Unavoidable Impacts of Streetworks Legislation Jon Butterworth MBE Director, National Operations
description
Transcript of Unavoidable Impacts of Streetworks Legislation Jon Butterworth MBE Director, National Operations
Unavoidable Impacts of Streetworks Legislation
Jon Butterworth MBE Director, National Operations
National Grid in the UK/US
UK: Owns high-voltage electricity transmission network in England and Wales and operates system across Great Britain
UK: Owns and operates high pressure gas transmission system in Britain. Distribution business delivers gas to 11
million homes and businesses
Distributes electricity to 3.3 million customers and provides natural gas to 3.5 million customers
Services 1.1 million customers of Long Island Power Authority (LIPA)
Currently owns over 4,000MW of generation
3
National Grid’s Distribution Operations Opex - £180m Capex - £70m Repex - £450m
Miles of pipe: 82,000
Customers: 11 million
Staff: 5300 (Direct Labour and Contractors)
Metering: 616,000 jobs
Emergency: 533,000 jobs
Gas Escapes: 70,000 jobs (7000 interference damage jobs)
Relay after escape: 20,000 jobs
Mains replacement/reinforcement: 2000km
Connections: 24,000 jobs
Winter / Trigger Survey: Full Network
High Rise Flats: 400 projects, 6,000 meter points
Diversions Major: 45km
20 major Incidents
Our job is to SAFEGUARD….
LIFE PROPERTY SECURITY OF SUPPLY
•Gas Emergency Service, 30/30 Mains Replacement Programme, Pass55 Asset Maintenance Programme, Domestic Connections,
Roadworks/Diversions and 3rd Party Activities
Range of Legislation and Governance• Pipeline Safety Regulation (Regulation
13) 1996
• Pipeline Safety Regulation ( Regulation 13A) 2003
• Traffic Management Act
• New Roads and Streetworks Act (NRSWA) 1991
• Construction Design and Management Regulations
• Control of Major Accident Hazards Regulations
• Corporate Manslaughter Legislation
• PAS-55 Asset Maintenance
• Streetworks Authorities (SA’s) Traffic Managers
• Permits – Ability to apply conditions
• Traffic Management Design
• Section 58 & 58A – Power to restrict
• Section 56 – Power to direct
• Section 54 – Advance notice
Poor Planning Poor Coordination
Legislation and its Impact on StreetworksA Constantly Moving Feast
S74 Charging
COP for Inspection’s
COP for Safety
Yorkshire Permits
LoPS – Tranche 2
Lane Rental
Northamptn Permits
Gtr Man Permits Scheme
2010-2011 2011-2012
Legislation changes currently being considered and may land soon?
“Every time there is a change to legislation it takes time to understand, implement and
embed these in to an organisation.
Some changes have also led to reduced productivity,
increased duration of works and increased customer
costs”
Legislation and the Cost Impact
0
30
60
Year
Mill
ion
s (
£)
S73/78 Legislation
Proposed Lane Rental
Permits (National)
Permits (London)Inspections
Increased costs from legislation changes - worst case costs assuming current levels of performance
Impact of London Permit Scheme on Productivity
Key Message
Central London productivity on mains replacement has reduced by 38% since the introduction of the Permit Scheme in the LA’s
which have implemented LPS.
Planned Works
National Grid - we are not sitting still…..Lean/Six Sigma Review has reduced unoccupied time on site
KPI 1 performance is as follow:-
NationalKPI 1 Banding Apr-10 May-10 Jun-10 Jul-10 Aug-100-2 7% 8% 9% 9% 14%2-4 22% 25% 24% 29% 39%4-5 31% 34% 34% 42% 52%5-7 56% 63% 64% 72% 75%7-10 78% 83% 82% 85% 88%10-20 93% 94% 94% 94% 96%20-30 97% 97% 96% 96% 98%>=30 100% 100% 100% 100% 100% KPI 2:-
NationalKPI 2 Banding Apr-10 May-10 Jun-10 Jul-10 Aug-100-2 49% 68% 69% 72% 72%2-4 57% 80% 82% 84% 86%4-6 63% 87% 87% 89% 91%6-10 69% 94% 94% 95% 95%10-20 73% 98% 98% 98% 99%20-30 74% 99% 99% 100% 100%>=30 100% 100% 100% 100% 100% KPI 3:-
NationalKPI 3 Banding Apr-10 May-10 Jun-10 Jul-10 Aug-100-1 1% 1% 1% 1% 4%1-2 5% 7% 9% 9% 21%2-3 14% 20% 22% 27% 44%3-5 34% 50% 49% 58% 72%5-7 58% 86% 86% 90% 92%7-10 73% 98% 97% 98% 98%10-20 76% 100% 99% 100% 100%>=20 100% 100% 100% 100% 100%
42% improvement
40% improvement
53% improvement
Duration in days of end to end repair process; open
notice to job closure
Duration in days of repair make safe process; measure
of time between notice request and request for reinstatement
team
Duration in days of reinstatement process; request
reinstatement to physical completion of reinstatement
work
Emergency Works
We are not sitting still….Committed to our Customers
National Grid takes Customer inconvenience seriously and is committed to finding solutions that minimise disruption to our stakeholders
Customer Communication
No Dig Solutions
Core & Vac, Trenchlink
and Forge
We are not sitting still…...Good Practise Becomes Common Practise
”
Digfest – Upper Thames
Street 14 Dec 08
Committed to the Code of Conduct
Summary
• Pipeline Safety Regulation (Regulation
13) 1996• Pipeline Safety
Regulation ( Regulation 13A) 2003• Traffic Management
Act• New Roads and
Streetworks Act (NRSWA) 1991• Construction Design
and Management Regulations• Control of Major
Accident Hazards Regulations• Corporate Manslaughter
Legislation• PAS-55 Asset Maintenance• Streetworks Authorities (SA’s) Traffic Managers• Permits – Ability to
apply conditions• Traffic Management Design
• Section 58 & 58A – Power to restrict• Section 56 – Power to
direct• Section 54 – Advance
notice
S74 Charging
COP for
Inspection’s
COP for Safety
Yorkshire Permits
LoPS – Tranche 2
Lane Rental
Northamptn
Permits
Gtr Man Permits
Scheme
Our job is to safeguard life
We are heavily codifiedLegislation changes present our
business with significant challenges
We are committed to the Code of Conduct