Umiray Transformer UPA1

9
UMIRAY-ANGAT TRANSBASIN TUNNEL REHABILITATION PROJECT PHASE II UNIT PRICE ANALYSIS ITEM No. QUANTITY 500(13) 1.00 Unit NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST Transformer 675,000.00 225kVA, 13.8kV-.46/.23kV, 3-Phase 675,000.00 NAME & CAPACITY # OF UNITS # OF HRS. RATE/HR. COST Crane/Boom Truck 1 4 2,000.00 8,000.00 Minor tools (5% of labor) 1 16 150.00 2,400.00 10,400.00 DESIGNATION # PERSONNEL # OF HRS RATE/HR. COST Foreman 1 8 113.09 904.73 Electrician 2 24 94.31 4,527.00 Laborer 3 24 83.48 6,010.55 11,442.28 TOTAL DIRECT COST 696,842.28 DIRECT UNIT COST 696,842.28 V.A.T. (12% of Equipment & Labor) 2,621.07 OCM & PROFIT(20% of Direct Unit Cost) 139,368.46 UNIT COST 838,831.81 ADJUSTED UNIT COST SAY 838,832.00 225 kVA Transformer, 13.8kV-.46kV/.23kV, 3-Phase M A T E R I A L Total for MATERIALS E Q U I P M E N T Total for EQUIPMENT L A B O R Total for LABOR

description

unit price analysis

Transcript of Umiray Transformer UPA1

Page 1: Umiray Transformer UPA1

UMIRAY-ANGAT TRANSBASIN TUNNEL REHABILITATION PROJECT PHASE IIUNIT PRICE ANALYSIS

ITEM No. QUANTITY

500(13) 1.00 Unit

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

Transformer 675,000.00 225kVA, 13.8kV-.46/.23kV, 3-Phase

675,000.00

NAME & CAPACITY # OF UNITS # OF HRS. RATE/HR. COST

Crane/Boom Truck 1 4 2,000.00 8,000.00 Minor tools (5% of labor) 1 16 150.00 2,400.00

10,400.00

DESIGNATION # PERSONNEL # OF HRS RATE/HR. COST

Foreman 1 8 113.09 904.73 Electrician 2 24 94.31 4,527.00 Laborer 3 24 83.48 6,010.55

11,442.28

TOTAL DIRECT COST 696,842.28

DIRECT UNIT COST 696,842.28

V.A.T. (12% of Equipment & Labor) 2,621.07

OCM & PROFIT(20% of Direct Unit Cost) 139,368.46

UNIT COST 838,831.81

ADJUSTED UNIT COST SAY 838,832.00

225 kVA Transformer, 13.8kV-.46kV/.23kV, 3-Phase

MATERIAL

Total for MATERIALS

EQUIPMENT

Total for EQUIPMENT

LABOR

Total for LABOR

Page 2: Umiray Transformer UPA1

UNIT PRICE ANALYSISDESCRIPTION OF ITEM UNIT

1a. 225kVA Transformer, 13.8kV-.46kV/.23kV, 3-Phase 1.00 UNIT

(A) NAME AND SPECIFICATION QUANTITY UNIT UNIT COST M Transformer, 225kVA, 13.8kV-.46/.23kV, 3-Phase 1 unit 675,000.00 675,000.00

A

T

E

R

I

A

L

S

TOTAL COST OF MATERIALS 675,000.00

(B) NAME & CAPACITY NO. OF UNIT

E

Q Crane/Boom Truck 1 4.00 2,000.00 8,000.00

U Minor Tools 1 16.00 150.00 2,400.00

I

P

M

E

N

T

TOTAL FOR EQUIPMENT 10,400.00

(C) DESIGNATION

L

A Foreman 1 8.00 57.44 459.52

B Electrician 2 24.00 37.50 1,800.00

O Laborer 3 24.00 29.09 2,094.48

R

TOTAL FOR LABOR 4,354.00

(D) TOTAL DIRECT COST (A + B + C) 689,754.00

(E) INDIRECT UNIT COST ( 20.00 % ) Total % of D 137,950.80

E1. Overhead, Contingencies and Miscellaneous Expenses (OCM) 10.00% 68,975.40

E2. Profit 10.00% 68,975.40

(F) VALUE ADDED TAX ( 10% of Labor & Equipment) 1,475.40

(G) TOTAL COST OF ITEM ( D + E + F ) 829,180.20

(H) UNIT COST OF ITEM ( G/Qty) 829,180.20

ITEM NO.

TOTAL QUANTITY

AMOUNT (P)

NO. OF HOURS

HOURLY RATE AMOUNT (P)

NO. OF PERSONNEL

NO. OF HOURS

HOURLY RATE AMOUNT (P)

Page 3: Umiray Transformer UPA1

(I) ADJUSTED TOTAL COST (H x Qty) say 829,181.00

UNIT PRICE ANALYSISDESCRIPTION OF ITEM UNIT

1a. Transformer Foundation 1.00 UNIT

(A) NAME AND SPECIFICATION QUANTITY UNIT UNIT COST M Cement 10 bag 175.00 1,750.00

A Sand 0.75 cu.m. 500.00 375.00

T Gravel 0.75 cu.m. 500.00 375.00

E Rebars 200 kg 75.00 15,000.00

R Formworks 2 sq.m. 600.00 1,200.00

I

A

L

S

TOTAL COST OF MATERIALS 18,700.00

(B) NAME & CAPACITY NO. OF UNIT

E

Q 1-bagger mixer 1 4.00 175.00 700.00

U

I

P

M

E

N

T

TOTAL FOR EQUIPMENT 700.00

(C) DESIGNATION

L

A Foreman 1 6.00 57.44 344.64

B Skilled labor 2 8.00 37.50 600.00

O Electrician 1 8.00 37.50 300.00

R Laborer 3 8.00 29.09 698.16

TOTAL FOR LABOR 1,942.80

(D) TOTAL DIRECT COST (A + B + C) 21,342.80

(E) INDIRECT UNIT COST ( 20.00 % ) Total % of D 4,268.56

E1. Overhead, Contingencies and Miscellaneous Expenses (OCM) 10.00% 2,134.28

E2. Profit 10.00% 2,134.28

(F) VALUE ADDED TAX ( 10% of Labor & Equipment) 264.28

(G) TOTAL COST OF ITEM ( D + E + F ) 25,875.64

(H) UNIT COST OF ITEM ( G/Qty) 25,875.64

ITEM NO.

TOTAL QUANTITY

AMOUNT (P)

NO. OF HOURS

HOURLY RATE AMOUNT (P)

NO. OF PERSONNEL

NO. OF HOURS

HOURLY RATE AMOUNT (P)

Page 4: Umiray Transformer UPA1

(I) ADJUSTED TOTAL COST (H x Qty) say 25,876.00

Page 5: Umiray Transformer UPA1

UNIT PRICE ANALYSISDESCRIPTION OF ITEM UNIT

1a. Rehab of 13.8kV Fusible Disconnect Switch 1.00 UNIT

(A) NAME AND SPECIFICATION QUANTITY UNIT UNIT COST M Miscellaneous Materials 1 lot 50,000.00 50,000.00

A

T

E

R

I

A

L

S

TOTAL COST OF MATERIALS 50,000.00

(B) NAME & CAPACITY NO. OF UNIT

E

Q Minor Tools 1 8.00 100.00 800.00

U

I

P

M

E

N

T

TOTAL FOR EQUIPMENT 800.00

(C) DESIGNATION

L

A 30% of Material Cost 15,000.00

B

O

R

TOTAL FOR LABOR 15,000.00

(D) TOTAL DIRECT COST (A + B + C) 65,800.00

(E) INDIRECT UNIT COST ( 20.00 % ) Total % of D 13,160.00

E1. Overhead, Contingencies and Miscellaneous Expenses (OCM) 10.00% 6,580.00

E2. Profit 10.00% 6,580.00

(F) VALUE ADDED TAX ( 10% of Labor & Equipment) 1,580.00

(G) TOTAL COST OF ITEM ( D + E + F ) 80,540.00

(H) UNIT COST OF ITEM ( G/Qty) 80,540.00

(I) ADJUSTED TOTAL COST (H x Qty) say 80,540.00

ITEM NO.

TOTAL QUANTITY

AMOUNT (P)

NO. OF HOURS

HOURLY RATE AMOUNT (P)

NO. OF PERSONNEL

NO. OF HOURS

HOURLY RATE AMOUNT (P)