UMKHANYAKUDE DISTRICT MUNICIPALITYukdm.gov.za/~ukdmgov/images/documents/Finance/NON... ·...
Transcript of UMKHANYAKUDE DISTRICT MUNICIPALITYukdm.gov.za/~ukdmgov/images/documents/Finance/NON... ·...
UMKHANYAKUDE DISTRICT MUNICIPALITY
NON-FINANCIAL MID-YEAR PERFORMANCE ASSESSMENT REPORT
1 JULY 2018 TO 31 DECEMBER 2018
Contents
1. Background ..................................................................................... 3
2. Key Performance Area Analysis ...................................................... .4
3. Recommendations/Planned Improvements ................................... 5
4. ANNEXURES .................................................................................... 5
4.1 Organisational Scorecard- 2018/2019 ...................................... 5
4.1 Mid-year Performance report for uMhlosinga Development
Agency- 2018/2019 ........................................................................ 5
2
1. BACKGROUND
The Performance Management System (PMS) is the primary mechanism to monitor,
review, and improve the implementation of IDP and to gauge the progress made in
achieving the objectives set out in the IDP. Furthermore, the PMS assists the
Municipality and Council to facilitate increased accountability, learning and
improvement, provide early warning signals and facilitate decision-making. This report
represents organisational targets that were selected per Key Performance Area.
Measurement of performance is engaged whereby a formal process of collecting and
capturing performance data to enable reporting takes place for each key performance
indicator and against the target set for such indicator. When performance
measurement is due, managers are expected to collect and collate the necessary
performance data or information and capture the result against the target for the
period concerned on the organizational scorecard and relevant SDBIP scorecard and
report the result accordingly.
Performance management then gets underway resulting in analysis which involves the
process of making sense of measurements. It requires interpretation of the
measurements as conducted in terms of the performance measurement to determine
whether targets have been met and exceeded and to project whether future targets
will be met or not. Where targets have not been met, performance analysis requires
that the reasons therefore should be examined and corrective action be taken, Where
targets have been met or exceeded, the key factors that resulted in such success
should be documented and shared so as to ensure organizational learning.
3
2. Key Performance Area Analysis
The following KPAs are analysed in a table format to illustrate areas of achievement and those that require more attention:
1. Municipal Transformation and Institutional Development 2. Service Delivery and Infrastructure Investment 3. Local Economic Development 4. Municipal Financial Viability and Management 5. Good Governance and Public Participation 6. Cross Cutting Interventions
• 59 organisational targets were selected to be reported on through SDBIP;
• Of the 59 targets, 2 were not due to be reported on as they are applicable TO quarter 1 ad 4;
• 26 out of 57 targets (including 13 targets partially achieved) were not achieved which represented 46% for the mid-year period;
• 31 out of 57 targets were achieved at an organisational level which represented 54% for the period under review
4
3. RECOMMENDATIONS/PLANNED IMPROVEMENTS
Challenges Recommendations ..
• There is poor alignment between • The process of reviewing targets must be
the organisational scorecard and concluded and be implemented for Q3 and
SDBIP Q4
• Formal performance evaluations • A suitable date must be identified and the
for the mid,year are still due performance evaluation committee must be
invited to conduct performance evaluations
• Lack of human resource capacity • Capable individuals to be identified and
to provide necessary support in provided with in-house training so as to
the in preparing departmental assist in preparing credible reports for
reports departments
• Accuracy of information • Departments must ensure that there is
submitted needs to be improved portfolio of evidence for all targets that
have been reported and information
supporting targets must be verifiable
• Some targets need to be • Whole numbers and percentages should be
reviewed more especially water considered in reporting water and
and sanitation so that they relate sanitation targets
better to issues of access and
backlogs
• Generally the culture of • Monitoring and evaluation processes as
performance management still well as oversight should be strengthened so
needs to be improved as to give thorough attention on non-
financial performance issues
4. ANNEXURES
4.1 Organisational Scorecard- 2018/2019
4.1 Mid-year Performance report for uMhlosinga Development Agency- 2018/2019
N. P- Mthlyane IDP/PMS Manager
5
,,~ Acting Municipal Manager
; 1
i I l ! ;
.-a ' 2 2 ' ' ' J
UMHLOSINGA DEVELOPMENT AGENCY
MID YEAR BUDGET AND
PERFOMANCE ASSESSMENT
2018/19
1. Pumose
The purpose of this report is to inform the Board of directors, on the mid-year budget and performance assessment for the Agency
as at 31 December 2018.
2. Legislative framework
Municipal Finance Management Act 56 of 2003, section 88 requires:
(1)The accounting officer of a municipal entity must by 20 January of each year-
(a) assess the performance of the entity during the first half of the financial year, taking into account-
(i) the monthly statements referred to in section 87 for the first half of the financial year and the targets set in the service
delivery, business plan or other agreement with the entity's parent municipality; and
(ii) the entity's annual report for the past year, and progress on resolving problems identified in the annual report; and
(b) submit a report on such assessment to-
(i) the board of directors of the entity; and
(ii) the parent municipality of the entity.
(2) A report referred to in subsection (1) must be made public.
For the purpose of this report, the operating budget, the service delivery and budget implementation plan, the annual report, the monthly
statements in tenns of section 87 of the MFMA and the actual performance in terms of the operating budget for the first six months of the
financial year have been used for the assessment.
3. DISCUSSION
REVENUE
For the first six months of the 2018/2019 financial year the performance of the actual revenue measured against the pro-rata budgeted
revenue can be summarized as follows:
21P >l g c -------~---
("!J,j[(~<)/1:
-- - "-·- - --- ---- - ---- ----2018/2019 Mid-Term 2018/19
Annual Budget Budget llc111Cfl _ _l..:!5!!.iance Voraince ReosotJs
Conditional Income
CATHSETA 1,266,400 633,200 879,276 246,076
ED TEA 30,000,000 15,000,000 0 (15,000,000)
MTN Business Enhanc. 515,000 257,500 0 (257,500)
I DC Packaging Machine 2,700,000 1,350,000 2,000,000 650,000
34,_48~,400 17,240,700 2,879,276 (14,361,424)
I
Operatin~ Income
Umkhanyakude DM 12,605,692 6,302,846 8,403,795 2,100,949 Only R4 201897 transferred
12,605,692 6,302,846 8,403,795 2,100,949
Other Income
Airport Fees 166,451 83,225.52 34,057 (49,169) ...
Interest on Investment 90,249 45,124.61 37,872 (7,253)
Other Income 29,931 14,965.72 (14,966)
Tender Monies 24,501 12,250.43 17,217 4,967
311,133 155,566 89,146 (66,421)
Total Income 47,398,225 23,699,112 11,372,216 (12,326,896)
The agency has projected to receive a total budget of R47 398 225 for the year 2018/19, based on the mid-year
assessment, the Agency has secured R11 372 216 for the first six months that indicate a short fall of R12 326 896
against the total budget.
The shortfall was caused mainly by the following reasons:
• The parent municipality is still to transfer second quarter operational grant.
• The EDTEA grant was not received, the CEO is following up the reasons why the department has not
approved the transfer of funds.
• As the project were not received, no tender sold and no investment made.
EXPENDITURE
3]Page
For the first six months of the 2018/19 financial year the performance of the actual expenditure compared with the pro-rata budget
can be summarized as follows
-~== - """-- --~--
" ___ " ________ 2018/2019 Mid-Term 2018/19 "_, ____
~"~~-
Annual Budget Budget flctllul " Variance Vantince Reasons -~·-~---~ ~~
Operating Expenditure Prevouis year S&Twhich was
Employee costs 6,800,000 3,400,000 3,542,867 (142,8671 not paid, paid in November
Training 100,000 50,000 28,570 21,430 New approved tarrifffor
Board of Directors 1,000,000 500,000 525,676 (25,676) board members
Security 6,420 3,210 2,768 442
Bank charges 22,326 11,163 10,224 938
Yearly paid, the estimate is
Insurances 32,330 16,165 32,141 (15,976) proratated
Internet and website 74,900 37,450 22,407 15,043
Office equipment rentals 85,600 42,800 50,642 (7,842)
Telephone and telefax 50,000 25,000 14,165 10,835
Printing and Stationery 35,000 17,500 6,963 10,537
Internal audit 316,000 158,000 153,376 4,624
Yearly paid, the estimate is
J\uditors general fees 492,307 246,154 415,978 (169,825) proratated
Legal Fees 50,000 25,000 - 25,000
Marketing Collateral 400,000 200,000 200,000
Audit Committee 350,000 175,000 71,086 103,914 -------- ----------Accomodation and car rentals 150,000 75,000 59,697 15,303
----------- - - ---------£1ccountirJ![fe es(l ice nee) 25,694 12,847 8,314 4,533
Adv_ertisin.!L _____ 5,000 2,500 11,700 (9,200) CEO post was costly Not budgeted at the begin of
Airport operations 38,907 (38,907) the year - --
Interest Paid 8,081 4,040 - 4,040 -- " -
Cleaning Material 5,725 2,862 5,459 (2,597) -------
Conference Workshop 38,405 19,203 12,965 6,238
"Depreciation on fixed assets 300,000 150,000 - 150,000
Repairs and maintenance 13,500 6,750 6,250 500 --~-- I"""""
Investment Promotion 300,000 150,000 - 150,000
"!otal Operating" Expenditure 10,661,288 5,330,644 5,020,157 310,487
Operating expense overspending was caused mainly by the following reasons:
• Airport operations was not initial budget as the management had negotiations with the district to pay for the costs
directed to the airport outside the budget.
• Board Fees exceeded because new tariff approved by council and number of board members increased as
compared to last year.
41 P a g e
(1f<Jirpa.<<)/l;
------ ---- ----·- --2018/2019 Mid-Term 2018/19
- - -Annual Budget Budget 1\ciua/ i Variance Voraim:e Heason' -- ~-~
Capital Expenditure
Municipal SCOA 788,856 394,428 113,869 280,559 ---
788,856 394,428 113,869 280,559
Projects /Capital Costs
Fresh Produce Online system
(RASET) 500,000 250,000 - 250,000
Feasi bi I ity Studies 1,000,000 500,000 500,000
IDC Packaging Machine 2,700,000 1,350,000 1,370,000 (20,000)
MTN Business Enhanc. 515,000 257,500 - 257,500
CATHSETA 1,203,080 601,540 355,500 246,040 Bursary not yet paid,
Terminal Building 30,000,000 15,000,000 - 15,000,000
RASET / NSN Programme
Assets- Laptops, furniture 30,000 15,000 15,000
35,948,080 17,974,040 1,725,500 16,248,540
Total expenditure 47,398,224 23,699,112 6,859,526 16,839,586
All capital project were underachieve due to the following reason:
• The EDTEA grant was not received, the CEO is following up the reasons why the department has not
approved the transfer of funds.
Overall midterm budget has been maintain except the notes mentioned above. When comparing the income versus the
expenditure, a profit of R4 512 690 is recorded, if the district had transfer the operational grant we would have had that
amount sitting in bank account
51 P 11 g e
4. Performance Management Report
The Mid-term Organizational Scorecard is as follows:
-1' No Checklist Compliance Checklist populated secretary for the task the target or request
reviewed by AC and to be completed. Board to de fer the
Adopted by the Boo. target till Company
Sec is
Shareholder Compact and No target Shareholder Annual Perfonnance Target Compact signed by signed by the UMDA's Mayor and Chairperson of the Board Chairperson and the Parent Municipality's
Quarterly reports submitted Quarter 1: None n/a
to the UKDM Draft Annual Report -1' Draft annual submitted to UKDM report submitted
Quarter 2: -1' Quarter 1 Report Quarter 1 Report submitted submitted toUKDM
Quarterly Board meetings Quarter 1: None n/a
1 Board meeting -1' 1 Board meeting
Quarter 2:
1 Board meeting -1' 1 Board meeting
Registration and training of Quarter 1: Board members were Register Board
Board members Updating Board of -1' Process of only appointed as full- members with laD in
Directors infonnatlon with Updal.ing Board of time members as from the third quarter.
CICP Directors 1 November 2018
infonnation with therefore which led to
Quarter 2: CICP has been the delay in registering
Registration of Board started them with CIPC and
members with laD laD
Quarterly Audit Committee Quarter 1: Audit Committee chair Audit committee
1 AC meeting ./1 AC meeting attended the meeting to be held in
Management meeting quarter 3
Quarter 2: called by the AG.
1 AC meeting There were no Internal
Audit report for the
committee to consider
which led to the
deviation.
Risk monitoring and Quarter 1: was
Risk management ./Quarter 2 Risk planned to be
workshop for Board and Management Report facilitated by the quarter.
Staff Provincial Treasury.
Planning for the Board
Quarter 2: Induction which will
Quarter 2 Risk include the workshop
Management Report led to the deviation.
61Page
Clrrlitp<r.<o11:
iii
KPI
Submission of business
plans and/or proposals for
Agreements with
stakeholders for funding
and/or technical support
Learnership support over
the duration of t>No years
for
Discretionary Grant from
CATHSSETA for 2019/20
Tourism
Facilitation ofT ourism
Career Guidance seminars
per Local Municipality in
uMkhanyakude
Establishment of a Route
22 Management
71 p II f; C
Quarter 1:
2 Business Plans submitted
for funding
Quarter 2:
2 Business Plans submitted
for funding
Quarter 1:
Projects profile
Quarter 2:
Learners
Quarter 1:
Engage institutions
Quarter 2:
AO!FUAL. PEfi~PRMANCE
./ 2 business plans
submitted for funding
./ 4 business plans
submitted for funding
./ Projects profile
./ 6 stakeholders engaged
./ learners attending
training
./ Institutions engaged
Prepare to submit application .; Application prepared
First draft of Skills Audit
questionnaire
Quarter 2: Skills Audit questionnaire
approved by CEO
Schedule of tourism career
guidance seminars or
workshops from
municipalities
Quarter 2:
Attend seminar or workshops
Quarter 1:
Draft Terms of Reference
Quarter 2:
Tenns of Reference
approved by CEO
and advisory committee
established
./ Skills Audit
questionnaire drafted
./ Skills Audit
questionnaire approved
CEO
./No schedule of Tourism
career guidance
workshops
./ Jozini Career Guidance
attended
./Draft Terms of Reference
./ Ternis of Reference
approved by CEO
Clurlrp8.wm:
programme, which
led to the deviation
None
i did not
submit their
schedules which led
to the deviation
n/a
to remove this
target as it is not
which the control
of the UMDA.
n/a
KPI TARGET AC:TUAL
PE~FO~r,IAf.icE
Tourism Assets Quarter 1: The whole district To request Big 5
Database Collect existing database from could not be verified Hlabisa and
LM's ./ Jozini and Mlubatuba which led to deviation. Umhlabuyalinga © municipality municipalities to
2 Quarter 2: submitted their submit in order to
Cross-reference check LM complete the Partly
database Achieved
database with UMDA's verification.
database
Tourism Events Quarter 1: None n/a
ldenlify events to be attended ./ Events identified
Quarter 2: ./ Tourism Event Attend events attended at
UMhlabuyalingana
Municipality
Commissioning of a Quarter 1: Delays in agreement to Appointment of service
Ndumo Pack house Establishment of secondary ./ Secondary Coop not working relationship provider by the 3rd © corporative established with the Coop Jed to quarter.
the deviation. 2 Quarter 2: ./ SCM Process Partly
Appoint a service provider for initiated Ach_leved
the packing facility
Operational Plan Quarter 1: None n/a
Development of operating ./ Process initiated systems
Quarter 2: ./ GIS coordinated for GIS coordinates for the land Food Security site and application for the site
Construction of Quarter 1: None n/a
Terminal Building Approval of designs ./ Designs approved
Quarter 2: ./ SCM process SCM process for the initiated appointment of contractor
Airport maintenance Quarter 1: None n/a
and revenue Quarterly report revenue and ./Report prepared enhancement reports maintenance report
./Report prepared Quarter 2:
Quarterly report revenue and
maintenance report
Completion of PDA Quarter 1: Service provider not Request Board for an
SCM process for the ./SCM process initiated appointed due to a adjustment of target.
appointment of Land Surveyor lack of market The target needs to be
response. adjusted to sourcing
Quarter 2: finds for the
Appointment of service appointment of service
providers providers.
8JPage
KPI ACTION
nla Signing of Performance Agreements signed Agreements
.; Verbal Perfonnance Quarter 2: Reviews conducted
.; Draft annual report the Board adopted by the
Board
Quarter 1: Delays in now 3 S87 (11) reports submitted to .; 6 S87(11) reports implementing MSCOA on time once MSCOA
MM submitted to MM resulted in the is fully operational @ deviation.
Quarter 2: 2
3 S87 (11) reports submitted to Porlly
MM Achieved
2017118 AFS Quarter 1: None
submitted to AG S122 Statements .; S112 Statements
submitted to AG
Process initiated
• Overview of UMOA's Organizational Scorecard performance
Rating Key No of targets Total%
Not Achieved 2 8%
2 Partially Achieved 9 36%
3 Achieved 12 48%
4 Target Exceeded 2 8%
5 Excellent 0 0%
Total 25 100%
Recommendation
For Audit Committee to note the Midterm Assessment Report along with proposed adjustment for the next six months;
For the Board to note the content of this report and consider it for approval of proposed adjustments for the next six months.
91 P 11 g e
T'
QUALITY CERTIFICATE
I, Dr Stanely Sharaunga, Acting Chief Executive Officer of Umhlosinga Development Agency, hereby certify that the mid-year review for
2018/2019 financial year and supporting documentation has been prepared in accordance with the Municipal Finance Management Act, and
the regulations made under the Act, and that the annual budget and supporting documents are consistent with the service level agreement
_with the district municipality.
Dr Stanely Sharaunga
Chief Executive Officer
Umhlosinga Development Agency
lO]Pa~~
------------- -~~--~-~~----~~~-· ' Cluslrp<'T:<i!ll;
To ensure compliance
with legislation
agreement between the UMDA and its Parent Municipality; UKDM must be in place.
!({
-;-h, •• ,.,,,c,h r- ~ . v~. 1 ~ ~ ·~t" ,_,· .-/e_ &..-:-- >L""">f /'lv:<-,(~_1(,
Vil1t'l"lf.i .. sn t~·:::21 .DC :>Z~
Compliance Checklist reviewed by Audit Committee and adopted by Board.
and Annual Performance Target signed by the UMDA's Chairperson of the Board and the Parent Municipality's Mayor
to submitted to the accounting officer
1 Compliance checklists reviewed by Audit Committee and adopted by the Board by 30 June 2019.
Signed Shareholder Compact and 2017/18 Performance Targets by 30 June 2019
4 Quarterly Perfonmance reports submitted to UKDM by 30 June 2019
applic~~le ~0 '-=o-ve-rs""'i--,gh"'t_o_n-----+-=B'"'o-ar--,d:-m-e-e""ti-ng-s---+-;-;;c:o-J-,Q,-u-a-,rte-r71y"'B:-o-a-rd'"'m-e-e-,;ti-ng-s---+-:-N:-u-m7b-er-o-=f_m_e-et"'in_g_s----+-,4-,B:-o-a""rd:-m-e-e-,;ti-ng-s-,-by ____ __,
mnt~t~lclpad perfonmance; risk and 30 June 2019 e 11esan . principals financial controls.
outlined in the Ki~g Ill Report
governance; performance management; risk assessment and financial controls.
members
Number of meetings
and reporting Number of reports
4 Audit Committee meetings 'ny 30 June 2019
Risk management reports for first, second and third quarter submitted to quarterly Audit Committee meeting by 30 June 2019
Pagel ofliW
To create partnership
that encourage investment to
uMkhanyakude
To develop world class Tourism products
Promotion
Tourism Skills development
required for funding and technical support
Research and Knowledge Management
Number of learners
Date completed
Number of events
Skills audit report for uMkhanyakude district by 30 June 2019
Support and participate in 1 district event, trade event and consumer show by 30 June 2019
Page 2 of1(1
To develop sustainable I house
commercialisat ion of
Agriculture and f-=-=-~-Agribusiness Food Security industries in Estate
the UMkhanyakude
District
AGRIBUSINESS DEVELOPMENT
Distribution
Establishing and commissioning of a Fresh Produce Packaging machine at Ndumo by 30 June 2019
pre-requisites for the Food Security Estate and application for funding by 30 June 2019
Page 3 of HI
To develop a 76 Ha plot into an airport and a vibrant multi-use non-aviation prescient with a shopping centre, a hotel, conference
To develop facility, hangers, offices
world class and residential
catalytic apartments
infrastructure
I that promotes Mkhuze
economic Airport Non-
development Aviation
Jozini Hydro To develop a Hydro electronic project
INFRASTRUCTURE DEVELOPMENT
12.5.1 I Construction of Terminal building
I 2.5.2 I Fire and Rescue service I Date of application
I 2.5.3 I Airport maintenance and I Number of reports
revenue enhancement reports
I 2.5.4 I Project phase I Commence PDA process for
Mkhuze Non-Aviation side
2.6 Engagement with Investors for Number of engagements Jozini Hydro
1 0% of Construction of a Mkhuze Airport terminal building by 30 June 2019
Source funding for the Establishment of a Fire and Rescue service at Mkhuze
30 June 2019 4 reports on revenue enhancement by 30 June 2019. Commencement of PDA application to Jozini Municipality by 30 June 2019.
2 engagement with potential investors for Jozini Hydro by 30 June 2019
Page 4 ofHt
lmpll!fllent Performance Management
Performance Management
I llmnlomonl i To improve the capacity of staff for service delivery
Personnel Development Plans
To improve delivery through the implementation of a performance management system
INSTITUTIONAL DEVELOPMENT
reviews of all employees by
30 June 2019
trained
by 30 June 2019
3 positions filled by
30 June 2019
Page 5 ofHt
Sound
Financial
Planning
and
Reporting
Annual Report report on performance of
the UMDA
Budget in line with I Budget
IDP and Strategy
Prepare Budget
2016/17 Budget
preparation
FINANCIAL VIABILITY AND MANAGEMENT
4.2.3 I 2019/20 Budget approved by Board Date approved
Adoption Draft annual report by
the Board by 31 August 2018
report
by the Board by 20 January
2019
approved by Board by 20
January 2019
January 2019
by 20
Approval of 2019/20 Budget by
the Board by 30 May 2019
Page 6 cf 10
------------------- ----~~~~-~~
Report on MFMA S87(11) Reporting 4.3.1 S87 (11) Reports submitted to MM Number of reports 12 reports submitted to MM by
Financial and 30 June 2019
Performance Prepare Interim AFS 4.3.2 Interim AFS submitted to Board and Date submitted Submission of Intern AFS by 20
Management UKDM January 2019
Preparation of MFMA S88 4.3.3 Mid-term budget and performance Date submitted Submission of Mid-term budget
Report assessment report submitted to Board and assessment report to the
and UKDM Board and UKDM by 20 January
2019. I
Preparation of MFMA S122 4.3.4 2017/18 AFS submitted to AG Date submitted Submission of AFS to AG by 31
Statements August 2018
- - - - ---
Page 7 of 11)]
NOTES ON ADJUSTMENTS:
by Audit Committee and adopted by Board.
1.3.2 I Registration and training Board members
by Audit Committee and adopted by Board.
Registration and training Board members
Wine Service Learnership over llearnership a duration of two years
Audit Committee and adopted by the Board by 30 June 2019.
Registration and training of Board Directors through loDSA by 30 June 2019
by Audit Committee and adopted by the Board by 30 June 2019.
reports on Wine Service Learnership by 30 June 2019
Company Secretary, in the absence ofthe Company Sec. the target needed to be reduced to one checklist which will allow management to be ready for external audit.
loDSA as a training provider removed to allow for SCM process when searching for a training provider.
not the UMDA.
UMDA only providing monitoring support to the programme which then led to the adjustment.
Page 8 ofl{~
2.2.3
Guidance Seminars per Local Municipality in uMkhanyakude
programmes as per signed contracts with UMDA
Conservation and Tour Guiding Learnership Programmes
4 Career by 30 June 2019
4 quarterly progress reports on monitoring of CATHSSETA Discretionary Grant by 30 June 2019
Nature Conservation and Tour Guiding Learnership Programmes by 30 June 2019
has contracts with CATHSSETA and is still paying student.
There is a need to continue monitoring the programme and adhering to the signed contracts.
an Tourism World for the implementation of the Hotel School programme.
Engagements with Tourism World have led to them requesting UMDA to support the programme by facilitating the recruitment process.
The target has been removed as it is externally depended.
The UMDA was going to assist municipalities in facilitating the seminars.
Page 9 of H:t
2.5.2
Development of operating systems for Food Security Estate projects
Fire and Rescue service
company
Accumulate all the pre-requisites for application funding
Fire and Rescue service
Jozini Hydro
Accumulate all the pre-requisites for the projects under the Food Security Estate by 30 June 2019.
Establishment of a Fire and Rescue service at Mkhuze Airport by 30 June 2019
Accumulate pre-requisites Food Security Estate and application for funding by 30 June 2019
Source funding for Establishment of a Fire and Rescue service at Mkhuze Airport by 30 June 2019
to Jozini Municipality by 30 June 2019 I 30 June 2019
engagement investors for Jozini June 2019
The _
to source funds for the establishment of the Fire and Rescue service.
The focus for this year will be in sourcing the required funds for implementation of target.
process requ1res the appointment of a Town Planner and Quantity Surveyor for zoning of the Non-aviation and submission of the application.
The agency needs to appoint these specialists and will be focusing and get the funds to commence with the process.
engage
implementation of the project. Currently, companies who have worked on the project on Risk have not yield positive results.
Page 16 ofHt