UNDERGROUND UTILITY LOCATIONS MAKING OHIO A … · UNDERGROUND UTILITY LOCATIONS MAKING OHIO A...
Transcript of UNDERGROUND UTILITY LOCATIONS MAKING OHIO A … · UNDERGROUND UTILITY LOCATIONS MAKING OHIO A...
UNDERGROUND UTILITY LOCATIONS
MAKING OHIO
A
SAFER PLACE TO EXCAVATE
Darren D. Owens, PE, SI
City Engineer
City of Lebanon, Ohio
TYPICAL PROJECT PROCESS
(Public & Private)
Design
Project owner hires a consulting firm to design project
Project area is surveyed to gather field data that includes contacting OUPS
Construction plans are prepared
Coordination with utility companies
Plans completed and project is bid for construction
Construct
Contractor is hired
OUPS is contacted for excavation tickets
Construction of project
PROTECTION OF UNDERGROUND UTILITIES BEGINS WITH THE
DESIGN PROCESS
STORM SEWER PROJECT
• Intent of project was to do a direct in-line replacement of an existing 30” storm sewer
• 1st Quarter of 2007 – Design
• 3/16/2007 - OUPS contacted by design firm for utility markings
• 10/25/2007 & 11/1/2007 - Project advertised for Bids
• 11/9/2007 - Project bids due
• 11/27/07 - Contract awarded
• 2/10/08 - Contractor call to OUPS for construction utility markings
• 2/12/08 – Numerous conflicts with underground utilities revealed. Complete redesign of
storm sewer system required while contractor on sight. Significant change order.
BID AMOUNT $373,873.81 FINAL CONTRACT AMOUNT $536,715.18
CASE STUDY
COMPLETED DESIGN PLANS AS PROVIDED FOR BIDDING
COMPLETED DESIGN PLANS AS PROVIDED FOR BIDDING
COMPLETED DESIGN PLANS AS PROVIDED FOR BIDDING
REVISED PLANS AFTER CONSTRUCTION MARKINGS
REVISED PLANS AFTER CONSTRUCTION MARKINGS
REVISED PLANS AFTER CONSTRUCTION MARKINGS
HOW DID THIS HAPPEN?
1) Installation of underground utility lines over top of existing storm sewer within the R/W.
2) Failure of utilities to be marked and/or information to be provided to design firm during the design
process. OUPS contacted on 3/16/2007 by design firm in accordance with ORC 153.64(B).
3) Design markings not required in contract between utility owner and locator.
4) Lack of communication between project owner/designer/utility companies/locator.
5) Plan review process.
HOW DO WE MAKE IT BETTER?
1) CHANGE of culture. For decades, when it comes to design services, surveyors/design engineers
have called OUPS to inform them there is a backhoe on site and they will be excavating.
2) Communication-Communication-Communication between project owner/design firms/utility
companies/locating companies
3) Education of higher management level positions of all parties involved regarding utility markings.
4) Understanding of the process for each stakeholder involved.
5) CHANGES TO OHIO’S DIG LAW
*Not a true one call State
OUPS – OGPUPS - LBP’s(Limited Basis Participants (LBPs) – owner/operator of underground facilities that elect to not be
classified as a full voting and participating member of OUPS. An LBP is not eligible to receive
excavation notifications from O.U.P.S.)
*2 Separate Laws – ORC 153.64 Public – Title 3781 Private
Lack of enforcement
Exemption of Municipalities/Government for less than 12”
*Not clear regarding utility markings during design
process
(*Corrected with passing of HB 458 in December 2012)
OHIO’S DIG LAW ISSUES
ORC 153.64 (Public Work) & Title 37 (Private Work)
• Ohio Designer, Engineer, Government Entity, Utility Partnership (ODEGEUP)
• Formed in February of 2010 in coordination with the Southwest Ohio
Utility Safety Council
• Group was established to discuss underground utility locates during the
design process
• Meets the 2nd Tuesday of the month OR when needed
• Ohio Underground Damage Prevention Coalition
• Formed in January of 2011
• Stakeholders involved – utility owners, contractors, governments,
locators, one call centers
• Numerous sub-committees – Marking Standards, Defined Limits,
Stakeholder Responsibility, Positive Response, Enforcement, Technical
OHIO’S DIG LAW HAS BEEN REVISED
&
STILL UNDER REVISION
PHMSA
PIPELINE & HAZARDOUS MATERIALS SAFETY
ADMINISTRATION
• PHMSA’s goal is to strengthen state damage prevention programs
• PHMSA promotes implementation of the “nine elements” of
effective damage prevention programs outlined in the Pipeline
Inspection, Protection, Enforcement and Safety (PIPES) Act of 2006
• PHMSA developed the Damage Prevention Assistance Program
(DPAP) Guide in 2008 to assist States with strengthening damage
prevention programs
• PHMSA’s position is that damage prevention law enforcement is a
state and local responsibility
• PHMSA has evaluated dig laws for all states to see how they meet
the 9 elements, which laws are deficient, and which states they need
to move into and assist with developing regulations
PHMSA
Ohio Results of State Damage Prevention Program CharacterizationsElement Legend:
The Nine Elements of Effective Damage Prevention Programs include the following. Follow each
link to see a map of how the elements are implemented among the states.
Element 1 - Enhanced Communication between Operators and Excavators
Element 2 – Fostering Support and Partnership of all Stakeholders
Element 3 – Operator’s Use of Performance Measures for Locators
Element 4 – Partnership in Employee Training
Element 5 – Partnership in Public Education
Element 6 – Enforcement Agencies’ Role to Help Resolve Issues
Element 7 – Fair and Consistent Enforcement of the Law
Element 8 – Use of Technology to Improve the Locating Process
Element 9 – Data Analysis to Continually Improve Program Effectiveness
• Meets the 4th Tuesday of every month in Columbus
• Information on the coalition can be found on OUPs web page:
http://www.oups.org/Home/LegislativeCoalition(OUDPC)
• Is a continuous working group to suggest modifications to Ohio’s dig
law to make excavation in the State of Ohio safer
• Through the work of the sub-committees and acceptance by the
Coalition, revisions to Ohio’s Dig Law were recently signed by the
Governor on December 20, 2012.
• House Bill No. 458 was introduced by Representative Robert Sprague
and Senate Bill No. 354 was introduced by Senator Bill Coley. Both
bills evolved to read the same. HB 458 was chosen by Congressional
Leadership to present to the Governor.
http://www.legislature.state.oh.us/bills.cfm?ID=129_HB_458
Ohio Underground Damage
Prevention Coalition
H.B. No. 458
CHANGES TO OHIO’S DIG LAW
ORC
SectionOHIO’S DIG LAW CHANGES
HB 458 – SIGNED BY GOVERNOR ON 12/20/12
153.64(B)(2) Provides language for utility owners to provide markings/plan information during design
153.64(C) Provide language for contractor to notify “protection service” of excavation. Sets up One Call service.
3781.25
This
represents
some of the
major
changes
(D) Approximate Location definition revised: means the immediate area within the perimeter of a proposed excavation site
where the underground utility facilities are located.
(E) Tolerance Zone definition added: means the site of the underground utility facility including the width of the
underground utility facility plus eighteen inches on each side of the facility.
(G) Surveyor added to the definition of “Designer”
(O) Definition of Commercial Excavator added: means any excavator, excluding a utility as defined in this section, that
satisfies both of the following: (1) for compensation, performs, directs, supervises, or is responsible for the excavation,
construction, improvement, renovation, repair, or maintenance on a construction project and holds out or represents oneself
as qualified or permitted to act as such; (2) Employs tradespersons who actually perform excavation, construction,
improvement, renovation, repair, or maintenance on a construction project.
(Q) Positive Response System definition added: means an automated system facilitated by a protection service allowing a
utility to communicate to an excavator the presence or absence of any conflict between the existing underground utility
facilities and the proposed excavation site.
(R) One Call Notification system definition added: means the software of communications system used by a protection
system to notify its membership of proposed excavation sites.
3781.26(D)
added
Each utility fully participating in a protection service pursuant to this section shall also participate in its affiliated positive
response system. Each utility participating in a protection service on a limited basis shall directly communicate to the
excavator the presence or absence of any conflict between the existing underground utility facilities and the proposed
excavation site.
H.B. No. 458
CHANGES TO OHIO’S DIG LAW
ORC Section OHIO’S DIG LAW CHANGESHB 458 – SIGNED BY GOVERNOR ON 12/20/12
3781.261
added
An excavator, contractor, or utility that utilizes a protection service shall obtain training in the protection of underground
utility facilities. An excavator, contractor, or utility shall be deemed to have obtained that training if the excavator, contractor,
or utility is a member of a protection service or a statewide association representing excavators, contractor or utilities and the
service or association provides that training. An excavator, contractor, or utility also may obtain the training from such a
service or association without becoming a member.
3781.27 Following wording removed: “Sections 3781.27 to 3781.32 do not apply to “public improvements” as defined in
Section 153.64 of the Revised Code”. This makes it one law.
3781.27(C)(2) Provides language for utility owners to provide markings/plan information during design
3781.271
added
Beginning on July 1, 2013, each protection service shall reasonably modify its one-call notification system so as to permit the
reasonable identification of the location of a proposed excavation site in a manner in which the protection service may then
notify any potentially affected limited basis participants. Each member of a protection service, including limited basis
participants, shall be responsible for providing current contact information to the protection service.
3781.28(E) Language added that requires utility owners and excavator to mutually agree to a marking schedule for larger project areas
based on the construction time line.
3781.29(C) Language added that provides marking standards for how utility owners mark their facilities.
3781.30(B)
added
When utilizing trenchless excavation methods, the excavator must comply with the following requirements, in a manner
consistent with division (A) of this section: (1)Expose and confirm all underground utility facilities at each crossing point by
the proposed excavation in a nondestructive manner to the installation depth of the new facility; (2) Expose all parallel
underground utility facilities in a nondestructive manner at the beginning and end of each trenchless excavation to the
installation depth of the new facility. If the proposed alignment is within the tolerance zone of any parallel underground
utility facility, the underground utility facility shall be exposed every one hundred feet. (3) Ensure that the final product
installation maintains the proper clearances of existing underground utility facilities as determined pursuant to division (E)4
of section 3781.27.
CHANGE the way it has always been done:
Engineers/surveyors calling in excavation tickets for design purposes
CHANGE is needed:
Change of process/Change of thinking/Change of Culture
Work together – We are all in this together
CHANGE must start with education of all parties involved:Local Governments
Set the Example
Designers/Surveyors
10 days to receive markings for design. Communicate.
Utility Owners
Know where your infrastructure is located. Educate your staff. Mark your utility
during project design.
Locators
Mark for design as you would for excavation, protection starts here.
DESIGN UTILITY MARKINGS
OHIO UNDERGROUND DAMAGE PREVENTION COALITION
MARKING STANDARDS SUB-COMMITTEE
RECOMMENDED LANGUAGE REVISIONS
153.64 (B) In any public improvement which may involve underground utility facilities, the
public authority shall, prior to preparing plans and specifications, contact the registered
underground utility protection services and the owners of underground utility facilities that are
not members of a registered underground utility protection service for the existence and location
of all underground utility facilities within the construction area. If physical markings are
requested, the owners of underground utility facilities within the construction area shall provide
the location of all underground utility facilities (excluding services to single family, two, three,
or four unit residences) by locates in accordance with the Ohio Universal Marking Standards,
within ten (10) business days from receipt of the locate request. If the owner of an underground
utility facility provides digital and/or paper drawings that are drawn to scale and includes
locatable items, such as, back of curb, sidewalk, edge of pavement, centerline of ditch, property
lines, and depict the location of the underground utilities, physical markings are not required.
The public authority shall include, in the plans and specifications for such improvement, the
identity and location of the existing underground utility facilities located in the construction area
as provided to the public authority by the owner of the underground utility facility and the name,
address, and telephone number of each owner of any underground utility facilities in the
construction area that does not subscribe to a registered underground utility protection
service……
OHIO UNDERGROUND DAMAGE PREVENTION COALITION
MARKING STANDARDS SUB-COMMITTEE
RECOMMENDED LANGUAGE REVISIONS
3781.27 (C) Each utility that has any underground utility facilities in the area of the proposed
excavation site shall notify the developer/designer of the approximate locations and description of the
utility's underground utility facilities located at the proposed excavation site or that the utility does not
have any underground utility facilities at the site. If physical markings are requested, the owners of
underground utility facilities within the construction area shall provide the location of all underground
utility facilities (excluding services to single family, two, three, or four unit residences) by locates in
accordance with the Ohio Universal Marking Standards, within ten (10) business days from receipt of
the locate request. If the owner of an underground utility facility provides digital and/or paper drawings
that are drawn to scale and includes locatable items, such as, back of curb, sidewalk, edge of pavement,
centerline of ditch, property lines, and depict the location of the underground utilities, physical
markings are not required. The utility shall make this notification within ten days of receiving a notice
under division (B) of this section or by a later date acceptable to the developer and the utility. In the
case of an interstate hazardous liquids pipeline or an interstate gas pipeline, the utility also shall provide
written notice to the developer/designer of any special notification requirements.
DESIGN MARKING LANGUAGE AS APPROVED IN HB 458
153.64 (B)(2)
If requested by the public authority, each owner of underground utility facilities within the
construction area, other than real property owners listed in divisions (C)(1) to (4) of
section 3781.25 of the Revised Code, shall do one of the following within ten days of
receiving notice form the public authority of a protection service:
(a) Mark the location of the underground utility facilities, other than those facilities
serving single-family or two-, three-, or four-unit dwellings, within the construction
area in accordance with the marking standards described in division (C) of section
3781.29 of the Revised Code;
(b) Provide digital or paper drawings, or both, that meet both of the following
requirements:
(i) They are drawn to scale and include locatable items. Locatable items may include
poles, pedestals, back of curb, sidewalk, edge of pavement, centerline of ditch,
property lines, and other similar items.
(ii) They depict the location of the underground utility facilities.
Compliance with division (B)(2) of this section does not relieve an owner of underground
utility facilities from compliance with the marking requirements of section 3781.29 of
the Revised Code.
DESIGN MARKING LANGUAGE AS APPROVED IN HB 458
3781.27 (C)(2)
If requested by the developer or the designer employed by the developer, each utility shall
do one of the following in order to comply with the notification requirements of division
(C)(1) of this section:
(a) Mark the location of the underground utility facilities, other than those facilities
serving single-family or two-, three-, or four-unit dwellings, within the construction
area in accordance with the marking standards described in division (C) of section
3781.29 of the Revised Code;
(b) Provide digital or paper drawings, or both, that meet both of the following
requirements:
(i) They are drawn to scale and include locatable items. Locatable items may include
poles, pedestals, back of curb, sidewalk, edge of pavement, centerline of ditch,
property lines, and other similar items.
(ii) They depict the location of the underground utility facilities.
Compliance with division (C)(2) of this section does not relieve a utility from compliance
with the marking requirements of section 3781.29 of the Revised Code.
PHMSA
Section of March 2013 letter to Governor Kasich from Tim Butters,
Deputy Administrator of PHMSA:
“
“
PHMSA
Ohio Results of State Damage Prevention Program CharacterizationsElement Legend:
The Nine Elements of Effective Damage Prevention Programs include the following. Follow each
link to see a map of how the elements are implemented among the states.
Element 1 - Enhanced Communication between Operators and Excavators
Element 2 – Fostering Support and Partnership of all Stakeholders
Element 3 – Operator’s Use of Performance Measures for Locators
Element 4 – Partnership in Employee Training
Element 5 – Partnership in Public Education
Element 6 – Enforcement Agencies’ Role to Help Resolve Issues
Element 7 – Fair and Consistent Enforcement of the Law
Element 8 – Use of Technology to Improve the Locating Process
Element 9 – Data Analysis to Continually Improve Program Effectiveness
THANK YOU
QUESTIONS?