Ucin1116271787
-
Upload
bloom-dido -
Category
Engineering
-
view
43 -
download
0
description
Transcript of Ucin1116271787
UNIVERSITY OF CINCINNATI Date:___________________
I, _________________________________________________________, hereby submit this work as part of the requirements for the degree of:
in:
It is entitled:
This work and its defense approved by:
Chair: _______________________________ _______________________________ _______________________________ _______________________________ _______________________________
MECHANISTIC-BASED PERFORMANCE PREDICTION
AND LIFE CYCLE COST ANALYSIS TOOLS:
AN APPLICATION TO THE OHIO ROUTE 50 TEST PAVEMENT
A thesis submitted to the
Division of Research and Advanced Studies
of the University of Cincinnati
in partial fulfillment of the
requirements for the degree of
MASTER OF SCIENCE
in the Department of Civil and Environmental Engineering
of the College of Engineering
2005
by
Pavan Kumar Tallapragada
B.Tech. (Civil), Indian Institute of Technology – Chennai (Madras), India, 2001
Committee Chair: Dr. Anastasios M. Ioannides, P.E.
iii
ABSTRACT
This study examines the development, utilization and application of performance
prediction and life cycle costing for rigid pavements. Emphasis is laid on selecting an
appropriate computer application that comprises mechanistic-based prediction equations and
life cycle costing, for application to the Ohio Route 50 Project.
A thorough literature review examining methods of collection and processing
pavement performance data, development of performance prediction equations for flexible
and rigid pavement systems, computer programs for rigid pavement performance prediction
and life cycle cost analysis, and usage of performance prediction and life cycle costing
methods by selected state highway agencies for planning and maintenance is presented.
Pavespec 3.0, developed for the Federal Highway Administration, is selected, and
over two hundred simulations of the program are completed, using the as-constructed
pavement system data from the Ohio Route 50 Project as inputs. Observed distress data
trends are used for calibration, and predictions for the service life of the Ohio Route 50
pavement system are generated. Life cycle cost analysis methods are utilized to determine
the relative cost effectiveness of various joint sealing options on the Project.
From the comparisons of predicted and observed distresses for the eastbound and
westbound sections of the Ohio Route 50 pavement, it is established that data points spaced
out over a longer period of time provide better regression curves, and subsequently, a more
reliable analysis. The slopes of observed distress curves for the international roughness
index, for transverse slab cracking and for spalling, are found to be many times higher than
the slopes of the corresponding predicted curves obtained from Pavespec 3.0. The
iv
differences are most pronounced in the case of transverse slab cracking. Previous
mechanistic analysis of this pavement system had attributed the very high cracking
percentage to longer slab length. In addition, it had been inferred that an unexpected flood
and various construction issues led to the premature deterioration of this pavement system.
Data calibration assumes a significant role in such cases, but Pavespec 3.0 uses a linear
regression method for this purpose, which is found to be inadequate.
Life cycle cost analysis methods are used to examine the cost effectiveness of the ten
joint sealant materials used on the Ohio Route 50 Project. Approximate rehabilitation life
cycle costs are calculated using Pavespec 3.0. Compression sealants, with the exception of
Techstar W050, are found to be the most cost effective sealing option, due to their lower
material and installation costs, consistently higher performance, and longer replacement
cycles.
v
ACKNOWLEDGEMENTS
I would like to express my heartfelt gratitude to my graduate advisor, Dr. Anastasios
M. Ioannides. His support and guidance during my graduate study at the University of
Cincinnati was valuable, and will definitely help shape up my professional career.
I would also like to thank Dr. Mark T. Bowers, Dr. Issam A. Minkarah, and Dr. Sam
Salem, for their consent to serve on my committee, and devoting time to help me at various
stages of my graduate study. My coursework and Master’s Thesis have been rewarding and I
am grateful to the faculty and staff at the University of Cincinnati.
I would like to thank my parents, my sister, and friends Sharat, Ravi Prasad and
Amar, for providing me with constant support and confidence that helped me successfully
complete graduate studies. Mahesh and Shelly at Totally Productive Group, Inc. deserve a
very special mention here, in appreciation of their efforts to let me work flexible hours and
take time off to complete my Master’s Thesis.
During my studies at the University of Cincinnati, I have received financial assistance
in the form of a Research Assistantship under Dr. Anastasios M. Ioannides (October 2001-
September 2002) and a University Graduate Scholarship.
vi
TABLE OF CONTENTS
Page
ABSTRACT iii
ACKNOWLEDGMENTS v
LIST OF TABLES x
LIST OF FIGURES xi
LIST OF ABBREVIATIONS xiii
SI* (MODERN METRIC) CONVERSION FACTORS xviii
1 INTRODUCTION 1
1.1 Introduction 1
1.2 Problem Statement 2
1.3 Research Objective 4
1.4 Research Significance 5
1.5 Thesis Organization 6
2 LITERATURE REVIEW 9
2.1 Introduction 9
vii
2.2 Pavement Performance Prediction 10
2.3 Performance Prediction Models for Flexible Pavements 13
2.3.1 AASHTO Model 13
2.3.2 Arizona DOT Model 14
2.3.3 Texas FPS Model 14
2.3.4 Highway Design and Maintenance Standards (HDM) Model 14
2.3.5 SUPERPAVE Research 14
2.4 Performance Prediction Models for Rigid Pavements 15
3 SURVEY OF CURRENT PRACTICE 22
3.1 Introduction 22
3.2 Computer Programs for Pavement Performance
Prediction 23
3.2.1 Programs for Rigid Pavements 25
3.3 Programs for Life Cycle Cost Analysis 30
3.4 Performance Prediction – Current
State-of-the-Practice 33
3.5 Pavement Management System’s Framework 34
3.5.1 Distress Data Collection 35
3.5.2 Data Categorization and Analysis 35
3.5.3 Pavement Performance Modeling 36
3.5.4 Application of Performance Prediction 38
viii
4 SENSITIVITY ANALYSIS USING Pavespec 3.0 46
4.1 Introduction 46
4.2 Discussion of Sensitivity Analysis Observations 48
4.2.1 Pavement Design, Dimensions and Lane Configuration 48
4.2.2 Traffic Factors 50
4.2.3 Climatic Factors 51
4.2.4 Sampling Methods 51
4.2.5 Acceptance Quality Characteristics 52
4.2.6 Maintenance and Rehabilitation Options 53
4.2.7 Cost and Interest Rates 53
4.3 Summary of Major Findings from Sensitivity Analysis 54
5 APPLICATION TO THE OHIO ROUTE 50 PROJECT 68
5.1 The Ohio Route 50 Project 68
5.1.1 Project Details 68
5.1.2 Experimental Plan 69
5.1.3 Performance Evaluation 70
5.1.4 Conclusions from the Ohio Route 50 Project 72
5.2 Distress Prediction for the Ohio Route 50 Project 74
5.2.1 Analysis Using the Ohio Route 50 Project Data 75
5.2.2 Sections with Compression Sealants – Eastbound 79
5.2.3 Sections with Silicone Sealants – Eastbound 81
ix
5.2.4 Sections with Hot Pour Sealants – Eastbound 82
5.2.5 Sections with No Sealants – Eastbound 82
5.2.6 Sections with Compression Sealants – Westbound 83
5.2.7 Sections with Silicone Sealants – Westbound 84
5.2.8 Sections with Hot Pour Sealants – Westbound 84
5.2.9 Sections with No Sealants – Westbound 85
5.2.10 Summary of Observations 85
5.3 Life Cycle Cost Analysis to Determine the Cost Effectiveness
of Sealants 86
5.3.1 Proposed M&R Steps and Costs 88
5.3.2 Cost Effectiveness of Sealant Material Using LCCA- Applied
Methodology 89
5.3.3 Results from the Analysis 90
6 CONCLUSIONS & RECOMMENDATIONS 133
6.1 Research Summary 133
6.1.1 Literature Review 133
6.1.2 Computer Programs Available 135
6.1.3 Current State-of-the-Practice 135
6.1.4 Sensitivity Analysis using Pavespec 3.0 136
6.1.5 Application to the Ohio Route 50 Project 137
x
6.2 Conclusions 138
6.3 Recommendations 140
7 REFERENCES 144
xi
LIST OF TABLES
Page
2.1 Prediction Models from the COPES study 20
2.2 Distress prediction models used in Pavespec 3.0 21
3.1 Distresses rated during inspections for the TxDOT PIMS pavement types 41
3.2 Significant pavement performance prediction programs-functions, features, modules and applicability 42 4.1 Range of input values provided for Input Output analysis of Pavespec 3.0 57
4.2 Sensitivity analysis results classified by importance 61
5.1 Inputs for Pavespec 3.0 used to simulate Ohio Route 50 pavement performance 91
5.2 Sealant unit costs, M&R costs and other inputs 93
5.3 Rehabilitation life cycle cost analysis for sealant materials used in the eastbound lanes of Ohio Route 50 Project 94
5.4 Rehabilitation life cycle cost analysis for sealant materials used in the westbound lanes of Ohio Route 50 Project 95
5.5 Data Filtering (IRI) for Eastbound Section with Delastic V 687 96 6.1 Correlation coefficients of observed distress curves for eastbound
and westbound lanes 138
xii
LIST OF FIGURES
Page
3.1 Computer based pavement management system, modules and outcomes 44
3.2 Data flow diagram for a Pavement Management System 45
5.1 Compression sealants Eastbound IRI comparison plots 97
5.2 Compression sealants Eastbound transverse slab cracking comparison plots 99
5.3 Compression sealants Eastbound spalling comparison plots 101
5.4 Silicone sealants Eastbound IRI comparison plots 103
5.5 Silicone sealants Eastbound transverse slab cracking comparison plots 105
5.6 Silicone sealants Eastbound spalling comparison plots 107
5.7 Hot pour sealants Eastbound IRI comparison plots 109
5.8 Hot pour sealants Eastbound transverse slab cracking comparison plots 110
5.9 Hot pour sealants Eastbound spalling comparison plots 111
5.10 No sealants Eastbound IRI comparison plots 112
5.11 No sealants Eastbound transverse slab cracking comparison plots 113
5.12 No sealants Eastbound spalling comparison plots 114
5.13 Compression sealants Westbound IRI comparison plots 115
5.14 Compression sealants Westbound transverse slab cracking comparison plots 117
5.15 Compression sealants Westbound spalling comparison plots 119
5.16 Silicone sealants Westbound IRI comparison plots 121
5.17 Silicone sealants Westbound transverse slab cracking comparison plots 123
5.18 Silicone sealants Westbound spalling comparison plots 125 5.19 Hot pour sealants Westbound IRI comparison plots 127
xiii
5.20 Hot pour sealants Westbound transverse slab cracking comparison plots 128
5.21 Hot pour sealants Westbound spalling comparison plots 129
5.22 No sealants Westbound IRI comparison plots 130
5.23 No sealants Westbound transverse slab cracking comparison plots 131
5.24 No sealants Westbound spalling comparison plots 132
xiv
LIST OF ABBREVIATIONS AND SYMBOLS
AADT Annual Average Daily Traffic
AASHO American Association of State Highway Officials
AASHTO American Association of State Highway and Transportation Officials
AC Asphalt Concrete
ACP Asphalt Concrete Pavements
ADOT Arizona Department of Transportation
ADT Average Daily Traffic
APA Asphalt Pavement Alliance
AQC Acceptance Quality Characteristics
CalTrans California Department of Transportation
CDOT Colorado Department of Transportation
CERL Construction Engineering and Research Laboratory
COMP Composite Pavement
COPES Concrete Pavement Evaluation Study
CPM Condition Prediction Model
CRCP Continuously Reinforced Concrete Pavement
CRS Condition Rating Survey
CRSI Concrete Reinforcing Steel Institute
CS Condition Score
DS Distress Scores
DVA Danish Void Analyzer
xv
ESALs Equivalent Single Axle Loads
FHWA Federal Highway Administration
FPS Flexible Pavement Design System
GIS Geographic Information System
HIPERPAV High Performance Concrete Paving Software
HDM Highway Design and Maintenance Standards
HPMA Highway Pavement Management Application
HPMS Highway Performance Monitoring System
IDOT Illinois Department of Transportation
ILLIPMS Illinois Pavement Information Management System
IPFS Illinois Pavement Feedback System
IRI International Roughness Index
JCP Jointed Concrete Pavements
JPCP Jointed Plain Concrete Pavement
JRCP Jointed Reinforced Concrete Pavement
L/l Ratio of Length of Slab (ft) to Radius of Relative Stiffness (ft)
LCCA Life Cycle Cost Analysis
LTPP Long Term Pavement Performance
M&R Maintenance and Rehabilitation
MAYS Mays Number
MnDOT Minnesota Department of Transportation
NCHRP National Cooperative Highway Research Program
OCI Overall Condition Index
xvi
ODOT Ohio Department of Transportation
PCC Portland Cement Concrete
PCI Pavement Condition Index
PCR Pavement Condition Rating
PDOT Pennsylvania Department of Transportation
PMS Pavement Management System
PRS Performance Related Specifications
PSI Present Serviceability Index
PSR Present Serviceability Rating
R2 Coefficient of Correlation
RPLCCA Rigid Pavement Life Cycle Cost Analysis
RPPR Rigid Pavement Performance and Rehabilitation
RSL Remaining Service Life
RUS Ride Utility Score
SD Structural Deduct
SHA State Highway Agencies
SHRP Strategic Highway Research Program
SLTE Stress Load Transfer Efficiency
SN Structural Number
SUPERPAVE Superior Performing Asphalt Pavements
TFHRC Turner-Fairbank Highway Research Center
TTI Texas Transportation Institute
TxDOT Texas Department of Transportation
xvii
TxPMIS Texas Pavement Management Information System
UPDI Unified Pavement Distress Index
xviii
1
1 INTRODUCTION
1.1 Introduction
The development and utilization of mechanistic principles and concepts for
pavement design, evaluation and maintenance have risen to prominence over the last
decade. Mechanistic-based methods combine theoretical analysis of responses induced in
a pavement system under the applied loads and calculated on the basis of mechanical
properties of materials, with statistical/empirical pavement performance considerations.
Consequently, mechanistic-based design and performance algorithms need to be
validated and calibrated using data representing in situ conditions (Paterson, 1987). A
mechanistic-based statistical regression equation calibrated with good experimental data
constitutes a popular basis for developing designs, predicting performance and
formulating maintenance plans for pavement systems.
Predicting the remaining life of or distress levels in a pavement section allows
engineers and highway agencies to plan ahead for maintenance and rehabilitation (M&R)
activities, to budget for future expenses, and thereby to minimize costs (Smith, et al.,
2001). Pavement performance monitoring can provide a quantitative trend of the
behavior of a pavement system, and can supply information for a life cycle cost analysis
(LCCA) necessary when comparing M&R options. Mechanistic-based performance
2
prediction has been gaining popularity due to its perceived universal applicability, and
the lack of exclusively mechanistic alternatives.
Pavement performance and cost are two important aspects of pavement
management, and they are often interrelated. Adding or changing a feature that increases
construction costs must be justified by a corresponding increase in pavement
performance (Wilde, et al., 2000). LCCA has been an important tool for assessing the
effect of various design features by comparing costs incurred to overall pavement
performance improvement. In the case of a newly constructed pavement system,
pavement performance can be modeled using distress prediction equations, and the
LCCA methodology can be applied for cost benefit analyses. Research presented in this
thesis focuses on mechanistic-based performance prediction and life cycle costing models
for rigid pavements.
1.2 Problem Statement
One of the most controversial issues in concrete pavement design is whether joint
sealants contribute in a cost effective manner to enhance long-term pavement
performance, as quantified by the extent of distresses, like roughness, spalling, cracking
and faulting, developing over the pavement’s service life. Whereas numerous previous
studies have examined the effectiveness of joint sealant materials and processes with
regard to the performance of the sealants themselves, relatively little effort has been
expended in assessing their impact on pavement structural performance. Consequently,
3
the question of cost effectiveness and desirability of joint sealing remains unanswered.
This thesis examines the application of long-term predictions of pavement distress levels
obtained from widely available mechanistic-based procedures to the assessment of the
relative marginal life cycle costs incurred by the use of a variety of joint sealant types.
Naturally, such an exercise involves calibration to local conditions, and this is
accomplished herein using monitoring data collected between 1998 and 2001 from the
Ohio Route 50 joint sealant experiment test site near Athens, OH (Ioannides, et al.,
2002). A third issue addressed in this work pertains to the sources of the discrepancies
between predicted and observed pavement structural performance. Moreover, through a
LCCA, this investigation seeks to assess the relative marginal cost effectiveness of a
variety of joint sealant types, installed at the test site, and reapplied according to different
M&R schedules.
To embark upon this problem, performance prediction in pavements has to be
studied and understood, so as to select an appropriate distress prediction methodology.
Distress predictions for the expected life of a pavement system provide an idea of its
future performance, allowing planners to formulate M&R measures. Emphasis is laid
upon mechanistic-based performance prediction, due to the increasing significance of this
approach in pavement design.
Furthermore, using LCCA methods, the age old dilemma of the cost effectiveness
of concrete pavement joint sealing can be examined. Prior research from the Ohio Route
50 Project has rated the sealants based on the functional effectiveness of each material
configuration but has not revealed any significant correlations between this and the
overall pavement structural performance. By comparing the rehabilitation costs that will
4
accrue for each sealant material over the life cycle of the pavement system, suggestions
can be made in relation to the cost effectiveness of the different kinds of sealant material
options that have been used in the Ohio Route 50 Portland cement concrete (PCC)
pavement.
1.3 Research Objective
Listed below are the significant objectives that this research attempts to address:
1. Examine the development of performance prediction concepts and equations for
rigid pavements. Included in the literature review of this study will be methods that have
been developed to predict fundamental pavement distresses, e.g., transverse slab
cracking, spalling, joint faulting, etc., or composite pavement condition indicators, e.g.,
international roughness index (IRI), present serviceability index (PSI), pavement
condition index (PCI), etc.
2. In addition to rigid pavements, a brief discussion will be included reporting
developments in performance prediction in the field of flexible pavements. This will
enable the reader to identify and understand the presence or lack of consistency of
developments in either field. A brief summary of practices of state highway agencies
(SHA) will also be presented in order to understand the current status of pavement
performance prediction and its applications.
3. Predicted and observed distresses for the Ohio Route 50 pavement system will be
compared. Distress trends will be predicted using a suitable computer program that will
5
be selected based on its applicability, mechanistic-empirical nature, availability, and
inclusion of life cycle costing methods. These trends will be plotted and compared to the
actual field observations. This analysis will assess the precision of distress prediction and
will highlight any similarities or dissimilarities that can lead to further discussion.
4. Utilizing the existing methods for LCCA, the cost effectiveness of different kinds
of sealant materials used in the Ohio Route 50 pavement will be determined. The cost
and performance data for joint sealants will be used to perform a rehabilitation cost
analysis of sealants over the life cycle of the pavement system.
1.4 Research Significance
Performance prediction and life cycle costing are two important aspects of the
process of pavement management. Pavements are expensive parts of the transportation
infrastructure. An investment of approximately $30 billion has been made in pavements
for the U.S. Interstate Highway System alone, and billions more are spent annually on
maintenance and upgrading. Thus, even a marginal improvement in the component
technologies of pavement management can result in large absolute savings (Haas, et al.,
1994).
The current state of practice in the field of performance prediction of pavements
will be examined to understand the advantages and shortcomings of various methods that
are being used by the SHA. A review of existing predictive tools, developed and used by
the Federal Highway Administration (FHWA), the American Association of State
6
Highway and Transportation Officials (AASHTO), the Asphalt Pavement Alliance
(APA), various SHA and other organizations, along with their characteristics, advantages
and limitations will enhance the decision making process of selecting an appropriate tool
for analyzing future projects.
The application of a selected predictive tool to the Ohio Route 50 test pavement
will assess the precision of predictions made on the basis of the initial conditions of the
pavement as constructed. It can also help gage the adequacy of monitored data that have
been collected from the project. Performance and life cycle cost simulation programs are
helpful, since decisions can be made for M&R in the abstract, by exploring various
available options and examining their cost effectiveness, without actually applying them.
A possible cost effective solution for a particular sealant configuration and type that may
be used in order to obtain better performance can be formulated from the results.
1.5 Thesis Organization
The thesis is organized into six chapters. The first chapter provides a brief
introduction to the research conducted. The problem statement, research objectives,
significance and important practical implications of the work are discussed.
Chapter 2 provides an overview of the historical development of performance
prediction concepts for pavement management. A literature review pertaining to the
collection and analysis of performance monitoring data, as well as the development of
distress prediction methods and of regression formulae using such data is conducted for
7
both concrete and asphalt pavements. The period covered spans from the emergence of
the pavement serviceability concept following the AASHO Road Test (Carey and Irick,
1960) to the development of the mechanistic-empirical equations prevalent today for
performance prediction.
Chapter 3 complements the preceding review with an analysis of the existing
methods and important programs developed and implemented for pavement management
by the FHWA, SHA, etc. Information concerning statistical regression prediction models
in use by various states across the nation is compiled. For some states, a more detailed
discussion of the pavement management programs used is presented, so as to elucidate
how performance prediction and life cycle costing methods are essential to a successful
pavement management program.
A suitable program, Pavespec 3.0, is selected from among those examined in
Chapter 3, for application to the Ohio Route 50 pavement system. To begin with, a
sensitivity analysis for this program is conducted in Chapter 4, so as to document the
accuracy and plausibility of its predictions. The selected program’s prediction and life
cycle costing module is tested with artificial inputs that are very low, moderate and very
high, and its outputs are assessed on the basis of information in documented literature and
engineering common sense.
The application of Pavespec 3.0 to data from the Ohio Route 50 pavement is
discussed in Chapter 5, where predicted and observed distress trends to date are
graphically compared for individual pavement sections, and long-term life cycle and
rehabilitation cost analyses of the various sealant materials used at the site are performed.
8
Finally, Chapter 6 presents a concise summary of the findings from this research,
of its conclusions and its recommendations for future work in suggested areas.
9
2 LITERATURE REVIEW
2.1 Introduction
In this chapter, the development of distress prediction methodologies in rigid and
flexible pavements is investigated. An attempt is made to take an in depth look at the
development of performance prediction concepts and the identification of related
performance indices as well as the formulation of mechanistic, mechanistic-empirical and
statistical/empirical models that can be used to calculate these indices over the life of the
pavement. In addition, the evolution of life cycle cost analysis (LCCA) as an important tool
in pavement management is examined. Reliable performance prediction models and cost
analysis concepts are essential elements of a pavement management system (PMS). Over the
years, there has been much research in these areas that resulted in many equations and
correlations for the purpose of predicting particular pavement distress indices. Deterioration
has been predicted in terms of these indices, and that in return has helped in the formulation
of appropriate maintenance and rehabilitation (M&R) plans for the pavement. There has
been considerable research on the application of life cycle costing procedures in evaluating
the cost effectiveness of new design features and M&R operations. Many state highway
agencies (SHA) across the nation use LCCA models that they developed in-house. The
American Association of State Highway and Transportation Officials (AASHTO) Guide for
Pavement Structures (AASHTO, 1994) suggested that agency costs and user costs be
included in the economic evaluation of alternative pavement strategies. A systematic
10
approach is followed in reporting the methods used to apply the LCCA concepts to pavement
features and systems as a whole. A simple classification of the conventional pavement types
is adopted viz., asphalt concrete (AC) (flexible) pavement; composite (AC over Portland
cement concrete) pavement (COMP); jointed plain concrete pavement (JPCP); jointed
reinforced concrete pavement (JRCP); and continuously reinforced concrete pavement
(CRCP) (Lee, et al., 1993). Prediction models have been developed to calculate distresses
related to these types of pavements, and composite pavement condition indices, such as
pavement condition index (PCI), pavement condition rating (PCR), condition rating survey
(CRS) and present serviceability index (PSI).
2.2 Pavement Performance Prediction
An important step to achieve good pavement performance prediction is determination
of pavement performance. Since the inception of pavement performance monitoring tests,
such as the Strategic Highway Research Program (SHRP), Long Term Pavement
Performance (LTPP) and the National Cooperative Highway Research Program (NCHRP),
there has been a large amount of pavement performance data that has been collected and
reported by various agencies. Means to improve the determination of pavement performance
by valid data analysis is necessary for appropriate prediction models to be developed. This
aspect becomes significant when the pavement performance prediction models being used
are statistical/empirical and mechanistic-empirical in nature. A brief summary of the
11
significant research studies in the late 1990s that help improve the determination of pavement
performance is presented below.
Juang and Amirkhanian (1992) developed a simple method for a pavement
management system based on priority ranking. Information from a pavement survey is
processed using fuzzy sets and the unified pavement distress index (UPDI) is defined and
used to evaluate the pavement distress condition. Fwa and Sinha (1992) demonstrated that
incorporation of quantified monetary values of pavement performance could have a
significant impact on the outcome of engineering economic analysis. Liu and Herman (1996)
proposed a new methodology to evaluate pavement performance data by applying Fechner’s
psychophysical law. It has been found that the American Association of State Highway
Officials (AASHO) road test data, as well as road test data obtained in Texas, Canada, and
the international road roughness experiment are organized well by the simple summation of
logarithmic terms or the roadway characteristic variables. This methodology can be further
applied to handle similar types of road test data. Buch (1997) provided a framework for the
development of Weibull reliability factors for joint faulting models using field data from
SHRP’s LTPP database. Pavement performance factors, such as climate conditions, soil
conditions, and load transfer conditions, are considered for calibration using this analysis
(Pierce, et al., 2002).
Numerous prediction models have been developed using various available
mathematical techniques. They can be classified as either deterministic or as probabilistic,
depending on the nature of the values predicted. Regression models are most commonly
developed, where mathematical applications and procedures such as statistical analysis and
comparisons are used to arrive at trend lines of distresses. These trend lines and equations in
12
turn are used to predict specific pavement distresses, and to evaluate composite condition
indices.
Pavement performance, deterioration, design methods and many other relevant
concepts were addressed after the AASHO road test. Another important milestone was the
precise definition of pavement performance through the serviceability-performance concept
(Carey and Irick, 1960). Pavement performance prediction models have been classified into
two basic classes, namely, deterministic and probabilistic. These are further broken down
into structural, functional and damage for the first type and survivor curve and transition for
the second type. For operational purposes, four basic types of prediction models are defined:
(1) Purely mechanistic; (2) mechanistic-empirical; (3) regression-based; and, (4) subjective.
The first type, purely mechanistic, has not been developed yet because pavement engineers
do not use primary or fundamental response parameters as ends in themselves. Rather,
responses are only useful if they can be related to pavement distresses or to pavement
properties. Consequently, in the mechanistic-empirical approach to predicting deterioration
the fundamental characteristics of a pavement system are related to the distresses, which are
used to compute deterioration indices. Regression analysis is the most common method for
deriving correlations among these characteristics. Pure regression-based models accomplish
this just by attempting to devise statistical correlations between the distress indices and
pavement performance (Haas, et al., 1994).
Use of mechanistic principles in the development of performance prediction models
was initiated by Rauhut, et al. (1984), whose research for the Federal Highway
Administration (FHWA) focused on using a mechanistic model calibrated empirically by
field data, to evaluate the traffic damaging effects for highway cost allocation. A
13
classification of prediction models for pavements was suggested in the work of Lytton
(1987), and was detailed by Mahoney (1990). This compilation, however, was primarily
focused on models for flexible pavements. One of the more important indices that have been
devised is the PCI, which is used in many mechanistic-empirical, regression algorithms and
prediction models. An important consideration of many SHA throughout the country is that
of a prediction model’s ability to predict performance adequately for their specific designs,
materials, subgrades, traffic and climatic conditions, as the data supporting each such model
are invariably inadequate to cover the limitless combinations of these factors (Haas, et al.,
1994).
2.3 Performance Prediction Models for Flexible Pavements
Performance prediction models are better developed in the area of flexible pavements,
as these types of pavements are more frequently used all over the world. Many performance
prediction models for flexible pavements have been developed from studies conducted in
various countries. The most significant ones are briefly mentioned in this section (Paterson,
1987).
2.3.1 AASHTO Model
The model predicting pavement performance developed from the AASHO Road Test
(1958-1960) in Illinois, that was incorporated into the subsequent AASHO Interim Design
Guide, consists of one damage function for serviceability only. This model predicts the loss
of serviceability that is closely related to the roughness (Paterson, 1987).
14
2.3.2 Arizona Department of Transportation Model
The model developed for a pavement management system by the Arizona Department
of Transportation (ADOT) was derived from two databases sampling the Arizona road
network, and includes functions for roughness progression, crack initiation and progression
(Paterson, 1987).
2.3.3 Texas FPS Model
Developed for the Flexible Pavement Design System (FPS) of the Texas A&M
University by Lytton, et al. (1982), this model was derived using data from the samples of
the Texas road network, and includes functions for serviceability (roughness) and cracking
progression (Paterson, 1987).
2.3.4 Highway Design and Maintenance Standards (HDM) Model
Developed from a comprehensive, factorially designed database of in-service
pavements, the HDM III Model includes modules for predicting cracking, rutting, roughness,
etc. The cracking models are developed for various types of surfaces of flexible pavements
(Paterson, 1987).
2.3.5 SUPERPAVE Research
The development of performance prediction models for Superior Performing Asphalt
Pavements (SUPERPAVE) has been an active research topic since the late 1980s.
SUPERPAVE performance models, a key part of the SUPERPAVE software, are used to
predict how well a specific asphalt mix will withstand rutting, fatigue cracking and low
15
temperature cracking. This task is being accomplished by various SUPERPAVE research
centers across the nation, in association with the FHWA (Witczack, 1996).
In addition, there are numerous models developed from comprehensive databases that
predict cracking and rutting of asphalt pavements. The HDM III, RTIM2 Models and the
Brazil models developed by Queiroz (1981) are the more significant ones (Paterson, 1987
2.4 Performance Prediction Models for Rigid Pavements
Distress prediction models have been developed since the 1990s, with much emphasis
on transverse joint faulting, transverse fatigue cracking, transverse joint spalling, and on the
computation of the international roughness index (IRI). These models take into
consideration some or all of the important data types, including: (1) traffic data; (2) design
feature characteristic data, viz., material, Portland cement concrete (PCC) slab support,
drainage, joints, etc.; (3) climatic data; and (4) time rate of accumulation of the above
mentioned significant distresses (Hoerner, et al., 2000).
To classify the significant rigid pavement distress prediction models, the most
common distresses in rigid pavements have to be identified. For concrete pavement types,
such as JPCP, JRCP and CRCP, the significant distresses common to all the types of
pavements are: transverse slab cracking, spalling of longitudinal and transverse joints, joint
faulting, joint sealant damage and pavement surface smoothness loss.
The NCHRP-Concrete Pavement Evaluation Study (COPES) was one of the first
research projects to develop prediction models for JPCP and JRCP. Through this research,
Darter, et al. (1985) developed models that predicted concrete pavement distresses, including
16
pumping, joint faulting, joint deterioration, slab cracking, as well as the present serviceability
rating (PSR). National models were developed using the COPES database that was compiled
from six states and other studies. The models proposed to predict slab cracking for JPCP and
JRCP are given in Table 2.1.
Dossey and Hudson (1994) developed distress prediction models for CRCP for
application in the Texas Pavement Management Information System (TxPMIS). These were
statistical /empirical models specific for the Texas pavements that were developed using
twenty years of data, and can predict punch outs, patches, crack spacing, loss of ride quality
and spalling.
The composite condition indices signify the overall condition of the pavement, and
have been an important indicator of pavement condition since the AASHO road test that
defined PSI for a pavement. Mechanistic-empirical concepts have been used in developing
models that predict such composite condition indices. The Pennsylvania Department of
Transportation (PDOT) model predicts the PSI of reinforced concrete pavements solely as a
function of the pavement age. The states of Washington and Mississippi have models
developed to predict the PCR for asphalt and rigid pavements (Haas, 2001).
Lee, et al. (1993) developed models to predict the PSR for the five recognized
pavement types, with the structural number (SN), age, and cumulative equivalent single axle
loads (ESALs) as the predictor variables. The Highway Performance Monitoring System
(HPMS) databases were used to develop these models. Different model forms, such as
linear, logarithmic, and other simplified forms, were examined to develop the predictive
model and the following functional form was chosen:
dcb CESALAGESTRaPSRPSR ×××−= 1
17
where PSR I = Initial value of PSR at construction
STR = existing pavement structure : structural number for flexible pavement, total asphalt
concrete overlay thickness for composite pavement (in.) and slab thickness for concrete
pavement (in.)
AGE = Age of the pavement since construction or major rehabilitation (yrs.)
CESAL = Cumulative ESALs applied to the pavement in the heaviest traffic lane (nos.)
Regression coefficients a, b, c, and d were proposed by the authors for each of the different
types of the pavements namely, flexible, COMP, JPCP, JRCP and CRCP.
For the Illinois interstate system, the CRS is used as an indicator, with prediction
models developed to calculate this index for all kinds of pavements (Hall, et al., 1994)
proposed prediction models for the CRS, applicable to the Illinois jointed reinforced and
continuously reinforced pavements.
Pavement age is an essential factor in all the models mentioned above with some
more complex ones including roughness, traffic, and structure of the pavement. It is
interesting to note that very few of these models incorporate actual distresses to predict the
composite indices. These models have been used in many performance prediction
applications that are essential elements of pavement management system.
Pavespec 3.0 is a computer program that consists of mechanistic-based prediction
models for rigid pavements. In this research study, this program has been used for
simulating pavement performance. Pavespec 3.0 uses models that provide the trends of
major distresses in rigid pavements. A more detailed analysis of these models is provided
below.
18
Important models employed in Pavespec 3.0 include those used to calculate
transverse joint faulting, transverse slab cracking and transverse joint spalling as well as the
IRI. Over the years much research was focused on developing statistical /empirical, and
mechanistic-empirical models to calculate these distresses for concrete pavements. A
compilation of the best available models is provided in the publication for Pavespec 3.0
(Hoerner, et al., 2000).
Databases from the LTPP experiment, FHWA Rigid Pavement Performance and
Rehabilitation (RPPR) experiment, and from many other regional and statewide pavement
performance monitoring experiments, have been used to develop prediction models for
transverse joint faulting. Mechanistic-empirical models have been developed by Yu, et al.
(1997, 1998) for doweled as well as un-doweled pavements, to predict all the important
concrete pavement distresses. Statistical empirical models to predict these distresses have
been developed by Simpson, et al. (1994) for un-doweled pavements. Further contribution
has been made by Titus-Glover, et al. (1999) and by Hoerner, et al. (1999) in the form of
mechanistic-empirical models for the FHWA LTPP program. The most suitable ones among
these models have been used in Pavespec 3.0. Pavespec 3.0’s mechanistic-empirical models
are mainly for the JPCP type of concrete pavements. Calibration of these models was
performed using databases from pavement performance monitoring experiments, such as
LTPP, FHWA RPPR, NCHRP 1-19, Extended AASHO Road Test and the Mn/Road
Database. A brief description of the models that have been used for distress prediction in
Pavespec 3.0 is presented in Table 2.2.
For transverse joint faulting, the model that was developed by Yu, et al. (1998) under
the NCHRP 1-34 project and modified by Hoerner, et al. (1999) was identified as the most
19
suitable for use in Pavespec 3.0. For transverse cracking prediction the largely mechanistic
model developed by Yu, et al. (1997) under the RPPR project was selected for use. The
transverse joint spalling model developed by Yu, et al. (1997) under the RPPR project that
was modified by Hoerner, et al. (1999) was identified as the most suitable model for
application in the deterioration prediction module of Pavespec 3.0. The IRI prediction model
developed by Hoerner, et al. (1999) was used because of its inclusion of the initial IRI and
key distresses, in addition to the extensive LTPP database that was used for its development.
Furthermore, Pavespec 3.0 organized the relevant data from the national databases for
calibrating these models. Engineering assessment, statistical analysis and sensitivity analysis
methods were used to achieve this (Hoerner, et al., 2000).
20
Table 2.1 Prediction Models from the COPES study (Darter, et al., 1985)
JPCP
CRACKS = ESAL2.755 [3092.4(1-
SOILCRS)RATIO10] + ESAL0.5 (1.233
TRANGE2.0 RATIO2.868) + ESAL2.416(0.2296 FI1.53
RATIO7.31)
CRACKS = Total length of medium and high severity deteriorated temperature and shrinkage cracks, (ft. /mile) SOILCRS =0 if subgrade is fine grained = 1 if subgrade is coarse grained RATIO = Westergaard’s edge stress/ modulus of rupture (stress computed under a 9-kip wheel load) FI = Freezing Index TRANGE = Difference between the average maximum temperature in July and the average minimum temperature in January
JRCP
CRACKS = ESAL 0.897 [7130.0 JTSPACE/
(ASTEEL * THICK0.5)] + ESAL 0.10 (2.281
PUMP5.0) + ESAL2.16 [1.81/ (BASETYP + 1)]
+ AGE1.3[0.0036 (FI +1) 0.36]
CRACKS = Total length of medium and high severity deteriorated temperature and shrinkage cracks, (ft. /mile) JTSPACE =Transverse joint spacing, (ft.) ASTEEL = Area of reinforcing steel, (in.2/ft.) THICK = Slab thickness, (in.) PUMP = 0 if no pumping exists, = 1 if low severity, = 2 if medium severity, and = 3 if high severity BASETYP= 0 if granular base, = 1 if stabilized base AGE = Time since construction, years (indicator of cycles of cold and warm temperatures stressing reinforcing steel) FI = Freezing Index
21
Table 2.2 Distress prediction models used in Pavespec 3.0 (Hoerner, et al., 2000)
Transverse Joint Faulting Model
FAULT=DAMAGE0.275*[01741-
.0009911*DAYS90+0.001082*PRECIP]
FAULT=Average Transverse Joint Faulting per joint, in. DAMAGE=n/N n=Actual number of cumulative applied ESALs N=Allowable number of cumulative applied ESALs DAYS90=Number of days per year with the maximum temperature greater than 90 F PRECIP=Average Annual Precipitation, in.
Transverse Slab Cracking
% CRACKED = 100/(1+1.16 FD-1.3)
%CRACKED = Percentage of Slabs Cracked FD = Fatigue Damage
Transverse Joint Spalling
%SPALL = [AGE/(AGE+0.01)]*[100/(1+
1.005-12*AGE+SF)]
%SPALL=Percentage joints spalled (medium and high severities) AGE=Time since construction, years SF=Scaling Factor based on site, design and climate related variables
IRI Model IRI =
IRI0+0.013*%CRACKED+0.007*%SPALL+
0.001*TFAULT+0.03*SITE
IRI0=Initial Smoothness Measured as IRI, m./km. %CRACKED=Percentage of slabs with transverse cracking and corner cracks (expressed as a number between 0 and 100) %SPALL= Percentage of joints with spalling (medium to severe) TFAULT=Total joint faulting cumulated per km,mm. SITE = Site factor=AGE*(1+FI)1.5*(1+P0.075)*10-6 AGE=Pavement age since construction, years FI=Freezing Index, C-days P0.075=Percentage of subgrade material passing the #200 Sieve
22
3 SURVEY OF CURRENT PRACTICE
3.1 Introduction
In the previous chapter, the reader was introduced to the concept of mechanistic-
based performance prediction and to the development of distress prediction models since
the American Association of State Highway Officials (AASHO) Road Test (1958-1960).
It provided an introduction from a research point of view to underlying concepts and
relations employed in the prediction of distresses in pavements. In this chapter, computer
programs and applications that help forecast pavement performance through distress
prediction models are briefly examined. Some of the programs examined, e.g., Pavespec
3.0 and Micro PAVER, have been developed from concepts and relations presented in the
previous chapter. The purpose here is to investigate the usage of mechanistic-based
performance prediction tools, and examine their suitability for a variety of possible
applications. Experiences in performance prediction by various state highway agencies
(SHA) across the nation will be assembled, and brief descriptions of methods used
around the country will be presented. This will enable the reader to understand the
current state of affairs with respect to mechanistic-based performance prediction, and also
to assess possible needs to adopt such practices in the future. A subsequent chapter will
apply a selected computer program to the Ohio Route 50 test pavement, and will present
an analysis of the results obtained.
23
3.2 Computer Programs for Pavement Performance Prediction
Statistical regression formulae for the prediction of pavement performance and for
life cycle cost analysis (LCCA) have been an integral part of pavement management
systems (PMS) used by SHA since the emergence of computerized analysis methods in
the transportation sector. The first such pavement management tools were developed in
the mid-1970s, and at present the most advanced are those applied in North America.
They have been helpful for the planning, and maintenance and rehabilitation (M&R)
processes that require assessment of different scenarios of pavement deterioration. In
order to perform effective planning, prediction models should have the ability to assess
the performance of any chosen set of M&R actions performed over the life cycle period.
Prevention of pavement deterioration is partly dependent on the type of treatment used
for M&R, and, therefore, a realistic prediction algorithm will help monitor the different
performance paths that the pavement system might traverse when a certain option is used.
With the increased use of computers, which permit the maintenance of large
databases and the development of relationships from data collected through sophisticated
statistical analyses, performance prediction has undergone a rapid evolution. Many SHA,
as well as federal organizations, army research centers and universities across the nation
have developed and implemented computer programs for pavement management,
consisting of modules for performance prediction and life cycle costing. Many programs
are currently being used by SHA for pavement infrastructure management and future
planning. Moreover, the data from the Long Term Pavement Performance (LTPP) of the
24
Strategic Highway Research Program (SHRP) and from WesTrack experiments have
been of much use for calibration of pertinent algorithms in order to increase the reliability
of predictions.
Existing programs for personal computers can be broadly grouped on the basis of
their applicability to specific types of pavement systems and of the functions they
perform. Many of these programs have stand-alone application modules for deterioration
prediction, selection of maintenance options and cost analysis, and these are linked with
each other on the basis of fundamental concepts. A brief overview of computer-based
pavement management application packages and their modules is presented in Fig. 3.1.
Important modules of a good pavement management system include: (1) performance
prediction module; (2) planning, maintenance and rehabilitation module; (3) LCCA
module; and (4) pavement performance database. Some significant outcomes are: (1)
distress predictions and remaining life estimates; (2) pavement management and
maintenance strategies; (3) evaluation of such options and strategies through LCCA; and
(4) improved planning methods for future pavement systems. The structure shown in
Fig. 3.1 is generic, but it may involve further levels and classifications for each module.
The type of database, methodologies used in the performance prediction modules, LCCA
methods employed and the kinds of pavements to which these models apply, are some of
the additional distinctions.
25
3.2.1 Programs for Rigid Pavements
There are many software packages that address pavement performance prediction
and life cycle costing in one way or another. For example, various programs were
developed during the 1990s that address issues such as early-age concrete pavement
behavior and performance prediction (HIPERPAV), M&R options and costing for
concrete pavements (SAPER), life cycle costing for rigid and flexible pavements
(LCCOST- Asphalt Institute, LCCP/LCCR- Maryland), etc. The objective of this
research, however, is to investigate the use of mechanistic-based performance prediction
for rigid pavements. For this reason, only the most significant of applications developed
for such pavements to predict performance and thus establish life cycle costs for
assessing design or maintenance alternatives, are summarized below. The programs were
selected based primarily on the criteria that: (1) the application should address distress
prediction of rigid pavements based on mechanistic-based models; (2) an LCCA module
must be present to evaluate the effectiveness of M&R measures; and, (3) the program
should include various input options that encompass a wide variety of climate, traffic,
design, M&R variables present across the nation. Table 3.2 provides information related
to the applicability, prediction methodology, and LCCA techniques applied in programs
that are considered appropriate for this research.
Pavespec 3.0 (FHWA)
Developed by Turner-Fairbank Highway Research Center (TFHRC), a division of
the research, the development and technology section of Federal Highway Administration
(FHWA), Pavespec 3.0 is a program that can be used in developing performance related
26
specifications (PRS) by predicting the performance of an as-constructed or to be
constructed pavement. Mechanistic-empirical distress prediction equations are used in
this program to model the performance of rigid pavements based on a specific set of
indicators. Furthermore, calculated distress results are used to compute life cycle costs,
pay factor charts, etc., which are helpful in developing PRS for the pavement. A
complete description of the abilities of Pavespec 3.0, and the prediction models
incorporated into it, has been provided in detail by Hoerner, et al. (2000). Pavespec 3.0
has the following capabilities: (a) Simulation of pavement performance in terms of (1)
transverse cracking, (2) transverse joint faulting (3) transverse joint spalling, and (4)
pavement smoothness over time; (b) Applications of a user-defined M&R plan to
compute life cycle costs; (c) Development of pay factor charts for the following
acceptance quality characteristics (AQC): (1) strength; (2) thickness; (3) air content; (4)
smoothness; and, (5) consolidation around dowels; (d) Computation of contractor pay
factors from actual construction test results for the five AQC mentioned; (e) Assistance in
executing sensitivity analyses for a given PRS to be developed.
RPLCCA (Center for Transportation Research, TxDOT)
Rigid Pavement Life Cycle Cost Analysis (RPLCCA) was developed by the
Center for Transportation Research of the University of Texas at Austin, for training and
implementation by the Texas Department of Transportation (TxDOT). This program is a
life cycle costing methodology for Portland cement concrete (PCC) pavements that
considers all the aspects of pavement design, construction and maintenance, as well as
user impacts during the entire analysis period. It predicts the pavement performance
27
using state-of-the-art performance algorithms and reliability concepts, from which M&R
needs are established. The modular nature of its methodology allows it to incorporate
accurate performance prediction models, as well as user costs and external costs
associated with highway construction. The development history of and user guidelines
for this program have been provided by Wilde, et al. (2000) and by Waalkes, et al.
(1999), who have also presented a sensitivity analysis. Important features of this
program are: (a) Performance models that predict the level of selected distresses to be
expected based on the construction, environmental conditions plus traffic loading over
time; (b) Incorporation of reliability concepts in the prediction models due to the
variability of inputs and outputs; (c) Usage of mechanistic-empirical and
statistical/empirical models; (d) Complete LCCA of the pavement system considering the
available M&R options.
The analysis includes agency, user and external cost components. RPLCCA
offers a very logical and organized approach to pavement performance modeling and life
cycle costing. A shortcoming of this program is that most of the factors considered,
including costs and rehabilitation options, are pertinent to TxDOT; consequently its
applicability as a general program to be used elsewhere is limited.
POWERPAVE (CRSI)
POWERPAVE is a computer program developed by the Concrete Reinforcing
Steel Institute (CRSI) that allows users to predict the early-age performance of
continuously reinforced concrete pavement (CRCP) systems. This is an easy-to-use tool
that optimizes CRCP options to allow owners, designers, and contractors to reduce risk,
28
control costs, and maximize investment returns and performance. Performance
predictions in POWERPAVE are based on design assumptions, such as material quantities
and types, as well as construction assumptions, including environmental factors and
construction methods. The software features a Microsoft Windows-based interface that
accepts inputs related to climate, construction methods, materials, traffic and other
significant factors. The program predicts early-age performance based on mechanistic
methods, but it is only applicable to CRCP systems.
Micro PAVER (US Army Corps of Engineers)
Micro PAVER is a PMS that aids pavement managers in deciding when and
where to appropriate funds for pavement M&R. Micro PAVER provides pavement
management capabilities to: (1) develop and organize the pavement inventory; (2) assess
the current condition of pavements; (3) develop models to predict future conditions; (4)
report on past and future pavement performance; and (5) develop scenarios for pavement
maintenance based on budget or condition requirements. Micro PAVER inventory
management is based on a hierarchical structure composed of networks, branches, and
sections, with the section being the smallest managed unit. This structure allows users to
organize their inventory easily, while providing numerous fields and levels for storing
pavement characteristics. Micro PAVER uses the “family method” developed by Nunez
and Shahin (1986) and by Shahin and Walther (1990), through a research program at the
U. S. Army Construction Engineering and Research Laboratory (CERL).
Micro PAVER has the following modules and applications to help monitor
pavement deterioration and formulate M&R options:
29
1. Inventory: The Micro PAVER program allows users to store pictures of individual
sections, sample units and distresses that can act as a repository of information.
2. Field Inspection: Micro PAVER enables users to fill out a standard form that can
be entered and edited in the database.
3. Condition Analysis: Data from prior inspections, predictions and analyses help
visualize the condition of pavement over the specified period of time.
4. Prediction Modeling: The program identifies groups of pavements that are
expected to be subjected to similar traffic, weather and loading conditions.
Historical data about such “pavement families” are used to develop the condition
prediction model (CPM) for the future maintenance. The CPM is designed to
permit users to blend knowledge about their pavements and local condition
measurements with powerful modeling tools to produce accurate estimates of
future pavement life.
5. Work Planning: The M&R plan utilizes basic inventory data combined with
inspection information, maintenance policies, maintenance costs and predictions
about future pavement condition to develop a work-plan specific to a site.
These features make Micro PAVER an important tool in pavement management.
This system is used by the U. S. Army, several SHA and many other organizations.
There are over five hundred users of MicroPAVER across the U.S, Canada and in Asia.
Pavement performance is predicted on the basis of grouping and networking data
gathered previously.
30
Highway Design and Maintenance Standards Model (HDM) (World Bank)
The Highway Design and Maintenance Standards Model (HDM) computer
program was developed by the World Bank for evaluating highway projects, standards,
and programs in developing countries. HDM has been undergoing continuous
improvement and has been released in several versions, the current one being HDM-4. It
is used to make comparative cost estimates and ergonomic evaluations of different
construction and maintenance options for a given road section or a road network. HDM-
4 assumes that construction, maintenance and vehicle operating costs are functions of
vertical alignment, horizontal alignment and road surface conditions. One of the major
disadvantages of this program is that it does not specifically model PCC pavements.
3.3 Programs for Life Cycle Cost Analysis
LCCA is an important methodology through which state agencies can evaluate the
effectiveness of new design features and maintenance as well as rehabilitation plans for
pavement systems. A list of the most notable LCCA programs that have been developed
for rigid and flexible pavements was compiled by Wilde, et al. (2000) as a part of the
research to develop RPLCCA for the TXDOT. What follows is a summary of
information provided by Wilde, et al., (2000).
31
LCCOST (Asphalt Institute)
The program LCCOST was developed by the Asphalt Institute. It incorporates the
initial construction costs, multiple rehabilitation action costs and user costs at the work
zones during the construction and rehabilitation activities. Yet it does not have a
performance modeling module nor does it have a structural pavement model. One
important aspect is that this program considers the routine maintenance costs that are
often ignored by transportation agencies.
DARWin (AASHTO)
The DARWin pavement design system is a program that automates the American
Association of State Highway and Transportation Officials (AASHTO) design equations
and simplifies the management of materials, layers and construction activities. The life
cycle cost module of DARWin accounts for project dimensions, initial construction, up to
five preprogrammed rehabilitation strategies, and the salvage value of the pavement.
This program focuses primarily on calculating agency costs associated with specific
projects rather than the complete LCCA.
LCCP/LCCPR (University of Maryland)
This set of programs was developed by the University of Maryland for rigid as
well as flexible pavements. These programs incorporate user operating costs associated
with pavement roughness and other measures of user costs. They were developed for
project-level analysis.
32
EXPEAR (FHWA)
The EXPEAR application was developed by the University of Illinois for the
FHWA. It performs project-level evaluation and requires data from visual evaluation
surveys. Based on these surveys, the program recommends rehabilitation techniques,
including reconstruction, resurfacing, and minor rehabilitation techniques. It does not,
however, does not consider user costs or other indirect impacts of the recommended
rehabilitation techniques.
MicroBENCOST (Texas Transportation Institute)
This program was developed in 1993 under the NCHRP project 7-12 by the Texas
Transportation Institute (TTI). It analyzes many types of projects including pavement
rehabilitation, added lane capacity, bridge, and bypass construction projects. It takes a
large number of inputs and compares a benefit/cost analysis that considers costs with and
without the specific alternatives. Its main function is to compare different alternatives
and evaluate the benefits and costs of selecting a particular alternative.
Real Cost 2.1 (FHWA)
Real Cost 2.1 is a Microsoft Excel based application developed by the FHWA for
performing deterministic as well as probabilistic life cycle costing of pavement
rehabilitation alternatives. The procedures followed for performing this analysis follow
the recommendations of the ‘Pavement Division Interim Technical Bulletin’ prepared by
Walls and Smith (1998) for FHWA. This bulletin outlines procedures for application of
LCCA for pavement design and rehabilitation. Real Cost 2.1 can consider the relevant
33
economic variables, project data, and available design alternatives to output simulated
life cycle costs, which are either deterministic or probabilistic.
In addition to the ones mentioned above, there are many other LCCA modules
developed internally by various SHA to perform cost evaluations of the feasible M&R
options.
3.4 Performance Prediction – Current State-of-the-Practice
The concepts of pavement performance prediction and LCCA have been
incorporated in the PMS of several SHA in the United States. A PMS provides
information necessary to find cost effective strategies for evaluating and maintaining
pavements in a serviceable condition. The basic components of a PMS are: (1) a
comprehensive database that contains current and historic pavement condition, traffic and
structural data; (2) a set of tools that assist in determining the current and future
pavement conditions, which are then used to predict financial needs for M&R operations
(Haas, et al., 1994). Performance prediction involves statistical/empirical methods,
whereas financial assessment relies on LCCA techniques.
To comprehend the state-of-the-practice of pavement performance prediction
among various SHA, a typical data flow chart in a PMS is useful. Figure 3.2 is a generic
data flow diagram for a PMS. It shows that data collected can be distinguished into: (a)
construction data obtained during pavement construction; and (b) condition data from
existing in-service roads. The data are allocated between three main destinations: (i) a set
34
of individual case studies investigated; (ii) a research database concerned with the
influence of a number of variables; and (iii) planning and reporting activity database,
serving the entire network (Smith, et al., 2001). The PMS incorporates equations
developed using these data for various purposes, as shown in the Figure 3.2. Using
statistical/empirical correlations, such algorithms can predict pavement structural
distresses or calculate composite indices, such as pavement condition rating (PCR),
present serviceability index (PSI), remaining service life (RSL), etc.
The following section provides a detailed description of the various aspects of a
PMS, to give the reader a better idea of the need for pavement performance prediction.
Along with brief explanations, methods and techniques used by various SHA to
accomplish the requirements for each task of a typical PMS are presented.
3.5 Pavement Management System Framework
An efficient PMS hinges on reliable data, appropriate methods of analysis to
identify sections needed for repair, and accurate prediction models that help in decisions
related to M&R of pavements in a timely fashion and within the allocated budget.
Application of a PMS involves several stages, such as data collection, data categorization
and analysis, performance modeling and formulation of recommendations for M&R. The
fundamental objective of a PMS, the performance prediction, and the cost analysis are
common to most SHA. The difference, however, lies in the procedures implemented by
each SHA, for each of the stages mentioned.
35
3.5.1 Distress Data Collection
The primary sources of pavement performance data are visual or automated
inspections conducted during construction and regular condition surveys of pavement
sections. High quality, reliable data form the substructure of a good PMS.
The Illinois Pavement Feedback System (IPFS) has international roughness index
(IRI), rutting, faulting and surface type data collected every two years. Information about
D-cracking, pavement construction, rehabilitation, reconstruction and repair, as well as
average daily traffic (ADT), equivalent single axle loads (ESALs), truck traffic, traffic
growth rates, etc., has also been procured (Bham, et al., 2001b). In Texas, pavement
condition data are collected annually from the highway network by visual inspection.
These include distresses such as patching, rutting and pavement roughness, deflection
data reflecting pavement strength, and skid data (Smith, et al., 2001). In Colorado,
primary distress data related to rutting, faulting, spalling, cracking, corner breaks,
bleeding, raveling, etc., and peripheral data pertaining to the shoulder type, shoulder
condition and width are collected every two years. Colorado Department of
Transportation (CDOT) uses an automated data collection vehicle for rut and ride
condition data, whereas all other data (from pavement type to distress severity) are
deduced from video tapes (Farrokhyar, et al., 2001).
3.5.2 Data Categorization and Analysis
Data collected for a PMS can be simply categorized as follows: (1) pavement type
information; (2) pavement distress data; (3) traffic data; and (4) maintenance information.
36
A condition indicator is assigned for each distress. Such indicators provide the SHA a
better idea of the current condition of a pavement section or network, with respect to
significant distresses, enabling personnel to take preventive maintenance actions. After
an initial condition assessment, prediction modeling concepts can be used to determine
the appropriate M&R procedures needed, and the associated costs.
Texas Department of Transportation (TxDOT) categorizes pavements in the
following types: (1) CRCP; (2) jointed concrete pavements (JCP); (3) asphalt concrete
pavements (ACP); each is then classified further based on other criteria, such as thickness
of asphalt layer, presence of reinforcement, etc. Table 3.1 lists the distresses reported for
each pavement type during visual inspections. For every pavement section monitored,
each one of the distress types is attributed a rating. Initial analysis is performed to
compute distress scores (DS) from such distress ratings, ride utility scores (RUS) using
measured ride values, and a final condition score (CS) calculated from DS and RUS
values. CDOT uses a similar methodology by initially attributing a rating (0 to 100) to
each pavement distress. Index values are computed from the distress ratings for ride
roughness, rutting, alligator cracking, block cracking, longitudinal cracking, transverse
cracking, load associated longitudinal cracking and corner breaking.
3.5.3 Pavement Performance Modeling
The fundamental use of pavement performance modeling is in predicting the
behavior and related costs of various M&R options for in-service pavement sections.
During the planning and design stages, reliable performance modeling can help predict
37
the pavement system behavior and life cycle costs, thereby helping SHA make effective
decisions.
Performance Curves and Equations
Performance curves and equations are most commonly implemented by SHA in
predicting pavement performance. Historical data are grouped by pavement type, traffic,
geographic region, climatic conditions etc., and appropriate performance prediction
curves or equations are generated. Statistical regression analysis and probabilistic
techniques are commonly used in the development of such curves or equations.
The Illinois Department of Transportation (IDOT) uses the historical CRS, IRI,
Annual Average Daily Traffic (AADT) and rutting information from various Interstate
sections as input parameters for the prediction models. These data are used to customize
the prediction equations programmed in the PMS software for each pavement type to
generate trends for CRS, IRI, rutting and traffic forecasting for each section of the
highway system. Examples of the prediction equations used are presented below:
YearsValueDeductCRSCurrentCRSFuture ×−= (3.1)
YearsaRutCurrentRutFuture ×+= (3.2)
YearsaIRICurrentIRIFuture ×+= (3.3)
where, Deduct Value and a are parameters obtained from historical data.
TxDOT Pavement Information Management System (PIMS) uses sigmoidal (S-
shaped) distress curves. Most of the PIMS distress types are assigned performance curve
parameters based on empirical analysis of past performance of similar pavement sections
(Smith, et al., 2001). In the state of Colorado, CDOT uses performance curves that are
38
site-specific developed using historical data collected from the site; pavement family
curves developed by grouping pavements based on type, traffic, climate, thickness; or
default curves. If historic data for more than five years are available for a section, site-
specific curves are used. In case data are not sufficient, pavement family or default
curves are utilized to project the trend of each distress type.
3.5.4 Application of Performance Prediction
Applications of performance modeling are numerous, spanning the areas of
pavement design, planning, construction and maintenance. Among various SHA,
performance modeling is used mainly to help in the decision making process related to
M&R operations for the pavement network. Alternative M&R treatments are examined
for their effectiveness by predicting the performance, and life extension of the pavement
system with the specific treatment options. Additionally, due to budget limitations, the
best pavement M&R treatment has to be applied to the pavement system that is projected
to deteriorate the fastest. Thus, performance modeling helps optimize the limited
monetary resources of SHA.
Maintenance and Rehabilitation
IDOT PIMS has a decision tree built into its performance modeling that conducts
a cost benefit analysis of each available M&R treatment option using weighted benefit
ranking methods. The input parameters for this analysis are the effects of rehabilitation
on CRS, IRI, and rutting for various types of pavements, unit costs for each potential
39
rehabilitation alternatives, and allocated budget. The analysis generates an optimized
multi-year pavement improvement program.
In the case of Texas, four treatment levels are specified: (1) preventive
maintenance; (2) light rehabilitation; (3) medium rehabilitation; and (4) heavy
rehabilitation or reconstruction, with detailed actions and options for each pavement type
built into the state PIMS. Based on the field data of distress scores, ride roughness,
rutting, etc., prediction equations are used to generate the performance trends for a
pavement section when each one of the four maintenance options is chosen. Based on a
cost benefit analysis performed subsequently, an M&R program is selected.
CDOT uses performance curves to predict the pavement distresses over the
pavement’s life cycle. A threshold value is assigned for each distress that will help
calculate the RSL of the pavement for each distress viz., ride, rut, alligator cracking,
block cracking, longitudinal cracks, transverse cracks for asphalt pavements, and ride,
rut, longitudinal cracks, transverse cracks and corner breaks for concrete pavements.
Various strategies are evaluated with the help of expert opinion to determine the M&R
treatments necessary based on RSL, costs associated and benefits provided by each
option.
Planning and Design
At the statewide pavement network level, performance modeling can help SHA in
planning and allocating resources better. Distress predictions for each section of a
pavement network can provide an idea of the projected repairs, and costs associated, thus
assisting the SHA in budgeting funds appropriately.
40
The IDOT PIMS uses Geographic Information System (GIS) based spatial
mapping of the entire pavement network. The system provides a graphical outlook of the
predicted pavement distress (CRS, IRI, rutting, etc.) for a selected pavement section.
Rehabilitation projects and associated costs based on each pavement distress can be
extracted from the system. Such analysis helps the IDOT allocate funds efficiently or
optimize spending on M&R projects within budget.
Other Applications
In addition to assistance in maintenance, performance modeling helps during the
construction phase of pavements. Prediction modeling can determine pavement
distresses over a pavement’s entire life cycle using initial inputs such as pavement type,
material and structural data, traffic projections, climate, etc. Such analysis will help state
agencies make the best decisions, and also assess pay factors for contractors. Pavespec
3.0, the program selected for this research, is one such application and uses mechanistic-
based performance modeling for jointed concrete pavements (JCP) to project distresses
and generate pay factor curves.
41
Table 3.1 Distresses rated during inspections for the TxDOT PIMS pavement types
CRCP DISTRESS TYPE JCP DISTRESS TYPE ACP DISTRESS TYPE
Spalled Cracks
Punch outs
Asphalt Patches
Concrete Patches
Average Cracking
Spacing
Failed Joints and
Transverse Cracks
Failures
Shattered Slabs
Slabs with Longitudinal
cracks
Concrete Patches
Apparent Joint Spacing
Shallow (6-12 mm) rutting
Deep (13-25 mm) rutting
Patching
Failures
Block Cracking
Alligator Cracking
Longitudinal Cracking
Transverse Cracking
Raveling (Optional)
Flushing (Optional)
42
43
44
Fig. 3.1 Computer based pavement management system, modules and outcomes
Computer based Pavement
Management Program
Pavement performance
Database
Performance or deterioration
prediction module
Maintenance and
Rehabilitation Module
Life Cycle Cost Analysis Module
Pavement Management
Plans and Strategies
Performance predictions in
terms of deterioration/ remaining life
etc.
Evaluation of the available M&R options via life cycle cost analysis
Improved planning for construction
and maintenance of
future pavements
45
Fig. 3.2 Data flow diagram for a Pavement Management System (Smith, et al. 2001)
46
4 SENSITIVITY ANALYSIS USING Pavespec 3.0
4.1 Introduction
In the previous chapter, various available computer programs for performance
prediction and life cycle costing were examined. For the current research undertaking,
Pavespec 3.0 was selected as an appropriate application. Pavespec 3.0 incorporates
mechanistic-empirical prediction models for rigid pavements, forecasts the performance of a
pavement system in terms of the significant distresses, and includes a module that provides
an approximate estimate of the life cycle and present worth costs of a specified pavement
system. Before Pavespec 3.0 is applied to the Ohio Route 50 Project data to generate distress
predictions to be compared with actual performance, a sensitivity analysis will be conducted.
Computer models that predict the performance and costs of design features of
pavements usually rely on data and empirical methods. In some cases, this reliance could act
as a drawback. A program that is developed and tested using a finite set of data may not
work properly for a completely different data set. Consequently, the need arises to conduct a
detailed sensitivity analysis, which involves examining the outputs produced by Pavespec 3.0
for different sets of input values. The traditional method utilized in conducting such an
analysis is to change one variable at a time, run the program and record the output. Another
approach available is to account for the interdependencies of variables and select
combinations of input variables to create outputs. The latter becomes complex as the number
47
of input variables increases. For the current research, which has identified seventy-nine
inputs, the former method is employed.
The primary objectives of this analysis are to identify the most significant input
variables in the program and to evaluate the reliability of outputs generated. Such analysis
will help the user assess whether the program responds as expected to the more important or
critical input variables. Expert opinion and existing performance trends can help verify the
reliability of outputs. The following steps have been performed to accomplish this objective:
1. The input variables for program Pavespec 3.0 are identified and classified by the
modules present in the program. These modules are: dimension and lane configuration,
pavement design, design traffic, climate data, acceptance quality characteristics (AQC)
sampling and testing, AQC target values, maintenance and rehabilitation (M&R), cost data
and analysis, and simulation control. A total of seventy-nine input variables for Pavespec 3.0
are identified and tabulated in Table 4.1, in which details of the inputs and the values
assigned for further analysis are also presented.
2. The input variables identified are assigned three levels of values to generate outputs
for subsequent comparisons. The first set of “medium” values consists of input variables that
are generally close to the Ohio Route 50 Project data, and form the baseline for comparisons.
The second set of “low” values would most likely result in low distresses. Finally, the last
set of “high” values would most likely result in high values of pavement distresses. This
information is presented in detail in Table 4.1.
3. Over a hundred and fifty simulation runs of Pavespec 3.0 are performed using these
sets of input values. The service life of pavement system in all the cases has been assumed to
be twenty-five years. Pavement distresses that are predicted by Pavespec 3.0 include:
48
transverse slab cracking percentage, transverse joint spalling failure percentage, transverse
joint faulting and pavement smoothness. For the life cycle costing module, inputs such as
unit costs, inflation percentage, depreciation, user cost percentage, etc., provide the total life
cycle costs incurred and present worth of these costs for the pavement system.
At the end of this chapter, for each distress predicted by Pavespec 3.0, corresponding
input variables that are highly significant and moderately significant are determined. In
Table 4.2, the bold and italic font distress values represent the outputs that changed
considerably with varying input values. The inputs that correspond to bold font distress cells
in Table 4.2 can be termed as of high significance. Discussion presented in the following
section explains this further by examining the input variables in each input module.
4.2 Discussion of Sensitivity Analysis Observations
The sensitivity analysis results for all the identified inputs of Pavespec 3.0 are
summarized in Table 4.2. Subsequent paragraphs describe the effect of varying inputs on the
outputs generated. The results are categorized by module.
4.2.1 Pavement Design, Dimensions and Lane Configuration
For a given average daily traffic (ADT), the two- and four-lane undivided
configurations incurred much more user costs (vehicle operating, delay and accident costs,
etc.) as expected. The divided configurations showed only slight increase in costs as the
number of lanes increased. It has to be noted that Pavespec 3.0 considers the M&R and user
49
costs, but not the initial construction costs. As the lane width increases, the cost indices
change as expected, while the distresses remained the same all through. The pavement
shoulder type used influences both distresses and costs. A widened lane is the most
inexpensive and best performing of the three shoulder types considered in terms of distress
indices; asphalt and tied Portland cement concrete (PCC) shoulders showed somewhat higher
distresses. A lower value of stress load transfer efficiency (SLTE) showed a considerable
increase in the spalling percentage and in the overall costs. The inner lane cracking
percentage had no marked effect on any of the output values. The road location, viz., rural or
urban, changes the total cost values but not the distresses. The design life of the pavement,
as expected, does not alter the distresses or costs at a given point of time. An undoweled
jointed plain cement pavement (JPCP) results in more costs and increased distresses
especially spalling and international roughness index (IRI), when compared to a doweled
system. It appears that the optimum dowel diameter is 1.25 in., since smaller and larger
diameters are associated with increased distresses and costs. As expected, slabs of smaller
length result in lower distresses and higher costs, but joint spacing of 30 ft. only results in a
slight increase in the distresses compared to 20 ft. Mild variation in the PCC modulus of
elasticity does not affect the distresses or the costs to a great extent. The effect of water-
cement ratio was pronounced in terms of the resultant joint spalling. The preformed
compression sealant provided best performance with negligible spalling when compared to
asphalt or silicone sealant materials. Spalling for asphalt and silicone sealant materials was
observed to be the same.
When the subgrade modulus, k, was small, it resulted in more distresses viz., faulting
and transverse cracking. Negligible transverse slab cracking and joint faulting values were
50
observed when k approaches the elastic solid limit (k = 500 pci). Increased finer material in
the subgrade increased the IRI of the pavement. The base layer permeability did not
influence the distresses or life cycle costs. A thin base layer resulted in an increased
transverse slab cracking percentage. All the other distresses did not change much with the
thickness of the base layer. The modulus of elasticity of the base layer did not affect the
distresses or life cycle costs considerably. A bonded PCC base interface eliminated the
transverse slab cracking percentage and reduced the IRI, when compared to the unbonded
case. Smaller values of the base erodibility factor resulted in lower joint faulting, IRI values
and costs.
4.2.2 Traffic Factors
Variations in the ADT produced outputs as expected: an increase in the ADT values
resulted in higher distresses and related costs. An increase in the traffic growth rate or a
variation from simple to compound interest computation of traffic growth resulted in
increased distresses and life cycle costs. Traffic directional factor had a considerable effect
on the distresses and the costs of the pavement. An increase in the percentage directional
factor resulted in increased distresses and costs incurred. Also, percentage trucks in the outer
lane showed a marked effect on the transverse slab cracking percentage. Other distress
indices, such as joint faulting and IRI, and life cycle cost values showed only a slight
increase due to higher truck percentage in the traffic mix.
51
4.2.3 Climatic Factors
The average annual freezing index is found to influence the IRI values of the
pavement. A higher index resulted in higher IRI values. High annual precipitation caused
more joint faulting and increased the IRI values, thus resulting in more costs. The number of
freeze-thaw cycles considerably influences the spalling failure percentages of the PCC slabs,
consequently increasing the life cycle costs of the pavement system. Warmer climate
resulted in better performing pavements since an increase in the number of days over 90°F
resulted in decreased faulting and IRI values. Influence of climatic zone designation was
observed to be pronounced in terms of joint spalling percentages. Wet non-freeze climate
zone produced maximum spalling and IRI values, followed by the dry non-freeze, wet freeze
and dry freeze climate zones, respectively. Cost differences were also noticed between the
climatic zones due to the distresses that were observed.
4.2.4 Sampling Methods
The AQC used in Pavespec 3.0 for distress prediction, cost analysis and pay factor
calculations are: strength, PCC slab thickness, air content and IRI. Variations in sampling
methods and techniques for each of these AQC may change the predicted outputs. Strength
sampling options provided are beam, core and cylinder tests. Beam tests give the flexural
strength of PCC, whereas cores or cylinders give the compressive strength. There were
miniscule differences observed in the results predicted for these sampling methods.
Thickness sampling methods of cores, probes or ground penetration made no difference to
the obtained distress values. Air content sampling methods of the Danish Void Analyzer
(DVA), air pressure meter and cores had very little impact on the results. The profilograph
52
reduction using manual or computerized methods made negligible difference to the final IRI
value. Life cycle costs and distresses that were predicted by simulation from the initial seed
values provided were observed to be slightly higher than the ones predicted just by
considering the initially specified mean values for input parameters.
4.2.5 Acceptance Quality Characteristics
AQC are the parameters of the pavement system, which can be measured during and
after construction and can be used to develop pay factors for the contractors. These are the
concrete strength, slab thickness, air content, initial smoothness and consolidation around
dowels. The distresses and life cycle costs predicted need to be appropriately sensitive to
these values. Concrete strength influences the transverse slab cracking, spalling and IRI to a
considerable extent, with a decrease in strength resulting in increased distresses. Joint
faulting is not affected much by the concrete strength. The distress indices of transverse slab
cracking percentage, spalling percentage, and IRI are dependent on the slab thickness. A
thinner PCC slab vastly increases these distress measures, as expected. Joint faulting is
influenced by the slab thickness only to a small extent. Air content in concrete affects the
spalling percentage to a greater extent than it does transverse slab cracking, smoothness and
joint faulting. Spalling percentage increased when the air content in the sample drops to 3%.
Varying the initial pavement smoothness values did not affect the distress indices
considerably. Changing the percentage consolidation around dowels influenced only the
joint faulting values. Increase in the percentage consolidation around dowels resulted in
decreased joint faulting and hence decreased costs.
53
4.2.6 Maintenance and Rehabilitation Options
In this section, the M&R options for the pavement system are altered to examine the
influence of each on the distresses and the life cycle costs. Replacing the sealants of a higher
percentage of joints at shorter time intervals slightly decreased the spalling and increased the
costs as expected. Repair of cracked and spalled joints at regular intervals did not show
much of an effect on the costs, probably due to the fact that in the general case, spalling and
cracking failure predicted by the program was minimal. Joint faulting was limited to a value
after which failure was said to have occurred and repair was to be performed. This did not
affect the distresses produced and costs incurred. On a similar note, IRI limiting values
defining failure conditions were regulated. This measure did not result in changes in the
pavement costs.
The global rehabilitation options available were asphalt concrete overlays, PCC
overlays and diamond grinding process. There were small variations in the costs incurred for
each rehabilitation option. Also, as the expected life of rehabilitation treatment extended, an
expected decrease in the total life cycle costs of the pavement system was observed.
4.2.7 Costs and Interest Rates
Results show that increasing the unit cost of sealing per joint greatly affects the total
life cycle cost of the pavement system. As predicted, greater unit costs for slab replacement
and joint repair resulted in elevated life cycle costs. As the annual inflation rate increased,
decreases in the life cycle and the present worth costs of the pavement were observed. This
is appropriate as an increase in inflation leads to the multiplication of costs annually. As the
time of construction of the pavement system considered was assigned to be 1998 (the
54
construction date of the Ohio Route 50 pavement system), one should observe a decrease in
costs as inflation increases. The pavement system distresses, as expected, remain unchanged.
Annual interest rates influenced the pavement system life cycle costs noticeably as a small
increase triggered a jump in the calculated costs. The user cost percentages that need to be
included for life cycle cost calculations are found to be crucial. As these calculations are
based on M&R costs and the percentage user costs, increasing the user cost percentage
sharply increased the calculated life cycle costs. Pavespec 3.0 recommends performing 500
trial simulations (referred to as “lots” in Pavespec 3.0) so as to assess the impact of each
factor reliably, yet it is found that the number of lots influenced the output values only
slightly. Smaller number of lots resulted only in a small increase in the life cycle costs. It
has to be noted that increasing the number of simulations enhances the quality of pay factor
curves that Pavespec 3.0 develops for performance related specifications (PRS). The
analysis life of the pavement system necessarily influences the distresses that occur at the end
of service life and the costs that are incurred. Extending the analysis life of the pavement
resulted in increased distresses and higher costs at the end of the time period.
4.3 Summary of Major Findings from Sensitivity Analysis
By observation, the factors that are of high importance in relation to pavement
distress occurrence can be noted. Pavement type (doweled, undoweled), dowel bar diameter,
percentage consolidation around dowels and PCC slab thickness inputs seemed to influence
the pavement joint faulting to the greatest extent. To a moderate extent, the shoulder type,
55
modulus of subgrade reaction (k-value), base erodibility factor, ADT, percentage trucks,
directional factor, and the average annual precipitation influenced the joint faulting measure.
For the PCC slab transverse slab cracking, a similar analysis was conducted.
Variations in concrete strength, PCC slab thickness, climatic zone, traffic factors and truck
percentages, base thickness and PCC base interface, k-value of subgrade, transverse joint
spacing, and SLTE produced changes in the percentage slabs cracked to a considerable
extent. Shoulder type, elastic modulus of the base layer and number of samples per sublot,
impact the slab cracking values to a moderate extent.
In order to identify the factors that increase spalling percentage, a similar analysis is
performed by examining the extent of distresses produced from changes in the input
characteristics. The factors that prominently influence the spalling percentages are joint
sealant type, water cement ratio, number of freeze thaw cycles, number of samples obtained,
concrete strength, slab thickness and air content. A moderate effect was produced by
variations in the strength sampling methods and number of simulation trials. The impact of
other factors on spalling percentage is found to be insignificant.
For studying pavement smoothness, the criterion considered was IRI. Factors such as
pavement type, dowel bar diameter, average annual freezing index, number of freeze thaw
cycles, number of days above 90°F, concrete strength, slab thickness and air content were
found to be significant in influencing the IRI values. Moderately influential were the factors
shoulder type, SLTE, transverse joint spacing, joint sealant type, k value, and water cement
ratio, base erodibility factor, ADT, traffic growth rate used, directional factor, percentage
trucks, average annual precipitation, climatic zone, and number of samples per sublot.
56
In conclusion, it can be inferred from the above results that slab thickness, concrete
strength, air content, pavement type and dowel bar diameter, and climatic factors such as
freeze thaw cycles and days above 90°F are the most important factors controlling pavement
distress occurrence. Additionally, k value of the subgrade, traffic factors such as ADT,
percentage trucks, directional factor, and number of samples seemed to influence the distress
criteria considerably.
57
58
59
60
61
62
63
64
65
66
67
68
5 APPLICATION TO THE OHIO ROUTE 50 PROJECT
5.1 The Ohio Route 50 Project
The Ohio Route 50 Joint Sealant Project was conducted between 1997 and 2001 by a
team of researchers from the University of Cincinnati (Ioannides, et al., 2002). This project
involved construction of an experimental stretch of pavement in which different kinds of joint
sealants and sealant configurations were used and performance monitored. Unsealed control
sections were included for comparison purposes. The objectives of this project were to assess
the effectiveness of a variety of joint sealing practices and to examine their repercussions in
terms of construction time and life cycle costs. Additionally, the project assessed the effect of
joint sealing on pavement performance for the purpose of identifying the materials and
procedures that are cost effective. The experimental design for this project was developed by the
Federal Highway Administration (FHWA) and the Ohio Department of Transportation (ODOT).
5.1.1 Project Details
The test site is a 3.3 km (2.0 mi) section of a 10.5 km (6.5 mi) four lane divided highway
along a stretch of U.S. Route 50 in Athens County, Ohio. The highway has a twenty-year design
period with average daily traffic (ADT) of 7820 and 10950 vehicles in the years 1993 and 2013,
respectively. The two eastbound lanes were built in the first phase of construction, during 1997-
1998, and the westbound lanes during the second phase of construction in 1998-1999. The
69
pavement section consisted of a 250 mm (10 in.) plain, jointed, wire reinforced Portland cement
concrete (PCC) slab, placed over a 100 mm (4 in) crushed aggregate, free draining base layer.
The subbase layer is 150 mm (6 in) of crushed aggregate, resting over a predominantly silty clay
local subgrade. The highway consists of two 3.7 m (12 ft) wide lanes in each direction,
incorporating tied PCC shoulders of variable width. Transverse joints sealed with various kinds
of sealants were provided at 6.4 m (21 ft) spacing. Epoxy coated steel dowels of 1.5 in diameter
were installed. The site is located in the wet-freeze climatic zone, with mean annual
precipitation of 40 in., mean monthly average temperature of 53°F, high average monthly
temperature of 75°F and a low average monthly temperature of 32°F.
5.1.2 Experimental Plan
Ten different joint sealants were used in the test sections, in addition to the control
sections that were left unsealed. Of the ten sealed sections, four received silicone sealants, two
single component hot-applied materials, and three preformed compression seals. In this
experiment, joints were cut in six geometric configurations that were numbered 1 to 6.
Configurations 1, 3 and 5 received a secondary cut and a backer rod was placed in
Configurations 1, 3 and 4. Configurations 2 and 6 were used in unsealed test sections, and
Configurations 1, 3 and 4 were used for liquid sealants. Two of the four silicone sealants,
designated as Crafco 903-SL and Crafco 902, were manufactured by Crafco Inc. The other two,
designated as Dow 888 and Dow 890-SL, were manufactured by Dow Corning Corporation. The
two hot applied sealants were named Crafco Roadsaver 221 and Crafco Superseal 444/777. The
compression seals used were Delastic V-687, Techstar W-050, and Watson Bowman WB-687.
70
All sealants were placed in accordance to the manufacturers’ specific installation procedures.
The construction procedures were described in detail by Ioannides, et al., (1999). A performance
evaluation plan was formulated by the research team at the University of Cincinnati (Ioannides,
et al., 2000).
5.1.3 Performance Evaluation
The research team of the University of Cincinnati, conducted various investigations
during the project from 1997-2001, monitoring the joint sealant effectiveness and pavement
performance of the Ohio Route 50 pavement test sections. The pavement was divided into thirty
different test sections, typically 180 m (600 ft) in length, consisting of about twenty-nine
transverse joints per section.
The performance evaluation during the initial construction and sealant installation phases
involved two profilometer analyses and two visual inspections of the test sections. The ODOT
profilometer equipment produced results in terms of Mays number (MAYS), present
serviceability index (PSI), and average international roughness index (IRI). The first and second
profilometer runs on the newly constructed eastbound lanes were performed in June, 1998 and
May, 1999 respectively. Also, an initial profilometer run on the newly constructed westbound
lanes was performed in May, 1999. The first and second visual inspections for the eastbound
lanes were conducted in October, 1998 and May, 1999 respectively, and in May, 1999 for the
westbound lanes. Because of construction constraints imposed on the team during these early
inspections, the pavement and the joint sealant condition were examined from the shoulder,
71
which did not permit a quantitative evaluation. The initial analysis was mostly descriptive.
Visual estimates of sealant damage were recorded for three transverse joints in each test section.
Beginning from Fall, 1999, the team developed a methodology to acquire performance
data in a more consistent and organized fashion. A joint sealant evaluation form was developed
that included the joint sealant and configuration combination (or treatment) type, the number and
location of sampled joints, the beginning and ending stations, as well as measured distress and
failure lengths. Six transverse joints were selected randomly from each test section for continual
monitoring. Sealant failures and joint distresses were observed and recorded over 6ft of the joint
length. These included joint distress spalling, sealant failures such as adhesion loss, cohesion
loss, stone intrusion, surface extrusion, gaps and sunken seals. The length and position of each
distress was recorded. The lengths of each observed failure is summed to give the total distress
of that particular joint seal. Percentage overall effectiveness is determined by dividing this sum
by the total joint length. From these individual percentages, average effectiveness for each
section is determined. In addition to sealant defects, distresses pertaining to the PCC pavement
system as a whole such as corner breaks, and longitudinal or transverse cracking in the pavement
slab were recorded.
Subsequent evaluations were conducted for the eastbound and westbound lanes during
the Spring and Fall seasons of 2000 and 2001, which included joint sealant, profilometer and
pavement performance surveys. Examinations conducted during this period included inspections
of the under drain outlets, which may significantly affect the overall pavement performance.
Comprehensive analyses and comparisons of the observed joint sealant and pavement
system distresses were presented by Ioannides, et al. (1999) and Ioannides, et al (2000).
Included in these analyses, were sealant performance rankings, comparisons of sealant
72
effectiveness to the profile survey data, and summaries of pavement distress in each section.
Furthermore, a mechanistic-empirical analysis was conducted to observe the effects of design
features on pavement performance. Features employed at the Ohio Route 50 project site and the
distresses observed were interpreted using mechanistic-empirical analysis.
5.1.4 Conclusions from the Ohio Route 50 Project
Observations of the sealant condition, pavement condition, smoothness and distresses
resulted in important conclusions and recommendations, especially in the areas of sealant
performance, its dependence on the type of material, placement technique and specifications of
the joint and the effect of sealing on overall pavement distresses.
The report for the initial phase of the project that involved construction, application of
sealant material to joints and performance inspections documented considerable deterioration of
silicone and hot pour sealants in the eastbound lanes, and recommended that the joint cleaning
and sealant placement methodologies needed to be revised. It was noted in the report that
manufacturer’s recommendations of sand blasting the joint were never adopted. It was also
recorded that the construction procedures employed for the pavement system were tightly
controlled, following pertinent specifications. By this time, a majority of the hot pour and
silicone sealants had experienced significant failure.
During subsequent performance evaluations, it was observed that compression seals, with
the exception of Techstar, outperformed the liquid sealants. The condition of sealants in the
westbound lanes was better than that of the sealants in the eastbound lanes due to the younger
age. Hot pour sealants were found to show the worst performance of the three types of sealants.
73
On the basis of visible distresses, unsealed sections were still performing better than most of the
sealed sections during this phase. At that point of investigation, transverse slab cracking
occurred in ten of the fifteen test sections and corner breaks in seven sections in the westbound
lanes. It was found that no correlation existed between sealant effectiveness and pavement
distresses such as transverse cracking, corner breaks, and surface roughness. It was noted from
the trends that pavement surface profile was dependent on the climatic factors that initiate
curling and warping of the slabs. Similar trends in spalling were not observed for the eastbound
and westbound lanes.
A significant feature of this project was the mechanistic analysis conducted to examine a
number of pavement features associated with sound pavement design. The primary focus was on
the effects of subgrade support, load transfer, transverse joint spacing and tied PCC shoulders.
The influence of such features on the Ohio Route 50 pavement site was determined by a series of
mechanistic computations using pavement engineering software. Weakening of the soil
subgrade support led to increased bending stresses and deflections in the slab. In a separate
investigation, effects of strength losses in the base and subbase layers on the bending stresses
were found to be insignificant. Load transfer elements such as shoulder ties and dowels helped
reduce the bending stress and deflections, thus increasing the pavement life and capacity. The
factor with the most pronounced effect on pavement performance was found to be transverse
joint spacing. Based on mechanistic considerations, it was proved that the appropriate spacing
for the Ohio Route 50 pavement system was 4.6m (15 ft), significantly shorter than the actual
joint spacing of 6.1m (21 ft). “This unfortunate discrepancy may lead to premature pavement
distress in the form of transverse cracking throughout the concrete slab,” stated Ioannides, et al
(2000).
74
The Ohio Route 50 joint sealant experiment is important inasmuch as it addresses the
significance of site specific factors, and the substantial role they play influencing the sealant and
pavement system performance. Sealant placement, configuration, joint cleaning procedures, and
climate conditions seemed to affect the sealant performance. A correlation between pavement
performance and sealant effectiveness was not established during this research.
5.2 Distress Prediction for the Ohio Route 50 Project
In the previous chapter, a sensitivity analysis was performed for Pavespec 3.0. From the
results obtained, it can be safely concluded that performance of the program conforms to
expectations. In this section, initial data from the Ohio Route 50 Project are input into the
program to simulate the distresses observed, and conduct a comparative analysis to investigate
the applicability of performance prediction.
Using the existing data, i.e., field reports and observations related to the Ohio Route 50
Project, values for all the necessary inputs for each module of Pavespec 3.0 were recognized.
These are presented in Table 5.1. Simulation runs using the software were performed to obtain
the distresses in each one of the sections which used a particular joint sealant material. This
provided the pavement system behavior over its expected life span in terms of spalling,
transverse slab cracking, joint faulting, and pavement smoothness (IRI) values. By giving
approximate unit costs of sealants, pavement repair, etc., to the program, the life cycle costs,
repair and rehabilitation costs for the pavement system over the specified period can be
calculated.
75
5.2.1 Analysis Using the Ohio Route 50 Project Data
A comparative analysis of the predicted and observed distresses was conducted for each
section of the pavement system that used a particular type of sealant material configuration.
Before the analysis results are discussed, the reader must become familiar with the basic
definitions, assumptions and study methods that were used.
Predicted Distresses
The simulation of pavement performance to calculate predicted distresses was
accomplished in the following steps. First, inputs for each module were extracted from the Ohio
Route 50 Project data, assumptions, and values used for mechanistic analysis. Second, a time
period of twenty years, the expected service life of this pavement system, was assigned for the
analysis. In all, fifteen sublots were simulated for each section, with the only input characteristic
varied for each section being the type of sealant used. The Ohio Route 50 joint sealants
experiment consisted of fifteen test sections in the eastbound and westbound lanes with each test
section using a specific sealant material configuration.
During the simulation, no maintenance and rehabilitation (M&R) options were input to
the software so as to accurately observe the distress trends. Annual distress predictions obtained
for the fifteen sections over the entire service life of the pavement system were averaged.
Observed Distresses
Observations from the Ohio Route 50 project provide data related to transverse slab
cracking, spalling, corner breaks, and IRI for each section of eastbound and westbound lanes.
These values were obtained from the periodic inspections conducted by the research team.
76
Calibrated Distresses
The Ohio Route 50 data was collected over a period of four years for a pavement system
with a service life of twenty years. In order to compare distresses for each section, using field
observations and predictions from Pavespec 3.0, data calibration becomes necessary. The
program has a built-in feature to use calibration coefficients that can reflect the future trend of
pavement distresses based on the obtained short term data. Using the observed distress and
predicted distress regression trends, calibration coefficients were obtained and calibrated
distresses were calculated for the entire service life of the pavement system. The following
section explains the assumptions and analysis methodology with detailed examples.
Analysis Methodology
For each section of the Ohio Route 50 pavement system with a different sealant material
configuration, observed, predicted and calibrated distresses were plotted on a time-distress
measure chart. The predicted and calibrated values were obtained from the averaged results of
Pavespec 3.0. The following are some important aspects of the prediction methodology.
(i) Curves for observed, predicted and calibrated data are obtained utilizing linear regression
capabilities of Microsoft Excel. The progression of distresses over time is assumed to be
linear in the form:
cmxy += (4.1)
where, y represents distress measure and x represents elapsed time.
Pavespec 3.0 allows the user to calibrate the predictions by defining the regression
coefficients A and B as follows:
BDistressredictedPADistressObserved += )( (4.2)
A and B can be most easily obtained by assuming that the distress curves are linear.
77
(ii) Boundary conditions for distresses are not imposed on any of the regression curves. This
resulted in distress curves with positive and negative intercepts, which can be explained
as follows. A positive intercept, in the case of transverse slab cracking or spalling curves
mean that distresses appeared immediately after the road section was opened to traffic. A
negative intercept means that for a period of time the pavement section distress values
were zero.
(iii) As predicted, observed and calibrated curves were obtained from linear regression
analysis, the coefficient of correlation (R2) becomes significant. In order to be
considered for analysis, the curves obtained should have R2 values greater than 0.5. In
several instances, the R2 values of observed trends are less than 0.5 and data filtering
becomes necessary to eliminate inconsistencies. For such cases, the best-fit linear
regression equation obtained is used to calculate the percentage deviation of each distress
from the distress curve values. This is computed using the following relation:
EquationfromDistressCalculatedDistressActualEquationfromDistressCalculatedDeviationPercentage /100)( ×−=
(4.3)
If, ,10≥DeviationPercentage the data point is eliminated from the next iteration
(iv) The data filtering was performed to a maximum number of two iterations to obtain
curves with R2 values greater than 0.5. In a few instances, if the iterations do not result in
this, further filtration was not performed and the curves were presented as existed.
Additionally, there were some cases in which
78
,10<DeviationPercentageMaximum and the data point with the highest
DeviationPercentage , was eliminated to produce the next iteration of the trend. A
maximum of two iterations were performed for data filtering for a distress measure.
(v) The transverse slab cracking model in Pavespec 3.0 does not provide accurate results
when calibration coefficients were assigned. As the results produced were inaccurate, it
was decided to eliminate the process of calibration for transverse slab cracking
altogether. The results presented only include the predicted and observed slab cracking
data and trends.
Analysis Example
The above concepts can be better illustrated with an example. The IRI comparisons of
Eastbound section Delastic V687 are examined below. If the observed IRI data is used, the
regression equation obtained is
758.631046.0 += xy , R2 = 0.1338 (4.4)
where, )(, MonthsTimeElapsedxIRIObservedy == .
This equation is used as the base to calculate the IRI values at the specific Elapsed Time
points, where the observations were made by the research team. The following formula is
used to compute the percentage deviation of actual data from the regression trend:
EquationfromDistressCalculatedDistressActualEquationfromDistressCalculatedDeviationPercentage /100)( ×−=
If, ,10≥DeviationPercentage the data point is eliminated from the next regression. The
details of this iteration are presented in Table 5.5. In the current example, this analysis
results in an IRI trend equation:
79
892.611323.0 += xy , R2 = 0.7133. (4.5)
As the R2 value is greater than 0.5, this equation can be used for further analysis.
For the same example, Delastic V-687, the calibration methodology may be explained as
follows: The linear regression equation obtained for the predicted distress trend is
747.610153.0 += xy (4.6)
and the observed trend is
892.611323.0 += xy (4.7)
Using the equation available from Pavespec 3.0,
BDistressedictedADistressObserved += )Pr(
The predicted and observed equations may be equated as:
)892.611323.0( +x =A ( 747.610153.0 +x ) + B (4.8)
Equating the coefficients of x and constants, one obtains A and B as 8.65 and -472.21
respectively. These values are then used to obtain the calibrated distress values from
Pavespec 3.0.
5.2.2 Sections with Compression Sealants – Eastbound
Compression sealants Techstar W-050, Delastic V-687, and Watson Bowman WB-687
were used in the eastbound lanes of the Ohio Route 50 project. According to the results from the
Ohio Route 50 experiment, the sealants Delastic V-687 and Watson Bowman 687 are performing
very well with an average effectiveness value of 94%, whereas the Techstar W-050 sealant was
19% at the last evaluation in Fall, 2001.
80
Pavespec 3.0 simulated the pavement and sealant related distresses of the sections. A
compression sealing option was used and the initial IRI values that were observed for each
section in the field were provided to the program. Distress curves were computed for a period of
20 years from the program. Calibrated curves were generated from the results of Pavespec 3.0
and using the methodology explained in the previous section. The plots are shown in Fig. 5.1,
5.2 and 5.3. It is important to note that the curves obtained using linear regression for the
observed data are not accurate. This is due to various reasons, some of them being data
inconsistency, insufficient field data to incorporate statistically sound regression curves, and the
assumption that the curves are linear. The predicted curves were observed to be conforming well
to linear regression methods, by producing high R2 values. The predicted, observed and
calibrated curves are compared for conclusions about pavement performance and sealant
effectiveness.
Pavement and Sealant Distresses
The distresses compared included pavement roughness in terms of IRI, spalling
percentage and transverse slab cracking percentage. The spalling percentage is the ratio of
spalled length to the total joint length; transverse slab cracking percentage is quantified using the
ratio of cracked slabs to the total number of slabs.
For sections with compression sealants, Pavespec 3.0 predicted negligible spalling during
the twenty year service life. Significant spalling was actually observed in the sections with
Delastic and Watson Bowman seals, and this is reflected in the calibrated trends. Techstar in the
eastbound lanes did not show any spalling, even though its average effectiveness was rated very
low. The predicted variation of IRI values with time exhibited a lower slope than the
corresponding calibrated trend. The slopes of calibrated curves were two to four times that of
81
predicted, indicating that deterioration was more rapid in the field. Data and related trend lines
indicate that the rate of transverse slab cracking in the field is much higher than predicted,
possibly due to the higher Slab Length/Radius of Relative Stiffness (L/l) ratio. The slopes of
observed transverse cracking curves in all three sections were similar.
5.2.3 Sections with Silicone Sealants – Eastbound
Silicone sealants that were used in the eastbound lanes of the Ohio Route 50 test section
are Crafco 903-SL, Crafco 902, Dow 890-SL and Dow 888. The results from Ohio Route 50
tests show that these sealants are performing well, and the slabs show little or no spalling.
Pavespec 3.0 simulated the values of IRI, spalling, transverse slab cracking and joint
faulting. The curves are shown in Figures 5.4, 5.5 and 5.6. Pavement performance related
distresses, IRI and transverse slab cracking observed in the field are several times higher than
predicted. Calibrated curves for IRI values were similar to the curves in the compression sealant
sections. Slopes of observed transverse slab cracking curves are similar to the compression
sealant sections.
Pavement sealant related distress spalling was also compared for the silicone sealant
sections. For spalling, an option of silicone sealants was used in the simulation program. The
curves show that sections with silicone sealants are performing comparably, and in a few cases,
better than the predicted.
82
5.2.4 Sections with Hot Pour Sealants – Eastbound
Hot Pour sealants that were applied to the eastbound sections of the Ohio Route 50
project are Crafco 221 and Crafco 444. Field data from the Ohio Route 50 pavement system
showed that the sealants and pavement distresses are similar to those observed in the other
sections. The sealant performance has been observed to be unsatisfactory for Crafco 444.
Crafco 221 in contrast has performed well and limited distresses were observed. Curves for the
hot pour sealant section distresses are shown in Figures 5.7, 5.8 and 5.9.
For the hot pour sealed sections in the eastbound lanes, the IRI values observed were
higher than the predictions from Pavespec 3.0, as was the case in all the other sections. Spalling
failure observed in the sections was higher than that predicted, indicating the role of faster
deteriorating sealant material. Transverse cracking occurred at a very similar rate as in the other
sections.
5.2.5 Sections with No Sealants – Eastbound
Two configurations of no sealants were applied in the eastbound lanes of the project.
Field data showed that the sections with no sealants were performing well and in some cases
better than the sealed sections in terms of joint related distress (spalling).
Figures 5.10, 5.11 and 5.12 show plots that illustrate the distress trends. The pavement
related distress measures such as IRI and transverse slab cracking were found to be in the same
range as those of other sealant types, viz., compression, silicone and hot pour. The IRI trend line
for the calibrated curves is about ten times steeper than that of predicted reiterating that the
deterioration of pavements is rapid in the field. The calibrated spalling trend was close to
83
predicted for the two configurations indicating a more accurate prediction from Pavespec 3.0 in
these cases.
5.2.6 Sections with Compression Sealants – Westbound
In the westbound lanes, Delastic V-687 and Techstar W-050, Watson Bowman WB-812
sealant configurations were used. Comparative trends of the distresses are shown in Figures
5.13, 5.14 and 5.15. Results from the field data indicate that compression sealants performed
very well, as did their eastbound counterparts. With the exception of Techstar W-050, which
performed poorly in both eastbound and westbound lanes, compression sealants were ranked as
the best of all sealants used in the Ohio Route 50 project.
As the input parameters are the same for westbound and eastbound lanes for the
performance prediction, distresses predicted were similar. Conclusions from the Ohio Route 50
project indicate that westbound lanes performed better in all aspects when compared to their
eastbound counterparts, mainly due to their younger age and improved construction and sealant
installation techniques.
IRI predictions for the westbound sections and comparisons to the calibrated curves
indicate a similar increased deterioration as was noted in the eastbound lanes. Transverse slab
cracking curves for the compression sealants were observed to be much greater in slope than the
eastbound counterparts. For the sealant related distresses, spalling predictions were almost
negligible when the compression sealants option was specified in Pavespec 3.0. The spalling
trend lines for the observed data also indicated a negligible slope signifying a good performance
of the sealants by far.
84
5.2.7 Sections with Silicone Sealants – Westbound
In westbound lanes, silicone sealants Crafco 903-SL, Dow 888, and Dow 890-SL were
used. These are performing much better than their eastbound counterparts. Average
effectiveness of sealants in the eastbound lanes was reported as 46%, whereas in the westbound
lanes it was 85%. Performance curves of predicted, observed and calibrated data are shown in
Figures 5.16, 5.17, 5.18.
Pavement surface roughness showed a downward trend for Crafco 903 SL configurations,
indicating that the pavement sections became smoother with age. Climatic factors such as
curling and warping were considered to be responsible for such behavior in the field. This was
not reflected in the results from the distress prediction model. Pavespec 3.0 predictions followed
similar trends for all the sealant configurations, and each of them showed an increase in IRI with
age. Transverse slab cracking slopes observed over time were much higher than predicted, as
was the case with all other sections of the Ohio Route 50 pavement system.
5.2.8 Sections with Hot Pour Sealants – Westbound
The sealant material configurations Crafco 221 and Crafco 444 that were applied in
eastbound lanes were used in the westbound lanes also. Crafco 444 performed much better than
Crafco 221 in the westbound lanes, maintaining an effectiveness of about 90%. This was in
contrast to the performance in the eastbound direction, where Crafco 444 was ineffective. The
distress trend comparison for these sections is shown in Figures 5.19, 5.20, 5.21.
The calibrated IRI curves for both sealant configurations were close to the predicted.
Transverse slab cracking observed in hot pour sealant sections was found to be much higher than
85
in their eastbound counterparts. In general, all sections in the westbound lanes had transverse
slab cracking levels higher than the corresponding eastbound sections. Spalling observed in
these sections was minimal when compared to the predictions from Pavespec 3.0.
5.2.9 Sections with No Sealant – Westbound
Two configurations of unsealed sections were applied in the westbound lanes. These
were control sections that were not sealed to monitor the differences between sealed and
unsealed joints. They performed well in both the east and westbound lanes. Predicted and
observed trend comparisons for the westbound sections are shown in Figures 5.22, 5.23, and
5.24.
The slope of the pavement smoothness indicator IRI for the no sealant sections was many
times higher than the predicted one, reaffirming the trend that was observed in almost all the
sections of eastbound and westbound lanes. Transverse slab cracking for the no sealant sections
was higher than the predicted values from Pavespec 3.0. Spalling percentages in the unsealed
sections of westbound lanes did not show a consistent trend.
5.2.10 Summary of Observations
From the results of the comparative analysis of predicted and calibrated distress trends,
the following observations can be reported:
1. Comparisons for the eastbound sections were statistically more significant than their
westbound counterparts. In general, the R2 values for observed trend lines were highest for the
eastbound IRI. The better results from linear regression analysis can be attributed to the higher
86
number of data points collected over a longer period of time. A total of 7 data points were
available, collected over a period of 40 months. Additionally, the eastbound lanes presented
distress trends with better R2 values, probably due to the same reason. Calibrating the
predictions using the observed values was more effective in the eastbound lanes than in the
westbound lanes due to better coefficients of correlation.
2. In a majority of cases, the calibrated IRI and spalling and transverse slab cracking values
were many times higher than the predicted. This could imply that (a) the pavement is
deteriorating faster, provided, one assumes that the predictions are accurate and reflect the way
such a pavement system should behave in the field, or (b) the prediction model provides
conservative estimates of distresses. It should be noted that the capabilities and accuracy of this
performance prediction program cannot be evaluated by one case study alone.
3. The observed transverse slab cracking curves presented similar slopes for all the sections
in the eastbound lanes. The westbound lanes exhibited this phenomenon, but the slopes of
curves were slightly higher.
5.3 Life Cycle Cost Analysis to Determine the Cost Effectiveness of Sealants
Research showed that life cycle costing is the most efficient way to examine the cost
effectiveness and benefits obtained from applying various features to the pavement system.
Sealant type, effectiveness levels, cost information and time intervals for replacement and repair
can all be incorporated in Pavespec 3.0 using the various input modules. Pavespec 3.0
simulations determine the sealant related distress of joint spalling and the corresponding
87
maintenance costs. By introducing in Pavesec 3.0 the above mentioned aspects of sealants used
in the Ohio Route 50 project, the approximate costs incurred in using a specific type of sealant
configuration were calculated. As the program provides rehabilitation options, an appropriate
plan was chosen for all sections. A final comparison of costs and frequency of repair necessary
will yield the most effective sealant configuration for the pavement system. These numbers are
just estimates, and the costs obtained may not be close to the real values. The significance of the
exercise lies in the fact that performance predictive algorithms are used and various available
rehabilitation options can be tested. Sealant replacement intervals have been chosen to be 3
years, or 6 years based on the observed sealant material performance. This will give us the
changes in the life cycle costs for each alternative methodology employed, provided the general
M&R plan remains unchanged.
Application of life cycle cost analysis (LCCA) to evaluate the cost effectiveness of
concrete pavement design features was discussed in detail by Cole (1998), using some available
models and the most common design features for concrete pavements. On similar lines, in this
study, joint sealing is considered as a pavement design feature, to compare the performance and
costs incurred. Ten different sealant materials were used in the Ohio Route 50 project. The
sealant material unit cost and cost per joint were reported by Ioannides, et al (1999). Using the
data from the Ohio Route 50 project, information from the literature pertinent to the Ohio
Department of Transportation (ODOT) pavement management system (PMS), and the available
options in Pavespec 3.0 for M&R, a rehabilitation plan for the Ohio Route 50 pavement to serve
as an input to Pavespec 3.0 is proposed.
88
5.3.1 Proposed M&R Steps and Costs
The steps involved in the proposed M&R plan are based on the available options in the
program and have been formulated to take into consideration, as much as possible, the
procedures followed by ODOT for M&R of PCC pavements. Rehabilitation steps are assumed
and applied in Pavespec 3.0 simulations for the Ohio Route 50 pavement section using the
methods and recommendations for life cycle cost analysis presented in ‘Pavement Preventive
Maintenance Program Guidelines’ (ODOT, 1999).
- 100% sealing of transverse joint sealants every 3 or 6 years (depending on sealant
material performance)
- 50% sealing of longitudinal joints every 5 years.
- 100% sealing of transverse cracks every 5 years.
- For the local rehabilitation plan, it is proposed that if the lot average percentage of
cracked slabs exceeds 50 %, then partial slab replacements be applied to 50 % of the
cracked slabs.
- If lot average percentage spalled joints exceeds 10 %, partial depth repairs are proposed
to 50% of spalled joints.
- If lot average IRI exceeds 99 in. /mi, then the global rehabilitation procedure is initiated.
- If the average transverse joint faulting exceeds 0.5 in., global rehabilitation procedure is
initiated.
- Global rehabilitation procedure prescribed as per the pavement type and ODOT
specifications is that of a PCC overlay that has an assumed service life of ten years, per
ODOT Rehabilitation Specifications (ODOT, 1999).
89
The proposed M&R plan is input in Pavespec 3.0’s maintenance module. The associated
cost of each step is provided. It has to be noted that only sealant material unit cost quotes are
accurate. The remaining quotes are obtained from M&R manual (ODOT, 1999), or the default
values available in Pavespec 3.0. The unit costs used as inputs for the proposed M&R plan are
provided in Table 5.1. It also shows the annual inflation rate and annual interest rate percentages
necessary to calculate the present worth costs, and the user cost percentage that needs to be
included for the LCCA.
5.3.2 Cost Effectiveness of Sealant Material Using LCCA – Applied Methodology
When examining the benefits of a design feature, increased life cycle costs should result
in increased overall pavement performance. The method suggested by Cole, (1998) is applied
herein to evaluate the cost effectiveness of the various joint sealant materials that were used in
the Ohio Route 50 project.
Based on the performance of each type of sealant material during the period of
observation of the project, a replacement time interval of 3 or 6 years is specified. The
recommendations formulated in the Ohio Route 50 project report (Ioannides, et al., 2002)
indicate that sealants whose performance is rated below 50% should be replaced.
The M&R plan presented in the previous section is applied for all the sealant materials
used in the eastbound and westbound lanes. Using the inputs specified in Table 5.1, Pavespec
3.0 calculates a life cycle cost summary for the lot, which includes a total rehabilitation life cycle
cost and the total rehabilitation present-worth life cycle cost. Comparing these values for all the
sealant materials that were used in the Ohio Route 50 project, the most effective joint sealing
90
material is selected. The costs resulting from such analyses can provide an approximate idea
only for comparison purposes.
5.3.3 Results from the Analysis
Results from the cost analyses of Pavespec 3.0 for all the sealant materials used in the
westbound and eastbound lanes of the Ohio Route 50 project are presented in Table 5.3 and
Table 5.4. These Tables show information related to the sealant material, frequency and
percentage of replacement that are calculated, as well as the total rehabilitation life cycle cost
and the total present-worth life cycle cost.
It can be inferred from the rehabilitation life cycle costs that the compression sealants,
with the exception of Techstar W-050, were the most effective in both eastbound and westbound
lanes. Techstar, with its high costs and frequent replacement needs, cannot be recommended for
further use from a cost and performance point of view. Silicone sealant Crafco 902 that was
used only in the eastbound lanes follows Techstar W-050 in terms of high costs and poor
performance. All the other sealant materials result in approximately equal total rehabilitation life
cycle costs. All the hot pour sealant materials used resulted in similar costs, and needed frequent
replacements. The hot pour sealants are found to be inconsistent in performance and cost
effectiveness, as Crafco 221 and Crafco 444 are cost effective in the eastbound and westbound
lanes, respectively.
91
Table 5.1 Inputs for Pavespec 3.0 used to simulate Ohio Route 50 pavement performance
INPUT VARIABLE VALUE FROM OHIO ROUTE 50 DATA
Lane Configuration Four Divided
Lane Width 12 ft
Shoulder Type Tied PCC
Stress Load Transfer Efficiency (39.1%-60.9%) – 25.5% typical value
Project Length 2.0 miles, 10560 ft.
Design Life 20 years
Pavement Type Jointed, Doweled
Dowel Bar Diameter 1.5 in.
Transverse Joint Spacing 21 ft.
PCC Modulus of Elasticity 27.6 GPa or 4000,000 psi
Transverse Joint Sealant Type None, Silicone, Hot Pour, Compression
Modulus of Subgrade Reaction (k) 150 pci
Water Cement Ratio 0.438
Base Layer Permeability Permeable Base
Base Thickness 4 in. (6 in. subbase)
Base Modulus of Elasticity 345 MPa or 50,000 psi
Base Erodibility Factor 0 or 1
ADT for the First Year ADT Design Year- 7820, Year of Usage- 8244
Directional Distribution Factor 50%
Truck Percentage in the Outer Lane 90%
92
Table 5.1 (contd.) Inputs for Pavespec 3.0 used to simulate Ohio Route 50 pavement performance
INPUT VARIABLE VALUE FROM OHIO ROUTE 50 DATA
Growth Rate 4%, Simple
Average Annual Freezing Index (0-100) 100 Considered
Average Annual Precipitation 40 in.
Average Annual Number of Days Over 90 F 30
Climate Zone Wet Freeze Zone
Average Modulus of Rupture of Beams Cast Mean 789 psi, SD 87 psi
Slab Thickness 10 in.
Air Content 6 +2 % as per ODOT Specifications
93
Table 5.2 Sealant unit costs, M&R costs and other inputs
SEALANT MATERIAL COST
Dow 890-SL $12.27 per joint
Crafco 903-SL $9.20 per joint
Dow 888 $10.74 per joint
Crafco 902 9.97 per joint
Crafco 444 2.68 per joint
Crafco 221 0.64 per joint
Watson Bowman WB-812 $43.26 per joint
Watson Bowman WB-687 $30.24 per joint
Delastic V- 687 27.72 per joint
Techstar W-050 3636.30 per joint
M&R COST
Longitudinal Joint Sealing $1.00 per foot
Transverse Joint Sealing $1.00 per foot
Partial Slab Replacements $80.00 per sq. yard
Partial Depth Repairs of Transverse Joints $ 50.00 per joint foot
PCC Overlay $ 15.00 per sq. yard
Annual Inflation Rate Used 3%
Annual Interest Rate Used 6%
User Cost Percentage Included 5%
94
95
96
Table 5.5 Data Filtering (IRI) for Eastbound Section with Delastic V 687
MONTHS IRI(in./mi) IRI FROM TREND
LINE(in./mi)
PERCENTAGE DIFFERENCE
FINAL IRI (in./mi)
0 60.37 63.758 5.31 60.37
4
11 64.48 64.9086 0.66 64.48
17
18 73.21 65.6408 -11.53
21 65.55 65.9546 0.61 65.55
28 66.59 66.6868 0.14 66.59
31 65.92 67.0006 1.61 65.92
40 65.77 67.942 3.19 65.77
97
IRI Comparisons,Techstar W 050 EB
Observedy = 0.4033x + 58.644
R2 = 0.4719
Predictedy = 0.0211x + 56.034
R2 = 0.9069
Calibratedy = 0.4136x + 60.207
R2 = 0.9044
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
D) (
in/m
i)
Observed
Predicted
Calibrated
IRI Observed (Linear)
IRI Predicted (Linear)
IRI Calibrated (Linear)
IRI Comparisons, Delastic V 687 EB
Calibratedy = 0.1326x + 61.861
R2 = 0.913
Observedy = 0.1323x + 61.892
R2 = 0.7133
Predictedy = 0.0153x + 61.747
R2 = 0.9131
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Observed
Predicted
Calibrated
IRI Calibrated(Linear)
IRI Predicted(Linear)
Fig. 5.1 Compression sealants Eastbound IRI comparison plots
98
IRI Comparisons, Watson Bowman EB
Predictedy = 0.0153x + 61.62
R2 = 0.9167
Observedy = 0.252x + 63.278
R2 = 0.6437
Calibratedy = 0.253x + 63.254
R2 = 0.9167
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
D) (
in/m
i)
Predicted
Observed
Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
Fig. 5.1 (Contd.) Compression sealants Eastbound IRI comparison plots
99
Transverse Slab Cracking Comparisons, Techstar W 050 EB
Observedy = 1.8333x - 20.033
R2 = 0.4808
Predictedy = 0.0017x - 0.0445
R2 = 0.9689
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted(Linear)
Transverse Slab Cracking Comparisons, Delastic V 687 EB
Observedy = 2.2487x - 44.441
R2 = 0.6905
Predictedy = 0.0003x - 0.004
R2 = 0.9761
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
labs
Cra
cked
(%)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Fig. 5.2 Compression sealants Eastbound transverse slab cracking comparison plots
100
Transverse Slab Cracking Comparisons, Watson Bowman EB
Observedy = 1.3821x - 5.8744
R2 = 0.9423
Predictedy = 0.0005x - 0.0131
R2 = 0.9694
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Trasverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Fig. 5.2 (Contd.) Compression sealants Eastbound transverse slab cracking comparison plots
101
Spalling Comparisons, Techstar W 050 EB
Observedy = 0
R2 = #N/A
Predictedy = 6E-06x - 0.0003
R2 = 0.6682
0
1
2
3
4
5
6
7
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)Spalling Predicted(Linear)
Spalling Comparisons, Delastic V 687 EB
Predictedy = 5E-05x - 0.003
R2 = 0.6682
Observedy = 0.0141x + 0.4206
R2 = 0.6482
Calibratedy = 0.0198x + 0.7505
R2 = 0.8786
0
1
2
3
4
5
6
7
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spa
lling
(%)
Observed
Predicted
Calibrated
Spalling Predicted(Linear)Spalling Observed(Linear)Spalling Calibrated(Linear)
Fig. 5.3 Compression sealants Eastbound spalling comparison plots
102
Spalling Comparisons, Watson Bowman EB
Observedy = 0.0096x - 0.1793
R2 = 0.6259
Predictedy = 4E-05x - 0.0012
R2 = 0.9137
Calibratedy = 0.0109x - 0.179
R2 = 0.8988
0
1
2
3
4
5
6
7
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Calibrated
Spalling Observed (Linear)
Spalling Predicted (Linear)
Spalling Calibrated (Linear)
Fig. 5.3(Contd.) Compression sealants Eastbound spalling comparison plots
103
IRI Comparisons, Crafco 903 SL EB
Predictedy = 0.0498x + 61.228
R2 = 0.9746
Observedy = 0.2878x + 59.427
R2 = 0.8188
Calibratedy = 0.2868x + 59.503
R2 = 0.9755
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Predicted
Observed
Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
IRI Comparisons ,Crafco 902 SL EB
Predictedy = 0.0313x + 65.575
R2 = 0.9763
Observedy = 0.0746x + 68.773
R2 = 0.0721
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Observed
Predicted
IRI Predicted (Linear)
IRI Observed (Linear)
Fig. 5.4 Silicone sealants Eastbound IRI comparison plots
104
IRI Comparisions, Dow 890 SL EB
Predictedy = 0.0234x + 62.145
R2 = 0.9184
Observedy = 0.3184x + 51.46
R2 = 0.6936
Calibratedy = 0.2988x + 49.972
R2 = 0.9131
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Time Elapsed (Months)
IRI (
in/m
i)
Predicted
Observed
Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
IRI Comparisons, Dow 888 SL EB
Predictedy = 0.0308x + 60.025
R2 = 0.9771
Observedy = 0.0796x + 60.118
R2 = 0.5384
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI
(in/m
i)
Predicted
Observed
IRI Predicted (Linear)
IRI Observed (Linear)
Fig. 5.4(Contd.) Silicone sealants Eastbound IRI comparison plots
105
Transverse Slab Cracking Comparisons, Crafco 903 SL EB
Observedy = 0.4615x - 3.3308
R2 = 0.4808
Predictedy = 0.0004xR2 = 0.9328
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Transverse Slab Cracking Comparisons, Crafco 902 SL EB
Observedy = 0.1872x + 34.29
R2 = 0.0168
Predictedy = 0.0005x - 0.0138
R2 = 0.9696
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Tranverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Fig. 5.5 Silicone sealants Eastbound transverse slab cracking comparison plots
106
Transverse Slab Cracking Comparisions, Dow 890 SL EB
Observedy = 0.4346x + 0.2577
R2 = 0.1196
Predictedy = 0.0002x - 0.0051
R2 = 0.9258
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Transverse Slab Cracking Comparisons, Dow 888 SL EB
Observedy = 0.9628x + 25.36
R2 = 0.596
Predictedy = 0.0006x - 0.0169
R2 = 0.9705
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Fig. 5.5(Contd.) Silicone sealants Eastbound transverse slab cracking comparison plots
107
Spalling Comparisons, Crafco 903 SL EB
Predictedy = 0.0767x - 1.164
R2 = 0.9371
Observedy = 0.0447x - 0.6646
R2 = 0.6534
Calibratedy = 0.0447x - 0.0674
R2 = 0.9372
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Calibrated
Spalling Predicted(Linear)
Spalling Observed(Linear)Spalling Calibrated(Linear)
Spalling Comparisons, Crafco 902 SL EB
Observedy = 0
R2 = #N/A
Predictedy = 0.0348x - 0.5844
R2 = 0.9306
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)
Spalling Predicted(Linear)
Fig. 5.6 Silicone sealants Eastbound spalling comparison plots
108
Spalling Comparisons, Dow 890 SL EB
Observedy = 0.0275x - 0.5418
R2 = 0.4949
Predictedy = 0.0096x + 0.3738
R2 = 0.9632
Calibratedy = 0.0274x - 0.5411
R2 = 0.9631
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Calibrated
Spalling Observed(Linear)
Spalling Predicted(Linear)
Spalling Calibrated(Linear)
Spalling Comparisons, Dow 888 SL EB
Predictedy = 0.0022x + 0.0106
R2 = 0.0198
Observedy = 0.0327x - 0.4548
R2 = 0.9385
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)
Spalling Predicted(Linear)
Fig. 5.6(Contd.) Silicone sealants Eastbound spalling comparison plots
109
IRI Comparisons, Crafco 221 EB
Predictedy = 0.0443x + 71.4
R2 = 0.9379
Observedy = 0.6407x + 71.4
R2 = 0.2923
Calibratedy = 0.6408x + 71.35
R2 = 0.9372
0102030405060708090
100110120130140150160170180190200210220230
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI
(in/m
i)
Observed
Predicted
Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
IRI Comparisons, Crafco 444 EB
Observedy = 0.2033x + 64.257
R2 = 0.1553
Predictedy = 0.0317x + 61.229
R2 = 0.9782
Calibratedy = 0.2032x + 64.262
R2 = 0.9781
0102030405060708090
100110120130140150160170180190200210220230
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI
(in/m
i)
Observed
Predicted
Calibrated
IRI Observed (Linear)
IRI Predicted (Linear)
IRI Calibrated (Linear)
Fig. 5.7 Hot pour sealants Eastbound IRI comparison plots
110
Transverse Cracking Comparisons, Crafco 221 EB
Predictedy = 0.0008xR2 = 0.9246
Observedy = 0.5538x + 17.423
R2 = 0.9231
0
10
20
30
40
50
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingPredicted (Linear)
Transverse CrackingObserved (Linear)
Transverse Slab Cracks Comparisons, Crafco 444 EB
Predictedy = 0
R2 = #N/A
Observedy = 0.3821x - 0.1744
R2 = 0.7249
0
10
20
30
40
50
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time(Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingPredicted (Linear)
Transverse CrackingObserved (Linear)
Fig. 5.8 Hot pour sealants Eastbound transverse slab cracking comparison plots
111
Spalling Comparisons, Crafco 221 EB
Predictedy = 0.0465x - 0.858
R2 = 0.9248
Observedy = 0.1233x + 5.3437
R2 = 1
Calibratedy = 0.1232x + 5.3424
R2 = 0.9248
0
5
10
15
20
25
30
35
40
45
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Calibrated
Spalling Predicted(Linear)
Spalling Obseved (Linear)
Spalling Calibrated(Linear)
Spalling Comparison, Crafco 444 EB
Observedy = 0.0923x - 2.0293
R2 = 1
Calibratedy = 0.0922x - 2.0286
R2 = 0.9497
Predictedy = 0.0369x - 0.3482
R2 = 0.9497
0
5
10
15
20
25
30
35
40
45
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
ObservedPredicted CalibratedSpalling Observed (Linear)Spalling Calibrated (Linear)Spalling Predicted (Linear)
Fig. 5.9 Hot pour sealants Eastbound spalling comparison plots
112
IRI Comparisons, No Sealant A EB
Predictedy = 0.0424x + 58.681
R2 = 0.9817
Observedy = 0.2905x + 57.79
R2 = 0.8602
Calibratedy = 0.2909x + 57.751
R2 = 0.9818
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
IRI Predicted
IRI Observed
IRI Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
IRI Comparisons, No Sealant B EB
Predictedy = 0.0324x + 48.47
R2 = 0.9769
Observedy = 0.2162x + 54.719
R2 = 0.8623
Calibratedy = 0.2164x + 54.704
R2 = 0.9768
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI
(in/m
i)
PredictedObservedCalibratedIRI Predicted (Linear)IRI Observed (Linear)IRI Calibrated (Linear)
Fig. 5.10 No sealants Eastbound IRI comparison plots
113
Transverse Slab Cracking Comparisons, No Sealant A, EB
Observedy = 1.1923x + 21.154
R2 = 0.4808
Predictedy = 0.0005x - 0.0126
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Transverse Slab Cracking Comparisons, No Sealant B EB
Observedy = 1.6026x - 7.6179
R2 = 0.4808
Predictedy = 0.0003x - 0.0095
R2 = 0.9721
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Fig. 5.11 No sealants Eastbound transverse slab cracking comparison plots
114
Spalling Comparisons, No Sealant A EB
Observedy = 0.0287x - 0.2165
R2 = 0.5836
Predictedy = 0.0588x - 0.19
R2 = 0.9648
Calibratedy = 0.0287x - 0.2155
R2 = 0.9648
0
5
10
15
20
25
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Calibrated
Spalling Observed (Linear)
Spalling Predicted (Linear)
Spalling Calibrated (Linear)
Spalling Comparisons No Sealant B EB
Predictedy = 0.0364x - 0.5235
R2 = 0.9336
Calibratedy = 0.0775x - 1.275
R2 = 0.9392
Observedy = 0.0783x - 1.3366
R2 = 0.9986
0
5
10
15
20
25
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Predicted
Observed
Calibrated
Spalling Predicted(Linear)Spalling Calibrated(Linear)Linear (Observed)
Fig. 5.12 No sealants Eastbound spalling comparison plots
115
IRI Comparisons, Delastic V 687 WB
Observedy = 0.3919x + 59.305
R2 = 0.6257
Predictedy = 0.0162x + 59.215
R2 = 0.9137
Calibratedy = 0.3903x + 59.29
R2 = 0.9134
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI
(in/m
i)
Observed
Predicted
Calibrated
IRI Observed (Linear)
IRI Predicted (Linear)
IRI Calibrated (Linear)
IRI Comparisons, Techstar W 050 WB
Observedy = 0.2746x + 63.633
R2 = 0.9815
Predictedy = 0.0162x + 64.615
R2 = 0.9137
Calibratedy = 0.2735x + 80.293
R2 = 0.9136
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240Elapsed Time (Months)
IRI (
in/m
i)
IRI Observed
IRI Predicted
IRI Calibrated
IRI Observed (Linear)
IRI Predicted (Linear)
IRI Calibrated (Linear)
Fig. 5.13 Compression sealants Westbound IRI comparison plots
116
IRI Comparisons, Watson Bowman 812 WB
Predictedy = 0.0162x + 65.915
R2 = 0.9137
Observedy = 0.0772x + 64.403
R2 = 0.246
Calibratedy = 0.0769x + 64.42
R2 = 0.9141
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Observed
) Predicted
Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
Fig. 5.13(Contd.) Compression sealants Westbound IRI comparison plots
117
Transverse Slab Cracking Comparisons, Delastic V 687 WB
Predictedy = 3.5344x - 19.829
R2 = 0.8976
Observedy = 0.0006x - 0.0153
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
100
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Transverse Slab Cracking Comparisons, Techstar W 050 WB
Observedy = 4.243x - 39.567
R2 = 0.85
Predictedy = 0.0006x - 0.0153
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
100
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed Transverse CrackingTechstar W050 WB
Predicted Slab Cracking Techstar W050 WB
Transverse Cracking Observed (Linear)
Transverse Cracking Observed (Linear)
Fig. 5.14 Compression sealants Westbound transverse slab cracking comparison plots
118
Transverse Slab Cracking Comparisons, Watson Bowman 812 WB
Observedy = 3.9043x - 29.757
R2 = 0.8979
Predictedy = 0.0006x - 0.0153
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
100
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Fig. 5.14(Contd.) Compression sealants Westbound transverse slab cracking comparison plots
119
Spalling Comparisons, Delastic V 687 WB
Observedy = 0.0005x + 0.047
R2 = 0.0014
Predictedy = 2E-05x - 0.0007
R2 = 0.8402
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)
Spalling Predicted(Linear)
Spalling Comparisons, Techstar W 050 WB
Predictedy = 2E-05x - 0.0007
R2 = 0.8402
Observedy = 0.0083x + 0.3565
R2 = 0.0231
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Predicted
Observed
Spalling Predicted(Linear)
Spalling Obseved(Linear)
Fig. 5.15 Compression sealants Westbound spalling comparison plots
120
Spalling Comparisons, Watson Bowman 812 WB
Observedy = 0
R2 = #N/A
Predictedy = 2E-05x - 0.0009
R2 = 0.9047
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed (Linear)
Spalling Predicted (Linear)
Fig. 5.15(Contd.) Compression sealants Westbound spalling comparison plots
121
IRI Comparisons, Crafco 903 SL WB
Predictedy = 0.0355x + 66.551
R2 = 0.977
Observedy = -0.0397x + 68.884
R2 = 0.0667
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Predicted
Observed
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Comparisons, Dow 888 WB
Predictedy = 0.0355x + 77.751
R2 = 0.977
Observedy = 0.4502x + 58.495
R2 = 0.756
Calibratedy = 0.4523x + 58.271
R2 = 0.9769
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Predicted
Observed
Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
Fig. 5.16 Silicone sealants Westbound IRI comparison plots
122
IRI Comparisons, Dow 890 WB
Predictedy = 0.0343x + 64.057
R2 = 0.9771
Observedy = 0.4585x + 64.72
R2 = 0.5643
Calibratedy = 0.4785x + 64.657
R2 = 0.9771
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Predicted
Observed
Calibrated
IRI Predicted (Linear)
IRI Observed (Linear)
IRI Calibrated (Linear)
Fig. 5.16(Contd.) Silicone sealants Westbound IRI comparison plots
123
Transverse Slab Cracking Comparions, Crafco 903 SL WB
Observedy = 1.7505x - 12.91
R2 = 0.8497
Predictedy = 0.0006x - 0.0153
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
100
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse Cracking Observed(Linear)
Transverse Cracking Predicted(Linear)
Transverse Slab Cracking Comparisons, Dow 888 WB
Observedy = 3.8452x - 36.008
R2 = 0.9018
Predictedy = 0.0006x - 0.0153
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
100
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse Cracking Observed(Linear)
Transverse Cracking Predicted(Linear)
Fig. 5.17 Silicone sealants Westbound transverse slab cracking comparison plots
124
Transverse Slab Cracking Comparisons, Dow 890 SL WB
Observedy = 0.8849x - 11.889
R2 = 0.8317
Predictedy = 0.0005x - 0.0136
R2 = 0.9702
0
10
20
30
40
50
60
70
80
90
100
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse Cracking(Linear)
Transverse Cracking(Linear)
Fig. 5.17(Contd.) Silicone sealants Westbound transverse slab cracking comparison plots
125
Spalling Comparisons, Crafco 903 SL WB
Observedy = 0.0228x - 0.1522
R2 = 0.4521
Predictedy = 0.0437x - 0.8239
R2 = 0.9232
0
1
2
3
4
5
6
7
8
9
10
11
12
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)
Spalling Predicted(Linear)
Spalling Comparisons, Dow 888 WB
Observedy = 0.0145x - 0.0716
R2 = 0.7323
Predictedy = 0.0437x - 0.8239
R2 = 0.9232
Calibratedy = 0.0145x - 0.475
R2 = 0.9232
0
1
2
3
4
5
6
7
8
9
10
11
12
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Calibrated
Spalling Observed (Linear)
Spalling Predicted (Linear)
Spalling Calibrated (Linear)
Fig. 5.18 Silicone sealants Westbound spalling comparison plots
126
Spalling Comparisons, Dow 890 SL WB
Observedy = 0.1929x + 0.286
R2 = 0.3699
Predictedy = 0.0413x - 0.7802
R2 = 0.923
0
1
2
3
4
5
6
7
8
9
10
11
12
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)
Spalling Predicted (Linear)
Fig. 5.18(Contd.) Silicone sealants Westbound spalling comparison plots
127
IRI Comparisons, Crafco 221 WB
Predictedy = 0.0355x + 70.351
R2 = 0.977
Observedy = 0.0142x + 71.622
R2 = 0.0046
Calibratedy = 0.0142x + 71.115
R2 = 0.9763
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Observed Predicted Calibrated IRI Predicted (Linear)IRI Observed (Linear)IRI Calibrated (Linear)
IRI Comparisons, Crafco 444 WB
Predictedy = 0.0355x + 63.551
R2 = 0.977
Observedy = 0.1036x + 64.132
R2 = 0.314
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI )
(in/
mi)
Predicted
Observed
IRI Predicted (Linear)
IRI Observed (Linear)
Fig. 5.19 Hot pour sealants Westbound IRI comparison plots
128
Transverse Cracking, Crafco 221 WB
Observedy = 1.4269x - 12.786
R2 = 0.68
Predictedy = 0.0006x - 0.0153
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Transverse Slab Cracking Comaparisons, Crafco 444 WB
Observedy = 2.1849x - 20.389
R2 = 0.7639
Predictedy = 0.0006x - 0.0153
R2 = 0.9703
0
10
20
30
40
50
60
70
80
90
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse Cracking Observed(Linear)
Transverse Cracking Predicted (Linear)
Fig. 5.20 Hot pour sealants Westbound transverse slab cracking comparison plots
129
Spalling Comparisons, Crafco 221 WB
Observedy = 0.0327x - 0.3694
R2 = 0.6178
Predictedy = 0.0437x - 0.8239
R2 = 0.9232
0
1
2
3
4
5
6
7
8
9
10
11
12
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed (Linear)
Spalling Predicted (Linear)
Spalling Comparisons, Crafco 444 WB
y = 0R2 = #N/A
Predictedy = 0.0437x - 0.8347
R2 = 0.9232
0
1
2
3
4
5
6
7
8
9
10
11
12
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)
Spalling Predicted(Linear)
Fig. 5.21 Hot pour sealants Westbound spalling comparison plots
130
IRI Comparisons, No Sealants WB
Predictedy = 0.0355x + 61.951
R2 = 0.977
Observedy = 1.0906x + 59.347
R2 = 0.8139
Calibratedy = 1.0959x + 59.386
R2 = 0.977
0
50
100
150
200
250
300
350
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
IRI (
in/m
i)
Predicted
Observed
Calibrated
IRI Predicted
IRI Observed (Linear)
IRI Calibrated (Linear)
Fig. 5.22 No sealants Westbound IRI comparison plots
131
Transverse Slab Cracking Comparisons, No Sealants WB
Observedy = 1.3441x - 19.288
R2 = 0.7168
Predictedy = 0.0006x - 0.0153
R2 = 0.9703
0
5
10
15
20
25
30
35
40
45
50
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Tran
sver
se S
lab
Cra
ckin
g (%
)
Observed
Predicted
Transverse CrackingObserved (Linear)
Transverse CrackingPredicted (Linear)
Fig. 5.23 No sealants Westbound transverse slab cracking comparison plots
132
Spalling Comparisons, No Sealants WB
Observedy = 0.0171x + 0.1729
R2 = 0.3636
Predictedy = 0.0437x - 0.8239
R2 = 0.9232
0
1
2
3
4
5
6
7
8
9
10
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168 180 192 204 216 228 240
Elapsed Time (Months)
Spal
ling
(%)
Observed
Predicted
Spalling Observed(Linear)
Spalling Predicted(Linear)
Fig. 5.24 No sealants Westbound spalling comparison plots
133
6 CONCLUSIONS AND RECOMMENDATIONS
6.1 Research Summary
This research presents a fundamental step-by-step approach toward utilizing
performance prediction programs to project the future condition of a pavement system
from the available data, and also to evaluate the effectiveness of pavement features using
such projections. The objectives of this study were to examine the evolution of pavement
performance prediction equations and concepts over the last two decades, present a
compilation of suitable computer applications for rigid pavement performance prediction
and life cycle costing, apply a selected program to the data obtained from the Ohio Route
50 Project and draw conclusions in the following areas: (1) applicability of performance
prediction for the project considered and its significance to future maintenance and
rehabilitation (M&R) operations; (2) data required for and computational methods
available for this purpose; (3) cost effectiveness of joint sealants used in the project.
6.1.1 Literature Review
The literature review presented spans the last two decades and encompasses
pavement performance data collection and categorization; techniques used for the
development of performance prediction equations; and studies conducted as well as
significant models developed by various organizations and research agencies for rigid
and flexible pavement systems.
134
It is found that statistical/empirical methods are most commonly used to analyze
pavement distress data collected over several years and develop regression equations for
distress predictions. Mechanistic-based equations and probabilistic analyses are some
less common but equally significant methods. Several federal, state, and other agencies,
such as Federal Highway Administration (FHWA), American Association of State
Highway and Transportation Officials (AASHTO), World Bank, etc., have been actively
involved in the development of all these types of equations.
Much research has been conducted in the area of flexible pavements nationally by
AASHTO, Arizona Department of Transportation (ADOT), Texas Department of
Transportation (TxDOT), as well as others, and by the World Bank internationally, to
develop regression equations for rutting, roughness, and composite distress indices
(Paterson, 1987). A number of research centers around the globe are in the process of
developing mechanistic-based performance equations for flexible pavement systems,
utilizing the Superior Performing Asphalt Pavements (SUPERPAVE) technology.
In the field of rigid pavements, the first comprehensive nationwide study
conducted to develop distress prediction equations for all types of rigid pavements was
the National Cooperative Highway Research Program (NCHRP)-Concrete Pavement
Evaluation Study (COPES), by Darter, et al. (1985). Simple regression equations were
developed for the common rigid pavement distresses. Since then, several equations have
been developed using national/statewide distress databases and statistical/empirical or
mechanistic-based analysis methods for distresses, such as transverse slab cracking, joint
faulting, joint spalling, and pavement smoothness, as well as for composite distress
indices.
135
6.1.2 Computer Programs Available
Upon compilation of equations for distress predictions from several studies,
computer programs have been coded, which can calculate future distresses of pavements.
Various computer applications have been developed to accomplish the objectives of
performance prediction, and of life cycle cost analysis (LCCA) for rigid as well as
flexible pavement systems. To examine the Ohio Route 50 Project, an application for
rigid pavements was required, incorporating mechanistic-based performance prediction,
life cycle cost estimation, and offering a variety of M&R options for the future.
MicroPAVER and Rigid Pavement Life Cycle Cost Analysis (RPLCCA) were considered
for adoption, but rigid pavement performance prediction program Pavespec 3.0 was
finally selected for this purpose. This program was developed for the FHWA for the
purpose of aiding the formulation of performance related specifications (PRS) for an as
constructed rigid pavement system. The software incorporates mechanistic-based distress
prediction models for transverse slab cracking, joint spalling, joint faulting and pavement
smoothness. Pavement section behavior can be simulated in terms of the distresses using
various as constructed inputs. The M&R module allows users to select from among
various options, and also to compare their life cycle costs using the LCCA module.
6.1.3 Current State-of-the-Practice
An equally important aspect of this research was to investigate the applicability
and usage of performance prediction in the pavement industry. Performance prediction
and LCCA have been integral parts of several pavement management systems (PMS) that
are used by various state highway agencies (SHA). Such tools involve collection, storage
136
and analysis of performance data, examination M&R scenarios and planning for repair
and construction of pavement systems.
The main aspects of a PMS are: (1) distress data collection; (2) data
categorization and analysis; (3) pavement performance modeling; and (4) application of
performance prediction for planning and maintenance. Even though these aspects are the
same for any PMS, each SHA has a specific methodology to accomplish these objectives.
The Illinois Department of Transportation (IDOT) has the most advanced system with
mechanistic-based distress prediction models, formulation of future trends for each
section in a pavement network and mapping using Geographic Information System (GIS)
technology. Similarly, efforts are underway to build GIS technology into the TxDOT
Pavement Information Management System (PIMS), as well. The latter employs
regression equations that enable distress prediction for a variety of pavement system
types. For its part, the Colorado Department of Transportation (CDOT) has the most
commonly used methodology for pavement management, incorporating regression curves
developed using data from past state pavement monitoring activities. In case such
historical data is not available, CDOT uses default curves for performance prediction of
individual pavement sections.
6.1.4 Sensitivity Analysis Using Pavespec 3.0
As mentioned in the previous section, Pavespec 3.0 was selected as the computer
application to be used for distress prediction and comparative analysis at the Ohio Route
50 Project. Before proceeding with this task, however, a sensitivity analysis was
137
performed in order to examine the behavior of the program in response to variations in
input values.
A total of seventy nine input parameters were identified. Each one of these was
assigned low, medium and high values so as to examine its effect on the final pavement
distresses, while holding all the other inputs constant. Approximately one hundred and
fifty simulations were completed to test the reasonableness of the program’s results. A
brief summary of the findings are presented in Table 6.1, which enumerates the set of
input parameters that had the greatest influence on each of the output pavement distress
measures. Results obtained are in good agreement with the conventional wisdom and
expert opinion.
6.1.5 Application to the Ohio Route 50 Project
The Ohio Route 50 Project was conducted in the period 1997-2001 and involved
the construction of a rigid pavement system, installation of several joint sealants and
observation of pavement system and joint sealant material behavior. The sealant material
performance, and the distresses of joint spalling, transverse slab cracking, corner breaks
and pavement roughness were documented by the University of Cincinnati research team.
Input parameters describing the pavement system were extracted from the field
data and design assumptions used for the Ohio Route 50 Project (Ioannides, et al., 2002).
About one hundred simulations were completed to predict pavement distresses and life
cycle costs for each test section that used a particular sealant material. Graphical
comparisons of observed, predicted and calibrated distresses for each section were made
to assess the applicability of performance prediction. A cost analysis of each sealant
138
material over the entire service life of the pavement was conducted to determine the
relative cost effectiveness of each sealant material.
Results presented indicate that more data is necessary to obtain better
comparisons and calibrations and to improve the accuracy of projections with respect to
future pavement system behavior. It is also noted that the predicted distresses from the
program are much lower in severity than most of the observed data.
6.2 Conclusions
Graphical comparisons of observed, predicted and calibrated pavement distresses
indicate that values from the eastbound lanes of the Ohio Route 50 Project provide plots
with a higher coefficient of correlation (R2) than the values from the westbound lanes.
This can be attributed to the higher number of data points available for analysis and also
the longer period of monitoring activities. The periods of evaluation of eastbound lanes
and westbound lanes span over 40 months and 29 months, respectively. Additionally, the
international roughness index (IRI) values present the highest R2, in both eastbound and
westbound lanes.
A comparison of these values for each sealant and distress types of eastbound and
westbound lanes is presented in Table 6.2. It is evident that a greater number of data
points spread over a large period of time resulted in regression equations with the highest
R2 values. From a practical standpoint, this indicates that in order to effectively utilize
139
pavement performance prediction methods, a threshold number of data points spread over
a specific minimum period of time need to be gathered from the pavement system.
The graphical comparisons of observed, predicted and calibrated distresses for
each sealant type, present several instances in which the slopes of calibrated curves are
several times greater than the slopes of the predicted curves. This behavior, though
common for all distresses, is pronounced in the case of transverse slab cracking. Based
on a mechanistic analysis, Ioannides, et al., (2000) attributed the observed high levels of
this distress to the length, L, of the pavement slabs, expressed as a ratio to the radius of
relative stiffness, l, of the slab-subgrade system. Site specific factors, such as an
unexpected flood that weakened the subgrade and construction issues, were also cited as
possibly responsible for the premature deterioration of the pavement slabs. Pavespec 3.0,
however, predicts minimal transverse slab cracking percentages for all sections. The
incongruence of observed and predicted results may reflect the importance of the site
specific factors noted and point to the need to tailor the prediction model accordingly.
Furthermore, when such discrepancies occur, data calibration assumes a more significant
role, but Pavespec 3.0 limits this to linear regression.
The cost effectiveness of each sealant material was also determined, assuming
sealant replacement intervals between three and six years over the entire service life of
the pavement system, thereby formulating a common M&R plan for all pavement
sections. Projected costs emanating from sealant material and joint related repair, and
frequency of material replacement for the entire life cycle of the pavement system, were
the criteria used. Results indicate that compression seals, with the exception of Techstar
W-050, were the most cost effective sealant and needed minimal replacement and repair.
140
Among sections with silicone sealants, westbound sections showed better performance
and, therefore, higher cost effectiveness than their eastbound counterparts. This affirms
the effects of site-specific issues, mainly related to sealant installation and construction
aspects, which were highlighted by Ioannides et al (2002). The hot pour sealants were
not consistent in their cost effectiveness measures and so a conclusion cannot be made
based on the results.
6.3 Recommendations
This research presents the basic framework and guidelines for the application of
performance prediction and life cycle costing methods. It is evident from the
conclusions, that performance prediction is a powerful tool in evaluating various M&R
options, and the cost effectiveness of pavement features, such as sealing, overlays, etc.
The findings of this research show that the nature and quantity of data available, analysis
and calibration methods used (such as linear or non linear regression) are highly
significant. A good correlation between the observed and predicted distresses with high
R2 values results in accurate predictions. The primary success factors, however, are the
accuracy and capabilities of the performance prediction tool itself.
In the current research, distress and performance data were collected over a
relatively short period of time. In order to use performance prediction methods
accurately for comparison and analysis, the appropriate distress data have to be recorded
over a long period of time. The threshold number of data points required and the period
141
over which data collection should continue cannot be determined from this research
alone.
By using distress prediction and LCCA methods, application of compression
seals, with the exception of Techstar W-050, can be recommended for the test pavement
considered and similar scenaria. Compression sealants resulted in fewer replacements
and moderate costs over the simulated service life of the pavement system.
When applied to Ohio Route 50 pavement system, the calibration feature in
Pavespec 3.0 does not provide accurate results for transverse slab cracking and needs to
be reconsidered. Moreover, the life cycle costing module of this application can be
improved further. Costs incurred for the construction and maintenance of a pavement
system can be represented in a more detailed manner. Perhaps, the framework presented
in FHWA’s RealCost 2.1, which includes detailed construction, agency and user cost
considerations in the calculation of deterministic and probabilistic life cycle costs for
various alternatives, can provide a guide for this purpose.
142
Table 6.1 Input parameters with maximum influence on pavement distresses
JOINT FAULTING(in.)
PCC TRANSVERSE SLAB CRACKING (%)
JOINT SPALLING (%)
PAVEMENT SMOOTHNESS (IRI) (in./mi)
Pavement Type Concrete strength Joint Sealant Type
Pavement Type
Dowel Bar Diameter
PCC Slab Thickness Water Cement Ratio
Dowel Bar Diameter
PCC Slab Thickness
Climate Zone Number of Freeze Thaw Cycles
Average Annual Freezing Index
Shoulder Type Traffic Factors Concrete Strength
Number of Freeze Thaw Cycles
k - Value Percentage Trucks Slab Thickness Days above 90ºF Average Daily Traffic
Base thickness Air Content Concrete Strength
Average Annual Precipitation
k-Value Slab Thickness
Joint Spacing Air Content Stress Load Transfer
Efficiency
143
Table 6.2 Correlation coefficients of observed distress curves for eastbound and westbound lanes
EASTBOUND SECTIONS IRI (in./mi.)
TRANSVERSE CRACKING (%) SPALLING (%)
PERIOD OF OBSERVATION (MONTHS) 40 12 23
NUMBER OF DATA POINTS 7 3 5
JOINT SEALANTS IRI (R2)
TRANSVERSE CRACKING (R2) SPALLING (R2)
Delastic V 687 0.7133 0.6905 0.6482 Techstar W 050 0.4719 0.4808 1
Watson Bowman 0.6437 0.9423 0.6259 Crafco 221 0.2923 0.9231 1 Crafco 444 0.1553 0.7249 1 Crafco 902 0.0721 0.0168 1 Crafco 903 0.8188 0.4808 0.6534 Dow 888 0.5384 0.596 0.0198 Dow 890 0.6936 0.1196 0.4949
No Sealant (2) 0.8602 0.4808 0.5836 No Sealant (6) 0.8623 0.4808 0.9986
WESTBOUND SECTIONS IRI (in./mi.)
TRANSVERSE CRACKING (%) SPALLING (%)
PERIOD OF OBSERVATION (MONTHS) 29 19 23
NUMBER OF DATA POINTS 6 4 5
JOINT SEALANT IRI (R2) TRANSVERSE CRACKING (R2) SPALLING(R2)
Delastic V 687 0.6257 0.9703 0.0014 Techstar W 050 0.9815 0.85 0.0231
Watson Bowman 812 0.246 0.8979 1 Crafco 444 0.314 0.7639 1 Crafco 221 0.0046 0.68 0.6178 Crafco 903 0.0667 0.8497 0.4521 Dow 888 0.756 0.9703 0.7323 Dow 890 0.5643 0.8317 0.3699
No Sealant 0.8139 0.7168 0.3636
144
7 REFERENCES
2004 Pavement Preventive Maintenance Recommendations. Pavement Management Unit,
Minnesota Department of Transportation. www.mrr.dot.state.mn.us/
pavement/PvmtMgmt/pavemgmt.asp#Publications.
Accessed February 2, 2004.
AASHTO (1994), “Guide for Design of Pavement Structures,” American Association of State
Highway and Transportation Officials, Washington D.C.
Abu-Lebdeh, G., Lyles, R., Baladi, G., Ahmed, K. (2003), “Development of alternative
pavement distress index models,” Final Report, Michigan State University, East Lansing,
MI. http://www.michigan.gov/documents/mdot_rc-
1436_80484_7.pdf. Accessed May 8, 2004.
Bham, G. H., Gharaibeh, N. G., and Darter, M. I. (2001a), “Development of a GIS-Based Illinois
Highway Pavement System,” Proceedings, Twenty-First Annual ESRI International User
Conference, Environmental Systems Research Institute, Inc., San Diego, CA (Jul., 9-13).
http://gis.esri.com/library/userconf/proc01/professional/pa
pers/pap511/p511.htm. Accessed May 10, 2004.
145
Bham, G. H., Gharaibeh, N. G., Darter, M. I., Heckel, L., and Hall, J. P. (2001b), “ Illinois’s
Experience with Pavement Analysis and Management Systems,” Transportation Research
Record 1769, Transportation Research Board, National Research Council, Washington
D.C., pp. 46-51.
Buch, N. (1997), “Calibration of Pavement Design Models Using Field Data,” Journal of
Transportation Engineering, Vol. 123, No. 2, American Society of Civil Engineers,
Reston, VA, pp. 132-135.
Carey, W. N. and Irick, P. E. (1960), “The Pavement Serviceability Performance Concept,”
Bulletin 250, Highway Research Board, National Research Council, Washington D.C.,
pp. 40-58.
Cole, L. W. (1998), “Use of Life Cycle Cost Analysis to Determine the Cost Effectiveness of
Concrete Pavement Design Features,” American Concrete Pavement Association,
Skokie, IL. www.pavement.com/techserv/acpafeatures.pdf. Accessed
February 1, 2004.
Darter, M. I., Becker, J. M., Snyder, M. B., and Smith, R. E. (1985), “Portland Cement Concrete
Pavement Evaluation System – COPES,” National Cooperative Highway Research
Program Report 277, Transportation Research Board, National Research Council,
Washington, D.C.
146
Darter, M. I., Gharaibeh, N. G., Bham, G. H., Heckel, L., and Hall, J. P. (2001), “ Illinois’s
Experience with Pavement Analysis and Management Systems,” Paper No. 01-2970,
Transportation Research Board, Washington, D.C.
http://www.mrutc.org/about/00486.pdf. Accessed May 8, 2004.
Distress Identification Manual for the Long-Term Pavement Performance Program (Fourth
Revised Edition). FHWA-RD-03-031, www.tfhrc.gov/pavement/
ltpp/reports/03031/03031.pdf. Accessed March 1, 2004.
Dossey, T. and Hudson, W. R. (1994), “Distress as a Function of Age in Continuously
Reinforced Concrete Pavements: Models Developed for Texas Pavement Management
Information System,” Transportation Research Record 1455, Transportation Research
Board, National Research Council, Washington, D.C., pp. 159-165.
Farrokhyar, A., Henry, S., Keleman, M., Piane, R., Zamora, R., and Zaturenskiy, M. (2001),
“The Colorado Department of Transportation’s Transition to a Remaining Service Life-
Based Pavement Management System,” Colorado Department of Transportation, Denver,
CO. http://www.eng.mu.edu/crovettj/courses/ceen188/00145.
Pdf. Accessed May 8, 2004.
Freeman, T. J. (2002), “Pavement Management Catalog,” Office of Asset Management, Federal
Highway Administration, Washington, D.C.
147
Fwa, T. F. and Sinha, K. C. (1992), “Quantification of Agency and User Values,” Journal of
Transportation Engineering, Vol. 118, No. 1, American Society of Civil Engineers,
Reston, VA, pp. 84-97.
George, K. P. (2000), “MDOT Pavement Management System, Prediction Models and Feedback
System-Final Report,” Department of Civil Engineering, the University of Mississippi,
University, MS.
Haas, R. (2001), “Reinventing the (Pavement Management) Wheel,” Lecture, Fifth International
Conference on Managing Pavements, Seattle, WA. http://www.asphalt.org/
GRAPHICS/Haaslecture.pdf. Accessed September 16, 2003.
Haas, R., Hudson, W. R., and Zaniewski, J. (1994), “Modern Pavement Management,” Krieger
Publishing Company, Malabar, FL.
Hall, K. T., Lee, Y. H., Darter, M. I., and Lippert, D. L. (1994), “Forecasting Pavement
Rehabilitation Needs for Illinois Interstate Highway System,” Transportation Research
Record 1455, Transportation Research Board, National Research Council, Washington,
D.C., pp. 116-122.
Harvey, J. T. and Lea, J. (2002), “Data Mining of the CalTrans Pavement Management Systems
(PMS) Database,” Draft Report, Pavement Research Center, University of California,
148
Berkeley, CA. http://www.its.berkeley.edu/pavementresearch/
PDF/PMS Dataminingreport1.1.pdf. Accessed May 8, 2004.
HDM-4 Features Homepage. HDM-4 Information Center, World Road Association, FRANCE.
hdm4.piarc.org/info/HDMfeatures-e.htm. Accessed January 15, 2004.
Hoerner, T. E. and Darter, M. I. (2000), “Improved Prediction Models for PCC Pavement
Performance-Related Specifications, Volume II: Pavespec 3.0 User’s Guide,” Federal
Highway Administration, Report No. FHWA-RD-00-131, McLean, VA.
Hoerner, T. E., Darter, M. I., Khazanovich, L., Titus-Glover, L., and Smith, K. L. (2000),
“Improved Prediction Models for PCC Performance Related Specifications, Volume I:
Final Report,” Report No. FHWA-RD-00-130, Federal Highway Administration,
McLean, VA.
Hoerner, T. E., Tarr, S. M., Darter, M. I., and Okamoto, P. A. (1999), “Guide to Developing
Performance-Related Specifications for PCC Pavements, Volume III: Appendices C
through F,” Federal Highway Administration, Report No. FHWA-RD-98-171,
Washington, D.C.
Ioannides, A. M., Minkarah, I. A., Hawkins, B. K., and Sander, J. A. (1999), “Ohio Route 50
Joint Sealant Experiment Construction Report (Phase 1 and 2) and Performance to Date
149
(1997-1999),” Department of Civil and Environmental Engineering, University of
Cincinnati, Cincinnati, OH.
Ioannides, A.M., Minkarah, I.A., Sander, J., and Long, A.R. (2000), “Mechanistic-Empirical
Performance of U.S. 50 Joint Sealant Test Pavement,” State Job No. 14668(0); Contract
No.:8527, University of Cincinnati, Cincinnati Infrastructure Institute, Department of
Civil and Environmental Engineering, Cincinnati, OH.
Ioannides, A. M., Minkarah, I. A., Long, A. R., Sander, J. A., and Hawkins, B. K. (2002), “Ohio
Route 50 Joint Sealant Experiment – Final Report,” Report No. FHWA/OH – 2002/019,
Department of Civil and Environmental Engineering, University of Cincinnati,
Cincinnati, OH.
Juang, C. H. and Amirkhanian, S. N. (1992), “Pavement Distress Index for Managing Flexible
Pavements,” Journal of Transportation Engineering, Vol. 118, No. 5, American Society
of Civil Engineers, Reston, VA, pp. 686-699.
Lee, Y. H., Mohseni, A., and Darter, M. I. (1993), “Simplified Pavement Performance Models,”
Transportation Research Record 1397, Transportation Research Board, National
Research Council, Washington, D.C., pp. 7-24.
150
Liu, C. and Herman, R. (1996), “New Approach to Roadway Performance Indices,” Journal of
Transportation Engineering, Vol. 122, No. 5, American Society of Civil Engineers,
Reston, VA, pp. 329-336.
Lukaken, E. O. (1986), “Development of Pavement Life Prediction Models,” Report No.
MN/RD-86/04, Pavement Management Section, Minnesota Department of
Transportation, St. Paul, MN.
Lukanen, E. O. and Han, C. (1994), “Performance History and Prediction Modeling for
Minnesota Pavements,” Proceedings, Third International Conference on Managing
Pavements, Transportation Research Board, National Research Council, San Antonio, TX
(May 22-26), Vol. 1, pp. 63-73.
Lytton, R. L. (1987), “Concepts of Pavement Performance Prediction and Modeling,”
Proceedings of Second North American Conference on Managing Pavements, Vol. 2,
Toronto, Canada.
Lytton, R. L., Michalak, C. H., and Scullion, T. (1982), “The Texas Flexible Pavement System,”
Proceedings, Fifth International Conference on Structural Design of Asphalt Pavements,
Vol. 1, The University of Michigan and the Delft University of Technology, Ann Arbor,
MI, http://www.asphalt.org/pubs/5th_conf_abst.html.
Accessed June, 5 2004.
151
Mahoney, J. (1990), “Introduction to Prediction Models and Performance Curves,” Course Text,
FHWA Advanced Course on Pavement Management, Washington, D. C.
MicroPAVER Homepage. Technical Assistance Center, University of Illinois at Urbana-
Champaign, Champaign, IL. www.tac.uiuc.edu /software/
paver/paver.htm. Accessed January 25, 2004.
Nunez, M. N. and Shahin, M. Y. (1986), “Pavement Condition Data Analysis and Modeling,”
Transportation Research Board, National Research Council, Washington, D.C.
Paterson, W. D. O. (1987), “Road Deterioration and Maintenance Effects, Models for Planning
and Management,” The Johns Hopkins University Press, Baltimore, MD.
Pavement Design & Rehabilitation Manual (1999), Office of Pavement Engineering, Ohio
Department of Transportation.
www.dot.state.oh.us/pavement/publications.htm
Accessed February 1, 2004.
Pavement Preventive Maintenance Guidelines (1999), Office of Pavement Engineering, Ohio
Department of Transportation. www.dot.state.oh.us/pavement/pvmtmgmt
/pavemgmt.asp#Publications. Accessed February 2, 2004.
152
Pierce, C. E., Baus, R. L., and Wang, D. (2002), “Calibrating Pavement Performance Prediction
Models for Interstate and Primary Highway Systems in South Carolina,” Report No.
FHWA-SC-02-07, Department of Civil and Environmental Engineering, University of
South Carolina, Columbia, SC.
Powerpave- CRCP CAD Software Homepage. Concrete Reinforcing Steel Institute, IL.
www.crsi.org/Pavement_Section/CRCP_Software/body_crcp_
software.htm. Accessed January 15, 2004.
Queiroz, C. A. V. (1981), “Performance Prediction Models for Pavement Management in
Brazil,” Thesis submitted in partial fulfillment of the requirements for the degree of
Doctor of Philosophy, University of Texas at Austin, Austin, TX.
Rauhut, J. B., Lytton, R. L., and Darter, M. I. (1984), “Pavement Damage Functions for Cost
Allocation,” Report No. FHWA-RD-84/017-020, Federal Highway Administration, U. S.
Department of Transportation, Washington, D.C.
Shahin, M. Y. and Walther, J. A. (1990), “Pavement Maintenance Management for Roads and
Streets Using the PAVER System,” Report No. M090/05, U.S. Army Construction
Engineering Research Laboratory, Champaign, IL.
Simpson, A. L., Rauhut, J. B., Jordahl, P. R., Owusu-Antwi, E., Darter, M. I., and Ahmad, M.
(1994), “Early Analysis of LTPP General Pavement Studies Data, Volume III: Sensitivity
153
Analysis for Selected Pavement Distresses,” Report No. SHRP-P-393, Strategic Highway
Research Program, Washington, D.C.
Smith, R. E., Mukherjee, B., Zulyaminayn, M., Pilson, C. C., Dossey, T. and McCullough, B. F.
(2001), “Integration of Network and Project Level Performance Models for TxDOT
PMIS,” Research Report No. FHWA/TX-01/1727-2, Texas Transportation Institute, The
Texas A&M University System, College Station, TX.
Stampley, B. E., Miller, B., Smith, R. E., and Scullion, T. (1995), “Pavement Management
Information System Concepts, Equations, and Analysis Models,” Texas Transportation
Institute, Report No. TX-96/1989-1, Austin, TX.
Stephanos, P. and Hedfi, A. (2000), “Pavement Performance Modeling: An Applied Approach at
the State of Maryland,” http://www.axiomds.com/Documents/175.pdf.
Accessed May 8, 2004.
Titus-Glover, L., Owusu-Antwi, E., and Darter, M. I. (1999), “Design and Construction of PCC
Pavements, Volume III: Improved PCC Performance,” Report No. FHWA-RD-98-113,
Federal Highway Administration, Washington, D.C.
Waalkes, S. M., Dossey, T., McCullough, B. F., and Harrison, R. (1999), “A Sensitivity Analysis
of the Rigid Pavement Life Cycle Cost Analysis Program,” Report No. 0-1739-2, Center
for Transportation Research, University of Texas at Austin, Austin, TX.
154
Walls III, J. and Smith, M. R. (1998), “Life-Cycle Cost Analysis in Pavement Design-Interim
Technical Bulletin,” Federal Highway Administration, Report No. FHWA-SA-98-079,
Washington, D.C.
Wilde, W. J., Waalkes, S. M., and Harrison, R. (2000), “Life Cycle Cost Analysis of Portland
Cement Concrete Pavements,” Report No. SWUTC/01/167205-1, Center for
Transportation Research, University of Texas at Austin, Austin, TX.
Witczack, M. (1996), “Performance Models Management and Support: An Overview,”
Superpave Models, Issue No. 1, Harrington, Hughes & Associates, Inc., Washington,
D.C.
Yu, H. T., Smith, K. D., Darter, M. I., Jiang, J., and Khazanovich, L. (1997), “Performance of
Concrete Pavements, Volume III: Improving Concrete Performance,” Report No.
FHWA-RD-95-111, Federal Highway Administration, Washington, D.C.
Yu, H. T., Khazanovich, L., Rao, S. P., Darter, M. I., and Quintus, H. V. (1998), “Guidelines for
Subsurface Drainage based on Performance, Appendices,” Project 1-34, National
Cooperative Highway Research Program, Washington, D.C.