UHPC North America UHPC North America · Repair and retrofit of bridges using UHPC Gaston Doiron,...
Transcript of UHPC North America UHPC North America · Repair and retrofit of bridges using UHPC Gaston Doiron,...
8/30/2017
1
2016 ICRI Kick‐Off Party | February 1, 2016
Repair and retrofit of bridges using UHPCGaston Doiron, P.Eng., M.Eng.Project Manager, LafargeHolcim
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC in North America
UHPC has been used on bridges projects for over 10 years in NA. Precast deckpanels connected with field cast UHPC joints has been the most popularapplication. Approximately 200 projects completed in more than 25 states andprovinces to date.UHPC has also been used for:
– Structural overlays– Headers and link slabs to replace traditional expansion joints– Jackets for columns/piers– Pier cap to column connections– UHPC precast elements to widen and strengthen existing bridges
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC projects in North America
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC projects in North America
8/30/2017
2
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC matrix
30 MPa (4 ksi) normal
150 MPa (22 ksi) UHPC
70 MPa (10 ksi) high performance
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC vs Normal Concrete
CharacteristicsNormal
Concrete Ratio UHPC
Mechanical
Compression - MPa (psi) 20 – 40 (3,000 - 6,000) 6 x 140 – 160 (20,000 – 23,000)
Flexure – MPa (psi) 30 (4,000)
Elastic Tensile Strength – MPa (psi) 8 (1,200)
Water / Cement ratio 0.40 - 0.70 < 2 < 0.25
Durability
Chloride ions diffusion(coulombs) > 2000 20 x < 100
Freeze / thaw cyclesscalling (g/m2) > 1000 100 x < 10
Abrasion (kg/m2) 1 100 x 0.01
2016 ICRI Kick‐Off Party | February 1, 2016
Steel fibers
Fibers = Ductility
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC in Flexure
Fibers = Stain hardening (1st crack at 4,000 psi)
0
510
1520
25
3035
4045
50
0.0 0.5 1.0 1.5 2.0Deflection (mm)
Equivalent Stress (M
Pa) Ductal
HPC 80
UHPC
HPC
First Crack
8/30/2017
3
2016 ICRI Kick‐Off Party | February 1, 2016
Chlorides penetration test
US Army Corps test site in Maine
UHPC steamed cured
UHPC ambient temp. cured
UHPC
2016 ICRI Kick‐Off Party | February 1, 2016
Design Guides ‐ FHWA
FHWA has published over 40 reports, TechNotes and Guidelines
2016 ICRI Kick‐Off Party | February 1, 2016
Design Standard – SIA 2052 ‐ 2016
Swiss Society of Engineers and Architects
2016 ICRI Kick‐Off Party | February 1, 2016
Design Standard ‐ NF P 18‐470 ‐ 2016
AFNOR (Association française de normalisation)
8/30/2017
4
2016 ICRI Kick‐Off Party | February 1, 2016
• In December of 2015, the Canadian Standards Association (CSA) formed a new “Working Group on UHPC” under A23.1, Chapter 8, with the mandate to develop a new annex on UHPC materials (CSA A23.1, 2014). Target 2019 edition of the next CSA A23.1‐19.
• American Concrete Institute (ACI)239 ‐ Ultra‐High Performance Concrete239‐A Emerging Technology Report239‐B Report on UHPC239‐C Structural Design on UHPC239‐D Materials & Methods of Construction with UHPC
Design Guidelines US/CanadaCommittee work in progress
2016 ICRI Kick‐Off Party | February 1, 2016
Batching equipment
On site batching is the preferred option for most projects.We have a fleet of portable mixers which can be rented by contractors.
A size for every job
4.5 m3 per truck(6 yd3)
0.15 m3 batches ‐ 0.6 m3 / hour(0.2 yd3) (0.8 yd3)
0.5 m3 batches ‐ 2 m3 / hour(0.65 yd3) (2.6 yd3)
1.0 m3 batches ‐ 4 m3 / hour(1.3 yd3) (5.2 yd3)
2016 ICRI Kick‐Off Party | February 1, 2016
Applications
2016 ICRI Kick‐Off Party | February 1, 2016
Joint fill / Closure Pours / Haunches
Typical connection detail
Installation of precast panels
UHPC has been used to joint precast elements together and also used to secure the deck to the supporting beams by filling the haunches and shear keys pockets.
DOT’s elaborate their own specificationsand designs.
Main issue: UHPC joints are now the stronger elements and not affected by live loads, freeze‐thaw or deicing salts.
Solution: UHPC joints allows for faster construction because no need to form decks on site and wait for deck curing. Also, ideal for remote areas where the contractor is not dependant on the availability of ready mix.
8/30/2017
5
2016 ICRI Kick‐Off Party | February 1, 2016
Pulaski Skyway, NJ 2014/17
5.5 km (3.5 miles) ‐ 4 lanes
2016 ICRI Kick‐Off Party | February 1, 2016
Pulaski Skyway, NJ
Traffic maintained on 2 lanes during construction
2016 ICRI Kick‐Off Party | February 1, 2016
Nipigon Bridge, east of Thunder Bay
Grouting precast deck panels with UHPC
2016 ICRI Kick‐Off Party | February 1, 2016
Surface before applying the overlay
Typical 200 mm (8 in) wide UHPC joints
UHPC casting completed
Bridge 56 precast panels – 3 span bridge ‐‐ 83 m (270 ft) x 17 m (56 ft)
Peoria Street Bridge, Chicago, IL
Photos by David Liu
8/30/2017
6
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC overlay
Application of dense layer of strain‐hardening UHPC with 25 to 60 mm(1 in to 2.5 in) thickness applied on the superstructure in zones of severe environmental and mechanical loads.
UHPC Reinforced UHPC
h ≥ 25 mmh ≥ 35 to 60 mm
reinforced concrete
protection protection +
strengthening
reinforced concrete
2016 ICRI Kick‐Off Party | February 1, 2016
UUPC overlay formulationSelf leveling mix to thixotropic mix
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC overlay – large project
Batching 60 to 75 m3 (75 to 100 yd3) capacity per day
Motorized buggies to bring material in front of the paver Portable batching plant; one silo for sand, one silo for the premix, 2 high shear mixers 1 m3 (1.5 yd3 ) batches
2016 ICRI Kick‐Off Party | February 1, 2016
UHPC overlay
Placing – industrialized system
1 spread in front of machine
23
vibration
finished surface
8/30/2017
7
2016 ICRI Kick‐Off Party | February 1, 2016
Chillon Viaducts, Switzerland 2014‐15
Work staged over 2 years with traffic maintained on one of the structures
Concrete paver developped by WALO
45 mm (1.75 in) cast‐in‐place overlay with rebar reinforcementThixotropic mix used to cast on 7% slope
2 parallel structureseach 12 m (40 ft) wide 2 km (1.2 mile) long51,000 m2 (61,000 yd2) total deck areaOriginal segmental box system built 1969
Main issue: ASR (alkali silica reaction) and lost of concrete performance
Solution: Thin structural UHPC overlay provides waterproofing to halt ASR progression and increase substantially the strength of the deck
UHPC cheaper alternative
2016 ICRI Kick‐Off Party | February 1, 2016
Concrete paver with customized dispensing system at the front
On site portable batching plant – 2 mixers
Material brought to the concrete machine with motorized buggies
Hydro demolition
Chillon Viaducts
2016 ICRI Kick‐Off Party | February 1, 2016
Iowa DOT, Buchanan Country, 2016
Diamond grinding equipment used to provide grooved running surface
Placing using a simple vibrating screed machine
38 mm (1.5 in) cast‐in‐place overlayThixotropic mix used to cast on 5% slope
30 m (100 ft) long, 3‐span deck8.5 m (28 ft) wide260 m2 (310 yd2) total deck area
Main issue: Pilot project to evaluate the constructability and performance of a UHPC overlay
Solution: Current low lump concreteoverlays are not performing optimally. A more durable UHPC product would provide added durability. This pilot project done in conjunction with Iowa DOT, Buchanan County, FHWA, local contractors and Lafarge will be monitored for long term durability.
2016 ICRI Kick‐Off Party | February 1, 2016
Cudrex Viaduct, Switzerland, 2016
UHPC overlay prior to installation of asphalt layer
Work performed at night on weekends with traffic back on Mondays
30 mm (1.25 in) waterproofing overlay 45 mm (1.75 in) used on curbs and sidewalk for deicing protection
Built in 1968440 m (1,450 ft) long9.5 m (31 ft) wide deck24,000 cars/trucks per day230 m3 (300 yd3) of UHPC
Main issue: Waterproofing at end of its life, supporting structure in good shape
Solution: Thin structural UHPC overlay provides waterproofing. Option with minimal traffic interruption.
UHPC cost comparable but more durable than other options.
8/30/2017
8
2016 ICRI Kick‐Off Party | February 1, 2016
443 m (1,450 ft) x 9.5 m (31 ft) wide deck
Cudrex Viaduct, Switzerland, 2016
2016 ICRI Kick‐Off Party | February 1, 2016
Kanderal Bridge, Switzerland, 2017
2016 ICRI Kick‐Off Party | February 1, 2016
Kanderal Bridge, Switzerland, 2017
2016 ICRI Kick‐Off Party | February 1, 2016
Mission Bridge, Abbotsford, BC, 2014
Completed project
Pier prior to final retrofit
230 mm (9 in) thick UHPC jacket used on a height of 3.5 m (11.5 ft) along with additional dowels and a rebar cage to confine the area.
Main issue: Final stage to complete the retrofit of the bridge. One pier on the south shore required additional work because of pour soil conditions.
Solution: Using a UHPC jacket allowed for a thin layer that does not obstruct the view or significantly alter the original appearance.
UHPC cheaper than using soil consolidation techniques.
8/30/2017
9
2016 ICRI Kick‐Off Party | February 1, 2016
Completed project
Delivery to the site (total of 4 trips)
Hoisting and casting from the top of the formwork
Loading and batching in ready‐mix truck at Lafarge plant
Mission Bridge, Abbotsford, BC, 2014
2016 ICRI Kick‐Off Party | February 1, 2016
CN Rail Bridge, Montreal, Quebec, 2013
Damaged pier prior to repair
UHPC jacket ‐ Ramp to Pont Victoria under the CN Rail track
115 mm (4.5 in) thick UHPC jacket cast around an existing pier which is 600 mm (2 ft) thick x 3.5 m (11.5 ft) in height.
Main issue: Deteriorated surface due to rebar corrosion and chloride spray because of the very narrow lanes.
Solution: Owner wanted to minimize maintenance and required a material with very low porosity and that could last at least twice as long compared to normal concrete.
2016 ICRI Kick‐Off Party | February 1, 2016
Casting – traffic maintained on adjacent lane
Completed repair
Formwork
CN Rail Bridge, Montreal, Quebec
2016 ICRI Kick‐Off Party | February 1, 2016
Grafstal Bridge, Switzerland, 2016
8/30/2017
10
2016 ICRI Kick‐Off Party | February 1, 2016
Grafstal Bridge, Switzerland, 2016
2016 ICRI Kick‐Off Party | February 1, 2016
Hooper Road Bridge, Union, NY, 2014
Completed connections
New precast pier cap set on existing columns
UHPC used to connect new precast pier cap elements to existing columns. Part of a 21‐day structure replacement.
Main issue: Original detail called for ducts and drilling of a total of 84 holes in the existing columns and grouting of each individual holes. Difficult to implement on site and potential for many delays and issues.
Solution: UHPC connection; initiated by the Contractor who was looking for an alternative solution. Saved 2 days on the schedule. Very short development length of 280 mm (11 in) required for the joint because using UHPC.
2016 ICRI Kick‐Off Party | February 1, 2016
Hooper Road Bridge, Union, NY, 2014
2016 ICRI Kick‐Off Party | February 1, 2016
(280 mm)
(1,020 mm)
(325 mm)
(1,070 mm ) 3’‐6” column diameter
existing and new #9 bars(28.6 mm) 1.1” in diameter
Female coupler cast in
Male coupler shipped looseExisting rebar
to remain
UHPC
Hooper Road Bridge, Union, NY, 2014
8/30/2017
11
2016 ICRI Kick‐Off Party | February 1, 2016
Hooper Road Bridge, Union, NY, 2014
2016 ICRI Kick‐Off Party | February 1, 2016
Precast UHPC slab ready to be anchored
Details of the bridge widening
Precast 200 mm (8 in) thick UHPC slabs added to extend the bridge by 1.5 m (5 ft).
cantilevered slabs are anchored to the existing structure with mechanical anchors.
Main issue: Narrow structure needed to be retrofitted to accommodate larger vehicles and provide a proper protected sidewalk
Solution: taking advantage of the flexural capacity and durability. Underside is exposed to elements. Low cost option in this case.
Pont de la Tine, Switzerland, 2011
2016 ICRI Kick‐Off Party | February 1, 2016
Francis Lewis Blvd., Queens, NY, 2015Removed existing steel angles and associated deteriorated concrete. Add new rebar and use 125 mm (5 in) x 300 mm (12 in) wide UHPC headersMain issue: Steel angle and rebar corrosion damage concrete, affect supporting beams and require maintenance.
Solution: Remove the original problem in header joint, the steel angle and rebar that can corrode. By using UHPC, the corners/edges of the slabs will no longer be affected by chlorides and water penetration.
2016 ICRI Kick‐Off Party | February 1, 2016
Link Slabs, Binghamton NY, 2014
Completed slab
Casting
Eliminating joints on bridge decks extends the life of the structure
Main issue: Expansion joints deteriorate over time and water/chloride penetrate and damage the slabs edges and the supporting girders.
Solution: By providing a continuous link on top of the piers (approx. 100 mm thick), water/chlorides can not longer deteriorate the structure. The UHPC slab can flex and the strain‐hardening provided by the steel fibers limit the width of micro cracks while maintaining the integrity of the link slab.
8/30/2017
12
2016 ICRI Kick‐Off Party | February 1, 2016
Link Slabs details, NY, 2016
2016 ICRI Kick‐Off Party | February 1, 2016
Contact
Gaston Doiron, P. Eng., M.Eng.Project Manager, Ductal®[email protected]: 416‐579‐7864