TW@ESI 27 th November 2016 Hope all of you had a good weekend The following is a record of what was done during the past week and a forecast of the next week.....

Transcript of TW@ESI update 27th November 2016

Page 1: TW@ESI update 27th November 2016

TW@ESI27th November 2016

Hope all of you had a good weekend

The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI update 27th November 2016

A General Note before we start-•Our Christmas party has been planned for Monday 12th December 2016- evening – please pencil this date and keep it free•Monday 5th December will be the date all who are joining the fun of Secret Santa will open our presents •For new employees Jerico, Kristiyan and Stoyan- can CVA/SSA/JGA ask them to join LinkedIn, ask to connect with me and I will include them in our group- speaking of new members in our Linkedin•Shawn has shared a website with me which I would like to share with all of you http://www.mcast.edu.mt/193 MCAST have a number of online course as part of “Get qualified” campaign – these courses are free (with fees being applied for certification) and I urge all of you to further qualify and self develop yourselves•Today, myself and John will be travelling to Qatar from 27th Nov till 2nd Nov – we will be holding various meetings to try and find further opportunities in this region

Page 3: TW@ESI update 27th November 2016

Projects and deadlines• 16_007_LeMeridien_BMS_upgrade- We have started working on phase

1 panels – phase 1 which has to be completed by Feb 2017- next steps are– We need to order the JACES and Field devices – Prepare the Software for the phase one panels- we need to form a plan here

as we are falling back!!– Once materials are here, design sketches are available and software is

available we will do change over.• 12_043_Life Sciences – we need to call for an inspection of snags to

close everything down- we need to complete the tenant building module- this is now a very urgent and hot project

• 13_075_Bosch_ProWatch_Genetec_Interface - The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

• 12_027- Parliament –We have done progress in closing off and we now need to finalise the documentation and finally integrate ProWatch

Page 4: TW@ESI update 27th November 2016

Projects and deadlines• 14_069- Q019 AS410 – Material from Siemens has been received,

RFIs are still unanswered from client• 14_069- Q021_TF4- panel build, panel installation, Patch panel

installation, FOC termination and testing• 12_025- The last issues on the DAC for SCM PH2- IT IS NOW A

PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• 14_081_Siggiewi School- there are some snags pending here which have to be seen to.

• 16_025_DeLaRue_OFX- We have kicked off and now need to start working on typical design- training by overseas specialists will be on 16/1/17

• 13_031_CCA- still issues with values on ILPS and we also have to execute some new works at CCA (new cameras, pagers)

Page 5: TW@ESI update 27th November 2016

Projects and deadlines• 15_011- Sliema apartments – We have done some terminations and will shortly start the

panel build• 16_023_GGY- we have some snags pending as well as the integration to the Acs- we also

have to transfer the old GGY system to the new platform• 14_083_Intercontinental – We have started works to start up the plant and start

commissioning here- software development has also now advanced on this project. Commissioning is planned for this week - The second Pool Panel- which is now completed

• 16_015_RSM- this lighting control project is to be completed by Beginning of December 2016 we need to really keep a good eye on what is happening on site by the main contractor- we must ensure the wiring and terminations are done properly- as soon as the main contractor collects the field devices we must ensure he tests the DALI loops and then we can commission and program

• 15_038_new_HA_Ovt and 15_026_Apap Residence are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation

• 13_070- SCM Lagoona Plant room We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue

Page 6: TW@ESI update 27th November 2016

Projects and deadlines• 16_041_RSM_Zebbug_Security- CCI and SAI will be

going through the scope during week of 18th Nov so as to allow me to start ordering- A kick off will be held during week of 5th Dec

• 16_051_Baxter_AHU_Controls- An extremely fast track project which was started off last week (Commissioning date is in the week after Christmas) – next steps are– Panel design and construction– Installation of main cables– Programming of Control description– Carry out installation and commission the system

Page 7: TW@ESI update 27th November 2016

DesignLast week• Completed Aurobindo Panel drawing site feedback as per CVA conclusion• Completed DAC template for CCI• Meridien: Released sketches of MCPM2, MCPM1, MCPB4 to CVA / CCI to

check /revert, before Panel mods on site (feedback still pending)• OTM – Printed Additional labels for field 5DP02, update conclusion of 5DP02

after CFH testing• Baxter AHU: with, Panel Sizing has been determined, material quote released &

gathered, material ordered & received, P&ID started & completed, Panel Design Started & completed too. Labels gathered & printed. Design start – Mon 21/12 Design completion – 25/11 – personal record for Julian here – well done

Next Week:• Sliema Graham Apartments – addition of PIR leg at Penthouse terrace• FM Environmental As built feedback• Baxter AHU: Monday morning release Panel design for panel building.• Meridien – continue with Panel Sketches

Page 8: TW@ESI update 27th November 2016

InstallationThis past week: • Connected electrical meter in showroom• Aurobindo changed TT sensor on Chiller and tested • Assisted Clifton on Intercontinental commissioning• Continued with works on Mosta workshopNext week:• OTM panel modifications labelling and updates of panel drawings• Lifesciences install batteries on Jaces and check some water

meters• Baxter, start cable pulling• Insulate and seal TT sensor at Aurobindo• Continue with works at Mosta workshop

Page 9: TW@ESI update 27th November 2016

Panel Build

Well done to the efforts done to catch up – we are still in slight delay

• Project 14_069 - OTM Additions panel is complete – Hallelujah! Testing will be in the next week

• Project 15_023 - FM Env Control Panels is done too!• Project 16_015 - RSM DALI panels are completed too • Project 16_051 – To be started and completed by next week• Project 15_011 - Graham Sliema Apts Blk completion target 9th

December 2016

Page 10: TW@ESI update 27th November 2016

Mater DeiWeek 48

Yearly Field devices checks, IR images & coordinated tests Nov--D07-CC1, D07-CC2, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1

Quarterly panel checks Nov -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1,

D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3, D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2, D12-CC1

Weekly update of antivirus on all BMS stations

ReactiveHandling of reactive work orders

Others• Participating in weekly fire drills• Tackling software work orders • New Angiography Project• Training of new team member• Integration of Samoc into Master

Page 11: TW@ESI update 27th November 2016

Sales and Business DevelopmentWe are working on quotes for a catering

establishment, lighting control systems is Qatar and trying to secure a large BMS project in malta.

Page 12: TW@ESI update 27th November 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 13: TW@ESI update 27th November 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable