facilities: M & O A : 1059k (endorsed by RRB-SG and RRB Apr 10) subdet specific: M & O B : 310k

4 phase planning , essential to complete phase 1 before the earliest plausible start-date for next long-shutdown

Visitor centre upper floor

4 year project : 2.8 M CHF, spend profile concentrated in 2010,11

Lockers, washroomhand-foot monitors

problem

problem

Prepared by CMS TC & EAM teams

Page 7: Upgrade week Apr10 AB CMS assembly  lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.

Upgrade week Apr10 AB

SX5 project

Provisional acceptance of building permit: final decision in 3 months.SX5/SL53/SHL project is still targetted for completion end of 2011.

“Walk-in” Visitor centre is a key feature

Confident we can now go ahead and “empty” the Hall cataloguing near complete temporary storage at SX5 (“buche agricole” – permis?)

long term storage SX5, 892 and 904 hangar

Priority is the SHL 1’st floor – roof of the proposed pixel clean room GS ready to go ahead with this - seeking solution for cable gallery access

Next priority is the access controlled zone and the initial rad workshop-first detailed estimate 159k …not far from 150k coarse guess.