DELOS NoE DELOS Network of Excellence on Digital Libraries Vittore Casarosa CNR-IEI, Pisa, Italy.
UP v Walfrido Delos Angeles
-
Upload
bangkamoon -
Category
Documents
-
view
232 -
download
1
Transcript of UP v Walfrido Delos Angeles
-
8/3/2019 UP v Walfrido Delos Angeles
1/6
Korea Technologies v LermaFacts:
Petitioner Korea (KOGIES) is engagedin the supply and installation of LPGcylinder manufacturing plants
Respondent, PGSMC is a domesticcorp
Both executed a contract whereKOGIES would set up a manufacturingplant while PGSMC would pay about$1,224,000 for machineries and$306,000 for installation
PGSMC also entered into a leasecontract with Worth
The machineries were delivered byKOGIES
However initial operations could notbe conducted as PGSMC encounteredfinancial problems but was able to
pay for the machines PGSMC issued to checks to cover for
the installation but both checksbounced bec payment was stopped.
KOGIES sent a demand letterthreatening criminal action
PGSMC complained that KOGIESdelivered a different brand from whatwas agreed; the checks were actuallyfunded but payments were stoppedbecause of this reason.
PGSMC informed KOGIES that it wasterminating the contract becauseKOGIES altered the quantity andlowered the quality of the equipment;It would dismantle and transfer themachineries
PGSMC then filed an estafa caseagainst KOGIES
KOGIES wrote PGSMC that it could notunilaterally rescind the contract nordismantle the facilities on imaginedviolations of KOGIES. Insisted on
settling dispute via arbitration asagreed upon in the arbitration clauseof the contract
PGSMC wrote back and stillthreatened to dismantle
This prompted KOGIES to institute anApplication for arbitration on theKorean Commercial Arbitration Board(KCAB)
KOGIES filed a complaint for specificperformance in RTC Muntinlupa. Italleged that PGSMC had conflictingreasons for the stopped payment andPGSMC cannot simply rescind thecontract.
PGSMC averred that the arbitration
clause was null and void because itousts the local courts of jurisdictionover the controversy
RTC: Ruled in favor of PGSMC; There is noreason to restrain PGSMC from dismantlingthe machineries
PGSMC filed a Motion for Inspection todetermine the alterations of quantityand lowering of quality
RTC: Ruled in favor of PGSMC granted the
motion for inspection and denied KOGIESMR
While waiting for the resolution of theMR pn the granting of motion ofinspection, KOGIES went to CA
RTC: Ruled on the issue and decided againstKOGIES; directed sheriff to conductinspection
Kogies informed CA about the RTC
order and claimed that the sheriffdidnt have the technical skills toascertain the facts required
The sheriff submitted his reportedand found that the machineries werenot fully installed
CA; AFFIRMED RTC and declared thearbitration clause to be against publicpolicy; the machineries were already fullypaid
ISSUE 1 Procedural2 WON the arbitration clause was valid
SC: 1 I will skip on the procedural issues
2. Article 15 of the contract on arbitration isnot null and void.
-
8/3/2019 UP v Walfrido Delos Angeles
2/6
Lex loci contractus the contract wasperfected here in the Phils therefore,our laws govern.
The clause was mutually andvoluntarily agreed upon; it is notcontrary to law, or against moral
In Gonzales vs Climax it was held
that: submission to arbitration is acontract and that a clause providingthat all matters in dispute shall bereferred to arbitration is a contract.
ARBITRATION CLAUSE IS NOTONTRARY TO PUBLIC POLICY theclause provides that arbitration bedone in Korea and that the arbitralaward is binding
RA 9285 incorporated the UNCITRALModel Law to which we are asignatory. For domestic arbitration,
we have particular agencies toarbitrate disputes arising fromcontractual relations. In case of aforeign arbitral body is chosen, weare committed to the Model Law
Among the pertinent features of RA9285 applying and incorporating theUNCITRAL Law are:
1. RTC must refer to arbitration inproper cases
2. Foreign arbitral awards mustbe confirmed by RTC they are
binding but not immediatelyenforceable. Sec 35 of UNCITRAL Law stipulates thatthe arbitral award to berecognized by a competentcourt for enforcement; It isclear that foreign arbitralawards when confirmed by theRTC are deemed not as a
judgment of a foreign court butas a foreign arbitral award, andwhen confirmed, are enforced
as final and executor decisionsof our courts of law.
3. RTC has jurisdiction to reviewforeign arbitral awards to setaside, reject or vacate aforeign award; Foreign awardswhile binding do not oust thecourts of jurisdiction as they
are not absolute and withoutexceptions as they are still
judicially reviewable4. Grounds for judicial review
different in domestic andforeign awards
5. RTC decision of assailedforeign award appealable tothe CA and thereafter SC
PGSMC has remedies to protect itsinterest
Unilateral rescission improper aparty may not unilaterally rescind thecontract for whatever cause withoutfirst resorting to arbitration
In this case, there was ACOMMITMENT TO ARBITRATE
There was grave abuse of discretionin allowing the inspection of things as
the matter should be subject toarbitration; besides, sheriff is nottechnically competent
RTC still has interim jurisdiction toprotect the rights of the parties it isnot incompatible with an arbitrationagreement to prevent fromirreparable loss
Interim measure (UNCITRAL) is anytemporary measure to maintainstatus quo, preserve asset, preserveevidence
Pendency of arbitral proceedingsdoes not foreclose resort to courts forprovisional measures
HELD: PARTLY GRANTEDParties are ordered to submit themselves toarbitrationPGSMC is allowed to dismantle
UP v Walfrido Delos AngelesF:
The land in question is a grant ofendowment to UP.
UP an ALUMCO entere into a loggingagreement extenible by 5 yrs to cutan collect timber from the land inconsideration of payment to UP ofroyalties, forest fees
-
8/3/2019 UP v Walfrido Delos Angeles
3/6
ALUMCO incurred an unpaid accountof php 219,362.94, several demandswere made by UP
After receiving a notice to rescind thelogging agreement, ALUMCOexecuted an Acknowledgement ofDebt and Proposed manner of
payments which was approved by thePresident of UP, it had a stipulationthat should ALUMCO fail in itsobligation, UP has the right to rescindthe agreement without the necessityof any judicial suit
ALUMCO continued with theoperations but failed to pay again
UP informed ALUMCO that it hadconsidered the agreement ineffectivean file a case against ALUMCO in CFI(QC) for collection or payment
Before the issuance of the preliminaryinjunction, UP took on anotherconcessionaire for the logging ops byadvertising an invitation to bidwhich was eventually awarded to StaClara
ALUMCO filed motions to dischargethe writsof attachment and preliminjunction but were denied by CT
ALUMCO filed another petition toenjoin UP from conducting biding andawarding rights to another company
UP received the order after itconcluded its contract with STa Clara
On motion of ALUMCO and Jose Rico,the CT declared UP in contempt andin the same order prohibited StaClara from exercising its loggingrights
UPs MR DENIED
ALUMCO gave several excuses as towhy it failed on its obligation Itsformer general manager, Cesar Guy
did not turn over management; thelogs turned out to be rotten;
It also contended the UPs unilateralrescission of the contract without a ctorder was invalid
ISSUE: WON UP can treat its contract withALUMCO rescinded and may disregard thesame
SC: Ruled IFO of UP
It was ALUMCO that expresslystipulated in the Acknowledgement ofDebt that UP has the right to rescindthe contract without the necessity of
judicial suit
Such stipulation in connection withArt 1191 of the civil code is valid:THERE IS NOTHING IN THE LAW THATPROHIBIT THE PARTIES FROMENTERING INTO AGREEMENT THATVIOLATION OF THE TERMS OFCONTRACT WOULD CAUSECANCELLATION THEREOF EVENWITHOUT COURT INTERVENTION(Froilan V Pan Oriental Shipping)
The party who deems the contractviolated may consider it rescinded
and act accordingly, without previouscourt action, but it proceeds at itsown risk. FOR IT IS ONLY THE FINAL
JUDGMENT OF THE CORRESPONDNGCOURT THAT WILL CONCLUSIVELYSETTLE WHETHER THE ACTION TAKENWAS OR WAS NOT CORRECT IN LAW.
The contracting party who finds itselfinjured must file a suit; in case ofabuse and error by rescinder, theother party is not barred fromquestioning the act in court
Besides, ALUMCOs excuses for notbeing able to pay is not sufficient.
HELD: Writ of Certiorari granted. LOWERCOURTS ORDER SET ASIDE
Mindanao Portland v McDonoughF:
Mindanao Portland and McDonoughexecuted a contract for theconstruction for a dry Portland
In a separate contract, Turnbull incwas engaged to design and manageconstruction of the plant, superviseconstruction etc
Alterations were made during theprogress of the construction so anextension for termination of projectwas initially agreed
-
8/3/2019 UP v Walfrido Delos Angeles
4/6
Respondent completed the project in1962 except the delivery of certainspare parts
Differences later arose. Petitionerclaimed from respondent damagesfor 2M bec of the delay in the projectscompletion.
Mc (Respondent) in turn asked formore than 450,000 for losses to costof extra work
A conference was held bet MindanaoPort (Petitioner) and Turnbull Inc andRespondent on the other but nosatisfactory results were reached
Petitioner sent respondent letters toarbitrate invoking the provision intheir contract regarding arbitration ofdisputes
Instead of answering said invitations,
Respondent with Turnbulls approval,submitted to Petitioner for paymentits final statement of work and askedfor the unpaid balance
Petitioner filed with CFI to compelRespondent to arbitrate ; It averredthat the deletions and additional tothe plans and specifications wereagreed upon during the progress ofthe construction, that disagreementarose bec of the cost of the additionalwork to be done and respondents
deviation from some agreedspecifications
Respondent filed answer and deniedthat there were disagreement. Itsclaim of 403,700 was not disputedand that claims for damages shouldbe resolved by Turnbull pursuant tothe exception in the arbitration clauseof the construction contract
Lower Ct: found that the Dispute betweenthe parties should be submitted toarbitration pursuant to par 39 of saidcontract
Respondent appealed to SC
ISSUE: WON the parties are duty bound tosubmit to arbitration
In the provision of the contract onArbitration of disagreements thereare questions to be determined bythe engineer, respondents contentthat there is no showing of disagreement
SC: the fact of disagreement has beendetermined by the court below upon thestipulation of facts and documentaryevidence
The duty of the court in this case isnot to resolve the merits of the claimsbut to determine if they shouldproceed to arbitration.
HELD: SUBMIT TO ARBITRATION
La Naval v CA, YaoFacts:
Yao alleged interference and dilatorytactics vs La Naval in theimplementation of the Arbitrationagreement in the contract of lease
Yao owns a commercial bldg. leasedby La Naval
La Naval exercised its option to leasethe same bldg. for another 5 yrs butthey disagreed on the rate
Yao, through notice expressed his
intent to submit to arbitration asprovided for in their contract of lease
Yao appointed Alamarez and LaNaval, Sabile but the confirmation ofthe 3rd arbitrator was held inabeyance bec the same should bedecided by the BOD of La naval
Yao prayed for the summary hearingand for Sabile and Alamarez toproceed with arbitration
LaNaval: the petition is prematurebec Yao hasnt formally requiredarbitrators to agree on the 3rd within10 days of notice (KASALANAN ni
YAO)
Yao filed an amended petition forenforcement of arbitration agreementwith damages praying that La Navalpay interest on unpaid rents
-
8/3/2019 UP v Walfrido Delos Angeles
5/6
Respondent CT admitted theamended petition
CT announced that the 2 arbotratorschose Narciso as 3rd arbit and orderedparties to submit their position paper
CA agreed with petitioner that ct maydetermine the issue of whether the litigants
should proceed or not to arbitration, butpetitioner is in estoppel from questioningthe competence of the ct to hear and decidethe summary proceedings having itself filedits own counterclaim
Lack of jurisdiction over the person of thedefendant may be waived expressly orimpliedly. When the defendant voluntarilyappears, he is deemed to have submittedhimself to the juris of the ct. Where thedefendant invoked an affirmative relief, he
is deemd to have submitted himself to the juris of the ct. VOLUNTARY APPEARNCECURES DEFECTS OF SUMMONS
Doctrine of estoppel: to avoid clearinjustice
CA must refrain from taking up claimsof the contending parties
MAGELLAN V ZOSAN:F: Magellan Holdings appointed MagellanCapital as manager of its operations
MH and MC entered into am elpoymentcontract with Zosa (Pres and CEO)
The employment agreement states thethe term of Zosa is co terminous with themanagement agreement or soonerterminated; grounds of termination areprovided
MCs BoD decided not to re electrespondent Zosa as Pres on account ofloss of trust and confidence violation ofresolution issued by MC and of the non-competition clause
However, Zosa was elected as MCs ViceChair for New Ventures
Zosa communicated his resignation asVice Chair on the ground that the positionhas less responsibility. He demanded fortermination benefits
MC did not accept the resignation ofZosa for good reason but instead theagreement is terminated for a cause
Zosa invoked the arbitration clause ofthe agreement
Zosa designate his bro as rep in panelwhile MH designated Atty Fojas and MH
Atty Quiason. Instead of submitting to arbitration,Zosa filed an action for damages vs MCand MH before RTC Cebu
RTC: Denied the Motion to Dismiss of MCand MH
1. The validity of the arbitrationprovisioncan only be determined aftertrial on the merits
2. The amount of damages falls withinthe jurisdiction f RTC
MR Denied It directed petitioners to file
responsive leading
MC and MH filed a petition with CA
CA: Gave due course to petition anddirected RTC to resolve issue on the validityof arbitration clauseDenied Motion for Reconsideration
RTC: in compliance with the CA decision
rendered a decision declaring the arbitrationclause partially void and of no effect in sofar as the composition of the panel ofarbitrators
ISSUE: 1.WON SEC has jurisdiction? NO
SC: 1. SEC doesnt have jurisdiction. Itdoesnt involve lection/appointment ofofficers
When the CA affirmed he trial courtsassumption of jurisdiction over the case
has become law of the case
Oil and Natural Gas vs CA
Oil is a foreign corp (India) dulyorganized in the Phils
Conflict between Oil and Pacific hasroots in a contract entered into by
-
8/3/2019 UP v Walfrido Delos Angeles
6/6
both. Pacific to supply oil well cementand Oil to pay
But there was delay in the delivery.Oil had already paid. There was also adispute as to the lcass of the material
Oil informed Pacific that it wasreferring its claim to an arbitrator
(sole arbitrator appointed to memberof the commission, venue ofarbitration shall be in India)
The chosen arbitrator Malhotraresolved for Pacific to pay andreimburse expenditure
TO enable Oil to execute the award, itfiled a petition for the