UNDERGROUND DUCT AND STRUCTURES FOR ??? DISTRICT …

8
THE CREEKS PHASE 4 ARCOLA AVE E CHUKA BLVD SANDPIPER CRES REGINA, SASKATCHEWAN SHEET ---- REGION ??? DISTRICT OFFICE UNDERGROUND DUCT AND STRUCTURES FOR SaskPower and SaskEnergy Turnkey Template R1 E 1 7 D 0 CALL AT LEAST TWO FULL WORKING DAYS BEFORE YOU PLAN TO DIG A FULL DRAFTING PACKAGE SHOULD CONSIST OF: 1. A GEOSPATIALLY ACCURATE BASE DRAWING SHOULD BE OBTAINED FROM THE CIVIL CONSULTANT. IT SHOULD BE IN NAD 83 COORDINATES AND IT SHOULD BE SPECIFIED WHETHER IN GROUND OR GRID PROJECTION AND STATE THE MONUMENTS USED AND THE SCALING FACTOR USED. THESE STEPS WILL HELP IMPROVE THE GEOSPATIAL RELIABILITY OF ALL UTILITY DRAWINGS . FOR MORE INFORMATION REFER TO THE CSA S250-11STANDARDS DOCUMENT WHICH COVERS INFORMATION WHICH WILL HELP STANDARDIZE UNDERGROUND DRAWINGS IN UTILITIES AND MUNICIPALITIES THROUGHOUT CANADA. 2. AN EASEMENT DRAWING WHICH WILL SHOW THE LOCATION AND TYPES OF EASEMENTS FOR THE PROJECT. 3. A PLANVIEW LAYOUT WHICH WILL SHOW THE CENTRELINE OF THE UTILITIES TRENCH BOTH ON PUBLIC ROADWAY AND ON THE PROPOSED EASEMENTS. THERE SHOULD BE AMPLE DIMENSIONING OF OFFSETS FROM PROPERTY LINE TO THE TRENCH CENTRELINE. THE DRAWING SHALL IDENTIFY THE AS-BUILT ACCURACY AS DEFINED BY THE FOLLOWING LEVELS: CSA S-250 DEFINED POSITIONAL ACCURACY OF AS BUILT RECORDSIS AS FOLLOWS: ACCURACY LEVEL 1 +-25mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTE - SURVEY GRADE) ACCURACY LEVEL 2 +- 100mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTE - SURVEY GRADE) ACCURACY LEVEL 3 +- 300mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTEOR RELATIVE) ACCURACY LEVEL 4 +- 1000mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTEOR RELATIVE) THE FOLLOWING ARE FOR SUPPLEMENTARY ACCURACY LEVEL 5 +- 1000mm BUT NOT EXPOSED IE: U/G LOCATE EQUIPMENT USED BY ACOMPETENT INDIVIDUAL - THERE IS NO Z COMPONENT SUPPLEMENTARY ACCURACY LEVEL 0 NO INFORMATION AVAILABLE, THE POSITION SHOWN ON THE DRAWING IS THE BEST POSSIBLE ESTIMATE OF THE ACTUAL LOCATION. A MINIMUM ACCURACY LEVEL 5 IS REQUIRED FOR ALL AS-BUILT DRAWINGS. ACCURACY LEVEL 2 IS PREFERRED FOR ABOVE GROUND FACILITIES. 4.A POWER OVERVIEW SHEET 5 A POWER SCHEMATIC SHEET DETAILING THE PRIMARY AND SECONDARY CONDUCTOR INFORMATION AND CONNECTIONS 6. STREET LIGHT LAYOUT SHOWING SUPPLY CONDUIT PEDESTAL DETAILS AND LIGHTING PROFILES AND DESIGN CRITERIA FOR THE SUBDIVISION STREET LIGHTING INCLUDING THE CONNECTION POINT TO THE ELECTRICAL SYSTEM.. 7. SASK ENERGY LAYOUT SHOWING PROPOSED AND EXISTING GAS INFORMATION AS REQUIRED BY THE UTILITY 8. SASK ENERGY LAYOUT STAKER`S COPY (FOR AS-BUILT FIELD NOTES) NOTE: A SET OF LAYOUTS SUFFIXED _ASB ARE INCLUDED FOR THE AS-BUILT DRAWING PRODUCTS SASK 1ST CALL LOGO MUST BE PLACED ON EACH DRAWING

Transcript of UNDERGROUND DUCT AND STRUCTURES FOR ??? DISTRICT …

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

SHEET

---- REGION

??? DISTRICT OFFICE

UNDERGROUND DUCT AND STRUCTURES FOR

SaskPower and SaskEnergy Turnkey Template R1 EXAMPLE1 7 D 0

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

A FULL DRAFTING PACKAGE SHOULD CONSIST OF:

1. A GEOSPATIALLY ACCURATE BASE DRAWING SHOULD BE OBTAINED FROM THE CIVIL CONSULTANT. IT SHOULD BE IN NAD 83 COORDINATES AND IT SHOULD BE

SPECIFIED WHETHER IN GROUND OR GRID PROJECTION AND STATE THE MONUMENTS USED AND THE SCALING FACTOR USED.

THESE STEPS WILL HELP IMPROVE THE GEOSPATIAL RELIABILITY OF ALL UTILITY DRAWINGS . FOR MORE INFORMATION REFER TO THE CSA S250-11STANDARDS

DOCUMENT WHICH COVERS INFORMATION WHICH WILL HELP STANDARDIZE UNDERGROUND DRAWINGS IN UTILITIES AND MUNICIPALITIES THROUGHOUT CANADA.

2. AN EASEMENT DRAWING WHICH WILL SHOW THE LOCATION AND TYPES OF EASEMENTS FOR THE PROJECT.

3. A PLANVIEW LAYOUT WHICH WILL SHOW THE CENTRELINE OF THE UTILITIES TRENCH BOTH ON PUBLIC ROADWAY AND ON THE PROPOSED EASEMENTS. THERE

SHOULD BE AMPLE DIMENSIONING OF OFFSETS FROM PROPERTY LINE TO THE TRENCH CENTRELINE.

THE DRAWING SHALL IDENTIFY THE AS-BUILT ACCURACY AS DEFINED BY THE FOLLOWING LEVELS:

CSA S-250 DEFINED POSITIONAL ACCURACY OF AS BUILT RECORDSIS AS FOLLOWS:

ACCURACY LEVEL 1 +-25mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTE - SURVEY GRADE)

ACCURACY LEVEL 2 +- 100mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTE - SURVEY GRADE)

ACCURACY LEVEL 3 +- 300mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTEOR RELATIVE)

ACCURACY LEVEL 4 +- 1000mm IN X,Y, AND Z CORDINATES WITH 95% CONFIDENCE LEVEL (ABSOLUTEOR RELATIVE)

THE FOLLOWING ARE FOR

SUPPLEMENTARY ACCURACY LEVEL 5 +- 1000mm BUT NOT EXPOSED IE: U/G LOCATE EQUIPMENT USED BY ACOMPETENT INDIVIDUAL - THERE IS NO Z

COMPONENT

SUPPLEMENTARY ACCURACY LEVEL 0 NO INFORMATION AVAILABLE, THE POSITION SHOWN ON THE DRAWING IS THE BEST POSSIBLE ESTIMATE OF THE

ACTUAL LOCATION.

A MINIMUM ACCURACY LEVEL 5 IS REQUIRED FOR ALL AS-BUILT DRAWINGS. ACCURACY LEVEL 2 IS PREFERRED FOR ABOVE GROUND FACILITIES.

4.A POWER OVERVIEW SHEET

5 A POWER SCHEMATIC SHEET DETAILING THE PRIMARY AND SECONDARY CONDUCTOR INFORMATION AND CONNECTIONS

6. STREET LIGHT LAYOUT SHOWING SUPPLY CONDUIT PEDESTAL DETAILS AND LIGHTING PROFILES AND DESIGN CRITERIA FOR THE SUBDIVISION STREET LIGHTING

INCLUDING THE CONNECTION POINT TO THE ELECTRICAL SYSTEM..

7. SASK ENERGY LAYOUT SHOWING PROPOSED AND EXISTING GAS INFORMATION AS REQUIRED BY THE UTILITY

8. SASK ENERGY LAYOUT STAKER`S COPY (FOR AS-BUILT FIELD NOTES)

NOTE: A SET OF LAYOUTS SUFFIXED _ASB ARE INCLUDED FOR THE AS-BUILT DRAWING PRODUCTS

SASK 1ST CALL LOGO

MUST BE PLACED ON

EACH DRAWING

M

R

1

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

SHEET

---- REGION

??? DISTRICT OFFICE

UNDERGROUND DUCT AND STRUCTURES FOR

SP7890123-RA1 1 D 0

EASEMENT

DRAWING

4 PARTY EASEMENT

4.0 meters

SASK ENERGY EASEMENT

3.0 meters

3 PARTY EASEMENT

3.0 meters

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

NOTES:

THE LANDBASE AND EASEMENT PLAN IS

PRELIMINARY AND MAY NOT BE

REGISTERED WITH ISC.

THE EASEMENT DRAWING MUST

INDICATE IF THE EASEMENTS ARE

PROPOSED OR REGISTERED WITH

ISC.

FOR EACH REVISION, INDICATE A

REMARK, DESIGNER, AND DATE

SCALE BAR MUST

MATCH VIEWPORT SCALE

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

LEAVE YELLOW AND BLUE #1 AL COILS AT

EXISTING TEMP PEDESTAL. SASKPOWER

CREWS TO REMOVE PEDESTAL AND

SPLICE BLUE AND YELLOW PRIMARY

CONDUCTORS.

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

SHEET

REGINA

UNDERGROUND DUCT AND STRUCTURES FOR

CREEKS PHASE 4

SERVICE PROVIDER NAME

NOTIFICATION NUMBER 2341235321

U07-23412343 7 D 1

1:500

2012-12-26

SHOWS THE CENTRE OF THE

TRENCH ALIGNMENT

GEO-SPATIALLY CORRECT. THE

PLAN VIEW DOES NOT SHOW WHAT

CABLES ARE INSTALLED IN THE

TRENCH; REFER TO THE

SCHEMATIC.

DIMENSIONED TO TRENCH

CENTERLINE

REPRESENTS THE 4-PARTY

SERVICE STUB BOX IN EACH LOT

ANNOTATE ANY ROAD CROSSINGS

ALL DEEP UTILITIES ARE SHOWN IN

LIGHT GRAY IN THE BACKGROUND

FOR REFERENCE

M

R

1

LEAVE YELLOW AND BLUE #1 AL COILS AT

EXISTING TEMP PEDESTAL. SASKPOWER

CREWS TO REMOVE PEDESTAL AND

SPLICE BLUE AND YELLOW PRIMARY

CONDUCTORS.

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

SHEET

REGINA

EAST

UNDERGROUND DUCT AND STRUCTURES FOR

CREEKS PHASE 4

SERVICE PROVIDER NAME

U07-23412344 7 D 1

1:500

2012-12-26

LEAVE YELLOW AND BLUE #1 AL COILS AT

EXISTING TEMP PEDESTAL. SASKPOWER

CREWS TO REMOVE PEDESTAL AND

SPLICE BLUE AND YELLOW PRIMARY

CONDUCTORS.

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

SHEET

REGINA

WORK ORDER NUMBER 123298908

PRIMARY AND SECONDARY SCHEMATIC DIAGRAM

CREEKS PHASE 4

NOTIFICATION NUMBER 12344555

U07-23412345 7 D 1

N.T.S.

2012-12-26

PEDESTALS TO BE ORIENTED SUCH

THAT THE SHADED SIDE FACES THE

SOURCE TRANSFORMER

DO NOT ANNOTATE SECONDARY

CABLE. REFER TO THE LEGEND AND

LINE TYPES.

CABLE FORMAT:

[NUMBER OF CABLES][CABLE

TYPE][CABLE PHASE]

I.E.: ONE CABLE OF #1AL ON BLUE

PHASE IS ANNOTATED AS 1X#1ALB

GIVE CREWS DETAILED

INSTRUCTIONS AT TIE-IN POINTS

PEDESTAL NUMBERS ARE FOR

REFERENCE ONLY. THEY WILL NOT

REPRESENT ANY NUMBER IN THE

FIELD OR AS-BUILT. TO BE USED

DURING THE I.F.R. AND

CONSTRUCTION STAGE FOR

CLARIFICATION.

INCLUDE LEGAL BLOCK LETTER

REFERENCES ON SCHEMATIC

INCLUDE STREET NAMES ON

SCHEMATIC FOR APPROXIMATE

REFERENCE

SCHEMATIC SHOULD BE NOT TO

SCALE (N.T.S.). IT SHOULD NOT BE

GEOSPATIALLY PLACED.

LABEL TRANSFORMERS AS AAAA,

BBBB, CCCC, INITIALLY; THE

SASKPOWER DESIGN LEAD WILL

PROVIDE ACTUAL NUMBERS

DURING I.F.R. STAGE.

M

R

1

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

SHEET

REGINA

EAST

STREET LIGHTING

SUBDIVISION NAME

SERVICE PROVIDER NAME

U07-23412346 7 D 1

1:750

2012-12-26

CONSTRUCTION NOTES:

1. INSTALL WASHINGTON POSTLIE 150W HPS LUMINAIRE AS PER

B-20-40 COLUMN A

2. ALL LUMINAIRES INCLUDE PHOTO CONTROL (STOCK #31640)

3. MOUNTING HEIGHT IS 4.88 m

4. Include B-20-35 fuse at all street light connections in the transformer.

DESIGN NOTES:

1. IES PHOTOMETRIC FILE IS AW15AHP00X3NXX

2. LIGHT LOSS FACTOR USED IS 0.65 AS PER SEP 4 DRAFT

3. LIGHTING MEETS IES SPECIFICATIONS BASED ON ILLUMINANCE

METHOD

4. MAXIMUM ALLOWED VOLTAGE DROP IS 8%. THERE ARE NO

VOLTAGE DROP ISSUES IN THIS DESIGN.

LUMINAIRE TEMPLATES CAN BE

IMPORTED FROM AGI32 SIMULATION

SOFTWARE IF AVAILABLE

ANNOTATE WORST CASE VOLTAGE

DROP

INDICATE THE LIGHTING LEVELS AS

PER IES AND RP8

INDICATE IF STREET LIGHT CABLE

WILL BE IN A JOINT TRENCH

OFFSET TO THE TRENCH

CENTERLINE

IDENTIFY WHICH LUMINAIRES ARE

USED IN THE DESIGN

M

R

1

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

SHEET

REGINA

EAST

UNDERGROUND DUCT AND STRUCTURES FOR

SUBDIVISION NAME

SERVICE PROVIDER NAME

E07-12312988

7 7 D 11:750

2012-11-26

REFERENCE EACH

MATERIAL ITEM USED AT

EACH LOCATION

SHOW WHICH SIDE OF THE TRENCH

GAS IS PLACED RELATIVE TO

OTHER 3 PARTIES

ANNOTATE WEHN GAS CROSSES

OVER OTHER FACILITIES

EACH LOT SHOWS A STUB AT THE

LOCATION OF THE 4-PARTY

SERVICE STUB BOX

GIVE DETAILED TESTING

INSTRUCTIONS TO THE CREWS AT

EACH TESTING POINT

OFFSET SHOULD BE TO EXACT

LOCATION OF THE PIPE

ANNOTATE THE EXACT DISTANCE

OF EACH STUB

PROPOSED GAS PIPE IS SHOWN IN

BLUE

EXISTING GAS PIPE SHOWN IN

GREEN

BREAK THE POLYLINE AT THE

EXACT LOCATION OF THE

REDUCER, BUT PLACE THE

REDUCER SYMBOL IN A VISUALLY

DISTINGUISHABLE LOCATION ON

THE LINE

ANNOTATE THE SIZE AND TYPE OF

EACH PIPE

M

R

1

THE CREEKS

PHASE

4

A

R

C

O

L

A

A

V

E

E

C

H

U

K

A

B

L

V

D

S

A

N

D

P

I

P

E

R

C

R

E

S

REGINA,SASKATCHEWAN

CALL AT LEAST TWO FULL

WORKING DAYS BEFORE

YOU PLAN TO DIG

SHEET

REGINA

EAST

UNDERGROUND DUCT AND STRUCTURES FOR

SUBDIVISION NAME

SERVICE PROVIDER NAME

E07-12312988

7 7 D 11:750

2012-11-26

THE STAKER'S COPY IS THE SAME

AS THE CONSTRUCTION DRAWING,

BUT SHOWS ONLY THE PIPE

LAYOUT.