Update on Nuclear Energy Programme in Bangladesh a y o f B e n g a l Proposed Power plant Location...
Transcript of Update on Nuclear Energy Programme in Bangladesh a y o f B e n g a l Proposed Power plant Location...
MOHAMMAD SOHELUR RAHMAN, MD. ABDUR RAZZAQUE and DEBABRATA DAS
BANGLADESH ATOMIC ENERGY COMMISSION (BAEC)
Update on Nuclear Energy Programme in
Bangladesh
Interregional Workshop on Advanced Nuclear Reactor Technology for Near-Term
Deployment, IAEA HQ, Vienna, Austria, 4-8 July 2011
CONTENTS
SITE AREA OF RNPP
RECENT DEVELOPMENT OF RNPP
ROADMAP FOR RNPP
ENERGY AND POWER SITUATION OF BANGLADESH
ENERGY POLICY AND GOVT. VISION
NUCLEAR OPTION FOR BANGLADESH
CONCLUSION
B a y o f B e n g a l
Proposed Power plant Location
Ganges
Gorai
Proposed Power plant Location
Ganges
Gorai
SITE AREA of Rooppur Nuclear Power Project (RNPP)
Project Site Area : 105 Hectare
Residential Area : 13 Hectare
Nuclear power was identified as a viable proposition for
Bangladesh as early as 1960's
The Rooppur Nuclear Power Project (RNPP) site was selected
in 1963
A number of feasibility studies were conducted, each of which
established that the project is technically and economically
feasible.
Pre-implementation phase activities for construction of two units of
reactors on the Rooppur site with a time lag of two years have been
initiated.
ABOUT RNPP SITE
TM/
WSP
5-9
Nov.
2007
Seismic loads
Wind loads
Tornado
Tsunami
Flood
Aircraft crash
Shock wave
FINALIZATION OF SITE SAFETY REPORT
Recent development of RNPP
Necessary studies for evaluation of site specific design basis parameters of the
reactor and sensitive structure and determination of cost-effective safe
engineering solutions for development of RNPP Site are required for
construction work
GEOLOGY, STRUCTURAL GEOLOGY AN
D SOIL MECHANICS
SEISMOLOGY AND GROUND STABILITY OF
THE AREA
METEOROLOGICAL AND TROPICAL CON
DITIONS OF THE AREA
Reviewing the geology and fault information
Compilation of earthquake database
Analysis of seismic source and seismicity characteristics
Probabilistic seismic hazard assessment for 200, 475, 2475 year
1D Site response analysis (Site specific) study
Development of site specific response spectrum
Declaration to implement RNPP was a Election
Manifesto of all major Parries in the last National Parliament election of 2008;
AT PRESENT, both the government party and the
opposition party are in favor of implementation of RNPP;
Recent development of RNPP
Recent development of RNPP
Signing of MOU between BAEC and ROSATOM and
initialed on Peaceful Uses of Nuclear Energy in
Peaceful Purposes between Russian Federation and
Bangladesh in 2009
A Framework Agreement between the Government
of the People’s Republic of Bangladesh and the
Russian Federation on cooperation in the field of the
use of nuclear energy for peaceful purposes was
signed on May 21, 2010.
Decision of immediate implementation on NPP was
taken by the National Parliament in 2010
Recent development of RNPP
To accelerate the activities for starting construction of
RNPP, the Government has formed eight Working Sub-
Groups (Bangladesh Gazette, June 21, 2010) each of
which consists of the representatives from the relevant
ministries, organizations.
These Working Sub-Groups are responsible for
assessing the Nuclear Infrastructure of the country in
the respective areas and identify the gaps of nineteen
infrastructure items of Phase II (Decision Making Phase).
An Inter-governmental Agreement between the People’s
Republic of Bangladesh and the Russian Federation on
Cooperation Concerning the Construction of a Nuclear
Power Plant was initialed on February 24, 2011.
Recent development of RNPP
A National Committee headed by the Head of
the Govt. was formed to review/supervise the
overall development activities/contractual
documents of RNPP (April 2011)
GOVERNMENT SUPPORT
Annual Development Project (2011 – 2012) Accomplishment of Essential Activities to Implement Rooppur Nuclear Power Plant Project
IAEA SUPPORT
IAEA’S TC Project (2009 – 2011) Establishing Nuclear Power (BGD 4024)
Activities to
implement first
NPP, the RNPP
Preparatory
work for
construction
of a RNPP
after a policy
decision has
been taken
Pre-Project
activities after
Agency
Mission
Readiness to
include nuclear
as a national
energy strategy
option since
1960s
PHASE 0 PHASE 1 PHASE 2 PHASE 3
Main
ten
an
ce a
nd
co
nti
nu
ou
s
infr
astr
uctu
re i
mp
rov
em
en
t
Infr
astr
uctu
re d
ev
elo
pm
en
t
pro
gra
mm
e
Pre-
project
RNPP
definition RNPP
Construction
Op
s
Commissioning
Nuclear power is
considered as a
possible option
MILESTONE 0
Ready to include
nuclear as realistic
national energy
strategy option
MILESTONE 1 Ready to make
commitment to a nuclear
MILESTONE 2 Ready to invite bids
for the first NPP
MILESTONE 3 Ready to commission
and operate first NPP
Pre-
policy
2008 2010 2012 2018-2019
RNPP Project Timeline (proposed according to Vision 2021 and Sixth Five
Year Planning of Bangladesh
Preparation for
RNPP Implementation
1960s
Per capita availability of electricity and energy in Bangladesh
is the lowest among the developing countries:
ELECTRICITY 220 kWh (per capita generation)
149 kWh (per capita consumption)
ENERGY 240 KGOE
(Share of commercial energy is about 60%)
Per capita GDP 638 USD
PPP GDP 1,572 USD
In terms of per capita GDP, per capita energy and electricity consumption, Bangladesh is a least developing country.
PRESENT ENERGY AND POWER SITUATION OF BANGLADESH
● Installed Capacity 6837.50 MW
● Generation Capacity 4000 - 4876 MW
● Peak Demand 5450 MW
● Load Shed 1000-1500 MW
o Max. Generation in 2011 4876 MW
.The unofficial demand is more
PRESENT ENERGY AND POWER SITUATION OF BANGLADESH
Bangladesh is mainly a mono fuel country
BPDB 66%
IPP 34%
● Relative share of Agriculture sector is decreasing
● Share of Industry is gradually increasing, which reflects the
positive trend of Industrialization
Infrastructure support that is adequate supply of energy and
electricity is essential for rapid growth in Industrial sector
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
81 85 90 95 2000 2005 2007
Agriculture Industry Service
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
6.00%
7.00%
8.00%
1981-04 1981-85 1986-90 1991-95 1996-00 2001-05
Agriculture Industry Service Total GDP
STRUCTURAL CHANGE IN ECONOMY
sectoral contribution in total GDP Growth of sectoral and total GDP
PRESENT ENERGY AND POWER SITUATION OF BANGLADESH
19
0%
2%
4%
6%
8%
10%
2009 2013 2017
6%
8%
10%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
2000 2008 2021
25.58% 20.87%
15%
25.70% 29.66% 40%
Agriculture Industry
0%
10%
20%
30%
40%
50%
Agriculture Industry Service
48%
16% 36%
30%
25%
45%
2009 Target Year 2021
VISION 2021 OF PRESENT GOVERNMENT
To transfer Bangladesh into a modern, knowledge-based a digital middle income
group country by 2021
Socioeconomic target by 2021
Sectoral contribution in
total GDP
GDP growth (%) Labor force
The contribution of the industrial share will increase gradually upto 40% by
2021 from its present level of 29% for achieving the GDP growth to 10% by
2017 to be sustained thereafter.
Installed Capacity of BPDB Power Plant as on June 2011
Unit type Capacity Unit Total (%)
Coal 250.00 MW 3.66 %
F. Oil 445.00 MW 6.51 %
Gas 5143.00 MW 75.22 %
HSD 769.50 MW 11.25 %
Hydro 230.00 MW 3.36 %
Total 6873.50 MW 100 %
Derated Capacity of BPDB Power Plant as on June 2011
Unit Type Capacity Unit Total (%)
Coal 220.00 MW 3.52 %
F. Oil 366.00 MW 5.86 %
Gas 4688.00 MW 75.03 %
HSD 744.00 MW 11.91 %
Hydro 230.00 MW 3.68 %
Total 6248.00 MW 100 %
Bangladesh Power Sector: At a Glance
SL. No. Items FY 2009-10
Upto May’10
1. Generation Capacity (MW) 5376
2. Maximum Generation, June 2011 4876
3. Net generation, MKWh (FY 2008-09) 26,533
4. Transmission line, km 8391
5. Grid sub-station capacity,MVA
(a) 400 KV and 230 KV
(b) 132 KV
6850
9626
6. Distribution line, km 2,66,460
7. Number of consumers (million) 12.00
8. Number of village electrified 53,281
9. Per capita generation, kwh 220
10. Access to electricity 47 %
Source: http://www.powerdivision.gov.bd/index.php?page_id=262
230x132KV, 132x33KV and
33/11KV Sub-stations
230KV, 132KV & 33KV
Transmission Lines (BPDB,
PGCB, DESA, REB, DESCO, etc)
EXISTING NATIONAL GRID SYSTEM
G. GRID ADAPTATION
RNPP is located almost in the center of the
western zone and is just about 5 km from
Ishurdi sub-station
The RNPP will feed into the Ishwardi Sub-
station of BPDB where the east-west electrical
inter-connector ties in
Grid Sub-Station AROUND RNPP SITE
G. GRID ADAPTATION
Name of lines Length Type
East-West Inter-
connector
358
Double
Khulna - Ishurdi 370
Double
Goalpara-Ishurdi
338
Double
Ishurdi-Bogra
212
Double
230 KV Transmission line
132 KV Transmission line
TRANSMISSION LINES AROUND RNPP SITE (existing)
G. GRID ADAPTATION
Government should actively consider the issue of HV
grid adaptation
An arrangement can be made through making a MOU
between BPDB or Power Cell or PGCB with a suitable
company of NPP operating country to address the
stability of the country’s T&D network for induction of
NPP
G. GRID ADAPTATION
Present Picture of Power Sector of Bangladesh
27
BANGLADESH IS FACING TWIN ENERGY CRISES
An urban energy crisis characterized by power shortages and gas shortage A rural energy crisis reflected in the increasing inability of the rural poor to access traditional biomass
Both crises need urgent attention, as they directly affect the nation’s
development prospects and the basic livelihoods of urban and rural
populations
PRESENT GOVT. VISION
Making electricity available for all by 2021
Ensuring reliable and quality supply of electricity
Providing electricity at a reasonable and affordable price
Addition of 20,000 MW of generating capacity by 2021
29
Targets of electricity production
By the year 2013: 7,000 MW
By the year 2015: 8,000 MW
Possibility
Domestic coal and imported coal based power plants
;
Availability of new gas both in offshore and onshore
Vision 2021: Energy Security and Electricity for all in 2021
Energy Target
Current (%) 2021(%) 2030 (%)
Gas 88 30 28
Coal 3.7 53 38
Oil 6 3 5
Hydro 2.7 1 4
Nuclear 0 10 19
Renewable 0 3 6
Perspective plan of Electricity generation mix: 2010 – 2021
30
PERIOD PLAN ON NPP
By 2020 Implementation of 2 units of NPP
By 2025 Addition of more 2 units to ensure 10% of
total generation from NPP
Beyond 2025 Nuclear share should be 25% in overall
generation mix
The Revised Draft National Energy Policy of Bangladesh (2008)
has outlined the nuclear power program as follows:
National Energy Policy of Bangladesh
Nuclear Energy Policy is a component of the National Energy
Policy
National Energy Policy, 1996: Nuclear energy was identified as
a component of energy mix
TARGET YEAR (Long Term Planning) 2021
Addition of more than 10,000 MW during the period
2015 – 2021
Annual new addition would be about 2000 MW
COAL
Total in-situ coal reserve is about 1000 MT
GAS
Current proven and probable (2P) reserves are 15 TCF
while cumulative production is about 7.0 TCF
ABOUT INDIGENOUS RESOURCES
HYDRO
Existing generating capacity: 230 MW Sangu and Muhuri are two potential sites with total capacity 350 MW
WIND Construction of total capacity 1.8 MW Wind potential is too limited and total potential capacity is about 350 MW
POWER AND ENERGY SYSTEM PLANNING: HIGH CASE
0.0
10000.0
20000.0
30000.0
40000.0
50000.0
60000.0
2005.0 2007.0 2009.0 2015.0 2025.0
solar
GasIm_PP
CoalIm_PP
GasIn_PP
Hydro
Oil_PP
NPP
CoalIn_PP
Nuclear Solar Hydro
2018 1000 100 230
2020 2000 500 430
2025 4600 2500 730
2030 12000 5000 730
Suggested: Ambitious Vision for Nuclear Scenario, Imported Gas
Coal & Renewable
Maximum utilization of indigenous gas and coal, imported
options of both coal, gas after 2015, introduction of nuclear from
2015 and ambitious expansion after 2020 and solar from 2020
LEGISLATIVE FRAMEWORK
Nuclear Safety and Radiation Control Act 1993 and
Rules 1997 based on IAEA BSS 115
A draft of new law entitled Bangladesh Atomic
Energy Regulatory Act (BAER Act-2011) has been
formulated by the Regulatory Body and awaits
approval.
For strengthening nuclear regulatory infrastructure suitable for RNPP, draft Bangladesh Atomic Energy Regulatory Act (BAER
Act 2011) has been prepared by BAEC on the basis of the IAEA guidelines and recommendations
This draft BAER Act-2011 was reviewed by IAEA for
technical comments and awaits for GOVT. approval
Article 6 of the draft BAER Act-2011 establishes the Regulatory Body which would be independent from any Licensees
The draft BAER Act-2011 has the provision of adoption of the codes, guides and regulations of the government of the supplying the first NPP, International Agency(s) and any advanced nations
Diversification of energy mix with indigenous
gas and coal, imported coal and gas, introduction
of nuclear and Renewable are necessary for
sustainable development
Nuclear Power has become an Inevitable Option
for ensuring energy security in the mid to long-
term future
CONCLUSIONS
PERIOD PLAN ON NPP
By 2020 Implementation of 2 units of NPP
By 2025 Additional 2 units to ensure 10% of total
generation from NPP
Beyond 2025 Nuclear share should 25% in overall
generation mix
Nuclear Vision
The Draft National Energy Policy of Bangladesh(2008)
has outlined the nuclear power program as follows:
CONCLUSIONS