Mechanical properties of hemp fiber and hemp/PP composites ...
Ultimate green building lime & industrial hemp
Transcript of Ultimate green building lime & industrial hemp
Ultimate Green Building: Lime & Industrial Hemp
Pine Ridge ReservationBadlands, South Dakota
May 2008
Alex White Plume - Oglala Sioux Tribe Jeremy Briggs - Rapid City, SD Lime Technology LimitedAmerican Lime Technology
In cooperation with:
Ultimate Green Building: Lime & Industrial Hemp
Community Center BuildingConstructed in 2001
Wood siding was removed and re-used as shuttering forms for the interior Hemcrete walls
A layer of OSB board was under the wood siding. This was also removed then re-used for the temporary support of the exterior Hemcrete wall
OSB board is removed carefully then cleaned and set aside
Cross-bracing installed to stiffen corners
The first interior shuttering forms installed ripped from the 5/8” wood siding securedin place with 8” hex-head deck screws
Hex-head deck screws
End of Day One – 13 May 2008
Mixing Begins…
Hemcrete Materials
Hemp Shiv
Hemp Lime Binder
MIX DESIGN:One Bag of Hemp ShivTwo Bags of Hemp Lime BinderThree Buckets of Water
Hemcrete staged on plywood at mixing stationMaterial can rest up to 6hrs before placement
Transfer to wheelbarrows
This batch was mixed with too much water and was spread on plywood and allowed to dry-out in the sun for a couple of hoursprior to placement
Installation of metal lath
This building required the use of metal lath on the exterior due to the wood framing not being encased in Hemcrete. The interior walls did not require metal lath as the Hemcrete material covers the wood framing by four full inches.
Re-attach OSB board back over metal lath to keep Hemcrete straight
Hemcrete is staged on floor for easy transfer to walls
Hemcrete is shoveled in by hand in six inch layers
Hemcrete is lightly tamped down with the end of a 2x4
2x4 tamping board
Next layer is added
Ready for next shuttering form to be installed
Alex
Hemcrete shown here behind the metal lath after removing the OSB board on the exterior - 30 minutes after placement
Finished Hemcrete interior wall after shutter forms are removed 30 minutes after placement
End of Day Two – 14 May 2008
120 cubic feet of Hemcrete placed
Remove the shuttering forms as soon as possible to allow the Hemcrete material to draw in the CO2 from the atmosphere which starts the carbonation process
INTERIOR: A two coat lime plaster will be applied directly to this rough surface texture of the Hemcrete after about one week
EXTERIOR: The exterior Hemcrete walls will receive a two coat hydraulic lime (½”) render after one week drying time. The new lime render will be finished with a beautiful natural earth limewash
End of Day Three – 15 May 2008
200 cubic feet of Hemcrete placed
BEFORE
AFTER
The Hemcrete Builders
www.americanlimetechnology.com