Unit iii braced_cuts

58
UNIT III BRACED CUTS UNIT III BRACED CUTS

description

 

Transcript of Unit iii braced_cuts

Page 1: Unit iii braced_cuts

UNIT III BRACED CUTSUNIT III BRACED CUTS

Page 2: Unit iii braced_cuts

TYPES OF VERTICAL CUTS

•Shallow cuts

•Deep cuts

•Open cuts

•Closed cuts

•Temporary cuts

•Permanent cuts In shallow cuts depth of excavation is less than 6 m. The bracings of this type of cut generally standard

In deep cuts depth of excavation is more than 6 m and the design of suitable bracings (supporting system) is necessary to safe guard the cut or trench against collapse

Page 3: Unit iii braced_cuts

DEPTH OF UNSUPPORTED VERTICAL CUT

The critical height (Hc) of vertical cut without supports is two times Zo

Hc = 2 Zo where,

a

oK

cZ

2

Where, Zo is point of zero pressure

a

cK

cH

4

Hence, Zo

2Zo

2 c Ka

Page 4: Unit iii braced_cuts

WHAT IS BRACED CUT?

An excavation supported by suitable bracing system are called braced cut.

These excavation support systems are used to, • minimize the excavation area, • keep the sides of deep excavations stable, and • ensure that movements of soil will not cause damage to neighboring structures or to utilities in the surrounding ground.

Design of braced excavation means selection of wales, struts, sheet piles and soldier beams to support the excavation without any collapseby estimating the lateral earth pressure to which the braced cuts will be subjected to.

Page 5: Unit iii braced_cuts

CROSS SECTION OF BRACED CUT

Page 6: Unit iii braced_cuts

soldier beam is driven into the ground before excavation and is a vertical steel or timber beam.

Laggings, which are horizontal timber planks, are placed between soldier beams as the excavation proceeds.

When the excavation reaches the desired depth, wales and struts (horizontal steel beams) are installed. The struts are horizontal compression members.

Type I use of soldier beams

Page 7: Unit iii braced_cuts

interlocking sheet piles are driven in to the soil before excavation.

Wales and struts are inserted immediately after excavation reaches the appropriate depth.

Type II use of sheet piles

Page 8: Unit iii braced_cuts

DIFFERENT TYPES OF SHEETING AND BRACING SYSTEMS

The following types of sheeting and bracing systems for cuts are commonly used.Vertical Timber Sheeting: Vertical timber sheeting consisting of planks about 8 to 10 cm thick are driven around the boundary of the proposed excavation to some depth below the base of the excavation. The soil between the sheeting is then excavated. The sheeting is held in place by a system of wales and struts. The wales are horizontal beams running parallel to the excavation wall. The wales are supported by horizontal struts which extend from side to side of the excavation. However, if the excavations are relatively wide, it becomes economical to support the wales by inclined struts, known as rakers. For inclined struts to be successful, it is essential that the soil at the base of the excavation be strong enough to provide adequate reaction.If the soil can be temporarily support itself an excavation of limited depth without an external support, the timber sheeting can be installed in the open or in a partially completed excavation.Vertical timber sheetings are economical up to a depth of 4 to 6 m.

Page 9: Unit iii braced_cuts

VERTICAL TIMBER SHEETING

Page 10: Unit iii braced_cuts

Steel Sheet Pile: In this method, the steel sheet piles are driven along the sides of the proposed excavation. As the soil is excavated from the enclosure, wales and struts are placed. The wales are made of steel. The struts may be of steel or wood. As the excavation progresses, another set of wales and struts is inserted. The process is continued till the excavation is complete. It is recommended that the sheet piles should be driven several meters below the bottom of excavation to prevent local heaves. If the width of a deep excavation is large, inclined bracing may be used.

Page 11: Unit iii braced_cuts

Soldier Beams: Soldier beams are H-piles which are driven at a spacing of 1.5 to 2.5 m around the boundary of the proposed excavation. As the excavation proceeds, horizontal timber planks called laggings are placed between the soldier beams. When the excavation advances to a suitable depth, wales and struts are inserted. The lagging is properly wedged between the pile flanges or behind the back flange.

Page 12: Unit iii braced_cuts

Tie Backs: In this method, no bracing in the form of struts or inclined rakers is provided. Therefore, there is no hindrance to the construction activity to be carried out inside the excavated area. The tie back is a rod or a cable connected to the sheeting or lagging on one side and anchored into soil (or rock) outside the excavation area. Inclined holes are drilled into the soil (or rock), and the hole is concreted. An enlargement or a bell is usually formed at the end of the hole. Each tie back is generally prestressed the depth of excavation is increased further to cope with the increased tension. Prestressed concrete is a method for

overcoming the concrete's natural

weakness in tension

Having been stressed before use

Methods of increasing the load bearing capacity of concrete by applying increased tension on steel tendons or bars inside a beam. ...

Page 13: Unit iii braced_cuts

Use of Slurry Trenches: An alternative to use of sheeting and bracing system, which is being increasingly used these days, is the construction of slurry trenches around the area to be excavated and is kept filled with heavy, viscous slurry of a bentonite clay-water mixture. The slurry stabilizes the walls of the trench, and thus the excavation can be done without sheeting and bracing. Concrete is then placed through a tremie. Concrete displaces the slurry. Reinforcement can also be placed before concreting, if required. Generally, the exterior walls of the excavation are constructed in a slurry trench.

Page 14: Unit iii braced_cuts

Design of Various Components of Bracing

Struts: The strut is a compression member whose load-carrying capacity depends upon slenderness ratio, l/r. The effective length ‘l’ of the member can be reduced by providing vertical and horizontal supports at intermediate points. The load carried by a strut can be determined from the pressure envelope. The struts should have a minimum vertical spacing of about 2.5 m. In the case of braced cuts in clayey soils, the depth of the first strut below the ground surface should be less than the depth of tensile crack (Zc), which is equal to ,

cZC

2

While calculating the load carried by various struts, it is generally assumed that the sheet piles (or soldier beams) are hinged at all the strut levels expect for the top and bottom struts.

Page 15: Unit iii braced_cuts

The reaction R1 per unit length is determined by taking moments of the forces acting on span a d at d, and equating them to zero. Once R1

has been determined, the reaction component R2’ is determined from the equilibrium equation in the horizontal for the span a d.

For sand

For clay

Page 16: Unit iii braced_cuts
Page 17: Unit iii braced_cuts

Sheet piles Sheet piles act as vertical plates supported at strut levels. The maximum bending moments in various sections such as ad, df and f h are determined.Once the maximum bending moments have been computed, the section modulus of the sheet pile can be computed and the section chosen.

Page 18: Unit iii braced_cuts

Other Criteria for Design of Braced Cuts

Braced cuts in clay may become unstable due to heaving of the bottom of the excavation. This is a type of bearing capacity failure and is discussed.

Braced cuts is sand are generally stable against heaving failure but these may become unstable to upward seepage of water into the cut if the water level inside the cut is substantially lower than that outside.

Piping failures is also one of the concern to be taken care of.

The walls of the braced cut may yield laterally and cause ground settlement in the surrounding area.

This effect should be carefully assessed and suitable measures adopted.

Page 19: Unit iii braced_cuts

MODES OF FAILURE OF BRACED CUT

• Failure of soil by bottom heave (applicable to clay)

• Failure of soil due to piping (applicable to sand)

• Failure by buckling of struts

When H / cu is less than 6, movement of bracing system and heave of clay are small.

When, H / cu approaches about 8, the movement of a well designed bracing system becomes very large.

When, H / cu exceeding 8, the bracing is likely to collapse because of large inward movement of clay outside the embedded portion/s of the sheet piles and excessive upward heave of clay beneath the excavation.

In this case, design of simple braced system will not serve the purpose.

Page 20: Unit iii braced_cuts
Page 21: Unit iii braced_cuts
Page 22: Unit iii braced_cuts
Page 23: Unit iii braced_cuts
Page 24: Unit iii braced_cuts
Page 25: Unit iii braced_cuts
Page 26: Unit iii braced_cuts
Page 27: Unit iii braced_cuts
Page 28: Unit iii braced_cuts

Design of Braced Sheeting in Cuts

Page 29: Unit iii braced_cuts

FOR DRY OR MOIST SAND

FOR SOFT TO MEDIUM CLAY

FOR STIFF CLAY

EARTH PRESSURE DISTRIBUTION BEHIND SHEETING

Page 30: Unit iii braced_cuts

Design of Braced Sheeting in Cuts

Sheet piles are used to retain the sides of the cuts in sands and clays. The sheet piles are kept in position by wales and struts. The first brace location should not exceed the depth of the potential tension cracks.

245tan

20

c

h

Since the formation of cracks will increase the lateral pressure against the sheeting and if the cracks are filled with water, the pressure will be increased even more. The sheeting of a cut is flexible and is restrained against deflection at the first series of struts. The deflection, therefore, is likely to be as shown in Fig. (a). The pressure distribution on sheet pile walls to retain sandy soil and clay soil are shown in Figs. (b) and (c) respectively.

a

b

c

Page 31: Unit iii braced_cuts

Design1. The sheet pile is considered as continuous beam

supported on wales either cantilevered at top, fixed, partially fixed, hinged, or cantilevered at the bottom depending upon the amount of penetration below the excavation line.

2. Bending moment and shearing force diagram are then obtained using moment distribution method.

3. Section of the sheet pile is then designed in the conventional way for the maximum bending moment.

A fast way of designing sheeting is to assume conditions as shown in Fig. (d). The top is treated as a cantilever beam including the first two struts. The remaining spans between struts are considered as simple beams with a hinge or cantilever at the bottom.

Struts are designed as columns subjected to an axial force. The wales as continuous members or simply supported members pinned at the struts.

d

Page 32: Unit iii braced_cuts

This picture shows an internally braced cofferdam supporting a 35 foot deep excavation for a combined sewer overflow structure in Augusta, Maine.

Page 33: Unit iii braced_cuts

Braced cut showing arrangement of sheet piles, wales and struts

Page 34: Unit iii braced_cuts

Here you see a circular cofferdam that is supported by two cast in place concrete beams that behave much like an arched bridge or culvert. This 20 foot deep cofferdam was used to support an excavation for two clarifiers for a wastewater treatment plant in Bar Harbor, Maine. The circular design allows construction of the concrete clarifiers without interference from internal bracing.

Page 35: Unit iii braced_cuts
Page 36: Unit iii braced_cuts

This photo shows a sewer excavation in San Francisco supported by a driven sheet pile wall, with pipe struts extending across the excavation. Wide flange beams distribute the loads of the pipe struts to the sheet pile walls. Because the struts are compression members, their capacities are controlled by considerations of buckling. Lateral supports reduce the effective lengths of the struts and increase their capacities.

Page 37: Unit iii braced_cuts

This photo shows an excavation for the bay area rapid transit (BART) system, beneath Shattuck Avenue in Berkeley, California. Street traffic is carried on timbers that form a roof on the excavation, while construction of the cut-and-cover tunnel goes on beneath. The work area is very constricted by the horizontal H-beam struts and the vertical supports for the roadway over head.

Page 38: Unit iii braced_cuts

Here the sheet Here the sheet pile wall around a pile wall around a building building excavation is excavation is supported by pipe supported by pipe struts. Those in struts. Those in the foreground, the foreground, which extend from which extend from one side of the one side of the excavation to the excavation to the other, are termed other, are termed “cross-lot”“cross-lot” braces. braces. In the corner of In the corner of the excavation the the excavation the sheet piles are sheet piles are supported by supported by corner braces.corner braces. Corner braces Corner braces reduce the reduce the constriction in part constriction in part of the working of the working area. area.

Page 39: Unit iii braced_cuts

This photo shows the This photo shows the excavation support excavation support system for a building in system for a building in the Embarcadaro the Embarcadaro Center in San Francisco. Center in San Francisco. The wall is a slurry The wall is a slurry trench concrete wall (a trench concrete wall (a concrete wall concrete wall constructed in a slurry-constructed in a slurry-supported trench in the supported trench in the ground). The sides of ground). The sides of the excavation are the excavation are supported by external supported by external supports -- H-piles supports -- H-piles driven through holes in driven through holes in the wall, which work in the wall, which work in tension to hold the wall. tension to hold the wall. The use of external The use of external support greatly reduces support greatly reduces the amount of the amount of congestion within the congestion within the excavation, making excavation, making construction faster and construction faster and less costly. Corner less costly. Corner braces support the braces support the corners of the corners of the excavation excavation

Page 40: Unit iii braced_cuts

Here the wall is supported by “rakers,” or inclined struts. The bottom ends of the rakers are braced against the central part of the building foundation slab. The excavation was carried to full depth at the center first so that the foundation slab could be poured. Prior to installation of the rakers, the lower part of the slurry trench concrete wall was supported by an earth berm. The earth berm remains at the far side of the excavation.

Page 41: Unit iii braced_cuts

A second, lower, set A second, lower, set of rakers was installed of rakers was installed after part of the berm after part of the berm was excavated. This was excavated. This photo was taken when photo was taken when the excavation was the excavation was complete. It is complete. It is interesting to see that interesting to see that the concrete wall, the concrete wall, constructed in a slurry-constructed in a slurry-supported trench, is supported trench, is very smooth and of very smooth and of good quality. good quality.

Page 42: Unit iii braced_cuts

CORNER BRACES This photo shows the This photo shows the excavation support system excavation support system for the Getty Center art for the Getty Center art museum garage in Los museum garage in Los Angeles, California. The Angeles, California. The excavation is about 75 feet excavation is about 75 feet deep. The sides of the deep. The sides of the excavation are supported excavation are supported by soldier piles and by soldier piles and lagging. The soldier piles lagging. The soldier piles are driven before are driven before excavation begins, and the excavation begins, and the wood lagging is installed as wood lagging is installed as the excavation proceeds the excavation proceeds down. On the sides of the down. On the sides of the excavation the soldier pile excavation the soldier pile and lagging wall is and lagging wall is supported by post-supported by post-tensioned anchors drilled tensioned anchors drilled and grouted into the soil and grouted into the soil around the excavation. The around the excavation. The corners are supported by corners are supported by corner braces. corner braces.

Page 43: Unit iii braced_cuts

The The weathered rockweathered rock at the bottom of the Getty Center at the bottom of the Getty Center excavation is stiff enough to support itself without lagging. excavation is stiff enough to support itself without lagging.

At the corner braces are used At the corner braces are used

Page 44: Unit iii braced_cuts

Work in progress on the new bulkhead with the tie anchors partially installed.

 Project Highlights

Mass Maritime Academy Pier Facility Bourne, Massachusetts

• Demolition of an existing wharf with timber piles and concrete deck.• Installation of a 350 foot long sheet-pile anchored bulkhead.• Installation of a new wharf structure (350 feet by 50 feet) supported on approximately 110, 16-inch diameter closed end pipe piles. The deck structure consisted of pre-cast concrete pile caps and deck with a finished cast in-place concrete surface.• Installation of new pre-cast concrete fender system.• Installation of new sewer line and pump station.• Installation of 2,000 tons of rip-rap bulkhead toe stabilization material.

Page 45: Unit iii braced_cuts

Cross section of sheeting and bracing systems

Page 46: Unit iii braced_cuts

Deflection pattern of braced cuts

Page 47: Unit iii braced_cuts

Deflection pattern of braced cuts

Page 48: Unit iii braced_cuts

EARTH PRESSURE DISTRIBUTION

• In sand

• In clay

Page 49: Unit iii braced_cuts

EARTH PRESSURE DISTRIBUTION IN SAND

Page 50: Unit iii braced_cuts

EARTH PRESSURE DISTRIBUTION IN CLAY

Page 51: Unit iii braced_cuts

EARTH PRESSURE DISTRIBUTION IN CLAY

Page 52: Unit iii braced_cuts

Tributary area method

Equivalent beam method

LOADS ON BRACES

Page 53: Unit iii braced_cuts
Page 54: Unit iii braced_cuts
Page 55: Unit iii braced_cuts

For the cut shown in figure determine, the

strut loads per meter run of excavation by,

1. Tributary area method

2. Equivalent beam method

Page 56: Unit iii braced_cuts
Page 57: Unit iii braced_cuts
Page 58: Unit iii braced_cuts