Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th September

12
Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th September

description

Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th September. Consultation scope & responses. Seeking views on: proposed models for the allocation of cross border transmission capacity and efficient use of electricity interconnectors regulation of new investment. - PowerPoint PPT Presentation

Transcript of Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th September

Page 1: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Update on Ofgem’s interconnector policy consultation

FUI IG, London, 13th September

Page 2: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Consultation scope & responses• Seeking views on:

– proposed models for the allocation of cross border transmission capacity and efficient use of electricity interconnectors

– regulation of new investment. • We received 21 responses from interconnector owners, TSOs, energy

companies and other organisations

IC owners TSOs Energy Companies

Organisations

IUK National Grid EON AEP

Moyle RTE Centrica APX

Britned Eirgrid EDF Consumer Focus

Elia RWE

Statnett Statkraft

SSE Mainstream Renewable Power

Statoil ASA

IPR

Page 3: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Consultation conclusions

• Published summary of responses – July – http://www.ofgem.gov.uk/Europe/Documents1/Summary%20of

%20Responses%20from%20Electricity%20Interconnector%20policy.pdf

• Preparing “next steps” letter – for publication end September– Sets out our next steps in:

• Market coupling in the FUI Region• Tackling barriers to market coupling in GB (TNUoS,

Firmness, 2 power exchanges)• Developing a new regulatory regime for interconnector

investment

Page 4: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Market coupling in the FUI Region

• Committed to implementation of the “enduring solution” for day ahead market coupling of the FUI to the NW Europe Region

• Steps to achieve this:– Britned to implement its “embedded solution” as an interim

step– Support for and participation in the NWE TSO and PX projects

to develop a common algorithm to support price coupling across the region

– GB to implement the enduring solution including both IFA and Britned

– In the longer term, through cooperation of NRAs in the FUI region, support extension of market coupling to include SEM (All Ireland market)

Page 5: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Tackling barriers to market coupling in GB: TNUoS Charging

• Problems highlighted by respondents:– TNUoS charges create a deadband that prevents price

convergence in coupled markets– Avoidance of “Triad” charge (demand TNUoS) causes

inefficient flows on interconnector• Solution proposed:

– National Grid consulted over summer on complete removal of TNUoS charge on Interconnectors

– Final conclusions published by National Grid 6th September– Decision by Ofgem Authority expected by end of September– If approved, changes to charging methodology effective 1st

October 2010.

Page 6: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Tackling barriers to market coupling in GB: Firmness

• Share view of many other NRAs that:– Implicit auctions require physical firmness as a prerequisite– Physical and financial firmness should work towards delivering

the same outcome• Recognise that Britned will be offering physically firm products• Consistency with CWE’s approach to firmness i.e. financial

firmness after nomination of capacity• Contributing to ERGEG work addressing firmness through the

framework guideline / network code process – leading to a common European approach

Page 7: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Tackling barriers to market coupling in GB:2 power exchanges

• Respondent highlighted existence of 2 PXs in GB as a potential barrier to market coupling

• We've been considering how market coupling could be implemented in GB..

• Possible solutions, already presented to IG...• We believe it is technically possibly for two Pxs to deliver a single

a coupling solution• TSOs, Pxs & IC owners should be part of a clear roadmap, for the

implementation of the enduring coupling mechanism

Page 8: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

LT Coordination

•Coordination of LT auctions, key priority for the FUI region.

•In our letter we highlight the next steps agreed by FUI IG...

Intraday timeframe

•The increased amount of intermittent generation expected in GB and SEM markets, places additional value to Intraday timeframe.

•Together with the Dutch NRAs, we are co-chairing, on behalf of FUI the Regulator’s group of the NW ID project: ID market coupling solution by 2012.

•In parallel, once SEM introduces ID trading, FUI will develop coordinated ID capacity products & work on the implementation of the ID coupling model

Page 9: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Developing a new regulatory regime for interconnectors

•Given that the preferred EU approach is a regulated model we are developing a regulated investment regime for non-exempt interconnectors, but remain open to the merchant route.

•Fully regulated approach would be a significant departure from our current approach, requiring several changes to our regime and longer time to implement.

•As respondents highlighted, the Cap and Collar model: – maintains merchant investment whilst safeguarding consumers from

taking undue levels of risk.– is a good compromise between the advantages & disadvantages of

the merchant and regulated models

Page 10: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Developing a new regulatory regime for interconnectors

•Project “NEMO”, is our “pilot” project in exploring how cap and collar model could be implemented in GB.

•Together with CREG, NG and Elia we aim to establish:– High level principles behind the new regime– Explore options for cap& collar design , satisfying these principles – Implementation mechanisms required to adopt a cap & collar (eg

changes in the regimes on both sides)Timeline:•Proposal by the end of 2010•Possible a joint consultation with CREG in 2011

Page 11: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September

Developing a new regulatory regime for interconnectors

•While, NEMO will be our pilot project to develop a regulated regime, we acknowledge that there are other ICs under discussion: e.g. links to France, Ireland, Norway..

•We envisage holding similar discussions with relevant TSOs and regulators to discuss if this approach could be seen as a high level solution for other non-exempt ICs..

•We also remain open to the merchant route.Under FUI workstream on IC investment, we intend to develop a coordinated approach towards exemptions with other regulators...

Page 12: Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th  September