Understanding the Technology

INTELLIGENT COMPACTION

Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014

Page 2: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Table of Contents

6-9

10-11

12

13

3-5Why Use Intelligent Compaction

TXDOT IC Projects

Benefits and Challenges

Future Plans

Summary

1

2

3

4

5

2

Page 3: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Ordinary Compaction

Density Control

• Compactive Energy

• Moisture Content

• Material Type

• Compact Lift Thickness

• Underlying Conditions

Why Use IC?

3

Page 4: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Why Use IC?

Not used in pavement design A layer-specific spot test providing

no info on the uniformity of compaction over the entire section

Only measured after compaction is complete providing no feedback in real time

4

Can We Do A Better Job?

Page 5: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Why Use IC?

Lose the track of rolling pass counts Compaction job becomes guesswork

Inconsistent and non-uniform density

Under/over compaction Premature pavement failure

5

Before

After

Page 6: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

TxDOT IC ProjectsFort Worth (7)FM156; US287 ; FM1938;

FM731; SH267; IH35W;

and IH30

El Paso (1)FM1281

Amarillo (1)LP335

Paris (2)US75SH24

Atlanta (1)FM450

Houston (1)SH35

6

  

 

      

  

  

    

        

  

  

    

    

    

  

    

        

 

    

         

    

 

   

 

  

        

 

  

      

    

   

     

   

 

 

   

        

    

           

 

 

 

   

    

   

    

      

    

 

     

   

       

  

    

       

 

    

             

  

  

  

  

    

 

 

   

  

 

 

      

  

  

 

     

         

 

          

  

      

  

      

  

  

  

 

          

          

  

         

 

Page 7: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

FM156, Fort Worth, TX

FHWA/TPF IC Study

SG, Lime Stabilized SG, and Flex Base

Ammann/Case padfoot drum IC roller

Dynapac singlesmooth drum IC roller

Ammann/Case smooth drum IC roller

FM156 Project

7

Page 8: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Case/Ammann single-drum

padfoot IC roller

Ks shows compaction progress and a soft spot

FM156 Project – Identify Soft Spots

Screen shots of kSΙPD maps for different passes on TB 1

8

Page 9: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

FWD

LWD

FM156 Project – IC vs. Conventional Tests

DCP

9

Page 10: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Benefits

Covers 100% of the area compacted

Monitors pass counts Identifies areas of poor compaction Intelligently picks areas to test for QC/QA Improves productivity and minimizes cost Improves safety in construction zones

10

Page 11: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Extensive training for DOT and contractors FHWA training workshops

Data management difficulties VEDA

More expensive than ordinary IC retrofit kit

High moisture variation No strong correlation b/w stiffness and density

Challenges

11

Page 12: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Workshops/Webinars and pilot projects in districts

Revise IC specification–Short Term: density based on

IC proof mapping

–Long Term: stiffness based on IC proof mapping

12

Future Plans

Page 13: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

Summary

1. IC is a continuous compaction control process.

2. IC is only for QC so far.

3. IC measures stiffness, not density.

4. IC reports both stiffness and pass count.

5. IC does not measure moisture.

6. IC measurements are sensitive to moisture.

7. IC improves safety in construction zones.

13

Page 14: Understanding the Technology INTELLIGENT COMPACTION Jimmy Si, Ph.D., P.E. Austin, TX, April 3, 2014.

QUESTIONS?