Summer Flexibility ForumUK Power NetworksJuly 2019
#flexibilityfirstWiFi NetworkTBC
Questions & feedback www.sli.do
Flexibility Forum #UKPNFlexForum
Introduction
Photo by George Bohunicky on Unsplash
Time Item Speaker3pm – 3.05pm Welcome from Chair Molly Webb
3.05 – 3.25pm Flexibility Commitment & Roadmap Progress Sotiris Georgiopoulos
3.25– 3.40pm Update on tender market – from market report Stathis Mokkas and Sam Do
3.40 – 3.55pm Q&A Sotiris / Stathis / Sam3.55pm– 4.15pm Break All
4.15pm – 4.50pm Tender feedback – How was it for you? Panel discussion: Linda Taylor – AMP Clean Energy Valts Grintals – Kaluza Simon Daniel – Moixa Sotiris Georgiopoulos
4.50pm – 4.55pm Chair to introduce Future View Molly Webb
4.55pm – 5.10pm Innovation Flexible Energy Trials Dr Giulia Privitera
5.10pm – 5.25pm Next steps: Active Networks Management Dr Phil Blythe 5.25pm – 5.30pn Q&A5..30pm – 5.40pm Summary and conclusion Barry Hatton
5.45pm – 7pm Drinks reception on roof terrace (weather dependent) All
Agenda
5
Flexibility Commitments
Photo by Karsten Würth (@karsten.wuerth) on Unsplash
Sotiris GeorgiopoulosHead of Smart Grid Development
Flexibility is at the core of our DSO strategy
Key Flexibility Roadmap Principles
Maximise available opportunities using economic principles
Improve accessibility Market testing Neutrality• Co‐design new arrangements• Adoption of digital platforms• Contribute to standardisation
• Open all LR capex at high voltage• Trials for EV‐driven constraints
• Publish info on size & location ahead of tenders
• Publish tender framework, assessment criteria, tender results
Driving a national approach to FlexibilityYou can view the full Flexibility Commitment document on the ENA website here:http://www.energynetworks.org/assets/files/ENA%20Flexibility%20Commitment%20Our%20Six%20Steps%20for%20Delivering%20Flexibility%20Services.pdf
Great Summary of all DNO Flexibility Initiativeshttp://www.energynetworks.org/electricity/futures/flexibility-in-great-britain.html
ENA Flexibility Workstream Consultation EventWednesday 10th July (London), 16th July Glasgowhttp://www.energynetworks.org/electricity/futures/open-networks-project/open-networks-project-stakeholder-engagement/events.html
9
UKPN’s ways of working – Learning by doing …or in plain English
10
Progress since Autumn 2018
• Clarity on value of flexibility
• Reduce participation threshold
• Published deferral value
• Reduced to 50kW (from 100kW, from 500kW)
• Visibility of market
• Longer contracts • Longer lead-in times
• Declare market size by 2023 + 200MW
• Four year contracts• Doubled lead-in time
• Improved tender interface
• Simplified customer experience
• First to partner with Piclo
• Introduced framework agreement
You asked We did
ESO
DSO
–HV
DSO
–LV
Planning & scheduling(Near‐Time)
Network development / Connections(Ahead)
Operations(Real‐Time)
DSO commercial product portfolio
11
Key:
Current
In progress
Flexible connections
LV Flex Product(Constraint Management)
Power Potential – Reactive power
Reinforcement deferral constraint management
Maintenance constraint management
Contracted services dispatch
Contracted services dispatch
Capacity based pricing
Market‐based constraint management
Dynamic / locational DUoS
Dynamic/ locational DUoS
Capacity‐based pricing
Post‐fault restoration support
Capacity‐based pricing
Dynamic / locational DUoS
Flex Connections dispatch (LIFO/Prorata)
Dynamic/locational DUoS
Summary
• We are creating meaningful DSO flexibility opportunities
• We are defining the future of local flexibility together
• High volume, small asset participation – DSO markets will drive innovation
Photo by Jason Blackeye on Unsplash
Any questions?Visit
www.sli.do and enter event Flexibility Forum
and code #UKPNFlexForum
Any questions?Visit
www.sli.do and enter event Flexibility Forum
and code #UKPNFlexForum
Market ReportStathis Mokkas and Sam DoFlexibility Team
Photo by Andreas Gücklhorn on Unsplash
15
Winter 18/19 Flexibility tender – Summary
94.76MWCapacity requirement
18.1MWFlexibility Contracts
4 met operational needs
Smaller volumes in 3 zones
28 zones tendered19 prequalified
15 bid
£450kNew revenue streams for
flexibility providers
40% batteries
Transitioning a nascent market from kW to MWs of flexibility
£12mFunding pot for Flexibility
Online dating…
“…Overworked substation seeking supportive battery…”
Counting MWs – From registration to contracts
94.76
69.356.6
23.0 18.1
020406080
100
CapacityRequirement
W19/20
Registration Prequalification Competition Outcome
Capacity (MW) per Stage
39.7
7.6
22.0
Battery DSR Genset
7.6
2.5
8.0
Battery DSR Genset
Flexibility – A network service
Brandon2MW
Lewes Newhaven
7MWRomney Warren
1.5MW
Leighton Buzzard5MW
Provided by…
New experiences, new feedback, further improvementsNew experiences, new feedback, further improvements
SignpostingSignposting Tender timelines & Evaluation processTender timelines & Evaluation process Flexibility contract Flexibility contract
It is never early enough to indicate
constraints
It is never early enough to indicate
constraints
Improved. Additional info & clarifications always welcome
Improved. Additional info & clarifications always welcome
Actions:Actions:
Focus areas:Focus areas:
Lesson:Lesson:
Simplify where possible.
Publish more info in advance, e.g. dispatch
frequency
Simplify where possible.
Publish more info in advance, e.g. dispatch
frequency
Continue to publish areas 6 months ahead of tender
&Develop heat maps 12‐24 months ahead of potential tender
Continue to publish areas 6 months ahead of tender
&Develop heat maps 12‐24 months ahead of potential tender
Make more accessible and less onerous on
providers
Make more accessible and less onerous on
providers
Support Open Networks efforts to standardise contracts
Support Open Networks efforts to standardise contracts
Timeline – the next few months
Completionof tender
Apr 2019
Flexibility Forum
May 2019
Flexibility contracts awarded
8 July 2019
Late July 2019
Publish new Flexibility zones for Q1 2020
Sept2019
Oct2019
Publish Flexibility zones to be re‐tendered Q4 2019Follow with updated
framework.
Close of registration and
bidding for flexibility tender
Nov – Dec2019
Take partVisit
www.sli.do and enter event Flexibility Forum
and code #UKPNFlexForum
Take partVisit
www.sli.do and enter event Flexibility Forum
and code #UKPNFlexForum
What is the appropriate tender noticeperiod – from signposting to bidding?
• 4‐6 months• 6‐9 months• >9 months
What is the appropriate tender noticeperiod – from signposting to bidding?
• 4‐6 months• 6‐9 months• >9 months
Questions
How much value does DSO Flexibility add toyour business model:
• It’s the main component• It’s an important part
• It’s a nice to have• Minimal
How much value does DSO Flexibility add toyour business model:
• It’s the main component• It’s an important part
• It’s a nice to have• Minimal
Questions
Two years ago we introduced FutureSmart, oneyear ago we produced our Flexibility Roadmap.Do you think we are heading the right direction?
• Yes• Partially
• No
Two years ago we introduced FutureSmart, oneyear ago we produced our Flexibility Roadmap.Do you think we are heading the right direction?
• Yes• Partially
• No
Questions
Q&AQ&A
Future Smart microsite: http://futuresmart.ukpowernetworks.co.uk/
Flexibility Roadmap: http://futuresmart.ukpowernetworks.co.uk/wp‐content/themes/ukpnfuturesmart/assets/pdf/futuresmart‐flexibility‐roadmap.pdf
Flexibility tenders framework landing page: https://www.ukpowernetworks.co.uk/internet/en/have‐your‐say/listening‐to‐our‐
connections‐customers/flexibility‐services.HTML
Flexibility revenues per area document: https://www.ukpowernetworks.co.uk/internet/en/have‐your‐
say/documents/Flexible%20Zones%20‐%20Revenue%20Range%20per%20Area.pdf
Future Smart microsite: http://futuresmart.ukpowernetworks.co.uk/
Flexibility Roadmap: http://futuresmart.ukpowernetworks.co.uk/wp‐content/themes/ukpnfuturesmart/assets/pdf/futuresmart‐flexibility‐roadmap.pdf
Flexibility tenders framework landing page: https://www.ukpowernetworks.co.uk/internet/en/have‐your‐say/listening‐to‐our‐
connections‐customers/flexibility‐services.HTML
Flexibility revenues per area document: https://www.ukpowernetworks.co.uk/internet/en/have‐your‐
say/documents/Flexible%20Zones%20‐%20Revenue%20Range%20per%20Area.pdf
Links
Break
Photo by NordWood Themes on Unsplash
Linda Taylor – AMP Clean EnergyValts Grintals – KaluzaSimon Daniel – Moixa
Linda Taylor – AMP Clean EnergyValts Grintals – KaluzaSimon Daniel – Moixa
Debate: Lessons learned
Dr Giulia PriviteraLow Carbon Technologies Delivery ManagerDr Giulia PriviteraLow Carbon Technologies Delivery Manager
Innovation Flexible Energy TrialsInnovation Flexible Energy Trials
30
Low Carbon Ready
Efficient And
Effective
Future Ready
UK Power NetworksInnovation Strategy
Our Innovation Strategy
20192010-13
Our Journey20182014-17
Low Carbon London
FlexiblePlug & Play EV trialsenergywise
32
We consulted a number of industry stakeholders on applicability of EV smart charging models in the UK and to form our position
Smart Charging and industry wide solution
Industry-wide solutions (2023+)Interim solutions (2021-23)Market trials (2019-20)
To investigate how DNO can support the market to manage smart charging
Shift - Smart Charging Market Trials
24h
Custom
er
demand (kW)
24h
Custom
er
access (kW)
Core capacity
Optional capacity purchase
Peak pricing
24h
Custom
er
DUoS
Price
“High”
“Low” “Low”
FlexibilityProcurement
Capacity based pricing
Time of UseDUoS
V2G opportunities - TransPower
Commercial Fleets ‘at work’ Public ‘on route’ Residential ‘at home’
Unblocking fleet transition“World’s biggest commercial EV trial” targeting 3,000 commercial vehicles
Depot Charging
Home Charging
Mixed Charging
Photo: Casey Gutteridge/Uber/PA/CC BY-SA 3.0
20192010-13
Our Journey20182014-17
Low Carbon London
FlexiblePlug & Play
Urban EnergyClubEV trialsenergywise
Empowering people to participate in emerging flexibility market
Time poor
Fuel poverty
Lack of flexibility in use of energy
Lackof digital skills
Lack of engagement in the energy market
Lack ofspace
Who might be left behind in the future?
38
Our journey is aligned to the flex roadmap
Flexibility is playing a role in the EV transition
Our trials are uncovering new opportunities in flexibility
Networks have a role in ensuring no one is left behind
Conclusions
Active Network ManagementSotiris Georgiopoulos & Dr Phil Blythe
Photo by Richard R Schünemann on Unsplash
The story so farFlexible Plug and Play trial (Peterborough/March) ‐ Success
Flexible DG rollout (FPP/Norwich) ‐ Success
Business process, BAU Handover and Training
DERMS trial (Power Potential) ‐ Ongoing
Regional Development Programme (ANM south coast) ‐Ongoing
Standard ANM System
2012 ‐ 2014
2015 ‐ 2016
2015 ‐ 2018
2017 ‐ 2019
2017 ‐ 2019
2018– ED1 / ED2
Active Network Management System benefits
.
42
Cover all three UKPN licenced regions Integrating innovation projects Phased rollout to all voltage levels
Solution characteristics
Distributed Energy Resource Management Constraint Management Operational forecasting and offline simulation Commercial capabilities (E2E flexibility provider management)
Key capabilities
Key Outcomes Flexible connections available at all areas from Q4 2019 Connection of c200MW of connections projects in the pipeline Enabling management/dispatch of flexibility contracts
Any questions?Visit
www.sli.do and enter event Flexibility Forum
and code #UKPNFlexForum
Any questions?Visit
www.sli.do and enter event Flexibility Forum
and code #UKPNFlexForum