Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 –...

36
Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course 1

Transcript of Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 –...

Page 1: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Tutorial 5: Two walls connected with strut and base slab

Deep Excavation LLC

DeepEX 2015 – Advanced course 1

Page 2: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

DeepEX is a software program for braced excavations in soils with 2D limit-equilibrium and non-linear analysis

methods, and structural verification of all elements (with AISC, ASD, Eurocodes).

It offers the ability to analyze walls with multiple braces (tiebacks) in multilayered soils.

The non-linear analysis considers elastoplastic behavior for the whole soil-wall-support system.

The program also offers the ability to perform traditional limit-equilibrium analyses.

The graphical interface is completely interactive and the input is simplified to a great extend.

The program utilizes archives of wall types, structural and soil materials, ground anchors etc.

The analysis can be performed in either an utlimate state or at a service state (allowable design, LRFD, or Eurocode 7

design approach methods).

The program offers the ability to automatically set all critical settings according to the desired design methodology.

Corso Paratie, Milano 30 settembre 2009

INTRODUCTION

DeepEX 2015 – Advanced course 2

Page 3: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Program layout

Wall selection

Project tree view

Design section list(right click)

General input tabsFile menu (click)

Model stages (right click options similar to

excel)Command prompt (enter coordinates)

Press to perform calculations.

Instruction box

Model space (left or right click on any item)

Mouse is over item Units

DeepEX 2015 – Advanced course

3D Model (Frames)

View and other

Page 4: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Enter basic project information1. Select this button

2. Define the project name etc.

3. Press OK

DeepEX 2015 – Advanced course

Page 5: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Move model elevations1. Select this button

2. Set new reference elevation to 100 ft

3. Check All boreholes (this moves all soil

layers)

4. Press OK

Page 6: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

1. Add a 2nd wall2. Double click on right wall3. Change dimensions3.1 Change xwall= 60ftDepth L= 45ft

Page 7: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Define basic model limits (top, bottom, left, right)

1. Select this button

2. Set Top= 130ftBottom= 40ft

Left= -60ftRight= 120ft

3. Press OKDeepEX 2015 – Advanced course

Page 8: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Modify soil types (database of soils)

1. Select this button.

Or

Expand the Soils Tree and Double click on FOptions: Right click or press Delete

Note: In DeepEX you can use any soil type in more than one borehole. For example the F soil can be used in boring 1 or boring 2 etc.

You can use any Boring on any design section. Thus changing any property of the F soil will affect all the excavation Design Sections where F is used!

Boring with F soil

Page 9: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Soil type data form

Available soil types

Add new, copy, delete, paste soil

DensityStrength

Short soil name, description and color.

Soil type & initial clay behavior

Test data for estimating soil properties

DeepEX 2015 – Advanced course

Page 10: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Soil type continued

Soil properties: GeneralSoil name: F (this appears in the boring)Description: Detailed soil description.Soil type: Sand gt= 125 kcf : Total unit weightgdry= 120 kcf : Dry unit weight (above water table)c‘= 0 : Effective cohesionF’= 30 degrees : Effective friction angle

v= 0.35 Poisson’s ratio

Kx = Horizontal permeabilityKz = Vertical permeability

Parameters only for claysSu = Undrained shear strengthFcv= Constant volume shearing angleFpeak= Peak shearing angle

DeepEX 2015 – Advanced course

Page 11: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Soil properties (Resistance and Elastic)

KoNC = At rest lateral earth pressure coefficient for normally consolidated state.

Enter elasticity values as shown before. Click on > buttons for more options.

DeepEX 2015 – Advanced course

Page 12: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Soil S1Soil properties: Change S1A. GeneralSoil name: S1 (this appears in the boring)Description: Sand Detailed soil description.Soil type: Sand gt =125 pcf : Total unit weightgdry= 120 pcf: Dry unitc‘ 0: Effective cohesionF’ = 36 degrees : Effective friction angleV = 0.35 Poisson’s ratio

C. Elasto-plasticE = 500 ksfrEur = 3

D. BondUltimate bond = 30 psi

Press OK

Page 13: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Edit Borings (soil layers)

To edit the soil layers double click on the model boring.

The borings can also be edited from:

a) Edit Borings Button.

Or from the:

b) Tree View – Stratigraphy – boreholes

Double click here (or right click) with the mouse.

DeepEX 2015 – Advanced course

Page 14: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Enter Soil Layers

To edit the soil layers click on the blue button and enter the top of layer elevation.

For this example type 90 here:

Then select soil type S1 here:

DeepEX 2015 – Advanced course

Press OK

Page 15: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

DeepEX 2015 – Advanced course

Page 16: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Double click on wall

DeepEX 2015 – Advanced course

Page 17: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

2. Select edit section data, to change wall properties

1. Change wall depth to 45ft

DeepEX 2015 – Advanced course

Number of nodes controls the divisions

along the wall in a limit-equilibrium analysis.

(Suggested 200 min, or set so that small

intervals (0.25 ft) are generated)

Page 18: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Change wall section AZ 19 sheet pile

1. Change wall type

2. Select AZ-19 section

3. Select A50 steel(fy= 50 ksi)

4. Select OK

DeepEX 2015 – Advanced course

Page 19: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Wall using AZ-19 wall section

Select OK

DeepEX 2015 – Advanced course

Page 20: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Add a new stage (Model Tab)

Or right click (to add a stage, similar to Excel)

DeepEX 2015 – Advanced course

Page 21: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Stage 1 change center El. 90

Stage 1

DeepEX 2015 – Advanced course

Page 22: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Add Stage 2: Add a strut at El. +92

Right click and add stage 2

DeepEX 2015 – Advanced course

Page 23: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

You can also drag the surface with your mouse

Page 24: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Select tool to add a strut

Note: After selecting the “Draw ground anchor button” the program tells you to select/enter the 1st tieback point at the wall (x z)

DeepEX 2015 – Advanced course

Page 25: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Add tieback with mouse

1. Select 1st point on left wall (we will modify the coordinates later 2. Select 2nd point on right wall

Page 26: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Edit strut section• Typing PP24x0.375 will generate a pipe 24” OD x 0.375” thick wall• Typing PM600x12 will generate a pipe 600 mm OD x 12mm wall

Page 27: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Add 3rd stage and excavate to El. +80

Page 28: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Changing the water table

• Double click or drag the water table• Change the water elevations in the general tab

• Click on the water table button• The drop down offers other possibilities for drawing user defined

water profiles.

Page 29: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Add stage 4: Draw in a slab between the two walls

Page 30: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Drawn model with slab

Page 31: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Edit slab properties• Create 3ft thick slab• Elevation refers to slab center• Specify +80 + 3ft/2 = El. +81.5• Change spacing to 1ft• Edit slab section to make a 3ft slab• Include slab weight in vertical

stress• Select “Use user defined unbraced

lengths” and use 10ft

Page 32: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Edit slab section to 3ft

• Slab thickness d= 36inches• Slab width b= 12”• Change

reinforcement bars to #9• Ctop and Cbot are

clearances to center of bars

Page 33: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Completed model with 3ft slab

• Green points show that slab is supported at “rigid points”• Slab is not really on

ground.• Slab weight is added to

vertical soil stresses.

NOTE: EXCAVATION IS NOT YET SEALED

Page 34: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Change water levels and seal excavation

• Change water elevations to El. +90• Go to analysis tab, and

apply seal excavation

Purple line shows that excavation is sealed (lined).

Dashed water table inside excavation shows the water potential and that

the excavation is dry within.

Page 35: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Reviewing vertical soil stresses and water pressures:• Important that total

vertical stress is greater than water pressures• Must maintain positive

vertical effective stress• Program does not

consider contribution from wall side resistance and dead weight.

Page 36: Tutorial 5: Two walls connected with strut and base slab Deep Excavation LLC DeepEX 2015 – Advanced course1.

Review forces on slab

• Double click on slab• Water pressure at bottom of

slab: 0.62 ksf (rounded)• Used FS STR= 1.6 shows the

safety factor used to determine the design capacities• This was defined in Design tab