Transcript of Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x...
![Page 1: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/1.jpg)
Update on new alignment kit update
20/3/12
1
![Page 2: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/2.jpg)
2
Complete table based on a standard table (2400 x 1200 x 150) and a halftable (2400 x 600 x 150).
![Page 3: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/3.jpg)
Two granite tables to go to two different establishments.
3
RAL’s table.....2400 x 1100 x 150 + Holes for stages
Liverpool table...2400 x 600 x 150
![Page 4: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/4.jpg)
• Add picture of items in R56
4
![Page 5: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/5.jpg)
Granite Status
• Granite (+2 sets of legs) delivered to RAL on the 19th... yesterday!
• The smaller piece delivered to Liverpool yesterday too.
• Installation in the R12 clean rooms expected Thursday 29th
(first day heavy gang is free and I am at RAL)
• To set up the granite level will take about half a day.
• It will then take a further 2 weeks (my weeks) to reinstate the frame, interlocks and cabling
• so April 19th we should be back where we were but on a granite table
5
![Page 6: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/6.jpg)
6
Top view of placement jig
Y adjustment
X and Theta adjustment
![Page 7: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/7.jpg)
Drawings/production
• Real drawings are now in exsistnace (rather than a model)• We have had round 1 where Ian and I have commented on some
features. We are now waiting for a second iteration.• We are concentrating on the ‘bridge ‘ structure first and the
associated walls.• The cantilever we will tackle second.• The plan is to construct 4 bridge structures but all the wall positions.• There will be no prototypes just the 4 items that we will alter as
appropreate.• No fancy finishes for these ‘prototype’ items
• Waiting for the Ok to buy the bought in items such as dowels and bearings
7
![Page 8: Update on new alignment kit update 20/3/12 1. 2 Complete table based on a standard table (2400 x 1200 x 150) and a half table (2400 x 600 x 150).](https://reader036.fdocuments.us/reader036/viewer/2022062322/56649ea85503460f94bac61d/html5/thumbnails/8.jpg)
Timescale to aim foractivity End date Time to
completeNote to
self..Last round of drawings 23rd March Order up commercial
items
granite installed 29th March
Refit frames safety cables 5th April 2 weeks
Restart software development
Sp stavelet to populate, also several pipes to pressure test.
Unspecified start time but schedule says end March
2 weeks
Install vacuum system 3rd May 1 week
Install fume extraction 10th May 1 week Need to buy suitable pipes etc
Install storage 17th May 1 week Check drawings and get items ordered
Expected delivery of manufactured items
Mid May 1 month from start
Fit and make work ????
Adhesive tests to perform 2 weeks
8