UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and...

18
UNIFORM GUIDANCE OVERVIEW December 2014 Update

Transcript of UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and...

Page 1: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

UNIFORM GUIDANCE OVERVIEW

December 2014 Update

Page 2: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Important Dates Applicable to new awards and (possibly) new funding increments

issued on and after December 26, 2014 UG is actually guidance to agencies and each agency must issue

an implementation; as of today only NSF has issued an implementation

We expect to see Final Agency implementations some time before or on December 26

Project will not be “done” by December 26, agency implementations and further OMB clarifications will necessitate further review and changes

Page 3: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Things we don’t know…

When will agencies release their implementations? What differences will be included? Agencies have the flexibility of applying or not applying

UG to non-competing increments. Agencies may revise existing awards to change terms to

UG. Will agencies waive some prior approval requirements?

Page 4: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Items that have been clarified

200.112 Conflict of Interest. This section applies to Purchasing conflicts of interest

200.307 Program Income. Income from license fees and royalties are excluded from the definition

Page 5: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Proposal Budget Preparation Guidance Administrative and Clerical Salaries 200.413 Still, normally indirect and should not be direct charged

However, may be appropriate if ALL of these criteria are met: Services are integral to a project or activity Individuals involved can be specifically identified with the project (normally not less than

15% commitment) Costs are explicitly included in proposal budget or have sponsor prior written approval Not also recovered as indirect

Prior written approval of the awarding agency must be obtained. If all of these requirements are met, Investigators/departments should add a new justification statement to proposals to facilitate the required agency approval. The budget justification must include a narrative that explains how these services are integral to the project.

Page 6: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Proposal Budget Preparation Guidance

Programmatic Salary Costs 200.430Costs related to protocol development and maintenance, managing substances/chemicals, managing and securing project-specific data, and coordination of research subjects are allowable direct costs when they are “contributing and directly related to work under an agreement.” Thus, these programmatic costs may be direct charged using the same underlying requirements as other types of direct costs, and are not subject to the extra approval requirements applicable to administrative and clerical costs. They are still subject to all regular costing requirements (e.g.; allocability, reasonableness, allowable by the terms of the award, incurred within award period).

Page 7: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Proposal Budget Preparation Guidance

Computing Devices 200.33, 200.48, 200.89, 200.439, 200.453C For awards effective 7/1/2015 and later

Computing devices under $2000 per unit may be direct charged if: The device is essential* and allocable to the project in that it is necessary to acquire, store, analyze, process, and publish data and other information electronically, including accessories (or “peripherals”) for printing, transmitting and receiving or storing electronic information. The project does not have reasonable access to the other devices or equipment that can achieve the same purpose; devices may not be purchased for reasons of convenience or preference. Items costing $2,000 or more per unit are considered general purpose equipment and follow federal equipment rules for when they can be direct charged. NOTE: $2000 is an anticipated dollar threshold; this issue is under review by the university.*Investigators are responsible for determining whether or not the device is “essential” and to what extent the cost of the device is allocable to the sponsored project. Investigators and departments should maintain documentation that describes how the proposed computing device meets the above requirements. The computing devices should be listed in the budget under “materials and supplies” and are subject to Facilities and Administrative costs (F&A).

Page 8: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Proposal Budget Preparation Guidance

Participant Support Costs 200.75, 200.456 Participant support costs are allowable with agency prior approval. This includes stipends or subsistence allowances, and registration fees paid to or on behalf of participants or trainees (but not employees) in connection with conferences or training projects. Participant support costs are not routinely allowed on research projects but can be charged if the project includes an education or outreach component and the agency approves such costs.

 

These costs should be explicitly listed in the proposal budget or approved by the funding agency after the award has been made. These costs must be excluded when calculating the Modified Total Direct Costs (MTDC) to determine the project’s F&A costs, therefore, a separate scope account will be established when these costs are included in the awarded budget.

Page 9: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Proposal Budget Preparation Guidance

F&A on Subawards 200.331A subrecipient’s negotiated F&A rate or an alternative rate as described as follows must be used for all subawards included in competitive proposals. If a federal program has a published statutory F&A cap, that rate must be used both by UK and all of its subrecipients. For all other federal programs, if a subrecipient has a federally negotiated F&A rate, it must be used. If the entity does not have a negotiated F&A rate, a 10% MTDC de minimis F&A rate must be used instead. Investigators may not negotiate or agree to lower rates with their subrecipients.

Page 10: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Proposal Budget Preparation Guidance

Fixed Amount Subawards 200.201, 200.332Agency prior approval is required to enter into a fixed amount subaward rather than a cost-reimbursement subaward, and the total value of each fixed amount subaward may not exceed $150K. To expedite agency approval, Investigators/departments should add a new justification statement to a proposal contemplating a fixed amount subaward which addresses why it is appropriate to use this funding mechanism (see 200.201). A statement is not needed for cost reimbursement subawards.

Page 11: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Proposal Budget Preparation Guidance

Voluntary Committed Cost Sharing 200.306Under the UG, funding agencies are prohibited from considering voluntary committed cost sharing in the merit review process. The National Science Foundation specifically prohibits voluntary committed cost sharing in proposals, unless specified in the funding opportunity announcement. Since the federal agencies cannot consider voluntary committed cost sharing in assessing a proposal’s merit, offering it will not increase the likelihood of an award.

 

Cost sharing means project costs not borne by the sponsor; also known as matching or in-kind contributions. Voluntary committed cost sharing is cost sharing that is not required by law, statute or regulation, nor written in the application guidelines, but was offered by the investigator in the proposal. Voluntary committed cost sharing is recorded in the University’s accounting system and must be reported internally. (See also BPM E-50- 2)

Page 12: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Procurement

200.317 – 326 Procurement StandardsGrace period until 7/1/2016 but much work to be doneMicro-purchases: $3000 or less, no competition requiredSmall purchases: $3000 - $149,999, price or rate quotations

required from adequate number of sourcesSimplified Acquisition Threshold is $150,000

Sealed bids RFPs

Page 13: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Procurement

Using Contract vendors will prevent need for additional documentation of competition under UG

http://www.uky.edu/Purchasing/pcts.htm Anticipate separate processes for federal UG procurement and

other sources Ability to visually identify federal UG funds by specified number

ranges in the future

Page 14: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

More updates….

Documentation of personnel expenses – Huron currently completing an Effort Review with report due in February

Official definition of Institutional Base Salary – Legal Counsel has draft Administrative Regulation prepared

Page 15: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

More updates…

Updated definitions for some g/ls Advisory Council 530135Conferences 530191Dues and Memberships 535011Subscriptions 535025Dues and Memberships – individual 535018Participant Costs 530170

Page 16: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

More updates…

Commercial air travel 200.474(d) UG would allow lowest unrestricted airfare which is much more

expensive than lowest restricted (non-refundable)UK will not change existing travel policy

Programming needs submitted to EAG and projects are approved

Page 17: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Going forward… Much we do not know When agencies release their implementation, we’ll know

more (we hope) New awards will note in the PADR Remarks that the

account is subject to UG

Page 18: UNIFORM GUIDANCE OVERVIEW December 2014 Update. Important Dates Applicable to new awards and (possibly) new funding increments issued on and after December.

Keeping you informed…

Town Hall general campus briefings Faculty meetings when invited by college Webinars sponsored by professional groups Existing Listservs Website http://www.research.uky.edu/UG/ Email [email protected]