UPCOMING DESIGN & CONSTRUCTION PROJECTS2nd Quarter 2020
(Project & Construction Management)
DESIGN PHASE PROJECTS
BCT - C3N Reconstruction
The scope of work includes the design and construction of approximately 25 acres of concrete pavement (18” roller compacted concrete) for storage of containers as well as traffic lanes to maintain traffic flow into and around storage areas.
Design Time Frame NIGP Codes Small Business Opportunities PHA Contact
3rd Qtr. 2020 – 4th Qtr. 2020 Consultants9253396258
Contractors913609132790976
• Demolition• Concrete• Grading• Excavation
Derek [email protected]
Bayport – Construct Wharf 7 and Optional Wharf 1
Design of Wharf 7 and Optional Wharf 1 at Bayport Terminal
Design Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 – 3rd Qtr. 2021 Consultants9625892533
Contractors90976912239143091438914849050591572
• Structural Concrete Repair• Steel Rebar• Concrete forming• Striping• Photography
Harvey [email protected]
CONSTRUCTION PHASE PROJECTS
BCT - Construct Maintenance Complex at BCT
Construction of a new Maintenance Complex at Barbours Cut Container Terminal including an approximate 128,000 sf maintenance building, fuel and wash areas, associated utilities, and parking.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
4th Qtr. 2020 – 2nd Qtr. 2022 90924 9143890976 9145091316 9146891360 9050591430 91572
• Utility Systems• Electrical Work• Plumbing• HVAC• Building Fixtures & Finishes • Photography
Jessica [email protected]
EXISTING BCT M&R BUILDING
BAYPORT M&R BUILDING
Barbours Cut - Demolition of Wharf cranes 7 and 8 and RTG Cranes P and S
This project will demolish 2 STS (Ship to Shore Cranes 7 and 8) and 2 RTG (Rubber Tire Gantry Cranes P and S)
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 - 3rd Qtr. 2020 9124096238
• Demolition Harvey [email protected]
Bayport - Port Road Expansion and Drainage
This project will add 1 additional lane to both the inbound and outbound lanes of existing Port Road. This project will also include installing new re-enforced concrete boxes under Port Road and in existing Ditch ‘D’ to drain 95.5 acre U shaped Port property.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 – 2nd Qtr. 2022 918329184692533
• Concrete reinforcement• Demolition• Earthwork
Harvey [email protected]
Land Development Preparation South of Port Road At Bayport Terminal
The project scope includes surveying, clearing, grubbing, grading, excavation, fill placement, drainage features, trench safety, concrete culvert installation, placement of topsoil and seeding. This is primarily an earth moving job with an aggressive schedule that needs to start quickly after ward.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
3rd Qtr. 2020 - 4th Qtr. 2020909769625290738
• Trucking• Storm Water Erosion
Protection• Trench Safety• Surveying
Brenda [email protected]
Bayport - Construct Container Yard 2 South at Bayport (CY2S)
Construction of approximately 18 acres of container yard (18” roller compacted concrete) and associated work at Bayport Container Terminal.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 - 4th Qtr. 2021 909769122391360914309143891276
96861925869050591572
• Material Testing• Surveying• Security• Electrical• Signs and striping• Photography
Jessica [email protected]
Bayport - Trench Drain Repairs
Repair of approximately 250 LF of trench drain at Bayport Container Terminal.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 – 4th Qtr. 2020 9122391430
• Concrete• Surveying
Jessica [email protected]
BCT - Fire Suppression System
The project consists of the preparation of detailed design of a water tank based fire suppression system at the Barbours Cut Terminal.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
1st Qtr. 2021 – 3rd Qtr. 2021 7202783034830739254292539
• Concrete Foundation• Plumbing Work• Electrical Installation• Pump House Repairs• Steel Tank Repairs
Bill Aguirre [email protected]
Bayport - Rehabilitation of Wharves 4 and 5
This project consists of strengthening the wharves 4 and 5 to accommodate taller cranes.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 - 2nd Qtr. 2021 91223914389097691430914009599095935
• Structural Concrete Repair• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography
Eddy Kharrazi [email protected]
Bayport - Construct Wharf 6, SSB #4 and Power
Construct new wharf, stevedore building and electrical infrastructure at Bayport Terminal Wharf 6 (approximately 600 linear feet).
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
4th Qtr. 2020 – 1st Qtr. 2023 9122390976912239136091316914509146890924
• Concrete• Plumbing• HVAC• Electrical
Derek [email protected]
Bayport - Container Yard 7 and TLT Yard Security
Provide security cameras, fiber optic cables, UPS, and network switches.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 – 4th Qtr. 2020 91316990002850091438
• Security cameras• Fiber optic cable• Network switches• Electrical
Bill Aguirre [email protected]
Bayport and Barbours Cut - Annual Wharf Crane & RTG Crane Painting - 2020
This project will consist of blasting, priming and painting the wharf cranes and RTG cranes on an "as needed" basis.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 – 4th Qtr. 2020 914849146192900
• Photography• Fuel Supplier• Portable Toilets
Derek [email protected]
Industrial Park East - Annual Pavement, Drainage and Dust Control 2020
Paving and repair of asphalt roads, ditch irrigation and spraying to off roads for dust control purposes.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 - 4th Qtr. 2020 9097691327
• Paving• Asphalt• Drainage
Derek [email protected]
Manchester - Rehabilitation and Repair of Wharf 2
Rehabilitating and repairing of Wharf M2 of approximately 600ft. to address issues in regards to slope stability, the structural decay and also to include the fender replacement.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
3rd Qtr. 2020 - 3rd Qtr. 2021 9148491223914389097691430
• Structural Concrete Repair• Fender Replacement• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography
Eddy Kharrazi [email protected]
Turning Basin North - Restrooms Restoration
Demolition and replacement of new restroom facilities at Northside Turning Basin including associated utility work.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
3rd Qtr. 2020 – 3rd Qtr. 2021 90924 9136091438 9143090976 9145091316 91468
• Electrical Work• Plumbing• HVAC• Building Fixtures & Finishes
Jessica [email protected]
Splash Zone Painting 2020
Painting and resurfacing of Steel Bulkhead walls to prevent corrosion and structural damage at Turning Basin North, South, and CARE Terminals
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
2nd Qtr. 2020 - 4th Qtr. 2020 91461914848100063159
• Painting • Steel Repair• Water blasting• Painting• Sandblasting
Derek [email protected]
Turning Basin North - Guardhouse and Arms Change (RR8 Speed Gate)
This project will remove existing Speed Gates and replace them with a Manned Guardhouse with Gate arms
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
4th Qtr. 2020 - 2nd Qtr. 2021 Contractors914739097692678
• Electrical • Fiber Optics• Demolition• Paving
Harvey [email protected]
Turning Basin - Transit Sheds 30-31 - Roof Repair
Roof repair at Transit Sheds 30/31.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
3rd Qtr. 2020 - 4th Qtr. 2020Contractors914739097692678
• Roofing Repair• Surveying
Harvey [email protected]
Turning Basin - Rehabilitation of Wharf 8
Rehabilitation of Wharf 8 at Turning Basin Terminal will consist of structural concrete repair and fender replacement.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
1st Qtr. 2021 – 3rd Qtr. 2021 Contractors90976912239143091438914849050591572
• Structural Concrete Repair• Fender Replacement• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography
Eddy Kharrazi [email protected]
Turning Basin South - City Dock 1 West Fender System
Designing a freestanding fender for City Dock 1 West of approximately 600ft.
Design Time Frame NIGP Codes Small Business Opportunities PHA Contact
1st Qtr. 2021 – 3rd Qtr. 2021 Contractors90976912239143091438914849050591572
• Structural Concrete Repair• Fender Replacement• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography
Eddy Kharrazi [email protected]
Turning Basin North – In-Depth Structural Assessment and Repair Design of Wharves 20, 21, 24, 25 and 26
Using information from FICAP to conduct in-depth inspection and then repair design of the wharves.
Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact
1st Qtr. 2021 – 3rd Qtr. 2021 Contractors90976912239143091438914849050591572
• Structural Concrete Repair• Fender Replacement• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography
Eddy Kharrazi [email protected]