UNITED STATES COURT OF APPEALS FOR THE TWELFTH …Team No. 45 Case Nos. 14-000123, 14-000124 UNITED...
Transcript of UNITED STATES COURT OF APPEALS FOR THE TWELFTH …Team No. 45 Case Nos. 14-000123, 14-000124 UNITED...
Team No. 45
Case Nos. 14-000123, 14-000124
UNITED STATES COURT OF APPEALS
FOR THE TWELFTH CIRCUIT
SYLVANERGY, LLC,
Petitioner,
v.
SHANEY GRANGER, in her official capacity as
Regional Administrator for Region XIII of the United States Environmental Protection Agency,
Respondent.
AND
SAVE OUR CLIMATE, INC.,
Petitioner,
v.
SHANEY GRANGER, in her official capacity as
Regional Administrator for Region XIII of the United States Environmental Protection Agency,
Respondent.
Consolidated Petitions for Review of an EPA Regional Administrator’s Final Order
PSD Appeal No. 15-0123
BRIEF OF PETITIONER, SAVE OUR CLIMATE, INC.
i
TABLE OF CONTENTS STATEMENT OF JURISDICTION 1.
ISSUES PRESENTED 1.
STATEMENT OF THE CASE 2. STANDARD OF REVIEW 3. SUMMARY OF THE ARGUMENT 4. ARGUMENT 5. I. This Court Does Not Need Jurisdiction Over the New Union Air Resources Board’s
Determination that Sylvanergy Required a PSD Permit. 5. A. Pursuant to Section 307(b), the Court Does Not Have Jurisdiction to Review a
State Agency’s Jurisdictional Determination. 7.
II. Sylvanergy’s Wood Pellet Production Facility is a Major Emitting Facility and Therefore Requires a Preconstruction PSD Permit. 7.
A. As a Fuel Conversion Plant that Would Emit 100 tons per year of Pollutants,
Sylvanergy’s Pellet Production Facility is a Major Emitting Facility. 7. B. Sylvanergy’s Facility is a Major Emitting Facility Because it has the Potential to
Emit 250 tons per year of a Pollutant. 9.
III. Biomass-fueled facilities are subject to PSD review as emitters of greenhouse gases. 10.
A. EPA’s Deferral Rule is defunct and would not exempt the Forestdale Biomass Facility even if it were in effect. 13.
B. The potential for carbon neutrality is not a relevant consideration in deciding
whether PSD review applies to a stationary source. 13.
IV. Wood Gasification and Partial Carbon Capture and Storage deserved consideration as BACT. 14.
A. Because wood gasification and partial CCS would not alter Forestdale Biomass
Facility’s fundamental purpose, the technologies should have been considered as BACT. 16.
ii
B. The plain language definition of Best Available Control Technology under the Clean Air Act allows for consideration of wood gasification and partial carbon capture and storage. 17.
V. EPA Cannot Use Reforestation as BACT. 18.
CONCLUSION 20.
iii
TABLE OF AUTHORITIES Cases Ctr. for Biological Diversity v. E.P.A.,
722 F.3d 401 (D.C. Cir. 2013) 11, 12. Chemical Mfrs. Ass’n v. EPA,
1995 WL 650098 (D.C. Cir. Sept. 15, 1995) (unpublished) 8. Citizens to Preserve Overton Park, Inc. v. Volpe,
401 U.S. 402 (1971) 4. Fairbanks North Star Borough v. United States Army Corps of Engineers,
543 F.3d 586 (9th Cir. 2008) 5, 6. Harrison v. PPG Industries, Inc.,
446 U.S. 578 (1980) 1. Hawkes Co. Inc., v. United States Army Corps of Engineers,
782 F.3d 994 (8th Cir. 2015) 6. Nat’l Min. Ass’n v. United States EPA,
59 F.3d 1351, (D.C. Cir. 1995) 8.
Puerto Rican Cement Co., Inc. v. United States EPA, 889 F.2d 292 (1st Cir. 1989) 5, 6.
In Re: Energy Answers Arecibo, LLC (Arecibo Puerto Rico Renewable Energy Project), 13-09, 2014 WL 1260977 (E.P.A. Mar. 25, 2014) 12. Sierra Club v. Slater,
120 F.3d 623 (6th Cir. 1997) 3. Sierra Club v. United States E.P.A.,
499 F.3d 653 (7th Cir. 2007) 15, 16. Sierra Club v. United States EPA,
762 F.3d 971 (9th Cir. 2014) 1. Utah Chapter of Sierra Club v. Air Quality Bd.,
226 P.3d 719 (Ut. 2009) 16. Util. Air Regulatory Grp. v. EPA,
134 S. Ct. 2427 (2014) 2, 11.
iv
Upper Blackstone Water Pollution Abatement Dist. v. United States EPA, 690 F.3d 9 (1st Cir. 2012) 3, 4.
Vidisksis v. EPA, 612 F.3d 1150 (11th Cir. 2010) 3. Weiler v. Chatham Forest Products, Inc.,
392 F.3d 532 (2d. Cir. 2004) 9. Statutes 42 U.S.C. § 7475(a)(1) 1, 11. 42 U.S.C. § 7475(a)(4) 15. 42 U.S.C. § 7479(1) 1, 4, 7, 11. 42 U.S.C. § 7479(3) 15, 18-19. 42 U.S.C. § 7602(a), (b) 6. 42 U.S.C. § 7602(k) 19. 42 U.S.C. § 7607(b)(1) 1, 6. Federal Register Deferral for CO2 Emissions From Bioenergy and Other Biogenic Sources Under the Prevention of Significant Deterioration (PSD) and Title V Programs,
76 Fed. Reg. 43490-01 11. Approval and Promulgation of Implementation Plans; Washington: Prevention of Significant Deterioration and Visibility Protection,
80 Fed. Reg. 23721-01 12.
1
STATEMENT OF JURISDICTION
Save Our Climate, Inc. (SOC) seeks judicial review of a final decision of Shaney
Granger, Regional Administrator of the United States Environmental Protection Agency (EPA)
for Region XIII. Regional Administrator Granger, granted Sylvanergy a Prevention of
Significant Deterioration (PSD) preconstruction permit pursuant to section 165 of the Clean Air
Act (CAA). 42 U.S.C. § 7475(a)(1). Sylvanergy proposes to construct an electric generating
facility near Forestdale, New Union.
As a United States Court of Appeals, this Court has exclusive jurisdiction to review
actions enumerated in section 307(b)(1) of the CAA and “any other final action of the
Administrator… which is locally or regionally applicable.” 42 U.S.C. § 7607(b)(1). The phrase,
“‘any other final action’… mean[s] exactly what it says.” Harrison v. PPG Industries, Inc., 446
U.S. 578, 589 (1980). Circuit courts review decisions to issue PSD permits pursuant to 42 U.S.C.
§ 7607(b)(1). See e.g. Sierra Club v. United States EPA, 762 F.3d 971, 975 (9th Cir. 2014). The
Regional Administrator’s decision to grant Sylvanergy a PSD permit for the Forestdale facility is
a locally applicable final action. SOC’s actions during the administrative process were timely.
For those reasons, this Court has jurisdiction to review the PSD permit.
ISSUES PRESENTED
1. When a party requests and receives a PSD preconstruction permit for a new source under the Clean Air Act, does this Court have jurisdiction to review an earlier determination by a state agency that the source was required to apply for a preconstruction permit, or is the issue of the Court’s jurisdiction over the earlier decision moot because the party received a final PSD permit over which the Court has jurisdiction?
2
2. Is Sylvanergy’s proposed biomass-fueled electric generation and wood pellet production facility a major emitting facility subject to PSD review for either or both of the following reasons: (a) the facility emits 100 tons per year or more of a pollutant and qualifies as a source listed under 42 U.S.C. § 7479(1), or (b) because restrictions on the facility’s hours of operation imposed by a municipality are not practicably enforceable and therefore the facility has the potential to emit 250 tons per year or more of a pollutant? 3. Whether a biomass-fueled facility that emits CO2 and is subject to PSD requirements for other pollutants must, consistent with the Supreme Court’s decision in Util. Air Regulatory Grp. v. EPA, 134 S. Ct. 2427 (2014), apply the best available control technology (BACT) to its CO2 emissions? 4. Whether the New Union Air Resources Board erred by failing to consider partial carbon capture and storage as BACT for Sylvanergy’s CO2 emissions? 5. Whether a forest plan that involves replanting trees but does not limit emissions from the facility and allows pollutants to accumulate in the atmosphere can qualify as a limitation of emissions for the purposes of BACT?
STATEMENT OF THE CASE
This case asks the Court to review the extent of EPA’s obligation under the Clean Air
Act’s prevention of significant deterioration program to limit the amount of CO2—a greenhouse
gas pollutant—emitted from facilities like Sylvanergy’s that burn biomass (tress and wood).
Sylvanergy’s proposed facility in New Union is capable of burning 150,000 tons of biomass fuel
per year to power a wood pellet production plant. Record at 5 (hereafter “R.”). The facility
would have 40 MW electric generation capacity. Id. Among other pollutants regulated under the
CAA, Sylvanergy’s pellet production plant has the capacity to release 110 tons per year of NOx
and 255 tons per year of CO. R. at 5. Running at maximum—96 percent—capacity, the facility
would emit 350,000 tons of CO2 equivalents per year (hereafter CO2 or carbon pollution). Id.
As part of its sight plan approval from the village of Forestdale, Sylvanergy agreed to
operate the production facility no more than 6,5000 hours per year. Id. This limitation can be
3
enforced by the village’s building inspector. Id. If followed, the hours per year limitation would
limit to facility to 75 percent capacity. Other than CO and CO2, facility would emit less than 100
tons per year of other regulated pollutants under the 6,500 hours per year limitation. Id. Even
with this limitation, however, the facility would emit 190 tons per year of CO. Id.
Sylvanergy initially requested, and was denied, a PSD non-applicability determination
(NAD) from the New Union Air Resources Board (NUARB). A non-applicability determination
is a statement by the NUARB that Sylvanergy’s pellet production facility would not need a PSD
permit. The NUARB asserted that the proposed facility required a PSD permit. Sylvanergy did
not appeal NUARB’s determination or ask the EPA for a determination.
Sylvanergy then applied for a PSD permit. NUARB issued a draft permit, and SOC
submitted public comments. NUARB issued the PSD permit to Sylvanergy on June 12, 2014.
The PSD permit determined BACT for the facility’s pollutants, including CO2. The NUARB
determined that a sustainable forest plan was the most appropriate form of BACT for CO2. The
NUARB rejected SOC’s assertion that NUARB must consider carbon capture and storage in its
evaluation of BACT for CO2 emissions. R. at 6-7. Both SOC and Sylvanergy filed
administrative petitions for review on July 10, 2014. On June 1, 2015, the EAB denied the
appeals and directed the Region XIII Administrator to publish notice of the decision in the
Federal Register.
STANDARD OF REVIEW
Upon review of an EAB decision, this Court reviews the entire agency action—that is,
both the regional permitting decision and the EAB’s review of the decision. Upper Blackstone
Water Pollution Abatement Dist. v. U.S. EPA, 690 F.3d 9, 20 (1st Cir. 2012). Under the APA, an
administrative determination should be set aside only if the petitioner can show that it is
4
arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with the law.” Sierra
Club v. Slater, 120 F.3d 623, 632 (6th Cir. 1997). In conducting that evaluation, courts must
consider whether the decision was based on “a consideration of the relevant factors and whether
there has been a clear error of judgment.” Vidisksis v. EPA, 612 F.3d 1150 (11th Cir. 2010)
(quoting Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 416 (1971)). An agency
cannot rely on factors which Congress has not intended it to consider, fail to consider an
important aspect of the problem, or offer an explanation for its decision that runs counter to the
evidence before the agency or is so implausible that it could not be ascribed to a difference in
view or the product of agency expertise. Upper Blackstone, 690 F.3d at 20.
SUMMARY OF THE ARGUMENT SOC first argues that the Court does not need to determine whether it has jurisdiction
over NUARB’s decision to reject Sylvanergy’s request for a non-applicability determination.
The NUARB asserted that it had jurisdiction over Sylvanergy’s proposed pellet production
facility under the PSD permitting program for new sources. Because Sylvanergy responded by
applying for a PSD permit, this Court has jurisdiction over the final permit. The Court does not
need jurisdiction over the NUARB’s initial determination to determine whether Sylvanergy was
required to obtain a PSD permit. Therefore the issue of whether an appellate court can review the
NUARB’s applicability determination is moot.
Next, SOC argues that Sylvanergy’s proposed pellet production facility is a major
emitting facility subject to PSD permitting requirements. Because the facility converts biomass
into pellets it qualifies as a fuel conversion facility and is therefore subject to the100 ton per year
threshold for major sources under 42 U.S.C. § 7479(1). SOC also argues that, regardless of the
5
6,500 hour per year operating limitation, the facility has the potential to emit more than 250 tons
per year of CO and is therefore a major emitting facility. Because the operating limitation are not
enforceable by a State or a local pollution control agency, and because the limitation does not
contain monitoring or reporting requirements, the 6,500 hours per year operating limit is not an
effective limitation for the purposes of the Act. The operating limit does not reduce the facility’s
emissions below the 250 ton per year threshold.
SOC argues that the NUARB was correct when it determined that biomass facilities can
qualify for PSD permits. The fact that trees can be regrown does not change the fact that burning
biomass as fuel generates pollutants, including CO2. SOC then argues the NUARB erred by
dismissing carbon capture and storage as BACT for CO2. Finally, SOC argues that the NUARB
erred when it considered reforestation as a BACT. Reforestation does not actually limit a
facilities emissions. And, in the lag time between the release of CO2 and CO2 uptake by growing
trees, the CO2 poses a threat to the environment. NUARB erred by failing to consider the
ineffectiveness of reforestation as BACT for CO2 emissions.
ARGUMENT I. This Court Does Not Need Jurisdiction Over the New Union Air Resources Board’s
Determination that Sylvanergy Required a PSD Permit.
The issue of whether the Court has jurisdiction to review the NUARB’s applicability
determination is moot. In this context, the purpose of seeking review of an agency’s
determination of its own jurisdiction is to determine whether the agency does in fact have the
authority to require a preconstruction permit. In Puerto Rican Cement Co., Inc. v. United States
EPA and Fairbanks North Star Borough v. United States Army Corps of Engineers, the
6
complaining parties wanted to avoid obtaining preconstruction permits. Puerto Rican Cement,
889 F.2d 292 (1st Cir. 1989) (PSD permit); Fairbanks, 543 F.3d 586 (9th Cir. 2008) (Clean
Water Act 404 permit). The threshold issue—decided differently in each case—was whether an
agency’s jurisdictional determination was a final agency action for the purpose of judicial
review.
Here, the Court can avoid the morass of the current circuit split. Compare Fairbanks, 543
F.3d 586 (9th Cir. 2008) (no jurisdiction over agency determination) to Puerto Rican Cement,
889 F.3d 292 (1st Cir. 1989) (court has jurisdiction) and Hawkes Co. Inc., v. United States Army
Corps of Engineers, 782 F.3d 994 (8th Cir. 2015) (same). Unlike the courts in Puerto Rican
Cement and Fairbanks, this Court does not need to determine whether an applicability
determination does or does not have legal consequences in the context of preconstruction
permitting. Simply put, the Court does not need jurisdiction over the NUARB’s applicability
determination to decide whether Sylvanergy’s facility requires a PSD permit.
Unlike circumstances in Puerto Rican Cement and Fairbanks, in which the complaining
parties sought judicial review of agency determinations before they obtained preconstruction
permits, Sylvanergy applied for and received a PSD permit. The procedural posture of this case
makes the question of this Court’s jurisdiction over NUARB’s applicability determination
immaterial. This Court has jurisdiction to review a final PSD permit. Therefore, the Court has the
ability to determine whether and to what extent Sylvanergy’s proposed facility is a major source
subject to the CAA preconstruction permitting process.
7
A. Pursuant to Section 307(b), the Court Does Not Have Jurisdiction to Review a State Agency’s Jurisdictional Determination.
Even if the Court decided that NUARB’s determination was final for the purposes of
judicial review, the Court does not have jurisdiction to review the decision. In this case, a state
agency—not the Administrator of the EPA—made the applicability determination. This Court’s
jurisdiction extends only to review of “final action[s] of the Administrator.” 42 U.S.C. § 7607(b)
(emphasis added). “Administrator” means “the Administrator of the Environmental Protection
Agency.” Id. at 7602(a). The term “Administrator” does not include a state “air pollution control
agency,” like the NUARB. Id. at 7602(b). For the purposes of judicial review under section
307(b), the NUARB does not stand in the stead of the EPA, and this Court does not have the
ability to review the state agency’s decision.
II. Sylvanergy’s Wood Pellet Production Facility is a Major Emitting Facility and Therefore Requires a Preconstruction PSD Permit.
A. As a Fuel Conversion Plant that Would Emit 100 tons per year of Pollutants,
Sylvanergy’s Pellet Production Facility is a Major Emitting Facility.
Sylvanergy’s proposed wood pellet production facility qualifies as a fuel conversion
plant. Fuel conversion plans that emit 100 tons per year of any pollutant qualify as major
emitting facilities. 42 U.S.C. § 7479(1). Powered by the biomass-fired electricity generation unit,
8
the plant would produce fuel pellets from compressed and “densified” wood.1 The production
facility would emit more than 100 tons per year of pollutants regulated under the CAA.
Neither the statute nor the relations define fuel conversion plant. EPA relies on case-by-
case determination of the source category. According to EPA guidance, “applicability for [the
fuel conversion plant] source category is determined by whether a facility changes the state (e.g.,
solid to gas) or form (e.g., process sawdust into a pellet) of a fuel.”2 In this case, the pellet
production facility changes the form of woody biomass from bulk biomass (trees) into pellets.
The production process shows why pellets are distinct from the bulk biomass. Pellets are
a refined product that requires processing. State Bioenergy Primer at 20. Pellets are made of
biomass feedstock that is dried in dryers, ground to size, and further conditioned to remove
moisture before being compressed into pellet form. Wood Pellet Basics.3 The end product is
different than the feedstock, both in form and function. Pellets are more dense, which increases
their energy per unit of weight, and they have a reduced and uniform moisture content. State
Bioenergy Primer at 20. For these reasons, pellets are a more expensive and energy dense fuel
than bulk biomass. Id.; Wood Pellet Basics. Pellets’ higher energy density, low moisture content,
and uniformity allow them to compete with other fuels like oil and propane. State Bioenergy
Primer at 20. These qualities also allow pellet to be used with automated systems. Unlike wood,
pellets are a specialized fuel intended for use with specialized boilers and stoves.
1 State Bioenergy Primer, Chapter 2 “What is Bioenergy” at 20 (hereafter “State Bioenergy Primer) (explaining densification and wood pellet production) (available at www3.epa.gov/statelocalclimate/documents/pdf/bioenergy_chapter2.pdf). 2 Letter from Edward J. Lillis, Chief Permits Programs Branch to George T. Czerniak, Chief Air Enforcement Branch, Region V, re: applicability determination of PSD for Cleveland Electric Inc. Plant in Willoughby, Ohio, May 26, 1992 at 3 (emphasis added). 3 Breakout in Developing a Wood Pellet/ Densified Biomass Industry in Washington State: Opportunities and Challenges; A Report to the Washington State Legislature December 2012. Washington State University Extension Energy Program at 11.
9
The difference in form and energy density means that wood and pellets are not
interchangeable fuels. Sylvanergy’s pellet production facility actively transforms bulk biomass
like trees into a specialized fuel with a new form. For that reason, Sylvanergy’s facility qualifies
as fuel conversion plant. The EPA and Sylvanergy are wrong when they assert that the 100 ton
per year threshold does not apply to a pellet production plant.
B. Sylvanergy’s Facility is a Major Emitting Facility Because it has the Potential to Emit 250 tons per year of a Pollutant.
Sylanergy’s proposed wood pellet production facility also qualifies as a major source
because it has the “potential to emit” 250 tons per year of a pollutant. 42 U.S.C. § 7479(1). After
the D.C. Circuit’s decision in Nat’l Min. Ass’n v. United States EPA, the D.C. Circuit vacated
EPA’s regulations that define “potential to emit.” Nat’l Min. Ass’n, 59 F.3d 1351, (D.C. Cir.
1995); Chemical Mfrs. Ass’n v. EPA, 1995 WL 650098 (D.C. Cir. Sept. 15, 1995) (unpublished)
(vacating regulation for PSD and Title V permits). In 1996, EPA published an interim policy. For
the purpose of determining a facility’s potential to emit, EPA will consider a limitation on a
facility’s operation as a reduction in the facility’s potential to emit if the limitation is “federally
enforceable or legally and practicably enforceable by a state or local air pollution control
agency.” EPA Interim Policy on Federal Enforceability Requirement for Limitations on Potential
to Emit, at 3-4 (January 22, 1996). A facility that is physically capable of emitting 250 tons per
year will be “considered a major emitting facility… unless there are legally and practically
enforceable mechanisms in place to make certain that the emissions remain below the relevant
levels.” Weiler v. Chatham Forest Products, Inc., 392 F.3d 532, 535 (2d Cir. 2004).
10
In this case, the limitation on Sylvanergy’s proposed pellet production facility is not
legally or practically enforceable by a state or local air pollution control agency. The local
municipality—the Village of Forestdale—is neither a state nor a local pollution control agency.
Sylvanergy has also failed to show that the limit on the hours of operation is practically
enforceable. The record does not disclose if Sylvanergy will report its hours of operation or how
the municipality will monitor and ensure compliance. The bare assertion that a building inspector
can enforce an ordinance does not make certain that enforcement will occur or that emissions
will remain below the relevant levels.
Because the operating limitations are not practically enforceable and cannot be enforced
by the State of New Union or a local pollution control agency, the facility must be considered a
major source for the purpose of obtaining a PSD permit. The pellet production facility is
physically capable of emitting 250 tons of regulated pollutants per year or more. Sylvanergy has
failed to show that any mechanisms are in place to make certain that emissions would remain
below the 250 ton per year threshold. The NUARB was correct to require a PSD permit for
Sylvanergy’s pellet production plant.
III. Biomass-fueled facilities are subject to PSD review as emitters of greenhouse gases.
Sylvanergy has not shown that the EAB erred in affirming NUARB’s decision to subject
the FBF to PSD review as a biogenic stationary source of greenhouse gases. In support of its
position, Sylvanergy simply relies on a defunct deferral rule and an uninspiring policy argument
that is neither statutorily justified nor logically sound. As a result, the Court should affirm the
EAB’s decision on this matter.
11
Under the Clean Air Act (“the Act”), parties wishing to construct a major emitting
facility in a NAAQS attainment area must obtain preconstruction approval in the form of a
Prevention of Significant Deterioration (PSD) permit. 42 U.S.C. § 7475(a). The Act defines
major emitting facilities as stationary sources of air pollutants that emit (or have the potential to
emit) more than the statutory threshold of “any air pollutant.” 42 U.S.C. § 7479(1). The air
pollutants referenced are not limited to those criteria pollutants for which NAAQS have been
established, but include each pollutant subject to regulation under the Clean Air Act. See Util.
Air Regulatory Grp. V. EPA, 134 S. Ct. 2427 (2014). Carbon dioxide, a potent greenhouse gas, is
an air pollutant subject to regulation under the Act. See id at 2436-37. In the wake of
Massachusetts vs. EPA (Supreme Court ruling that EPA could regulate greenhouse gases under
the Act), the EPA promulgated regulations to curb tailpipe carbon dioxide emissions. Id at 2437.
That regulatory action triggered EPA’s subsequent regulation of stationary sources of
greenhouse gases through the existing PSD permitting program. Id.
Shortly thereafter, EPA deferred regulation of biogenic stationary sources for three years
(the “Deferral Rule”), from July 2011 through July 2014, citing scientific uncertainty over how
to account for biogenic greenhouse gases’ unique role in the carbon cycle. Ctr. for Biological
Diversity v. E.P.A., 722 F.3d 401 (D.C. Cir. 2013); Deferral for CO2 Emissions From Bioenergy
and Other Biogenic Sources Under the Prevention of Significant Deterioration (PSD) and Title
V Programs, 76 Fed. Reg. 43490-01. The deferral rule postponed PSD review of biogenic carbon
dioxide sources that had the potential to emit over the statutory thresholds, but still allowed
regulation of biogenic sources that were "anyway" sources (that is, they would be subject to PSD
review anyway for another regulated pollutant). Ctr. for Biological Diversity, 722 F.3d at 407. In
12
2013, the District of Columbia Circuit rejected the deferral rule before it would have expired on
its own terms. See id.
Since 2010, the EPA has solicited stakeholder input regarding its eventual long-term
approach to regulating biogenic carbon dioxide sources. Janet G. McCabe, Addressing Biogenic
Carbon Dioxide Emissions from Stationary Sources (Nov. 19, 2014), (available at
http://www3.epa.gov/climatechange/downloads/Biogenic-CO2-Emissions-Memo-111914.pdf.)
In a 2014 memo, the agency stated its intent to exempt some biogenic carbon dioxide sources
from PSD review in the future. Id. Under that scheme, stationary sources that employ waste-
derived feedstocks or non-waste feedstocks derived from sustainable forest or agricultural
practices would be exempt. Id. However, EPA has not yet implemented those exemptions, so
stationary sources of biogenic carbon dioxide are currently subject to PSD review as if they were
traditional sources. Approval and Promulgation of Implementation Plans; Washington:
Prevention of Significant Deterioration and Visibility Protection, 80 Fed. Reg. 23721-01.
Recent permitting decisions for biogenic stationary sources have required PSD review. In
In Re: Energy Answers Arecibo, LLC (Arecibo Puerto Rico Renewable Energy Project), the
Environmental Appeals Board remanded a permitting decision to a regional EPA authority after
the latter issued a PSD permit for a resource recovery facility without regulating its biogenic
greenhouse gas emissions. 13-09, 2014 WL 1260977, at *23 (E.P.A. Mar. 25, 2014). It follows
that EAB did not err in affirming NUARB’s permitting decision on this point. Sylvanergy holds
the burden of proof to show otherwise, yet it cannot point to any current law to support its
position. Instead, it relies on a vacated deferral rule and a policy argument that is severely flawed
in its logic.
13
A. EPA’s Deferral Rule is defunct and would not exempt the Forestdale Biomass Facility even if it were in effect.
After Sylvanergy relied on the deferral rule in front of the EAB, the Board aptly noted
that the D.C. Circuit in Center for Biological Diversity had stricken the rule down. Unfortunately
for Sylvanergy, that court’s decision preceded the commenting period for the draft permit by two
full months.4 The Board’s reasoning was sound, but it missed an important point: even if the FBF
were subject to the deferral rule, the facility would still require a PSD permit due to its status as
an “anyway” source (this status is explained at length previously in this brief).
Without the exemption afforded by the deferral rule, Sylvanergy’s argument has no legal
foundation to stand on. Indeed, implicit in the EPA’s promulgation of the deferral rule is the
notion that biogenic sources would be fully subject to PSD review without the rule.
B. The potential for carbon neutrality is not a relevant consideration in deciding whether PSD review applies to a stationary source.
Without any supporting law, Sylvanergy argues that its facility should be exempt from
PSD review because the FBF will be carbon neutral. Its argument assumes that future carbon
dioxide sequestration in living biomass will offset the emissions from its facility. However, its
logic is flawed. The sequestration of its emissions by future biomass is not guaranteed. That
process is wholly independent from the resource’s harvest and use as a fuel. Where a permit
applicant does not commit to regenerating its biomass feedstock, all of its emissions may remain
in the atmosphere indefinitely. That is an unacceptable outcome under a PSD regulatory
mechanism that exists to limit emissions where control technologies allow for it.
4 The rule was invalidated on July 12, 2013, while NUARB did not open Sylvanergy’s draft permit to public comment until September 12, 2013.
14
Furthermore, because sequestration of greenhouse gas emissions in future biomass is not
guaranteed, Sylvanergy’s argument essentially posits that stationary sources should be exempt
from PSD review where their emissions can be sequestered. This is problematic, of course,
because emissions from fossil fuel sources can also be drawn from the atmosphere. There is little
logic in subjecting one to PSD review but creating an exemption for the other based on a quality
that they both possess. Adopting Sylvanergy’s position would require that both biogenic and
fossil fuel sources be exempt, which is clearly unreasonable given the EPA’s settled
interpretation of the Act.
Subjecting biogenic stationary sources to PSD review is very important where, as here, it
is uncertain whether a facility’s carbon emissions will ever be redrawn from the atmosphere.
Through PSD review, that uncertainty can be remedied by applying reforestation as a control
measure. More importantly, it will only have been applied if it survives the five-step BACT
selection process. Other control technologies may be found more effective after making all of the
appropriate considerations.
Ultimately, Sylvanergy has not shown that NUARB’s decision was erroneous. The
vacated deferral rule clearly does not exempt FBF, and Sylvanergy’s policy argument is not
statutorily justified nor logically sound. The Court should affirm the EAB’s decision on this
matter.
IV. Wood Gasification and Partial Carbon Capture and Storage deserved consideration as BACT.
Because wood gasification and partial carbon capture and storage (“partial CCS”) do not
redefine the fundamental purpose of the FBF, they should have been considered by the NUARB
15
as potential control technologies. Furthermore, the plain language definition of BACT allows for
their consideration. EAB’s approval of NUARB’s permitting decision to the contrary was plainly
erroneous and inconsistent with the requirements of the Act.
The Clean Air Act defines BACT as the “emission limitation” achievable by “application
of production processes and available methods, systems, and techniques, including fuel cleaning,
clean fuels, or treatment of innovative fuel combustion techniques.” 42 U.S.C. § 7479(3). As a
major emitting facility, FBF must have “the best available control technology for each pollutant
subject to regulation.” 42 U.S.C. § 7475(a)(4). The EPA's long-held position is that BACT
cannot require a significant redesign of the proposed facility such that its fundamental scope—its
purpose—is changed. Sierra Club v. United States E.P.A., 499 F.3d 653, 654 (7th Cir. 2007). A
project’s fundamental scope includes its basic means (here, a biomass power generation plant)
and ends (the production of electricity). See id. To illustrate the rule, applicants for a coal-fired
power plant cannot be required to build a wind farm in its place (a redesign of the project’s
means), or develop energy efficiency resources in lieu of providing electricity service (a redesign
of ends). See EPA, New Source Review Workshop Manual: Prevention of Significant
Deterioration and Nonattainment Area Permitting (1990).
Redesigns are permissible, however, where the facility’s fundamental purpose remains
intact. Sierra Club, 499 F.3d at 656. For example, the Seventh Circuit in Sierra Club v. United
States E.P.A. held that an “adjustment in the design of (a) plant” would be permissible “if it were
no more than would be necessary (to switch) from a dirtier to a cleaner fuel.” Id. By contrast,
where a coal plant is conceived of and designed for the purpose of extracting a specific reserve
of high-sulfur coal to burn on-site (as in the aforementioned case), a BACT mandate to purchase
16
low-sulfur coal from distant mines is an impermissible redesign of the project’s fundamental
purpose. Id at 657.
The Supreme Court of Utah adopted and expanded on the reasoning in Sierra Club,
adding that the fundamental scope of a project “must relate to the basic business purpose of the
proposed facility.” Utah Chapter of Sierra Club v. Air Quality Bd., 226 P.3d 719, 733 (Ut. 2009).
According to the court, the business purpose of the proposed facility—a coal-fired power plant—
was simply to operate as “an electric power generating plant fueled by coal.” Id. In light of that
finding, the state permitting authority’s refusal to consider gasification technology as BACT was
deemed impermissible because gasification would not redesign the plant in a way that changed
the high-level business purpose. Id. Importantly, the court also rejected the notion that acceptable
control technologies are limited to those that can be added onto the existing design of a proposed
facility; they also include production processes and systems “that can be ‘designed into’ a
proposed (facility).” Id at 731.
A. Because wood gasification and partial CCS would not alter Forestdale Biomass Facility’s fundamental purpose, the technologies should have been considered as BACT.
Here, wood gasification and partial CCS would not alter the fundamental purpose of
FBF. The project’s high-level business purpose is to generate electricity from wood feedstock
and to produce wood pellets; no other discernable objectives appear in the record. Applying
wood gasification and partial CCS would not alter that purpose by any degree. It would not
change the facility’s feedstock (as in Sierra Club), its location, the end achieved, or any other
fundamental quality of the project. Instead, it would result in changes to the systems and
processes involved—changes that were deemed permissible in both Sierra Club and Air Quality
17
Board. It is instructive, too, that gasification was the technology approved for consideration as
BACT in the latter.
B. The plain language definition of Best Available Control Technology under the Clean Air Act allows for consideration of wood gasification and partial carbon capture and storage.
The EAB’s permitting decision also contradicts the plain language of the Act. To
reiterate, BACT is achieved through the “application of production processes and available
methods, systems, and techniques, including fuel cleaning, clean fuels, or treatment or innovative
fuel combustion techniques for control of each such pollutant.” According to the case law and
EPA’s interpretation of that language, the only general limitation on this provision of the Act is
that the BACT may not change the fundamental purpose of the facility. Where that does not
occur, however, all “methods, systems, and techniques” listed above, and many more (the use of
“including” is significant), are worthy of consideration as BACT.
In light of the above, the EAB’s refusal to consider wood gasification is plainly
erroneous. Its reasoning—that requiring Sylvanergy to burn wood gas instead of the wood itself
is a redefinition of the plant’s “source”—fails to support its conclusion that wood gasification
would redefine the fundamental scope of the facility itself. Indeed, the two concepts are different;
a redefinition of the source (which the EAB equates to a plant’s fuel) is permissible, while a
redefinition of the fundamental scope is not. Wood gasification, as a clean fuel alternative, is
permissible as BACT under a plain reading of the Act (not to mention under the standard set
forth in Sierra Club, which explicitly allowed for redesigns to accommodate cleaner fuels).
Furthermore, even if wood gasification were considered a change in process rather than a change
18
in fuel, as the court in Air Regulatory Board did, it would again be permissible under the plain
language allowing for “innovative fuel combustion techniques.”
Lastly, the EAB based its decision solely on the supposed fuel change caused by wood
gasification and failed entirely to address the partial CCS component of the proposal. Rejecting
the technology without reason is enough to support a reversal of the EAB’s decision. The
Board’s decision is especially faulty, though, given that it wrote extensively about the potential
benefits of partial CCS as a potential control technology.
In summary, because wood gasification and partial CCS do not redefine the fundamental
purpose of the FBF, they should have been considered by the NUARB as BACT. Furthermore,
the plain language definition of BACT allows for the application of these technologies. EAB’s
approval of NUARB’s permitting decision to the contrary was plainly erroneous and inconsistent
with the requirements of the Act.
V. EPA Cannot Use Reforestation as BACT.
With respect to applying reforestation BACT, the EAB and the NUARB make two
serious errors. First, reforestation does not meet the definition of BACT. Second, the EAB failed
to consider the environmental consequences of using reforestation as BACT. Among other
environmental impacts, reforestation does not address the immediate effect of CO2 released as a
result of burning biomass. In terms of carbon emissions, biomass combustion is similar to
burning fossil fuels.
Reforestation can be a useful tool to reduce the amount of CO2 in the atmosphere. That
said, there is a difference between mitigating emissions after the fact and limiting emissions at a
19
source. The usefulness of reforestation in mitigating climate change does not mean that
reforestation meets the statutory definition of BACT—“an emission limitation.” 42 U.S.C.
§ 7479(3). Reforestation is not BACT because it does not qualify as an emission limitation. 42
U.S.C. § 7602(k). Reforestation does not “on a continuous basis” limit the “quantity, rate, or
concentration of emissions of pollutants.” Id. In short, reforestation does not limit emissions.
Planting trees will do nothing to staunch the quantity, rate, or concentration of CO2
emissions from Sylvanergy’s facility. Instead, reforestation acts like a sponge used to clean up a
spill. The source releases polluting carbon emissions, and reforestation absorbs the pollution
after the fact. Unlike an emission limitation, a sponge does not stop or reduce the rate of a spill
from a source. As a carbon pollution sponge, the benefits of reforestation doe not accrue for
decades. In the interim, Sylvanergy’s CO2 emissions will accumulate in the environment.
By using reforestation as BACT, the EPA ignores the deleterious environmental
consequences that can result from the lag between the spill and the clean up. As a pollutant, CO2
has an immediate deleterious effect. Each molecule released into the atmosphere traps a little bit
more heat. Unlike carbon capture and storage, reforestation does not prevent or mitigate the
immediate harm of CO2 emissions. Reforestation is not a limit on emissions from a source, and
because of the lag in its efficacy, it is not continuous. Therefore, reforestation does not meet the
statutory definition of BACT.
The environmental consequences of allowing carbon pollution to continue to increase in
the short-term can be disastrous. Governments across the planet have a decision to make about
how quickly to carbon emissions and other GHGs. In addition to the overall amount of green
house gas reductions, the speed of the reduction matters. Reducing emissions to zero over the
course of 200 years would have more disastrous impacts than reducing emissions to zero in 100
20
or 50 years. By allowing Sylvanergy to use reforestation as BACT, EPA ignores the
environmental and economic harm that can occur by effectively slowing the overall rate of
reduction of CO2 emissions. EPA’s reasoning in this case allows carbon to continue spilling into
the atmosphere unabated.
Reforestation as BACT sets dangerous precedent under the CAA. Allowing carbon
pollution from biomass generation sources like Sylvanergy’s to accumulate in the near term
could push the climate system past a tipping point beyond which further reductions in
anthropogenic CO2 will not stop global warming. EPA improperly ignores the both the near-
term and potential long-term impacts of its decision to spill CO2 into the atmosphere first and
allow biogenic sources like Sylvanergy to delay clean up until later.
CONCLUSION
For the foregoing reasons, SOC requests that the Court vacate Sylvanergy’s PSD permit.
DATE: December 1, 2015.
Respectfully Submitted, Counsel for Petitioner, Save Our Climate, Inc.