    QC TurnoverIndex

    1)

    Scope of Work

    2) Provincial Documents (AB-83, AB-81, AQP, PP # & CWB Certs )

    3)

    Inspection Test Plans (ITP)

    4)

    Drawings (Plot Plan, GA, P&ID ISOs and Cut sheets)

    5)

    As Built / Redlines Drawings

    6)

    Welding Procedures

    7)

    Welder Log with Qualification Records

    8)

    Weld Map

    9)

    Weld / NDE Log

    10)

    NDE Procedure Copies

    11)

    NDE Technicians Qualifications12)

    NDE Reports (RT, UT, PT, MT, FT, HT, PMI etc)

    13)

    PWHT Reports

    14)

    Pre-Hydro checklists

    15)

    Hydro Test Certificates

    16)

    Gauge Calibration Certificates

    17)

    Post Hydro check list (Reinstatement)

    18)

    Bolt Torque reports

    19)

    NCR Log and NCRs

    20)

    RFI Log and RFIs

    21)

    Punchlists / Deficiency lists

    22)

    MTRs / MRIRs

    23)

    Painting / Coating reports (If applicable)

    24)

    Miscellaneous