Updates on Tevatron and LARP
description
Transcript of Updates on Tevatron and LARP
Updates on Updates on Tevatron and LARPTevatron and LARP
Vladimir ShiltsevFNAL/Accelerator Physics
LARP/Accelerator Systems
APEX Mtg 11/02/2006 - Shiltsev 2
In short
FY06 goals 725 / 580 pb-1
Delivered 620 pb-1
FY07 goals ~1750 / 760 pb-1
Delivered by Nov.1 50 pb-1
Yesterday, CDF Detector celebrated 2fb-1 of data delivered !
APEX Mtg 11/02/2006 - Shiltsev 3
• Pbar production task force initiated Dec-Feb 2006• Best luminosity before shutdown:
– 171e30 cm-2s-1– 25 pb-1/week
• Shutdown to Upgrade D0 detector Mar-June 2006• Fast start up (<2 weeks)• Rush of records: 171182191205228229e30• Current best:
– store 229.0e30 (avg CDF & D0)– week 33pb-1– month ~120pb-1
• Average store 27-32 hrs (longest 54hrs), ~120-130 hrs/week36x36 bunches ~270e9 p/bunch, 60-80(max) pbars/bunch
Details
APEX Mtg 11/02/2006 - Shiltsev 4
• Reduction of beta* to 28 cm Sep’05 ~8 % • Pbar production task force Feb’06 ~10 %• Tevatron 150 GeV helix more p June’06 ~10 %• Tev collision helix lifetime July’06 ~15 %• New RR WP emittances, loss Sep’06 ~25 %• D0 luminosity counters rescaled Oct’06
15/2=8%
Improvements over last ~1yr
APEX Mtg 11/02/2006 - Shiltsev 5
Content
APEX Mtg 11/02/2006 - Shiltsev 6
• Pbar production (not cooling!) : – still less 20e10/hr
• Beam-beam effects in Tevatron:– Ksi~0.025 for pbars losses/emittances– Ksi ~0.015 for protons losses/emittances
• Availablity: component failures no L time– 10/30/06 - ??11/08/06?? Tev Cryo vacuum– 10/09/06 - 10/23/06 Tevatron Q,D,spool– 02/23/06 - Tev magnet failure , early Shtdn start– 01/14/06 - 01/27/06 Tev magnet – 01/03/06 - 01/06/06 AA magnet– 11/22/05 - 12/12/05 Tevatron magnet
• Plus, power glitches, etc: – Jul-Aug’06: 45 stores , 15 aborts/quenches– Sep-Oct’06: 36 stores , 17 aborts/quenches
Major Limitations
APEX Mtg 11/02/2006 - Shiltsev 7
Content
APEX Mtg 11/02/2006 - Shiltsev 8
• Pbar production: – AA optics
– Faster AA to MI to RR transfers (<15 min)
– Pbar Target optimization
• New Tevatron WP:
– To improve luminosity lifetime (less losses, no dEmm)
– Allow higher Np and Na
Next Steps (till ’09?)
(yr?) V.Lebedev
APEX Mtg 11/02/2006 - Shiltsev 9
Content
APEX Mtg 11/02/2006 - Shiltsev 10
STATE of LARP…after
• Doe Review Jun’06
• LHC Upgrades Workshop in Spain, Oct’06
• LARP Collaboration Meeting at BNL, Oct’06
• Executive Committee Mtg, Oct’06
APEX Mtg 11/02/2006 - Shiltsev 11
LARP Accel Systems Progress ‘06
• Schottky being baked, will go into LHC tunnelSchottky being baked, will go into LHC tunnel• TCFB: success at SPSTCFB: success at SPS• 4 long-term hardware commissioners @CERN• SLAC joins commissioning forces• LHC@FNAL to open in Nov’07, new - LAFS• RC work at full speed, a lot of changes, delay• SPS beam studies: BBQ PLL, Q’ head-tail, bent
crystal, etc• Wires built for RHIC tests• # of LARP presentations at Valencia workshop
APEX Mtg 11/02/2006 - Shiltsev 12
4.8GHz Schottky Detector
APEX Mtg 11/02/2006 - Shiltsev 13
PLL Success on SPS Ramp
APEX Mtg 11/02/2006 - Shiltsev 14
2007 – First Year of “Deliverables”
• “Hard deliverables” are the projects which
CERN needs but can not back-up itself in
case of failure (thus, special attention and
protection needed):
– Lumi Monitors for 2 IPs (2007)
– Tune Feedback (2007)
– Beam Commissioning (2007-2009-beyond)
– Phase II rotating collimators prototype (2009)
APEX Mtg 11/02/2006 - Shiltsev 15
Accelerator Systems FY07 Priorities
1. Lumi-Monitors: construct, install, start commissioning
2.2. Tune&Coupling FB: deliver design, participate in installation Tune&Coupling FB: deliver design, participate in installation
and commissioningand commissioning
3. Schottky: participate in installation and commissioning
4. Hardware Commissioning: execute current plan – SAFELY!
5. Beam Commissioning: develop acceptable/detailed
execution plan for FY08+ by ~mid-07 (more from BNL!)
6.6. Physics experiments: Physics experiments: RHIC (BBLR),RHIC (BBLR), Tevatron(PLL), ecloud Tevatron(PLL), ecloud
7. Other tasks: execute Task Sheet’s Plans
APEX Mtg 11/02/2006 - Shiltsev 16
CARE–HHH: upgrades discussed
• IR Upgrade:– both quad first paths NbSn, NbTi
• Magnet R&D… Magnet R&D…Magnet R&D– D0 3.5m from IP– <1mrad Crab Crossing not excluded
•Low cost, potential high gain:– low-noise feedback – collimator schemes (RC, LEL, Crystals)– beam-beam compensation schemes (W,LEL)
• Upgrade of Injector Chain:– new Linac, PS+, PS2– SPS+ incl. SF-SPS
APEX Mtg 11/02/2006 - Shiltsev 17
RHIC BBLR wires – assembly
wires (2.5m long) with strong-back (-profile) 7 support points
NEG coated chambersduring assembly
APEX Mtg 11/02/2006 - Shiltsev 18
Things not in FY’07 budget
ProjectProject Reason Reason
• Longitudinal Density Monitor budget
• Fast Magnet Ramp Measurement System budget
• Crab Cavity – hardware part budget
• E-lenses budget
• Bent Crystal collimation (see below) too early
• LER-LHC 1.5TeV (see below) little $$
• Optical Stochastic Cooling too big for LARP
APEX Mtg 11/02/2006 - Shiltsev 19
Summary:
• DoE Review was (overall) successful
• LTVAC started
• Instrumentation tasks are of the highest
priority in FY’07
• Constrained by budget, #of tasks dropped
• Plans to further improve CERN-LARP
communication