Upgrade Plan of KEKB Vacuum system

19
Upgrade Plan of Upgrade Plan of KEKB Vacuum system KEKB Vacuum system 2008.03.19 Pre-kickoff Meeting @ KEK 1 Y. Suetsugu KEKB Vacuum Group Contents Challenges for vacuum system Designs for key issues Beam ducts, Flanges, RF-shielding, Cures for ECI,, Remained issues Technical General Summary

description

Upgrade Plan of KEKB Vacuum system. Y. Suetsugu KEKB Vacuum Group. Contents. Challenges for vacuum system Designs for key issues Beam ducts, Flanges, RF-shielding, Cures for ECI,, Remained issues Technical General Summary. Challenges for vacuum system. - PowerPoint PPT Presentation

Transcript of Upgrade Plan of KEKB Vacuum system

Page 1: Upgrade Plan of  KEKB Vacuum system

Upgrade Plan of Upgrade Plan of KEKB Vacuum systemKEKB Vacuum system

2008.03.19 Pre-kickoff Meeting @ KEK 1

Y. SuetsuguKEKB Vacuum Group

Contents Challenges for vacuum system Designs for key issues

Beam ducts, Flanges, RF-shielding, Cures for ECI,,

Remained issues Technical General

Summary

Page 2: Upgrade Plan of  KEKB Vacuum system

Challenges for vacuum systemChallenges for vacuum system Key parameters for vacuum system:

High current (LER:9.4 A, HER:4.1 A) Short bunch (z = 3 mm)

2008.03.19 Pre-kickoff Meeting @ KEK 2

Intense SR power◦ Max. power density of 28 kW/m (40 W/mm2) even a

half aperture of 110 mm, for example.High photon density

◦ Photon density ~1x1019 photons/m/s in average◦ Large gas desorption

Gas load ~ 5x10-8 Pa m3/s/m (for = 1x10-6 molecules/photon) Average pressure ~ 5x10-7 Pa for S ~ 0.1 m3/s/m

◦ Electron Cloud Instability (ECI) becomes a big issue in positron ring

Intense HOM (higher order mode) power◦ For a loss factor of 1 V/pC, loss power ~ 200 kW

Page 3: Upgrade Plan of  KEKB Vacuum system

Present designs for key itemsPresent designs for key itemsWe have been developing key components and

techniques to tackle these issues.Beam duct

◦ Copper beam duct with ante-chambers Low SR powerPumping system

◦ Distributed pumping scheme Effective pumpingConnection flange

◦ Special MO-type flange Secure RF bridgeRF shielding of bellows and gate-valves

◦ Comb-type RF shield basically Secure RF shieldMovable mask (collimator)

◦ Stealth type (still under study) Low impedanceCures for ECI

◦ TiN coating or (groove) Low secondary electron yield◦ Clearing electrode Direct elimination of electros

2008.03.19 Pre-kickoff Meeting @ KEK 3

Low Impedance

Little photoelectron

Page 4: Upgrade Plan of  KEKB Vacuum system

Beam ductBeam ductCopper beam duct with ante-chambers

◦ Copper is required to withstand intense SR power

Features (compared to simple pipe):◦ Low SR power density◦ Low photoelectrons in beam pipe◦ Low beam impedance◦ Expensive

2008.03.19 Pre-kickoff Meeting @ KEK 4

BeamSR

Pump

LER HER(90)

Page 5: Upgrade Plan of  KEKB Vacuum system

Beam ductBeam ductSeveral test ducts have been installed in KEKB

positron ring.Reduction of photoelectrons was confirmed.All ducts at arc section should be replaced.

2008.03.19 Pre-kickoff Meeting @ KEK 5

Straight duct

~3.6 m

90 mm

Q-duct with BPM

Electron numbers

-30 V1/1284/3.77

Duct with ante-chamber

Circularduct

Page 6: Upgrade Plan of  KEKB Vacuum system

Beam ductBeam ductBending and installation of slits are now under

study

2008.03.19 Pre-kickoff Meeting @ KEK 6

Bent duct for LER ( 90 mm) Slit for pump channel

Page 7: Upgrade Plan of  KEKB Vacuum system

Distributed pumping systemDistributed pumping systemMultilayer NEG strips in an antechamber

◦ Increase capacity and pumping speed◦ Small impedance if set in an ante-chamber

Auxiliary pump: Sputter ion pump

2008.03.19 Pre-kickoff Meeting @ KEK 7

Pump

Prot-type: ST-707 strip Three layers Indirect heating

Multilayer NEG strips for test (three layers)

Heaters

SR

12 m

m

1 m

Page 8: Upgrade Plan of  KEKB Vacuum system

Connection flangeConnection flangeSpecial MO-type flange for a beam duct with ante-

chambers.

Features (Compared to usual one):◦ No gap inside◦ Sure RF bridge◦ Applicable to a complex

aperture◦ Simple structure

Already applied to test beam ducts and bellows with ante-chambers.

2008.03.19 Pre-kickoff Meeting @ KEK 8

MO-type flange for bellows

MO-type flange for beam duct

Page 9: Upgrade Plan of  KEKB Vacuum system

RF shielding RF shielding Comb-type RF shield

Features (compared to finger type):◦ Low beam impedance◦ High thermal strength◦ Applicable to complex aperture◦ Little flexibility (offset)

Effect of RF shielding wasdemonstrated in KEKB.

Finger-type as an option◦ If more flexibility is required.

2008.03.19 Pre-kickoff Meeting @ KEK 9

Without cooling fan

Comb-type RF-shield

Temperature of bellows

Page 10: Upgrade Plan of  KEKB Vacuum system

RF shielding RF shielding Already applied to bellows chambers and gate-

valves, with an aperture of beam duct with ante-chambers.

They have been installed into KEKB and tested.

2008.03.19 Pre-kickoff Meeting @ KEK 10

Bellows chamber Gate-valve

Page 11: Upgrade Plan of  KEKB Vacuum system

Movable mask (collimator)Movable mask (collimator)Big impedance sources in the ringPlanning to use “stealth” type (Ver.6)

◦ Low beam impedance Present Ver.4 ~ 1V/pC ( 90 mm) 200 kW power loss

◦ Loss factor decreases to ~1/10 ( 90 mm). Manageable by conventional HOM absorber

2008.03.19Pre-kickoff Meeting @ KEK 11

Loss factor

Bunch length [mm]Lo

ss f

acto

r [V

/pC

] Ver.4

Ver.6

Ver.4

Ver.6

Page 12: Upgrade Plan of  KEKB Vacuum system

Movable mask (collimator)Movable mask (collimator)Trial models were installed and tested with beam.

◦ Principle was proved experimentally. Temperature rise of bellows decreased to 1/2 ~ 1/3.

◦ But, could not withstand a high intensity beam yet.Start with Ver.4 ?

◦ While beam current is low.

2008.03.19 Pre-kickoff Meeting @ KEK 12

Head of Ver.6 (trial model)

Temperature of bellows near masks

Beam

HeadSupport

Page 13: Upgrade Plan of  KEKB Vacuum system

Cure for ECI_1Cure for ECI_1A critical issue for positron ringTiN coating on inner surface

◦ Decrease secondary electron yield (SEY): Max. SEY ~0.9◦ A test stand for the coating was built in KEK, and applied to a test duct with ante-

chambers. Decrease of electrons at high current region was demonstrated.

2008.03.19 Pre-kickoff Meeting @ KEK 13

~4

m

90 mm

Electron numbers

Page 14: Upgrade Plan of  KEKB Vacuum system

Cure for ECI_2Cure for ECI_2Clearing Electrode

◦ A possible measure even inside of magnetAn electrode for test with a low beam impedance was

developed, and tested.◦ The principle was proved experimentally.◦ Electrons decreased to ~ 1/10 by applying 500 V.◦ Under study

Grooves will be also tested.

2008.03.19 Pre-kickoff Meeting @ KEK 14

Clearing electrode for test

Electron numbers

-500V 0V +500VE

lect

ron

Cur

rent

[A]

Applied voltage [V]

Head

Page 15: Upgrade Plan of  KEKB Vacuum system

Remained issues _ TechnicalRemained issues _ TechnicalOptimization of beam duct shape

◦ CSR (Coherent Synchrotron Radiation) problem have a great effect on the luminosity.

Deformation of beam duct by heating◦ Displacement gauge for every BPM?

2008.03.19 15Pre-kickoff Meeting @ KEK

(50)

Larger aperture ---- Smaller aperture

Low impedance Cure for CSR (ex, resistive wall) [Low cost?] Effective pumping

(90)?

Page 16: Upgrade Plan of  KEKB Vacuum system

Remained issues _ TechnicalRemained issues _ TechnicalRequired pressure

◦ Now 5x10-7 Pa is a goal.◦ First Ion Instability require lower pressure in a simulation,

~1x10-7 Pa for example.◦ More pumps?

Cures for ECI in magnet◦ Still studies are undergoing.◦ Clearing electrode ? Grooves? Only TiN?◦ Drift space: TiN coating + Solenoid will be OK.

Design of special components◦ Septum, Abort window, HOM absorber, Cross section, …

Design of vacuum system at IR.◦ IR optics is still floating.◦ How to keep sufficient aperture, how to deal intense SR,,

2008.03.19 16Pre-kickoff Meeting @ KEK

Page 17: Upgrade Plan of  KEKB Vacuum system

Remained issues _ GeneralRemained issues _ GeneralCost

◦ Vacuum components are more complicated than those of other machine to achieve high current, i.e., Luminosity.

◦ Possibility of cost-reduction are continuously considered, such as to use aluminum duct for weak SR sections (with copper SR crotch?).

Vendor◦ Manufacture ~2000 copper beam ducts ( 2 ~ 6 m long) in 3

years!◦ Find available vendors widely, all over the world.

Some R&D were performed with BINP, for example.Installation

◦ Install ~2000 beam ducts and bellows in 2 years! Stored place, Installation procedure, Preparation process,,

Man power

2008.03.19 17Pre-kickoff Meeting @ KEK

Page 18: Upgrade Plan of  KEKB Vacuum system

SummarySummary

2008.03.19 18Pre-kickoff Meeting @ KEK

Upgrade of KEKB is a great challenge for the vacuum system.

R&Ds have been performed for these years, and basic designs of key vacuum components is near completion.

But, various practical problems are still remained.Any solutions should be found in this one year.

We will appreciate your corporation.

Page 19: Upgrade Plan of  KEKB Vacuum system

2008.03.19 19Pre-kickoff Meeting @ KEK