Upgrade of Aircraft Apron - Pavement design

16
A CASE STUDY - UPGRADE OF THE TERMINAL APRON AT MUMBAI INTERNATIONAL AIRPORT By: Paul McCullagh and Manoj Tipnis Larsen & Toubro Limited, Engineering Construction & Contracts (ECC) Division Gate 1, North Block 2, Powai Campus, Saki Vihar Road Mumbai, MH 400072, India Phone: +91 22 2858 1401; Fax: +91 22 2858 1401 [email protected] [email protected] PRESENTED FOR THE 2010 FAA WORLDWIDE AIRPORT TECHNOLOGY TRANSFER CONFERENCE Atlantic City, New Jersey, USA April 2010

description

This document outlines methodology used to upgrade the aircraft pavement to cater to larger aircraft in Mumbai Airport.

Transcript of Upgrade of Aircraft Apron - Pavement design

  • ACASESTUDY-UPGRADEOFTHETERMINALAPRONATMUMBAIINTERNATIONALAIRPORT

    By:PaulMcCullaghandManojTipnis

    Larsen&ToubroLimited,EngineeringConstruction&Contracts(ECC)DivisionGate1,NorthBlock2,PowaiCampus,SakiViharRoad

    Mumbai,MH400072,IndiaPhone:+912228581401;Fax:+912228581401

    [email protected]@Lntecc.com

    PRESENTEDFORTHE2010FAAWORLDWIDEAIRPORTTECHNOLOGYTRANSFERCONFERENCE

    AtlanticCity,NewJersey,USA

    April2010

  • McCullaghandTipnis 1

    INTRODUCTION

    ChattrapatiShivajiInternationalAirport(CSIA)atMumbai,India,currentlyhandlesinexcessof21millionpassengersand465,000metrictonnes(512,500Tons)ofcargoperannum.Thesefiguresareforecasttogrowto40millionpassengersand1millionmetrictonnes(1.1millionTons)ofcargoperannumby2015.

    InApril2006,MumbaiInternationalAirportPrivateLimited(MIAL)signedanOperational,ManagementandDevelopmentAgreementwiththeAirportsAuthorityofIndia(AAI)tooperate,maintain,develop,design,construct,upgrade,modernize,financeandmanagetheairportforaperiodof30years,withanextensionoptionforafurther30years.In2007,Larsen&ToubroLimited,ECCDivision(L&T)wereawardedacontractbyMIALtoupgradetheairportaspartoftheCSIAExpansionandRenovationProgram.MIALisajointventurecompanyownedbyaGVKGroupconsortiumandAirportsAuthorityofIndia(AAI).

    AspartoftheCSIAExpansionandRenovationProgram,theexistinginternationalterminalandtheassociatedapronsarebeingreplaced.Theprojectconsistsofthereplacementofapproximately540,000m2ofexistingrigidpavementswithover950,000m2ofnewpavement.Theapronswillbeinusethroughoutthe3yearconstructionperiod,andarecurrentlyoperatingnearsaturationtrafficlevels.Detailedstaginghasbeenimplementedtoachieveabalancebetweentheoperationaluseoftheapronsandadequateworkfacestoachieveconstructionefficiency.Theprojecttimelineisfurthercomplicatedbyanannualmonsoonperiodoffourmonthsduration.

    ThereconstructedapronshavebeendesignedtoICAOstandardsutilizingFAARFIELDsoftwareforpavementdesign.GeometricandpavementdesignsweredesignedinaccordancewithICAOAnnex14[1]andICAOAerodromeDesignManualParts1,2and3[2,3,4].FAAAdvisoryCircular150/5320-6E[5]wasusedasaguideforpavementdesignsanddetailing.

    TheforecastusageforeachaprontaxilaneandaircraftstandwasanalyzedandpavementthicknessesweredeterminedusingFAARFIELD.Theaircraftparkingstandsweredesignedusingfewerdeparturesbutwithcorrectionfactorstocaterforreducedwander.Bothdesignsgavesimilarresults,henceauniformpavementthicknesswasadoptedthroughout.

    Themajorityofthenewapronfootprintrestsoverexistingconcreteandflexiblepavementswhichwillbeusedasafoundationforthenewrigidpavementstoeconomizethedesignandexpediteconstruction.Theapronrequiresverticalshapecorrectionwhichleadstovaryingdegreesofcutandfillovertheexistingsurface.Theexistingapronpavementwillbereusedinanumberofways,includingrubblizationoftheexistingconcretepavements,recyclingofotherconcretepavementsforuseassubbasewhererubblizationisnotfeasible,andremovaloftheexistingwearingcoursesandutilizationoftheunderlyingpavementcoursesassubbase.Wherenoneofthisispossibleduetoinadequatecoveroversubgrade,newfulldepthpavementshavebeenadopted.

    Thesubbaseforthenewconcretepavementsisthereforeamixtureofrubblizedconcrete,existingsubbaseandnewsubbase.Utilizingrubblisedconcreteasasubbasefornewrigidpavementsisahighlightoftheproject.

  • McCullaghandTipnis 2

    EXISTING&PROPOSEDAPRONLAYOUTS

    Therunways,taxiwaysandapronsatCSIAarecurrentlycertifiedforusebyICAOCodeE(FAAAirplaneDesignGroupV)aircraft,howeversomemovementareasarebeingupgradedtoICAOCodeF(FAAADGVI)requirementsaspartofthisproject.CSIAcurrentlycatersforaround21millionpassengersperannumand550aircraftmovements(arrivalsanddepartures)perday,splitbetweenadomesticterminalcomplex(T1)andaninternationalterminal(T2).Atthecommencementoftheproject,theoriginalinternationalterminal(T2)wasaconvexshapedsingleconcoursebuildingwith14CodeEcontactstands.ThegreaterT2apronalsoprovidedafurther15CodeD/E(ADGIV/V)and6CodeC(ADGIII)remotestands.Thisgaveatotalof35standsontheexistingapronatthecommencementoftheproject.

    AspartoftheCSIAExpansionandRenovationProgram,theexistingT2buildingandapronarebeingreplacedwithanewx-shapedintegratedterminal(with3convexshapedfaces)thatwillbeusedforbothdomesticandinternationaloperations.Intheinitialphaseofdevelopmentdueforcompletionin2013,thenewapronwillprovide3CodeF(ADGVI),40CodeE(ADGV),0CodeD(ADGIV)and5CodeC(ADGIII)stands,givingatotalof48standsonthenewapron.Duringthepeakdomestictimes,17ofthelargercontactstandscanbeconvertedona2for1basisintoCodeCstands.Theremoteapronsalsocanconvert11CodeEstandsinto21CodeCstands.Inthefinalphaseofdevelopmentatotalof38CodeE/Fcontactstands,14CodeE/Fremotestandsand19CodeCremotestandswillbeprovided(total71stands).

    Theorientationoftheexistingandproposedterminalbuildingfacesdiffersignificantly(byupto90degrees),whichmeansthattheexistingapronpavementscouldnotberetainedforusewiththenewbuildingduetoincorrectorientationofslopes,drainageandundergroundservicesandageneralleveldifferencebetweentheexistingandproposedterminalbuildings.Theproposedaproncoversanareaofapproximately950,000m2(10,225,000ft2).

    CONSTRUCTIONSTAGING

    Thelocationofthenewinternationalterminalbuildingsitsdirectlyonthesiteoftheexistingterminalbuilding,carparkandapron.Atthecommencementoftheproject,theairportoperatordeclaredthattheexistingterminaland24widebodyparkingstandsmustremainoperationalthroughoutthedurationoftheproject,hencetheterminalandaprondevelopmentsmustbeconstructedinaseriesofdiscreetstagesinordertomaintainairportoperations.Thenewpavementsareplannedtobecompletedbymid2013.ThisisadifficulttaskgiventhatMumbaiexperiencesaheavytropicalmonsoonperiodforfourmonthsperyear(JunetoSeptember)whicheffectivelyhaltsallcivilworks.Thisleavesaround32monthstocompletethepavementworks,atarateofnearly30,000m2(325,000ft2)permonth.

    Numeroustemporaryparkingstandlayoutswereanalyzedduringtheinitialdesignphaseoftheprojectinordertodeterminehowmanyoftheexistingparkingstandscouldbetemporarilyrelocatedtofreeupspaceforconstructionofthenewapron,taxiwaysandterminalbuilding.Anadditional3widebodyparkingstands(2contactand1remote)wereconstructedontheeasternsideoftheexistingapronatthecommencementoftheprojecttoprovidesomeflexibilitytoshuffleparkingstandsduringtheworks.Evenwiththisadditionalcapacity,amaximumofonly5existingwidebodystandscouldbedecommissionedduringtheinitialconstructionstages.

  • McCullaghandTipnis 3

    Giventhatlimitedspacewasavailableontheinternationalapronfortemporaryparkingofwidebodyaircraft,theconstructionstagingsequencingwaslimitedtoshufflingbetweensmallareas,andcommissioning/decommissioningsmallnumbersofstandsatthecompletionofeachstage.Forexample,duringthefirsthalfoftheproject,parkingstandswerecommissionedingroupsof3,2,1,4,4,3and5atthecompletionofeachstage.

    Atotalof15constructionstageshavebeendesignedfortheproject,asshowninFigure1below.Eachstagerequiredcarefulplanningofairportoperations,siteaccessroutes,safetymarkings&barricadesaswellasdetailedplanningoftheconstructionsequencingandcommissioningscheduletoenableaeronauticalchartsandNOTAMstobepublishedwellinadvanceoftheworks.

    Theconstructionstagingledtooptimizationofaircrafttaxiwaysandassociatedsafetyclearancesinordertomaximizetheconstructionworksarea.Althoughthisexercisewaslargelysuccessful,someworkshadtobeplannedtobeundertakenonatimelimitedbasiswithinthetaxiwaystrips.Underthisprocedure,menandequipmentwouldenterthestripundersupervisionofworkssafetyofficers,andwouldvacatetheworkssiteforeachwidebodyaircraftmovement.

    ItshouldbenotedthattheinternationalapronredevelopmentispartofthewiderCSIAExpansionandRenovationProgram,whichincludesmajorwidening,strengtheningandshapecorrectionofbothoftheairportscrossrunways,realignmentofthemainparalleltaxiwaytoCodeFclearances,constructionofover625,000m2(6,725,000ft2)ofnewtaxiwaypavement,aswellas12km(7.5miles)ofnewopendrainsandboxculverts,anewairfieldgroundlightingsystemwithover5,000newlightsand500km(310miles)ofcabling,and60km(37miles)ofnewAGLandelectricalductbanks,allwithinthesametimeperiod.Asaconsequence,theT2constructionstagingalsohadtobecognizantoftheimpactontheairportoperationsandworksareasfortheremainderoftheairport.

    EXISTINGPAVEMENTS

    The new apron area is located over varying terrain including existing flexible & rigidpavements, former building sites and grass areas. All the existing contact and remote aircraftparkingstands are rigidpavements, apron taxilanesareamixof flexibleand rigidpavements,andgroundserviceequipmentstorageareasaregenerallyreducedstrengthflexiblepavements.

    Extensivegeotechnicalinvestigationswereundertakenwithanaimtoestablishthestructureof all existing pavements and to determine the subgrade classification and strength across theentireapron.Atotalof45boreholeswereundertakenontheexistingpavements todeterminethe USCS materials classification and thickness of each pavement layer. Standard PenetrationTests(SPT)wereconductedonthesubgradethrougheachboreholetodeterminetheNvalueswhich could be correlated to provide subgrade E modulus, CBR & coefficient of subgradereaction(k)valuesforpavementdesignpurposes.Asthepavementshavebeeninplaceformanyyears,itwasagreedthatthesubgradewasatanequilibriumstateandthatfieldsubgradereactionwas a better option to laboratory derived values. A limited number of plate load tests andlaboratory CBR tests were conducted to verify the correlations used to calculate CBR and kvaluesfromthefieldmeasuredNvalues.Theplateloadtestingwasparticularlylimitedduetooperationalrestrictionsattheairport.

  • McCullaghandTipnis 4

    Figure1.T2ApronConstructionStages(Notallstagesshown).

  • McCullaghandTipnis 5

    The3mainpavementsidentifiedbythegeotechnicalinvestigationwere:

    Rigidaircraftpavements

    Flexibletaxilanepavementsand

    GroundSupportEquipment(GSE)flexiblepavements

    Theexistingrigidpavementsareofvariousages,rangingfrom3to30years.Theolderrigidpavements are presently in various stages of deterioration, with longitudinal and transversecracks as well as edge spalls and corner breaks noticeable on around 30% of existing slabs.Differential settlement (faulting) is also evident across some slabs, up to 15 mm (0.5). TheexistingrigidtaxilaneandaircraftparkingstandpavementshavePCCvaryinginthicknessfrom400mm(15.75)to600mm(23.5)withEmodulusvaluesinrangeof16,000MPa(2,320,000psi) to 22,000 MPa (3,190,000 psi). The E modulus values were estimated by compressiontestingextractedcoresasper IndianStandardIS-516(equivalent toASTMC469).ThePCCisgenerally constructed over a 150 mm (6) thick stabilized base layer of Dry Lean Concrete(equivalent to P-304) over 600 mm (23.5) to 1,000 mm (40) thick granular subbase(equivalent to P-154). The minimum pavement thickness analyzed for design purposes was400mm (15.75) P-501 PCC on 150mm (6) P-304 CTB on 850mm (33.5) P-154 granularsubbase.Thetotalpavementthicknessis1,400mm(55).

    Theexistingflexiblepavementsdonotshowanymajorsignsofdistress,apartfromroutinesurfacedefectsrequiringongoingmaintenancesuchasoxidation,ravelingandminorbleeding.Theexistingflexiblepavementsconsistofapproximately650mm(25.5)ofasphalticconcretewearing course / base course (P-401) over approximately 750 mm (29.5) granular base /subbase(P-209andP-154).Thetotalpavementthicknessis1,400mm(55).

    Theborelogsestablishedthepresenceofrockstrataunderthepavementatdepthsvaryingfrom1,750mm(69)onthewesternsideoftheapronto5.5m(18ft)ontheeasternside.ThesubgradelayerabovetherockstrataconsistsofresidualsoilwhichhasbeenclassifiedasSiltyClaywithlowtohighplasticity(USCSCLCH).ThecorrelatedCBRcalculatedfromfieldNvaluereadingsforthesubgradesoilvariedfrom1.6%to2.5%.Thewatertableintheareavariesseasonallybetween2m(6.5ft)to3m(10ft),asperthePeisometerreadingstakenovertheyear2008-2009.Fordesignpurposes,asubgradeCBRvalueof2%andakvalueof11kPa/mm(40pci)wereadopted.

    SUBBASEPREPARATIONOPTIONS

    ThenewinternationalapronistobeconstructedfromrigidPortlandCementConcrete(PCC)pavement,withtheexceptionoftheheadofstandroad,groundserviceequipmentstorageareasandtaxiwayshoulders,allofwhichwillbeconstructedfromasphalticconcretesurfacedflexiblepavement.Rigidpavementsarepreferredfortheaircraftparkingstandsandtaxilanesduetotheveryhighstressesthatheavilyweightedslowmovingandstaticaircraftplaceonthepavement,andduetofuelandoilspillsthatcanoccurfrommaintenanceandrefuelingoperationsontheapronstands.

  • McCullaghandTipnis 6

    Thefootprintofthenewapronliesoverexistingflexible&rigidpavements,formerbuildingssitesandgrassareas.Thelevelsoftheproposedpavementsvarysignificantlyfromtheexistinglevels,withthemajorityoftheareasneedingtoberaisedtomeetthedesignprofile.Assuch,itbecameevidentthatalargequantityoftheexistingpavementscouldbereusedassubbaseforthenewapronpavementinordertoprovideaneconomicalalternativetofulldepthreconstructionoftheentireapron.Fulldepthreconstructionwouldonlyberequiredinareascurrentlyoccupiedbybuildingsorgrassislands,orinareasofcutwhereinsufficientcoveroversubgradecouldnotbeachieved.

    Anumberofoptionswereinvestigatedforeconomicalreuseoftheexistingpavements,includingreuseofexistingintactpavements,bonded&unboundedconcreteoverlays,cracking&seatingofexistingPCCpavements,rubblizationofexistingPCCpavements,reuseofexistingsubbaseandrecyclingofPCCandasphalticconcretematerials.Thefollowingparagraphsdiscussthetechnicalmeritsofeachofthesubbasepreparationoptionsconsideredinthedesign.ThepavementsectionsadoptedforpavementthicknessdesignareshowninTable1below.

    ReuseofExistingIntactPavements.Intactexistingpavementscouldonlybereusedinareaswheretheproposedlevelsmatchedtheexistinglevels,andprovidedthattheconditionandstructuralcapacityoftheexistingpavementswouldprovideanadequatedesignlifewithoutsignificantmaintenanceorreplacement.Afterreviewingthesefactorsitwasdecidedthattheareasthatcouldbereusedwereinsufficienttowarrantimplementationofthisoption.

    BondedConcreteOverlays.Bondedconcreteoverlayscouldbeusedwheretheexistingrigidpavementswereinverygoodcondition,wherethejointpatternoftheexistingslabsmatchedtheproposedjointlayoutofthenewpavement,andwheretheverticalgeometricprofileoftheproposedsurfacematchedtheexistingsurfaceprofile,toavoidvaryingthicknessesoftheoverlay.Afterreviewingthesefactors,itwasdecidedthatthisoptionwasnotfeasible.

    UnbondedConcreteOverlays.Unbondedconcreteoverlayscouldbeusedwheretheexistingrigidpavementswereinverygoodconditionandtheverticalgeometricprofileoftheproposedsurfacewassimilartotheexistingsurfaceprofile,toavoidthickasphalticconcreteprofilecorrectioncoursesbeingconstructedbetweenthetworigidpavements.Afterreviewingtherelativelevelsoftheproposedandexistingsurfaces,itwasdecidedthattheprofilecorrectioncourseswouldbeuneconomicalandunfeasible.

    Cracking&SeatingofExistingPCCPavements.CrackingandseatingofexistingPCCpavementsisgenerallyutilizediftheoverlaymaterialisintendedtobeasphalticconcrete.Inourcase,theoverlaymaterialwasintendedtobePCC.Inordertoavoidasandwichpavement,theprofilecorrectioncoursewouldneedtobeastabilizedmaterialsuchasP-401asphalticconcreteorP-304cementtreatedbase.Notonlywasthiscorrectioncoursedeterminedtobeuneconomical,itwouldresultinanextremelystiffsubbaseonwhichtoconstructthenewPCC,whichcouldleadtoearly-agedistresssuchastop-downcracking.Afterreviewingthesefactors,itwasdecidedthatthisoptionwasnotfeasible.

    RubblizationofExistingPCCPavements.RubblizationofexistingPCCpavementsisgenerallyutilizediftheoverlaymaterialisintendedtobeasphalticconcrete,andtherewerenoknownexamplesofnewrigidpavementsbeingconstructedoverarubblizedconcretepavement.

  • McCullaghandTipnis 7

    AftercarefulconsiderationitwasdecidedthattherubblizationprocesswouldshattertheexistingPCCslabssufficientlytoeliminatetheslabactionoftheexistingPCCpavement,therebyreducingthelikelihoodofreflectioncrackingfromtheunderlyinglayers.Sincetherubblizedmaterialiseffectivelygranularinnature,theprofilecorrectioncoursecouldbeconstructedfromgranularmaterials(P-209andP-154)withoutthesectionactingasasandwichpavement,andthereforethisoptionwasconsideredtobefeasible.

    ReuseofExistingSubbase.TheexistingsubbasecouldbereusedinsituafterremovalofasphalticconcreteorPCCwearingcoursesprovidedthatthesubbasewasofsufficientthicknesstoprovidetherequiredcoveroversubgradeandofsufficientquality.Afteranalyzingthestrengthoftheexistingsections,itwasdecidedtoretainaminimumof600mm(23.5)ofexistingsubbaseunderthenewPCCandstabilizedbasecourselayers.Thisoptionwasconsideredtobemoreeconomicalandenvironmentallyresponsiblethanimportingnewsubbasematerials.Accordingly,thisoptionwasconsideredtobefeasible.

    FullDepthReconstruction.FulldepthreconstructionwouldberequiredinareaswhereneitherrubblizationofexistingPCCpavementsorretentionofexistingsubbaseoptionswerefeasible.Thiswouldoccurinareasofcut,orareascurrentlyoccupiedbybuildings,shouldersandgrassislands.

    RecyclingofPCCandAsphalticConcreteMaterials.InareaswhereexistingasphalticconcreteorPCCwearingcoursesweretoberemoved,recyclingofthematerialsforreuseasasubbasecoursewasinvestigated.VendorswereidentifiedthatcouldprovidemobilecrushingplantsonsitethatcouldcrushPCCandasphalticconcreteintoamaterialwithequivalentpropertiestosubbase(P-154)qualitymaterial.Asanalternative,theexistingasphalticconcretecouldberemovedbycoldmillingandthemilledmaterialcouldalsobeusedinlieuofP-154material.Bothmethodswereconsideredtobemoreeconomicalandenvironmentallyresponsiblethanimportingnewsubbasematerials.Accordingly,thisoptionwasconsideredtobefeasible.

    Table1.PavementSectionsAdoptedforPCCThicknessDesign.

    Layer PCCoverRubblizedConcretePCCoverExistingSubbase

    PCCFullDepthReconstruction

    WearingCourse P-501PCC P-501PCC P-501PCC

    StabilizedSubbase 150mm(6)P-304CTB150mm(6)P-304CTB

    150mm(6)P-304CTB

    CrushedAggregateCappingLayer

    200mm(8)P-209crushedaggregatebasecourse

    200mm(8)P-209crushedaggregatebasecourse

    200mm(8)P-209crushedaggregatebasecourse

    ProfileCorrectionCourse

    P-154(orequivalent)aggregatesubbase

    P-154(orequivalent)aggregatesubbase

    P-154(orequivalent)aggregatesubbase

    Subbase/SelectFillRubblizedPCC,E=1,400MPa(200,000psi)andunderlyingsubbase

    RetainedexistingP-154equivalentaggregatesubbase

    900mmofSelectFillCBR6%

    Subgrade k=11kpa/mm(40pci)k=11kpa/mm(40pci)

    k=11kpa/mm(40pci)

  • McCullaghandTipnis 8

    AIRCRAFTTRAFFICANALYSIS

    Therigidpavementsweredesignedfora30yearlife,andtheannualtrafficwasconsideredforboththetaxilanesandaircraftparkingstandstoenableacomparisonoftheresults.Thetrafficwasestimatedbasedonadetailedanalysisoftheaircraftparkinglayoutandpredictedoperatingmodesoftheapron.ThenewT2terminalbuildingwilloperateMultipleAircraftRampSystem(MARS)standsandswinggates,sothatasinglestandcanaccommodateeitheronewidebodyaircraftortwonarrowbodyaircraft,ineitherdomesticorinternationalconfiguration.Accordingly,theparkingstandswerecategorizedintothreemaingroupsbasedonthelikelyoperatingscenariooftheapronandterminalbuilding;dedicatedinternationalusage,dedicateddomesticusage,andmixedinternational/domesticusage.Inaddition,thetaxilanetrafficwassplitinto8differentsegmentsandtrafficwascalculatedaccordingtotheestimatedusageofstandsbeingfedfromeachofthe8taxilanes.ThelayoutoftheapronisshowninFigure2below.

    CSIAcurrentlyhandlesapproximately550dailyairtrafficmovements(arrivalsanddepartures),howeverthisusageisforecasttoincreaseto888dailymovementsby2015.The2015forecastusagerepresentstheconstrainedcapacityoftheairport,hencetrafficisexpectedtoremainconstantafterthistime.ThemostlikelyaircraftfleetmixfortheairportwasdeterminedfromtrafficforecastreportscommissionedbyMIAL,andisshowninTable2below.

    Figure2.T2ApronLayoutwithTaxilanesandOperationalScenarioGroups.

  • McCullaghandTipnis 9

    Table2.CSIAAircraftFleetMixPercentages.Aircraft A320 A321 A300 A330 A340-300 A340-600 A380FleetMix 16.7% 2.3% 10.7% 10.7% 4.1% 4.1% 0.3%

    Aircraft B737-800 B767-400 B747-400 B747-8 B777-300 B777-300ER MD11FleetMix 26.0% 5.6% 5.9% 0.3% 8.2% 3.4% 1.8%

    Theabovefleetmixwasnotapportionedtoaircraftstands,asairlinestendtohavepreferredstandsandsomestandsmaybeutilizedmorethroughoutadaythanothers.Consequently,regardlessofwhetherastandisusedforinternationalordomesticaircraft,thatstandmaybeusedtoservicealargemixofaircrafttypes,oritmaybeusedpredominantlytoserviceonlyafewaircrafttypes.Certainstandsoneachapronareamaybeallocatedtothepredominantairlines(oraspecificramphandler),whichmayoperatealimitedfleetrange.Hence,itisreasonabletoexpectthatastandmaybesubjectedtoregularusageofcriticalwideandnarrowbodyaircrafttypesratherthanthefullairportfleetmix.Basedonthefleetmixandflightschedulesprovidedbythecapacitystudy,itwasclearthatthemajordomesticoperatorswerefavoringB737-800andA320/1aircraft,andthemajorinternationaloperatorswerefavoringB777-300,B777-300ERandA330-300aircraft.Aftercarefulconsiderationofthesefactors,wedeterminedthatthefollowingfleetmixeswouldrepresentthemostlikelyworstcasetrafficsituationsfortheapron.

    DedicatedInternationalFleetMix30%B777-300ER,40%B777-300,30%A330-300.

    DedicatedDomesticFleetMix12.5%A330-300,12.5%B777-300,37.5%A321,37.5%B737-800.

    MixedInternational&DomesticFleetMix4.3%B777-300ER,5.6%B777-300,4.3%A330-300,42.9%A321,42.9%B737-800.

    Theannualtaxilaneusagewascalculatedforeachofthe8taxilanesbasedonthedailyairporttraffic,aircraftfleetmixandtaxilaneusagefactors.Thetaxilaneusagefactorsareexpressedasthepercentageofnarrowbodyandwidebodystandsthatcanbeaccessedviaeachtaxilane.Thefollowingformularepresentsthecalculationoftheannualtaxilaneusageforanygiventaxilaneandforanygivenaircrafttype:

    365= tuffmdaa PPTT

    Where: Ta = Annualdeparturesofparticularaircrafttypeforspecifictaxilane Tda = Totaldailyairportdepartures Pfm = Percentageofaircraftfleetmixapplicabletoaircrafttype Ptuf = Percentagebasedtaxilaneusagefactorforspecifictaxilane

    ThecalculatedannualdeparturesforeachtaxilaneareshownTable3below:

  • McCullaghandTipnis 10

    Table3.AnnualDeparturesforeachTaxilane. P1a P1b P1c Ha Hb Hc M1a M1bA320 7,624 17,790 17,790 0 1,271 3,812 13,978 7,624A321 1,054 2,460 2,460 0 176 527 1,933 1,054B737-800 11,599 27,064 27,064 0 1,933 5,799 21,265 11,599A300 896 4,181 5,674 2,389 2,389 1,493 4,181 896B767-400 473 2,207 2,995 1,261 1,261 788 2,207 473A330 896 4,181 5,674 2,389 2,389 1,493 4,181 896A340-300 348 1,626 2,207 929 929 581 1,626 348A340-600 348 1,626 2,207 929 929 581 1,626 348B747-400 373 1,742 2,364 995 995 622 1,742 373B777-300 662 3,089 4,193 1,765 1,765 1,103 3,089 662B777-300ER 284 1,324 1,797 757 757 473 1,324 284A380 0 0 0 0 365 73 0 0B747-8 0 0 0 0 365 73 0 0

    Theannualparkingstandusagewascalculatedforeachofthe3operatingscenariogroups(dedicatedinternational,dedicateddomesticandmixedinternational/domestic),basedonthedailystandusage,standfleetmixandPasstoCoverageRatiocorrectionfactor.FAARFIELDassumesanormaldistributionofaircraftwanderaboutthepavementcenterline,howeverthedegreeofwanderexperiencedonaircraftparkingstandsistypicallyverysmallduetotheuseofVisualDockingGuidanceSystemsandnose-wheelguidancecameras.Toaccountforthis,adjustmentsweremadetothetrafficfigurestoartificiallyaccountfortheinbuiltPCRfactorsusedbyFAARFIELD.

    Internationalpassengeraircrafttypicallytakelongertoservicethandomesticaircraft.Asaworstcasescenarioaninternationalstandcouldservice8aircraftperday,adomesticstandcouldservice16aircraftperday,andamixedstandcouldservice14aircraftperday.Thefollowingformularepresentsthecalculationoftheannualparkingstandusageforanygivenoperatingscenariogroupandforanygivenaircrafttype:

    365= PCRPTT fmsa

    Where: Ta = Annualdeparturesofparticularaircrafttypeforspecificstand Ts = Totaldailystanddepartures Pfm = Percentageofstandfleetmixapplicabletoaircrafttype PCR = PasstoCoverageRatiocorrectionfactor

    ThecalculatedannualdeparturesforeachoperatingscenariogroupareshownTable4below:

  • McCullaghandTipnis 11

    Table4.AnnualDeparturesforeachParkingStandOperatingScenarioGroup.

    PasstoCoverageCorrectionFactor

    DedicatedInternational

    DedicatedDomestic

    MixedInt.&Domestic

    B777-300 4.13 4,824 3,015 1,206B777-300ER 3.86 3,381 0 845A330 1.88 1,647 1,372 412A321 3.46 0 7,577 7,577B737-800 3.53 0 7,731 7,731

    PAVEMENTDESIGNUSINGFAARFIELD

    DesignswereconductedusingFAARFIELDbasedontaxilaneandparkingstandtraffic,andtheresultsarepresentedinTable5andTable6below.

    Table5.CalculatedPCCThicknessesbasedonTaxilaneTraffic.

    RubblizationofExistingPCC

    RetentionofExistingSubbase

    FullDepthReconstructionTaxilane

    mm Inches mm Inches mm InchesP1a N/A N/A 450 17.75 440 17.25P1b N/A N/A 485 19 475 18.75P1c N/A N/A 490 19.25 485 19Ha 335 13.25 470 18.5 460 18Hb 335 13.25 470 18.5 465 18.25Hc N/A N/A 460 18 455 17.75

    M1a 380 15 480 19 475 18.75M1b 335 13.25 450 17.75 440 17.25

  • McCullaghandTipnis 12

    Table6.CalculatedPCCThicknessesbasedonParkingStandTraffic.

    RubblizationofExistingPCC

    RetentionofExistingSubbase

    FullDepthReconstructionOperating

    ScenarioGroupmm Inches mm Inches mm Inches

    DedicatedInternational 375 14.75 485 19 475 18.75

    DedicatedDomestic 325 12.75 445 17.5 435 17

    MixedInternational&Domestic

    N/A N/A 455 17.75 445 17.5

    ThedesignPCCthicknessescomputedbasedontaxilanetrafficandaircraftstandtrafficwerefoundtobecomparable,andthereforeasperstandardpractice,thedesignthicknessesascomputedfortaxilanetrafficwereadoptedforboththetaxilanepavementsandadjacentparkingstands.

    ConstructioncostscouldbeoptimizedbyadoptingvaryingPCCthicknessesforeachtaxilaneandadjacentparkingstands,howeverinviewofpracticalconsiderationsandsimplificationofformworkandconstructionmethodology,threestandardPCCthicknesseswereadoptedacrosstheapron.ThePCCthicknessesadoptedforconstructionwere400mm,450mmand485mmasperTable7below.AlthoughthethicknessescomputedforthenewPCCoverrubblizedexistingPCCsubbasewereintherange335mmto380mm(13.25to15),itwasconsideredprudenttoadoptaminimumPCCthicknessof400mm(15.75)inordertoallowforsomeconservatisminthedesignandtomitigateagainstpossibleadditionalwarpingandcurlingstressesassociatedwithathinnerpavementoveracomparativelystiffsubbase.

    Table7.PCCThicknessesAdoptedforConstruction.

    RubblizationofExistingPCC

    RetentionofExistingSubbase

    FullDepthReconstructionTaxilane

    mm Inches mm Inches mm InchesP1a N/A N/A 450 17.75 450 17.75P1b N/A N/A 485 19 485 19P1c N/A N/A 485 19 485 19Ha 400 15.75 485 19 485 19Hb 400 15.75 485 19 485 19Hc N/A N/A 485 19 485 19

    M1a 400 15.75 485 19 485 19M1b 400 15.75 450 17.75 450 17.75

  • McCullaghandTipnis 13

    PAVEMENTSECTIONSFORNEWRIGIDPAVEMENTS

    Therelativecostsofeachfeasibleoptionwereconsideredindetail,includingthecostofplacingprofilecorrectioncoursesandthewearingcourseovertheinsitu/recycledsubbaseinordertoascertainthecostbenefitsofeachmethod.TheinitialbasiccostcomparisondeterminedthatinsiturubblizationofexistingPCCpavementswasthemosteconomicalsolution,followedbyretentionoftheexistingsubbasewithrecycledsubbasecorrectioncourses.Fulldepthreconstructionwastheleasteconomicalsolution.

    Fromthepavementthicknessdesignanalysisitwasdeterminedthatthesubgradetreatmentoptionsweredictatedbytheexistingpavementstructureaswellastherelativeleveldifferencebetweentheexistingandproposedpavements.Thefollowingpointsweredeterminedfromtheanalysisforselectionofthemostappropriatepavementtypesforeachoftheapronareas:

    RubblizationofexistingPCCpavementscouldoccurinareasofexistingrigidpavementswheretheleveldifferencebetweentheproposedandexistingsurfaceswasadequateforaccommodatingthenewPCCandstabilizedsubbase(P-304CTB)thicknesses.Followingareviewofthepavementthicknessrequiredouranalysisshowedthatthispavementsectioncouldoccurwheretheleveldifferencewasinexcessof550mm(21.75)infill.The550mmlowerlimitconsistsofnew400mm(15.75)PCCand150mm(6)P-304CTB,asdepictedinFigure3below.Forleveldifferencesgreaterthan550mm,aprofilecorrectioncoursewouldbeconstructedusingrecycledPCCorasphalticconcretesubbasematerials.Intheeventofashortfallinrecycledproducts,P-154materialwouldbeimportedfromoffsite.

    Retentionofexistingsubbasecouldoccuriftheareahadsufficientthicknessofsubbasetoprovidecoveroverthesubgradeafterremovaloftheasphalticconcreteand/orPCCwearingcourses.Followingareviewofthepavementthicknessrequireditwascalculatedthatthispavementsectioncouldoccurwheretheleveldifferencewasbetween-165mm(6.5)incutand550mm(15.75)infillforexistingrigidpavements,orabove-165mm(6.5)incutforexistingflexiblepavements.The-165mmlowerlimitconsistsof485mmP-501PCC+150mmP-304CTB+600mmP-154existinggranularsubbase1,400mmexistingpavementthickness,asdepictedinFigure3below.Forleveldifferencesabove-165mmincut,aprofilecorrectioncoursewouldbeconstructedusingrecycledPCCorasphalticconcretesubbasematerials.Intheeventofashortfallinrecycledproducts,P-154granularsubbasewouldbeimportedfromoffsite.

    Fulldepthreconstructioncouldoccurinareasbelow-165mm(6.5)incut,orwhereexistingbuildings,shouldersorgrassislandswerepresent.Inconsiderationoftheplasticandswellingnatureofthesubgradesoilidentifiedthroughgeotechnicalinvestigations,thepavementdesignincorporatedreplacementof900mm(3ft)ofexistingsubgradewithselectfillmaterialofCBR6%minimum,aspertheguidelinesprovidedinTable3-7ofFAAAdvisoryCircular150/5320-6E[5].

  • McCullaghandTipnis 14

    Figure3.TransitionsbetweenFullDepthReconstruction,KeepSubbaseandRubblization.

    Afinalchallengeexistedinthattheexistingfuelhydrantmain(whichwastoremainoperationalthroughouttheconstruction)ranbeneaththesite.Astheoperatingfuelcompaniesprohibitedtheuseofvibratingrollersandrubblizationequipmentwithin3m(10ft)ofthepipeline,theseareasweredesignedspecificallytoprotectthepipeline.

    Theproposedsurfacelevelsweremodeledinthe3-dimensionalgeometricdesignsoftwareprogram12D.Atthecompletionofthegeometricdesign,afull3-dimensionaltriangulationmodelwaspreparedofboththeexistingandproposedsurfaces,andtin-to-tindepthcontourswerepreparedtoshowtherelativedepthsbetweeneachsurface.Fromthisoutputthedesignerswereabletotracethe-165mm(6.5)cutand550mm(15.75)fillcontoursonalayoutplaninordertodeterminethepointatwhichthetypeofsubbasepreparationtransitionedfromfulldepthreconstructiontoretentionofexistingsubbasetorubblizationofexistingPCCpavements.

    Thefinalstepinthedesignoptimizationprocesswastooptimizethenewterminalbuildingfloorlevelandaprongradientsinordertojudgetheeffectonpavementmaterialquantitiesandassociatedcostbenefits.Theaimofthisexercisewastoachieveabalancebetweenraisingthelevelssufficientlytomaximizetherubblizationarea,whilstlimitingthevolumeofprofilecorrectioncoursematerial.

    The final areas of the various subbase treatment options achieved for the apronreconstructionarepresentedinTable8.

    Table8.SubbaseTreatmentAreas.SubgradeTreatment Area(m2) Area(ft2)RubblizationofExistingPCC 535,000 5,759,000RetentionofExistingSubbase 155,000 1,668,000FullDepthReconstruction 220,000 2,368,000ConstructionoverExistingFuelLine 30,000 323,000

    Total 940,000 10,118,000

  • McCullaghandTipnis 15

    CONCLUSION

    ThepaperhashighlightedthecomplexityoftheapronpavementdesignandconstructionstagingatMumbaiInternationalAirport.Theoperationalconstraintsofthisprojecthaveresultedintherequirementtoconstructtheaproninaseriesofdiscreetstages,anditisimportanttorecognizetheneedtoimplementadvancedplanning,monitoringandcontroltechniquesinordertomaintaintheprojectscheduleinaverychallengingoperationalenvironment.

    Withanaimtoeconomizethepavementdesignandconstructiontime,theexistingapronpavementlayershavebeenutilizedwhereverfeasible,inconsiderationoftheverticalgeometryoftheapronandstructuralrequirementforsupportingthedesignaircrafttraffic.ThedesignoptimizationapproachadoptedforthisprojectresultedinpavementsectionscomprisingofconstructionoverrubblisedPCC,constructiononexistingsubbase,andfulldepthconstruction.TheproposedconstructionofrigidpavementsoverrubblisedPCCisahighlightofthisprojectandtheperformancewillbemonitoredtoprovideforfutureguidelines.

    Thedesignaircrafttrafficwasderivedonthebasisofadetailedtrafficanalysisandalsoonthebasisofthecriticalaircrafttrafficonstandscorrectedforpasstocoveragefactors.Thedesignthicknessesestablishedforboththetrafficscenarioswerefoundtobecomparable.Itisgenerallyacceptedpracticetodesignanapronbasedonthetaxilanetrafficandtoadoptthesamethicknessfortheparkingstands.Astherelativetrafficontaxilanesandstandsmayvarydependingonthenumberofstandsservicedbyaparticulartaxilane,itisrecommendedtocheckbothscenariosandtoadoptthehigherthickness.

    Thisprojectisatruereflectionofhowsoundengineeringcan,intimesofeconomiccrisis,beanaidtoanairportbyprovidinginnovativesolutions,detailedanalysesandoptimizationofdesigns.Larsen&ToubrowouldliketoacknowledgethesupportoftheGVKGroup,MumbaiInternationalAirportLimited,andCH2MHILL(ProjectManagementConsultants)fortheproductionofthispaperandtheirsupportinadoptinginnovativeandnon-standarddesigns.

    REFERENCES

    1. InternationalCivilAviationOrganization,Annex14totheConventionofInternationalCivilAviation,FifthEdition,July2009

    2. InternationalCivilAviationOrganization,AerodromeDesignManualPart1Runways,ThirdEdition,2006

    3. InternationalCivilAviationOrganization,AerodromeDesignManualPart2Taxiways,ApronsandHoldingBays,FourthEdition,2005

    4. InternationalCivilAviationOrganization,AerodromeDesignManualPart3Pavements,SecondEdition,Amendment21989

    5. FederalAviationAdministration,AirportPavementDesignandEvaluation,AdvisoryCircularAC150/5320-6E,2009