Update on the progress of the
3February2016
CrisCotino
TRANSPARENCY PLATFORM
3rdMarketEuropeanStakeholderCommittee,Brussels
Page 2
Update on UI and download functions
Data completeness and quality
Conclusions
1
2
3
Developmentsandenhancements totheTransparencyPlatform
Page 3
Graphical User Interface AlistofquickwinshasbeenagreedfollowingalsotherecommendationsoftheUserGroup• Rememberingcountryandtime-settings• Browsercompatibility• OptimizingthescreendisplayThedevelopmentsshallbeavailableinthefirstreleaseofthePlatformfor2016(plannedforlateJanuary/beginningofFebruary)
ENTSO-EisassessingtheopportunitytobuildanewUI
• SimplifyM2MConnection• Combinedatainextracts• Crossreferenceofdata• Ad-hocaccesstocommonlyuseddata
• Upgradedsubscriptionmodule
Expressed needs Operating Efficiency
Page 4
• Lowermaintenanceandhostingcosts
• Improvedperformance• Morestableenvironment• Reducednumberofdataextractmodules
Improvements intheDataExtractionFunctionalities
Click to edit Master title style
Page 5
EMFIP
MySQL Replica
Data Reposities
Data Repositories1. Load
2. Generation3. Transmission
4. Balancing
Key• Remainsas-is• DataExtraction
EMFIP – Data GatheringECP è data gateway è MySQL
EMFIP
Data Gathering Data Usage and Reporting
M2MConnection
Proposedsolutionfordataextracts
Improvements intheDataExtractionFunctionalities
Page 6
• Deliverables• DataRepositiories4areas:load,generation,transmision,
balancing• Delivermostpopulardata• AdhocAccesstodatarepositorythroughAPI• Subscriptionmodule• RestfulAPIwithaccesstosubscribers
• Implementationtimeline:1November-1June
Delivery1June2016
UpgradedSubscription Module
30/4/2016
M2Mavailable,RestfulAPI
31/3/2016
DeliveryPilotDataRepository
31/12/2015+Monthlyupdates
FirstDelivery30/11/2015(EMOSdata)
KickOff01/11/2015
Updateontheprogress indatacompletenessandquality
Page 7
Data completeness• FollowingthedecisionsofthelastAESAGmeeting2reportsweresubmittedtoACER• OnereportonaggregatedinformationperdataiteminJuly• SecondreportwithinformationperdataitemanddataproviderinSeptember
• ENTSO-EregisteredasRRMforreportingunderREMITIAandstaredreportingtoACERon7October
• Thetechnicalissuesencounteredinthefirstphaseofreportingseemtobesolved- Successrateoffilessubmitted>90%
• Basedontheresultsofthechecks,theprovisionofdatatothePlatformreached90%inQ42015
Updateontheprogress indatacompletenessandquality
Page 8
Data quality• AdataqualityproposalwouldalsoimplychangestothetechnicaldocumentationoftheTP
• ThisisataskforENTSO-Efollowingthe1styearaftertheGoLive ofthePlatform
• Therevisionofthedocumentsstartedwithaworkshopon21-22January2016
• TheupdatedMoPwillbesubmittedtoACERforanopinion
• Thisplanningwouldallowenoughtimeforindividualprojectstobeplannedandimplemented
Concluding remarks
Page 9
• DevelopmentsinGUItobeimplementedsoon• Thesolutionondatadownloadswillbedeliveredonastep-wiseapproach
• ThedevelopeddownloadfacilitywillmakeuseofdatarepositoriesandtheRESTAPI
• Thesolutionrepresentsasignificantamountoftheyearlybudget
• Datacompletenessreached90%• WorkonreviewingthedocumentationisongoingØTheENTSO-EUserGroupisbeinginformedontheongoingdevelopments
Thank you for your attention
Cristina Cotino ENTSO-E WG MIT Convenor TERNA Regulatory Affairs Dept. [email protected]