Update on Review of Embedded Generation Benefits

11
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Update on Review of Embedded Generation Benefits Andy Wainwright

description

Update on Review of Embedded Generation Benefits. Andy Wainwright. Background. Standard Licence Condition C13 Introduced at BETTA (2005) Addressed different treatment of 132kV connected small generation in Scotland (transmission) with that in England and Wales (embedded) - PowerPoint PPT Presentation

Transcript of Update on Review of Embedded Generation Benefits

Page 1: Update on Review of Embedded Generation Benefits

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

Update on Review of Embedded Generation Benefits

Andy Wainwright

Page 2: Update on Review of Embedded Generation Benefits

2

Background

Standard Licence Condition C13

Introduced at BETTA (2005)

Addressed different treatment of 132kV connected small generation in Scotland (transmission) with that in England and Wales (embedded)

Time limited: due to expire 1st April 2016

Embedded review needs to consider overall implications on GB generation

Informal industry focus group established Spring 2013

Page 3: Update on Review of Embedded Generation Benefits

3

Objectives of transmission charges

Cost reflectivity

Facilitate competition

Developments in transmission businesses

Recover transmission costs

Non-discrimination

Affected transmission ‘charges’

TNUoS BSUoS Losses

Focus Group agreement to consider TNUoS first

Page 4: Update on Review of Embedded Generation Benefits

4

TNUoS Charges - Locational Element

-10

-5

0

5

10

15

20

25

30

A B C D E

Gen

Dmd

TNUoS Locational Elements only

Charging Zones

Ta

riffs

Net approach

Embedded generation nets with demand

Therefore subject to a negative demand locational signal

Based on output at Triad

Equivalent to generation signal: zoning limitations

Gross approach

Embedded generation receives same generation signal as transmission connected

All demand receives locational signal

Page 5: Update on Review of Embedded Generation Benefits

5

The effect of the generation residual element

-10

-5

0

5

10

15

20

25

30

A B C D E

Gen

Dmd

Avoidance of generation

residual charge

Embedded generator avoids paying generation residual element

Page 6: Update on Review of Embedded Generation Benefits

6

The effect of the demand residual element

-10

-5

0

5

10

15

20

25

30

A B C D E

Gen

DmdNetting of positive demand

Positive demand can avoid paying the demand residual element if able to net with embedded generation

Embedded generation therefore has a value equal to the demand residual element

Page 7: Update on Review of Embedded Generation Benefits

7

Combination of both residual elements In summary, embedded generation can receive TNUoS ‘benefit’

through two effects on residual elements;

netting of positive demand (i.e. reducing demand charge)

avoidance of generation residual charge

-10

-5

0

5

10

15

20

25

30

A B C D E

Gen

Dmd

Avoidance of generation

residual charge

Netting of positive demand 2 x Residual

uplift

Page 8: Update on Review of Embedded Generation Benefits

8

Year Cost Residual

2012/13 £1.41/kW £27.07/kW

2009/10 £1.30/kW

(equates to £1.47/kW in 2012/13)1

£20.74/kW

(equates to £23.53/kW in 2012/13) 1

1 RPI factor for 2009/10 to 2012/13 = 1.132992

0

0.5

1

1.5

2

2.5

3

3.5

4

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

£/kW

Project

Annuitised demand related infrastructure costs

Average

How much benefit should be paid for offsetting +ve demand?

NGET GSP infrastructure reinforcement costs

Page 9: Update on Review of Embedded Generation Benefits

9

Average TNUoS charge: £7.57/kW (2013/14)

Transmission Function (Use) Transmission connected G

Embedded G

Net transfers inject NetAccess to Market (s) GB & wider EU

Security / Quality of Supply

Should embedded generation pay for transmission?

How does embedded generation use transmission?

Comparing transmission and distribution charges

Note 2013/14 average TNUoS charge: £7.75/kW

Page 10: Update on Review of Embedded Generation Benefits

10

Other areas under consideration

Impact on >100MW generators

Exporting GSPs

Offshore Transmission Implications

Page 11: Update on Review of Embedded Generation Benefits

11

Next steps

National Grid report to be published October

Include Focus group & bi-lateral discussions

Three week open letter

Formal CUSC modification proposal potentially later in Autumn