UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

19
UNIVERSITY OF MINES AND TECHNOLOGY FACULTY OF MINERAL RESOURCES TECHNOLOGY MINING ENGINEERING DEPARTMENT SEMINAR PRESENTATION TOPIC ASSESSMENT OF THE DEVELOPMENT AND STOPING EFFICIENCIES OF A MINING BLOCK - A CASE STUDY BY: SUPERVISOR: OBENG-SIKA JOSEPH MR. EMMANUEL M. BUABA 1

Transcript of UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

Page 1: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

UNIVERSITY OF MINES AND TECHNOLOGY

FACULTY OF MINERAL RESOURCES TECHNOLOGY

MINING ENGINEERING DEPARTMENT

SEMINAR PRESENTATIONTOPIC

ASSESSMENT OF THE DEVELOPMENT AND STOPING EFFICIENCIES OF A MINING BLOCK -

A CASE STUDY

BY: SUPERVISOR:OBENG-SIKA JOSEPH MR. EMMANUEL M. BUABA

1

Page 2: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

MODE OF PRESENTATIONPROBLEM DEFINITION OBJECTIVESMETHODS USED DATA ANALYSISCONCLUSIONSRECOMMENDATIONS

2

Page 3: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

STATEMENT OF PROBLEMUnderground mine development involves the

excavation of series of openings to gain access to the orebody for eventual stope production.

For enhanced stope productivity, development operations is co-ordinated with production stages.

AGA Obuasi Mine has been a vibrant underground mine and a major backbone of the Ghanaian economy for several decades.

3

Page 4: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

STATEMENT OF PROBLEM CONT’D

The mine has experienced a decline in its production tonnages for the past few years primarily due to the fall in the rate of advance of secondary development openings.

This project seeks to assess the efficiencies of the secondary development and stoping operations of the Brown Sub Vertical Shaft (BSVS) Mine of AGA.

4

Page 5: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

OBJECTIVESTo determine the development efficiency

(Ed) of the block.

To determine the stoping efficiency (ES) of the block.

To identify the relationship between the development and stoping efficiencies of the block.

5

Page 6: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

METHODS USEDLiterature review on the subject area

Field visits and interaction with personnel at the stopes in Block 8 Lower of BSVS Mine.

Analysis of collected data

6

Page 7: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS

Fig. 1 Development Cycle in Underground Mines 7

Page 8: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

Fig. 2 Sublevel Stoping Cycle 8

Page 9: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

Janua

ry

Febr

uary

March

April

May June

July

Augus

t

Sept

embe

r

Octobe

r

Novem

ber

Decem

ber

0

50

100

150

200

250

300

FORECAST ACHIEVED AVERAGE ACHIEVED AVERAGE FORECAST

Adva

ncem

ent

(m)

Fig. 3 Development Advance for 2013 9

Page 10: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

Janua

ry

Febr

uary

March

April

May June

July

Augus

t

Sept

embe

r

Octobe

r

Novem

ber

Decem

ber

0

5,000

10,000

15,000

20,000

25,000

FORECAST ACHIEVED AVERAGE FORECAST AVERAGE ACHIEVED

Prod

ucti

on T

onna

ges

(t)

Fig. 4 Production Tonnages for 2013 10

Page 11: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

=

11

Page 12: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

 MONTH

 

ACHIEVED DEVELOPMENT (m) ACHIEVED

TONNAGES (t)

DEVELOPMENT EFFICIENCY

(m3/t)LATERAL VERTICAL

January 141.6 33 18,812 130.54February 175.4 40 15,737 192.98

March 178.8 40 14,974 206.44April 203.7 40 18,715 186.47May 181.7 40 16,315 192.31June 214.1 40 15,333 238.44July 214.6 20 12,182 291.32

August 225.3 19 16,451 225.78September 223.0 34 15,251 246.80

October 239.1 33 16,097 249.47November 265.5 15 13,472 321.73December 213.0 49 17,778 207.57

Table 1 Monthly Development Efficiencies for 2013

12

Page 13: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

MONTH No. of Days ACHIEVED Es (t/employee-

shift)January 31 18,812 37.93

February 28 15,737 35.13March 31 14,974 30.19April 30 18,715 38.99May 31 16,315 32.89June 30 15,333 31.94July 31 12,182 24.56

August 31 16,451 33.17September 30 15,251 31.77

October 31 16,097 32.45November 30 13,472 28.07December 31 17,778 35.84

Table 2 Monthly Stoping Efficiencies for 2013

13

Page 14: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

Januar

y

Febru

ary

March

April MayJune

July

August

Septe

...

October

Nove..

.

Decem

ber50

100

150

200

250

300

350

Development Ef -ficiencyAverage Devel-opment Efficiency

Dev

elop

men

t Effi

cien

cy (

m³/

t)

Fig 5 Development Efficiency Trend for 2013 14

Page 15: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

Janua

ry

Febr

uary

March

April

May June

July

Augus

t

Sept

e...

Octobe

r

Novem

ber

Decem

ber

10

20

30

40

50

60

Stoping Efficiency Average Stoping EfficiencyMaximum Stoping Efficiency Minimum Stoping Efficiency

Stop

ing

Effici

ency

(t/e

mpl

oyee

-shi

ft)

Fig. 6 Monthly Stoping Efficiencies Against Standardised Values 15

Page 16: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

DATA ANALYSIS CONT’D

16

24 26 28 30 32 34 36 38 4050

100

150

200

250

300

350

f(x) = − 10.3870285802834 x + 564.347288121788R² = 0.682399192336567

Stoping Efficiency (t/employee-shift)

Dev

elop

men

t Effi

cien

cy (

m³/

t)

Fig 7 Relationship Between Development and Stoping Efficiencies

Page 17: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

CONCLUSIONThe average monthly Ed was 224.23 m3/t,

implying for every 10 m advance, a tonne of ore is obtained.

The ES ranged between 24.56 t/employee-shift to 38.99 t/employee-shift.

Ed is inversely proportional to ES.

17

Page 18: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

RECOMMENDATIONSJumbos should be employed over the

use of jackhammers.

Development and stope preparations should be done in advance as the current stope is mined to allow for concurrent stoping.

Standard ES and Ed values should be generated against which field values are assessed. 18

Page 19: UNDERGROUND DEVELOPMENT AND STOPING EFFICIENCY CORELLATION

THANK YOU

19