Turning water into capital: Political ecology of financing hydropower development The influence of financial actors in the Mekong Basin Vincent Merme MSc Thesis Environment and Resource Management Student n° 2205452 [email protected] Joyeeta Gupta First supervisor Professor of climate change law and policy at the Vrije Universiteit ‐ Amsterdam ‐ and Professor of water law and policy at the UNESCO‐IHE ‐ Delft Rhodante Ahlers External supervisor Senior Lecturer in Water Resources Management at the UNESCO‐IHE ‐ Delft Word count: ≈ 21 000

Transcript of Turning water into capital: Political ecology of financing ......Turning water into capital:...

Page 1: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

     

  

     Turning water into capital:  Political ecology of financing    hydropower development 

 

        The influence of financial        actors in the Mekong Basin     

 Vincent Merme  MSc Thesis  Environment and Resource Management Student n° 2205452 [email protected]    

  Joyeeta Gupta ‐ First supervisor  Professor of climate change law and policy at the Vrije Universiteit ‐ Amsterdam ‐  and Professor of water law and policy at the UNESCO‐IHE ‐ Delft  Rhodante Ahlers ‐ External supervisor  Senior Lecturer in Water Resources Management at the UNESCO‐IHE ‐ Delft    

Word count: ≈ 21 000  

Page 2: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   2 

Abstract Foreword Abbreviations List of tables and figures 1  Introduction ................................................................................................................................... 5 1.1  Problem definition .............................................................................................................. 5 1.2  Background: The Mekong River ................................................................................... 9 1.3  Methodology ....................................................................................................................... 12 1.3.1  Literature review ..................................................................................................... 12 1.3.2  Conceptual framework .......................................................................................... 14 1.3.3  The Mekong Basin and the Case study ........................................................... 16 1.3.4  Contacts and others ................................................................................................ 17 

1.4  Focus and limitations ..................................................................................................... 18 1.5  Outline ................................................................................................................................... 18 

2  Historical context of hydropower development in the Mekong Basin .............. 19 2.1  Mekong regime history .................................................................................................. 19 2.1.1  Inception of the Mekong regime: 1957‐1975 .............................................. 19 2.1.2  Geopolitical hitches to MC progress: 1975‐1991 ...................................... 20 2.1.3  Regionalization and economic development in the post Cold war context: post 1991 .................................................................................................................. 21 

2.2  Financial context evolution .......................................................................................... 23 2.2.1  Reform process in the power sector ............................................................... 24 2.2.2  Drivers of structural reforms ............................................................................. 25 2.2.3  Implications for hydro‐development .............................................................. 26 

3  Case study: the Nam Theun 2 Project Company ......................................................... 27 3.1  Context and Background ............................................................................................... 27 3.2  Financial flows and actors ............................................................................................ 29 3.3  Implications for NTPC .................................................................................................... 35 

4  Stakeholders and mechanisms of hydropower development ............................... 38 4.1  Stakeholders involved .................................................................................................... 38 4.1.1  National states .......................................................................................................... 38 4.1.2  Multinational companies ...................................................................................... 39 4.1.3  Financial actors ........................................................................................................ 40 

4.2  Hydropower financing mechanisms ........................................................................ 42 4.2.1  Contractual arrangements ................................................................................... 42 4.2.2  Financial flows .......................................................................................................... 43 

5  Analysis and generalization: Influence of financial actors ..................................... 46 5.1  Shifting source of funds ................................................................................................. 46 5.2  Relationships between financial actors .................................................................. 48 5.3  Weighting of objectives ................................................................................................. 50 5.3.1  Political objectives .................................................................................................. 50 5.3.2  Economic objectives ............................................................................................... 51 5.3.3  Normative and Instrumental objectives ........................................................ 52 5.3.4  Internal objectives ................................................................................................... 53 

5.4  Implication for hydropower development ............................................................ 55 6  Conclusion and recommendations .................................................................................... 57 Bibliography Appendixes   

Page 3: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   3 

Abstract  The  current  potential  of  economically  feasible  hydropower  projects  in  developing countries equals around 1,330 GW. It would roughly require more than US$2 trillion to  commodify  the  energy  confined  into  these  waters.  Although  past  hydropower investment  returns  were  disappointing,  financial  attractiveness  tends  to  increase. Despite  the  considerable  funds  and  the  irremediable  social  and  environmental impacts at stake, common and clearly defined scientific knowledge on the financial dynamics related to dam building remains sparse. This surprising gap  in knowledge leads  to  the  following  research  question:  how  do  financial  actors  influence hydropower development? Using  a  political  ecology  approach,  this  report  examines  the  role  of  the  financial actors  in  hydropower  development  through  a  literature  review.  Dam  proponents evolve  in  a  politicized  environment  around  the  contested  water  resource.  This research uses  the Mekong Basin and an explanatory  case  study,  the Nam Theun 2 power company, to excavate the financial dynamics behind dam building. Along  its eventful  institutional history, the Mekong regime has met geopolitical and financial hurdles to fully develop the hydropower potential of its basin. But following the end of  the Cold War and the structural  reforms of  the  riparian countries power sector, large‐scale  hydropower  development  is  back  on  the  agenda with  100  dams  under construction,  licensed  or  planned  in  the  lower  Mekong  basin  ‐  of  which  11  are planned  on  the  lower  mainstream.  The  Nam  Theun  2  started  its  commercial operations  in  2009  following  years  of  negotiation  and  financial  scheme  building. Based  on  the  case  study,  financing  trends  were  identified  and  generalized. Stakeholders  of  large  dams  are  interconnected  throughout  the  water  resource. Financial backers’  influence  takes  shape at  the outset of  contractual  arrangements and  financing  mechanisms.  The  general  understanding  of  hydropower  financing actors  and  mechanisms  helps  structure  this  investigation  and  draw  relevant conclusions.  The  analysis  shows  that  financial  actors’  leverages  of  influence  imply  practical consequences  over  dam  building.  Shifting  sources  of  funds,  interplays  between financiers and weighting of objectives sway the forthcoming hydropower prospects. It appears that the normative rationalization and sustainable hydropower financing promoted by investors mislead the real purpose of hydropower development, at the expense  of  recipient  country  sovereignty  and  poorest  people’s  livelihoods.  Capital surplus needs  to be  invested  in growing privatized energy markets;  large dams are suitable infrastructures to embrace such aspiration.    Foreword This research project took place at the UNESCO‐IHE, Institute for Water Education in Delft, from April to July 2012. It forms part of my MSc Thesis, a compulsory course of the  Environment  and  Resource  Management  Master  at  the  VU  University  of Amsterdam.  The  UNESCO‐IHE  provided  the  central  topic  of  this  investigation. Joyeeta Gupta and Rhodante Ahlers supervised me along my Thesis, and helped me to stay on track and to structure this report. In addition, Ineke Kleemans was of great support to conduct efficiently this research. I was extremely pleased to work with my supervisors on this fascinating subject and would like to thank them sincerely.  

Page 4: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   4 

Abbreviations ADB    Asian Development Bank ASEAN   Association of Southeast Asian Nations BDA    Bilateral Development Agency CA    Concession Arrangement ECA    Export‐Credit Agency EIA    Environment Impact Assessment  EIB    European Investment Bank GMS    Greater Mekong Sub‐region HCC    Head Construction Contract ICOLD    International Commission On Large Dams IFI    International Financial Institutions IHA    International Hydropower Association  IMC    Interim Mekong Committee IMF    International Monetary Fund LMB    Lower Mekong Basin MC    Mekong Committee MDB    Multilateral Development Bank MRB    Mekong River Basin MRC    Mekong River Commission MRC DB  Mekong River Commission Data Base OECD    Organization for Economic Cooperation and Development NTPC    Nam Theun 2 Power Company PPA    Power Purchase Agreement  PCL    Private Commercial Lenders SAP    Structural Adjustment Program SH    Shareholders Agreement UMB    Upper Mekong Basin UN    United Nations WB    World Bank WCD    World Commission on Dam WWF    World Wildlife Fund List of tables and figures • Figure 1: Construction of dams by decade – 1900‐2000 • Figure 2: Hydropower development ratio for world regions and top five countries 

with the highest potential  • Figure 3: Hydropower development in the Mekong Basin • Figure 4: Conceptual framework • Figure 5: Cumulative installed hydropower capacity (MW) in the LMB • Figure 6: Key existing and proposed dams in the Nam Theun Basin  • Figure 7: NTPC financing scheme • Figure 8: Schematic representation of the main financial flows after and before 

dam commissioning and the main contractual arrangements • Table 1: Hydropower development in the Mekong Basin – Number of dams and 

hydroelectric capacity per country and status • Table 2: Main characteristics of NTPC • Table 3: NTPC source of funds 

Page 5: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   5 

1 Introduction   1.1 Problem definition    During  the  20th  century, more  than  45.000  large  dams were  built  throughout  140 countries  (WCD,  2000).  According  to  the  International  Commission on  Large Dams (ICOLD), a large dam has a height of 15 meters or more from the foundation and has a volume reservoir of more than three million cubic meters. Dam building pace has not been  linear,  rather  it has evolved along with major  international periods. After World War  II,  the  reconstruction  of  Europe  led  to  the  construction  of many  large dams.  The  US  Marshall  Plan  helped  to  rebuild  Europe 1  and  open  the  era  of multilateral and bilateral foreign aid. The success of this plan led to the creation of the International Bank for Reconstruction and Development (later called the World Bank)  aimed  at  exporting  the  western  model  of  economic  development  in developing  countries. Dams  suited well  for materializing  this model  of  foreign  aid. During  the  cold  war,  building  large  dams  became  a  symbol  of  state  control  over natural  resources  in  communist  regimes. While  for  the western bloc, dams  turned into an instrument of development to slow down communist expansion in sensitive regions  (WCD,  2000;  Temple,  2010;  Hirsch,  2010).  However,  during  the  last  two decades  of  the  past  century,  the  pace  of  dam  building  dropped  down.  The development  of  most  attractive  hydropower  sites  in  Europe  and  North  America partly  explains  this  decline.  In  addition,  rising  global  environmental  and  social concerns,  together  with  financial  constraints,  slowed  down  dam  expansion  (WCD, 2000; WB, 2009)  (see Figure 1 below). Today, hydropower development  is back on the world  agenda.  In  an  increasingly  globalized  context,  new opportunities  for  the energy sector appear and stimulate a  revival  in dam  investment by  traditional and emerging donors (WCD, 2000; ADB, 2002; WB, 2009; IHA, 2011).                

Figure 1: Construction of dams by decade – 1900‐2000 (WCD, 2000) (Graph excludes dams in China) 

                                                        1 With the transfer of US$ 17 billion aid (WCD, 2000).  2 Mainly International Financial Institutions (IFIs) and dam industry.  

Page 6: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   6 

Proponents2 of  large  dams  claim  that  the  general  purpose  is  to  meet  water  and energy needs and help economic development. Depending on the region, large dams serve different overall objectives. In water‐abundant regions such as North America, Northern  Europe  or  the  Amazon,  dams  are  generally  built  for  hydropower generation. In dryer countries such as South Africa, Australia or Spain, dams are built for  water  supply.  In  East  and  Southeast  Asia,  where  hydraulic  flows  change significantly along the year, dams are built for flood control during the monsoon and water  supply  during  the  dry  season.  Though  large  dams  are  built  for  a  specific purpose, electricity generation remains either the primary purpose or an additional function in many countries. Today, hydropower provides around 17% of the world’s electricity supply (WCD, 2000; WB, 2009a; IHA, 2011).  Large dams demand substantial investment. The World Commission on Dams (WCD) 2000 report estimated a worldwide  investment of at  least US$ 2 trillion during the 20th century. In 1998, Briscoe estimated an average US$65 billion annual investment in  water‐related  infrastructure  in  developing  countries  during  the  90’s,  of  which US$15 billion was used for hydropower3 (Briscoe, 1998). In 2000, the WCD estimated an  annual  investment  during  the  1990s  in  hydropower  dams  between  US$  19‐28 billion  (WCD, 2000; Bosshard, 2010).  In 2001,  the WCD gave another rather coarse estimation, with an annual dam investment  in developing countries  in the range of US$21‐31 billion in the 1990’s (WCD, 2001). This shows a rather large inconsistency in  these  financial  data.  Such massive  investments  are  justified by dam proponents with  the  argument  that  water  infrastructure  plays  a  crucial  role  in  promoting economic development and social welfare (WB, 2009).   According  to  the  International  Hydropower  Association,  in  2009  the  global hydropower  installed  capacity was  around  980  gigawatts  (GW)  (IHA,  2011).  Today the  potential  for  scaling  up  hydropower  production  remains  huge,  especially  in developing countries where 70% is not yet exploited (see Figure 2; it is worth noting that  substantial potential  remains  in developed countries)  (WB, 2009a;  IHA, 2011). According  to  the World Bank,  75% of  the  total potential  in  South Asia has not  yet been exploited. The economically feasible hydropower potential equals 1330 GW in developing countries4. The economic feasibility is determined by a hydropower plant load factor5 that determines the price of a kWh. The economic feasibility is different from the financial attractiveness. The  later  is determined by the ability to compete with  other  energy  sources.  This  hydropower  potential  estimation  far  exceeds  the actual  existing  capacity 6  (WB,  2000;  WB,  2009a)  (see  Figure  2).  In  his  study commissioned  by  the  World  Bank,  Chris  Head  (2000)  roughly  estimated  the hydropower cost between $1,000 and $3,000 per kW capacity. Consequently, a very                                                         2 Mainly International Financial Institutions (IFIs) and dam industry.  3 US$25 for water and sanitation, US$25 billion for irrigation and drainage (Briscoe, 1998).  4 The total hydropower capacity in developing countries exceeds 1,900 MW, of which 70% (1330 GW) is not yet exploited (WB, 2009b). Economically feasible if benefit cost ratio exceed 1.  5 The  load  factor  is  the ratio of  the actual energy produced over a period of  time and the potential energy production if the plant would produce at its full capacity.  6 Existing hydropower installed capacity: 437 GW in developing countries and 315 GW in Europe and North America (WB, 2009b).  

Page 7: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   7 

broad  approximation  of  the  investment  required  for  developing  hydropower potential  in  developing  countries  stands  between  US$1,33  and  $3,99  trillion.  The profit  for equity donors  is around 20‐30% while  it  is around 2‐3%  for debt  lenders (WB,  2000;  WCD,  2001).  This  gives  a  general  idea  of  the  prospective  market  for investors in developing countries.    

            

 Figure 2: Hydropower development ratio for world regions  and top five countries with the highest potential (IEA, 2010) 

 Unfortunately, little research has been done to record overall dam investments, and even  less  to  understand  the  influence  of  financial  actors  in  hydropower development. In 1997, Usher wrote a book titled “Dam as aid: a political anatomy of Nordic  development  thinking”,  in  which  the  author  deals  with  the  intractable dilemma  for Western  donors  when  giving  dams  as  aid,  as  the  negative  effects  of dams are disproportionally borne by poor people, which  these donors aim  to help (Usher,  1997).  This  book  addressed  specifically  the  role  of  bilateral  cooperation  in hydropower  development  but  not  other  types  of  financial  actors.  In  1998,  Briscoe made an assessment of public and private investments in water‐related projects for the  UN  Commission  on  Sustainable  Development.  He  used  World  Bank  general financial data as pointers to build up his study. Nonetheless, the author highlighted the fact that “reliable data on trends in hydro financing are not available”  (Briscoe, 1998:p.14).  In  2000,  Chris  Head  authored  a  study  on  the  modalities  of  private hydropower  financing,  commissioned  by  the  World  Bank.  In  it,  he  explains  the financing mechanisms and contractual arrangements linked to hydropower projects. Even  though  this  report  is  valuable  in  that  it  provides  an  overview  of  issues  and challenges related to the private financing of hydropower in developing countries, it does not provide a critical analysis on the influence of financial actors. In 2001, the World  Commission  on  Dams  published  a  report  titled  “Trends  in  the  financing  of water and energy resource projects”. In addition to offering a strategic overview of dam financing, it reviews the financial actors involved in dam building and highlights the  influence of the changing financial context  in water resource management (i.e. decision‐making,  planning,  policy,  option  assessment  etc.).  In  its  work,  the Commission  acknowledges  the  overall  lack  of  reliable  financial  statistics  related  to 

Page 8: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   8 

hydropower  projects.  It  strongly  recommends  developing  a  global  picture  of  total investments  in  dams  by  drawing  together  fragmented  data  from  a  wide  range  of sources (even these data seem rather scarce) (WCD, 2001).  In 2003, World Wildlife Fund (WWF) commissioned a report titled “Policies and practices  in  financing  large dams”. This investigation tries to assess the influence of financial institutions in dam projects  using  empirical  data  to  evaluate  the  funding  mechanisms,  policies  and practices  of  twelve  commercial  banks  and  three  development  banks  related  to  23 globally  distributed  large  dams.  Subsequently,  the  Dam  and  Development  Project (DDP),  hosted  by  the  UNEP,  organized  in  April  2004  a  two  day  workshop  on  the theme of  financing  dams  and  sustainable  development with  central  focus  on  risks (financial  and  investment  risk,  reputational  risk,  risk  to  livelihoods  and environmental risk). Interesting background papers were submitted. Finally, in 2010, the WWF organized a conference to discuss sustainable hydropower financing in the Mekong  Basin.  It  gathered  multilateral  and  bilateral  agencies,  investors  and hydropower experts (WWF, 2010).   As explained above, large dam development is facing a new revival after a significant decline  was  observed  at  the  end  of  the  past  century.  At  first  glance,  water  and energy  needs  are  the  likely,  predominant  forces  driving  this  renaissance.  Quickly growing  economies  have  increasingly  emerged  from  the  so‐called  South  in  an expansively  globalized  context,  and  require  energy.  Hydropower  represents  a straightforward  way  to  exploit  the  potential  of  natural  resources  while  supplying electricity and foreign currency for regional development. Nevertheless, hydropower development  remains  feasible  only  with  access  to  large  volumes  of  capital  and financial attractiveness compared to conventional sources of energy. In this context, the role of financial actors seems crucial in the future path of dam development.   To sum up, the resurgence of dam development in developing countries is driven by a  combination  of  factors:  a  huge  hydropower  supply  potential,  a  growing  clean energy  demand  from  emerging  economies  and  potential  profits  to  be  made (Matthews, 2012). As past century dam expansion turned dams into highly contested objects,  this  reviving  global  interest  in  dam building  raises  a  number of  questions, especially  regarding  financial  aspects.  This  thesis  focuses  on  (i)  mapping  out  the financial  actors  and  dynamics,  (ii)  identifying  leverage  of  influence  and  (iii) characterizing how these investments translate into claims over the landscape.    This  research  investigates  the  role  of  the  financial  actors  on  hydropower development  from  a  political  ecology  perspective.  Because  the  literature  on  dam financing  is  scarce,  this  study  uses  one  basin  to  excavate  the  financial  dynamics behind  dam  development:  the  Mekong  River  Basin.  Furthermore,  this  research employs  the Nam Theun 2  dam as  an  explanatory  case  study  to  identify  financing trends. This leads to the following central research question: 

 How do financial actors influence hydropower development? 

   

Page 9: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   9 

In order to answer the research question, sub‐questions are defined as follows: 1. How  has  the  Mekong  regime  evolved  since  the  inception  of  the  Mekong 

Committee in 1957? a. What are the decisive political and economical periods of the Mekong regime 

evolution? b. To what extend has the financial context changed in the greater Mekong sub‐

region and what does this imply for hydropower development?      2. How has the Nam Theun 2 dam been developed? 

a. Who are the actors  involved and how are they related to each other? What are the financial dynamics related to the project? 

b. What are the implications along the NT2 life cycle? 3. Who are the actors involved and how does financing hydropower work?  

a. What is the role of each advocating stakeholders? b. How  are  stakeholders  officially  related  to  each  other?  What  are  the  main 

financial flows along the life cycle of a dam project?  4. To what extend do financial actors influence hydropower development? 

a. Which  leverages  of  influence  embodied  in  financial  actors  can  affect hydropower development? How are they characterized?  

b. How do these leverage of influence materialize along the life cycle of a dam project? 

   1.2 Background: The Mekong River  The  following  section  addresses  the  ecosystems  services  provided  by  the Mekong River, the status of dam developed in the basin and the cost related to hydropower.  The Mekong River and its tributary system shape the Mekong River Basin (MRB). The Mekong drains the eastern watershed of the Tibetan plateau, together with its sister rivers, the Salween and the Yangtze (UNEP, 2006; Mehtonen, 2008). The Mekong is an international water body that runs through parts of six riparian countries: China, Myanmar,  Lao  PDR,  Thailand,  Cambodia  and  Vietnam.  It  takes  its  source  in  the Tanggula mountain range  in Qinghai province  in China at around 4000 meters high and discharges in the South China Sea about 4900 kilometres downstream, creating the Mekong delta in South Vietnam (MRC, 2010; UNEP, 2006; ADB, 2002; Morgera, 2011).  The MRB  is  divided  in  two  parts  known  as  the  Lancang  or  Upper Mekong Basin  (UMB)  and  the  Lower Mekong  Basin  (LMB).  The UMB, mainly mountainous, drains  the western  part  of  the  Chinese  Yunnan  Province  and  forms  the  northeast border of Myanmar. The LMB, mostly consisting in lowlands and floodplains, covers around 70% of the whole MRB (MRC, 2010; UNEP, 2006; Hirsch, 2006; see Appendix I).   Approximately 70 million people live in the MRB, of whom around 60 million live in the LMB. The population in the MRB consists mostly of fisherman and farmers, with about 80%  living  in  rural areas. Within  this  rural population, 25 million people  live within  a  15  kilometres  corridor  either  side  of  the  Mekong  mainstream,  with  the higher proportion  in Cambodia (75%) and Lao PDR (53%) compared to the national population  (MRC,  2010a).  The  population  in  the  MRB  depends  largely  on  the 

Page 10: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   10 

ecosystem services provided by the Mekong River for their livelihoods, food security and source of incomes (UNEP, 2006; MRC, 2010a). On the one hand, farmers depend on Mekong waters to irrigate their crops and benefit from natural flood fertilization, especially rice crops in the southern part of the LMB. This is one of the reasons why the  Mekong  delta  is  the  most  productive  rice‐growing  area  in  Vietnam  (Bakker, 1999).  On  the  other  hand,  the  Mekong  supports  a  very  rich  freshwater  fishery (UNEP, 2006; Hirsch, 2006; Grumbine, 2011). The Mekong also presents high species diversity  (second after  the Amazon) with around 60  important commercial migrant species. Around 50% of fish catches depend on long distance migration (MRC, 2010c, pp.97). Fish provides the main source of quality protein at low‐cost. In 2003, roughly 40  million  people  in  the  LMB  were  economically  engaged  in  Mekong  fishery activities,  at  least part‐time  (MRC, 2003; MRC, 2010). With a  yield of more  than 3 million tons a year, the Mekong fishery has an estimated value from US$2 to 3 billion per year (Lee, 2009; MRC, 2009), contributing notably to the economies in the LMB. Fishery  in Cambodia,  for example,  contributes 16% to  the GDP. People’s economic dependency  greatly  relies  on  the  river  ecosystem.  The  previous  figures  show  the dependency of local population livelihoods on the Mekong river system (MRC, 2010, pp.153).   Besides the ecosystem services delivered, the MRB presents another valuable asset: its hydropower potential. So far, hydropower projects built in China on the Lancang River are located on the mainstream, whereas all hydropower plants built in the LMB are  located  on  the  tributary  system  (MRC,  2010a).  Four  operational  dams,  called Manwan, Dachaoshan, Jinghong and Xiaowan, are situated on the mainstream upper Mekong for a total installed capacity of 8,800 megawatts (MRC, 2010a; Stone, 2011). The lower Mekong tributary dams total 5,808 MW7 installed capacity spread over 36 operational dams, with the following repartition per country: 2,284 MW in Vietnam, 745 MW in Thailand, 2,778 MW in Lao PDR and 1 MW in Cambodia (MRC DB, 2009; see Appendix  V:  Location map of  hydropower  project  in  the  LMB).  Thus,  the  total hydropower capacity  installed  in  the MRB amounts  to more  than 14,600 MW. The estimated hydropower potential according to the Mekong River Commission equals to  53,000  MW,  of  which  33,000  MW  are  identified  for  the  lower  Mekong.  Only around 18% of this potential has been developed in the LMB, mostly in the past two decades.  The  potential  hydropower  growth  is  considerable.  According  to  the Mekong  River  Committee  Hydropower  Database  (MRC  DB,  2009),  the  number  of existing, under construction and planned dams listed is: 

‐ 136 dams  in  the  LMRB.  74% are  in  Lao PDR and 10% are  in Cambodia  and Vietnam each. Thailand is not planning any more dam projects8; 

‐ 8 mainstream dams in the UMB, all in China (MRC, 2010a).     

                                                        7 This  figure  has  been  updated  compared  to  2009.  Actually,  11  projects  have  been  completed between the creation of the database in 2009 and 2011.  8 In 1995, after years of criticisms, the Thai government announced that no more hydropower plants will be built in the country (Usher, 1997). 

Page 11: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   11 

Status

Country Existing Under

construction Licensed Planned Capacity per country (MW)

Thailand 7 - - - 744.7 Vietnam 13 - 1 1 2,583.0 Cambodia 1 - - 13 5,590.0 Lao PDR 15 3 22 609 20,792.6

China 4 2 2 - 15,805.0 Myanmar10 - - - - - Number of dams 40 5 25 74 144 Capacity per status (MW) 14,608.1 6,692.0 5,130.6 19,084.6 45,515.3

Table  111:  Hydropower  development  in  the Mekong  Basin  –  Number  of  dams  and hydroelectric capacity per country and status (based on data from MRC DB, 2009 and MRC, 2010a)  

 Figure 3: Hydropower development in the Mekong Basin12  

(based on data from MRC DB, 2009 and MRC, 2010a)  The total cost for the 100 dams under construction, licensed or planned in the LMRB, of  which  11  are  planned  on  the  lower  Mekong  mainstream,  is  estimated  to  be around  US$50  billion.  Regional  investors  and  developers  (mainly  from  China, Malaysia,  Thailand  and  Vietnam)  are  leading  the  renewed  interest  of  constructing 

                                                        9 Thailand  and  Lao  PDR  share  border  on  two  planned  mainstream  dam.  These  dams  are  counted under Lao PDR in this table.  10 No reliable and updated hydropower data found for Myanmar.  11 Some uncertain data from the MRC DB (2009) may create some inaccuracies in this table.  12 Hydropower development in Myanmar is not included in this chart.  

2 000 

4 000 

6 000 

8 000 

10 000 

12 000 

14 000 

Existing  Under construction 

Licensed   Planned 

(in MW)  Hydropower development in the Mekong Basin  

Thailand 

Vietnam 

Cambodia 

Lao PDR 

China (Yunnan) 

Page 12: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   12 

mainstream dams in the LMB, accompanied by rising private sector investment and continual support from IFIs (IR, 2008a; MRC, 2010b; Middleton, 2011). Thus, financial actors  have  an  important  role  to  play  in  the  future  prospects  of  hydropower development in the Mekong Basin. This topic will be discussed further in Chapter 3. These 100  licensed and planned dams will have  several  impacts, both positive and negative. On the one hand, proponents of such large dam development plan praise their  benefits.  At  regional  level,  they  will  secure  power  availability  and  allow  for increased  trade and  foreign  investment. At national  level,  these dams will  support economic  development  and  contribute  to  poverty  alleviation  (WCD,  2000;  ADB, 2002).  On  the  other  hand,  negative  consequences  of  such  a  plan  are  widely documented.  Mainly,  these  dams  will  affect  the  integrity  and  diversity  of  the Mekong ecosystems. Consequently, impacts on fishery and agriculture will threaten food  security  in  the  region.  Finally,  social  and  economics  systems  of  affected communities will be disturbed (MRC, 2010b; Li, 2011; Vaidyanathan, 2011). The  following  section  describes  the  methodology  used  to  answer  the  research questions. 

  

1.3 Methodology   The subsequent section describes specific activities to answer the research questions and  the  methods  to  collect  data.  It  also  provides  an  overview  of  the  existing literature  related  with  the  research  questions  and  its  implications  for  this investigation. It describes the conceptual framework and its application. In addition, it explains the role of the Mekong basin and the case study. Finally, it highlights the employment of contacts with experts and scientists.  

1.3.1 Literature review  This research was mainly based on literature review. The literature used consists of relevant  scientific  documentation  (peer‐reviewed  articles  and  papers,  books, reports, websites) and was seen through an appropriate theoretical  framework. To find  and  access  the  literature,  open  access  databases  of  VU University  library  and SciVerse  Hub  (500 millions  scientific  records)  were  used.  Other  tools  such  Google Scholar  were  also  used.  Different  kind  of  scientific  journals  available  online  were identified and consulted. All issues from the inception of each journal were checked. These journals are classified by themes as follows: 

‐ Development: World Development, Perspectives on Global development and Technology,  Futures,  Journal  of Development  Economics,  Science Magazine, Contemporary Southeast Asia 

‐ Economics:  European  Journal  of  Political  Economy,  Journal  of  Asian Economics,  Journal  of  World  Business,  Radical  Political  Economics,  New proposals:  Journals  of  Marxism  an  interdisciplinary  inquiry,  L’Eveil Economique de l’Indochine, Hand book of Development Economics 

‐ Water  and  Energy: Water  Alternatives,  Water  International,  Energy  Policy, Energy 

Page 13: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   13 

‐ Politics and Sociology: Political Geography, The Journal of American History, Regards Sociologiques 

‐ Geography  and  Ecology:  Climate  Policy,  Frontiers  in  Ecology  and  the Environment,  Singapore  Journal  of  Tropical  Geography,  Petermanns GeographischeMitteilungen, Nature. 

 In  addition,  public websites  from  international  institutions  (e.g. World  Bank,  Asian Development  Bank,  World  Commission  on  Dam,  Mekong  River  Commission,  UN Environmental  Programme)  and  international  NGOs  and  associations  (e.g. International Rivers, WWF, Oxfam, International Hydraulic Association, International Institute  for  Sustainable  Development)  were  examined  to  access  more  empirical data. .   On  the  one  hand,  a  specific  research  amid  the  media  described  above  was conducted to strength the point raised in the problem definition (see 1.1) regarding the gap in knowledge about the financial dynamics and influence of financial actors over  hydropower  development.  The  key words  “hydropower”  (or  “infrastructure”) and “finance” (or “investment”) were searched in the title and abstract. This has led to the following results: 

‐ VU  University  library:  6  hits,  mostly  on  private  investment  necessity  to develop infrastructures and services in developing countries and incentive to attract capital. No results on influence of financial actors in hydropower; 

‐ SciVerse  Hub:  49  hits,  multilateral  and  bilateral  hydropower  financing, international  finance  and  power  sector,  hydropower  controversy  and impacts,  influence  of  financial  actors  in  developing  renewable  energy projects  (exclude hydropower). No valuable  results on  influence of  financial actors in hydropower; 

‐ Google Scholar: 58 hits, climate change and hydropower, investment risk and management,  small  hydropower,  incentives  and  barriers  to  invest.  No valuable results on influence of financial actors in hydropower. 

 This  research  process  confirms  a  major  gap  in  knowledge.  In  addition,  a  brief research  in  French  and  Spanish  was  done  to  corroborate  the  lack  of  defined knowledge on  influence of  financial actors  in hydropower development among the scientific community.   On  the  other  hand,  an  intense  research was  conducted  to  gather  and  collate  the information needed to write this report. This  investigation sought to have an inter‐disciplinary approach, focused on the Mekong Basin. In order to research efficiently, the  research was  divided  in  five  themes.  To  access  relevant  literature,  a  snowball method was used, beginning the search using general terms and gradually narrowed down using more specific terms provided below.  For each theme, a set of keywords was identified: 

1. General  data  on  the  Mekong:  Mekong,  fishery,  agriculture,  livelihoods, impacts, hydropower, geography, ecosystem services. 

Page 14: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   14 

2. Mekong  regime  evolution: Mekong  Committee, Mekong  River  Commission, Asian  Development  Bank,  Greater  Mekong  Sub‐region,  International Monetary Fund, structural adjustment, energy sector, economic integration. 

3. Case  study:  Nam  Theun  II,  donors,  loan  disbursement,  conditionality, controversy, financing arrangements, contracts, cost, benefit, impacts. 

4. Actors  and  mechanisms:  hydropower,  multilateral  development  bank, bilateral aid agency, export credit agency, commercial banks, private sector, recipient,  equity,  debt,  concession  arrangements,  contractual  agreements, World Bank, Asian Development Bank. 

5. Influence of financial actors: investment conditionality, hydropower building, private  sector,  multilateral,  loan  condition,  disbursement,  investment guarantee, risk, profitability, accountability, corruption, participation. 

 Based  on  keywords  listed  above,  more  than  100  documents  consistent  with  this research  have  been  found  (roughly  50  peer‐review  publications,  and  50  official reports and presentations). Little work is deeply focused on the financial aspects of dam building (see 1.1.). An annotated bibliography identified and classified relevant sources.   Based on this research, we assume that there is extensive literature on the following issues:  

• Dam impacts and hydropower challenges; • Dam historical evolution and hydro‐politics; • Foreign power infrastructure investment and the private sector. 

Nonetheless, there is little common and clearly defined scientific knowledge on: • Hydropower financing dynamics; • Financial actors influence in dam building; • How investments translate into claims over the landscape/basin. 

 

1.3.2 Conceptual framework  

This  research  intends  to  understand  and  analyse  the  intrinsic  financial  drivers  of hydro‐development.  Few  studies  focus  on  the  influence  of  financial  actors  in  dam building  (see  1.1.).  This  investigation  aims  at  providing  a  preliminary  investigation and  raising  questions  related  to  dam  financing.  It  is  part  of  broader  research currently  on  going  at  the  UNESCO‐IHE,  considering  landscape  analysis  as  an integrated approach  for  analysing  socio‐ecological  transformation and dynamics of large water‐related infrastructures, e.g. dams (Ahlers, 2011). Beyond the usual pros and  cons  debate  related  to  dams,  this  investigation  applies  an  interdisciplinary analysis  of  hydropower  development  in  the  Mekong  Basin  over  time  through  a critical socio‐ecological lens. The political ecology perspective allows us to study dam development beyond the usual cost‐benefit argumentation provided by technocrats and bureaucrats, and the endless  list of adverse effects claimed by the civil society and environmental scientists (Baghel et al., 2010).  

Page 15: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   15 

Political  ecology  is  employed as  an appropriate approach  in  critically  analysing  the influence of financial actors in hydropower development. This integrated framework highlights  the  interrelations  between  politics,  people,  economy,  technology  and environmental  change. Water  is  a  critical  resource  in  thriving human  societies and ecosystems.  Powerful  actors  commonly  manage  the  water  resource,  whose decisions  impact each  level of a  society  (Sneddon et al., 2006; Matthews, 2012). A critical  interdisciplinary perspective  is  required  to embrace all dynamics associated with water‐related infrastructure financing.  

A  four‐dimensional  representation  forms  the  conceptual  framework  of  this  study. Three  interconnected dimensions  shape our  spatial  system:  (i)  the  socio‐economic system,  (ii)  the biophysical  system and  (iii)  the  technology.  They are not  static but evolve  (iv)  over  time.  This  investigation  aims  at  understanding  how  hydropower investments  transfer  into  claims  over  the  landscape.  To  do  so,  we  need  first  to analyse the interdependent evolution of the human organization and the biophysical system over  time.  This  historical  analysis  examines  dynamics  between politics  and socio‐economic driving factors in relation with dam development. A special attention is given on the evolution of the financial system and its effects on the power sector, and  thus  hydropower  development.  In  addition,  the  dam  life  cycle  is  a  second component of the temporal dimension at a project‐scale. It will help to identify the implications of leverages of influence over the project life cycle, for both case study and  generalization.  Based  on  the  case  study  and  in  order  to  explain  the  potential influence  of  financial  actors  over  dam  building,  we  must  understand  who  else  is involved  in  the  process  and what  their  formal  and  informal  interrelations  are  (the size of boxes  reflects  the  focus). This  is  important  to show which  leverages can be activated  by  financial  players.  Finally,  to  assess  the  role  of  financial  actors,  three leverages  of  influence  were  identified:  (i)  a  shifting  source  of  funds,  (ii)  the relationship between  financial actors and  (iii)  the weighing of  their objectives. This may  allow  identification  of  emerging  trends  in  dam  financing  and,  consequently, assessment of the role of financial actors. The conceptual framework is schematically represented in the figure below. 

Page 16: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   16 

Figure 4: Conceptual framework 

 

The  impacts  caused  by  the  dam  on  the  River  Basin  and  on  the  adverse  affected people are not studied  in this  investigation. However, there are represented  in the previous figure to depict the global picture of dam building from a political ecology perspective. The dam company has strong interelations with the river basin, as well as adversed affected people have a substantial interdependency with the biophysical system.  

1.3.3 The Mekong Basin and the Case study  The  Mekong  Basin  was  chosen  as  a  spatial  background  framework  for  this investigation,  essentially  because  of  (i)  the  notable  hydropower  revival,  (ii)  the interest of financial actors, (iii)  its regionalization and economic integration and (iv) the literature available.   The Nam Theun 2 Power Company (NTPC) is the explanatory case study selected for this  investigation. An explanatory case study is not only used to study and depict a peculiarity,  but  also  to  explain  causal  relationships  and  to  develop  theories.  An explanatory case study includes a precise description of facts, considering alternative interpretations.  Then,  it  leads  to  conclusions  based  on  reliable  explanations  and consistent  with  the  facts  (Mills  et  al.,  2010).  The  role  and  implication  for  this research are to analysis and  identify trends  in dam financing dynamics with special attention on the influence of financial actors. The financial patterns detected in the case study are crosschecked with other regional projects  (and to some extent with worldwide  dams  planned).  Then,  these  trends  are  analysed  and  generalized  and finally lead to conclusions and recommendations.  The Nam Theun 2 Power Company was chosen for the following reasons: 

‐ NTPC is representative to understand future hydropower development in the Mekong basin (especially mainstream dams planned in the lower basin). It is 

Page 17: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   17 

a  financing  prototype model.  However,  it  has  a  limited  representativeness compared to most dams previously built in the Mekong Basin; 

‐ It has a complex financing scheme with 27 parties  involved. Financial actors are diverse (e.g. from international financial institutions to commercial banks, from  traditional  to  emerging  actors)  and  have  different  motivations  and conditions for loan disbursements; 

‐ So far, it is the largest investment ever made in Lao PDR; ‐ It is in Lao PDR, where approximately 70% of forthcoming dams are planned; ‐ There is broad literature and empirical data on the project.   

 The main characteristics of the Nam Theun 2 Project Company are found in table 2 (Chapter 3 gives further details): 

Nam Theun 2 Project Company Installed capacity (MW)  1,070  Height / Width (m)  39 / 436 Total cost (US$ billion)  1,25  Reservoir (km2)  450 Construction start  2002  Commissioning year   2009 Table 2: Main characteristics of NTPC (WB, 2005; MRC DB, 2009) 

 Finally,  contacts  were  established  to  fill  the  gap  in  the  literature  and  crosscheck trends  identified  in  the  analysis  of  the  case  study.  Moreover,  other  tools  were applied to support this study. 

1.3.4 Contacts and others  During  this  research, several contacts were established to access  information or  to counterbalance the gap in knowledge. Professionals from specialized institutions and scholars from universities were contacted by email. The Appendix IX lists the position and location of key informants contacted along the research.   In addition, a table was created in order to list all dams built over the Mekong using the  publicly  available  Mekong  River  Commission  Data  Base  (2009).  This  database provides  an  overview of  status  of  the  LMB dams  and  related  overall  costs.  As  the MRC  DB  dated  from  2009,  status  data  were  updated  (dam  under  construction  in 2009 which are now operational). The compiled table can be consulted in Appendix IV.  Furthermore,  to map out  the  financial dynamics, a  schematic  representation of donors and  their  contractual and  financial  interactions with other actors was done (see  Figure  8).  The  relevance  of  this  diagram  was  corroborated  with  contacts  in France and Australia (see Appendix IX).   The four previous sub‐sections have presented the methodology used to answer the research questions. The following section describes the focus and limitations of this investigation.     

Page 18: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   18 

1.4 Focus and limitations  This research is limited in time and space. The spatial limitation of this study refers to the Mekong basin. This research mostly focuses on the lower Mekong, with a special emphasis  on  the  relationship between Thailand and  Lao PDR  (because of  the  case study  selected).  The  consideration  of  the  lower Mekong  basin  is  justified  because eleven  mainstream  hydropower  plants  are  back  on  the  agenda.  Furthermore, downstream  riparian’s  dwellers  suffer  from  upstream  building  effects.  Thus  the assemblage of dams (mainstream and tributary) is examined as a whole with special attention  on  the  NTPC  case  study.  Even  though,  China  already  built  three mainstream dams (Manwan, Dachaoshan and Jinghong) over the Lancang Jiang River (name of the upper Mekong) and plan to build five more mainstream dams (Lee et al., 2009; Hirsch, 2010), the upper Mekong is overlooked along this study mainly due to  financial data accessibility concerns. The temporal scope  is established from the inception of the Mekong Committee in 1957 to date. This is consistent as first official talks  and  negotiations  over  dam  planning  started  with  the  creation  of  the Committee. The following section describes the outline of the report.   1.5 Outline   This investigation is conducted through a political ecology framework. This implies to connect  multiple  disciplines  in  a  logical  and  analytical  thread  along  this  study.  In Chapter 1, the research problem is defined, the context of the Mekong river system depicted and the methodology to answer the research questions explained. Chapter 2  gives  a  political  and  economical  historical  analysis  of  the  Mekong  Basin,  with special  emphasis  on  the  path  of  dam  development  and  the  financial  context evolution.  Then, Chapter  3  explores  the explanatory  case  study,  the Nam Theun 2 power company. It provides a brief contextual history of the project, a description of the  financial  dynamics  and  actors  involved  and  draws  alternative  explanations. Subsequently,  Chapter  4  points  out  large  dam  proponent  roles  and  financial mechanisms  of  hydropower  development.  Successively,  Chapter  5  provides  an analysis of financial  leverage of influence and seeks to generalize findings based on the case study. Finally, Chapter 6 concludes with further conclusions and gives policy and scientific recommendations.  

        

Page 19: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   19 

2 Historical  context  of  hydropower  development  in  the Mekong Basin  

 2.1 Mekong regime history  

 The  following paragraphs expose briefly  the key milestones of  the Mekong  regime evolution  in  a  changing  geopolitical  context.  In  addition,  a  depiction  of  the hydropower projects achieved during each period is presented.   

2.1.1 Inception of the Mekong regime: 1957‐1975   The  institutional  history  of  the  Mekong  River  Basin  management  emerged  in  the 1950s, with  regional  dialogue  on  trans‐boundary water  collaboration  between  the four  emerging  nation‐states,  four  years  after  the  withdrawal  of  France  from Indochina: Lao PDR, Kampuchea (currently Cambodia), Thailand and South Vietnam (Hirsch,  2006;  Morgera,  2011).  In  1957,  the  Committee  for  the  Coordination  of Investigations  of  the  Lower  Mekong  Basin,  or  “Mekong  Committee”  (MC),  was created under the auspices of the United Nation Economic Commission for Asia and the  Far  East  (ECAFE 13 ).  The  mandate  of  the  Committee  was  to  coordinate investigation,  research  and  study  of  the  LMB  water‐related  development  projects and to appeal for bilateral and multilateral financial and technical assistance. Its core areas  of  activity were  at  this  time  hydropower,  irrigation,  flood  control,  drainage, navigation,  watershed  management  and  water  supply  (Makim,  2002).  Its  primary task  for  this  period  was  the  collection  of  hydrologic  data  required  to  build  large dams,  especially mainstream dams  (Sneddon  et  al.,  2006).  The  two upper  riparian countries,  China  and  Burma  (currently  Myanmar),  were  not  involved  in  the  MC. However, they agreed in 1960 a bilateral treaty14 to regulate trans‐boundary  issues and establish navigation rules over the Mekong (Morgera, 2011).   The Mekong Committee was born in the cold war context with rising influence of the United  States  of  America  (USA),  the Union  of  Soviet  Socialist  Republic  (USSR)  and People’s  Republic  of  China  (PRC)  over  Southeast  Asia.  Complex  and  changing ideological  alliances  took  place  between  the  allies  of  the  capitalist  bloc  and  the communist  bloc  (Makim,  2002).  The  Vietnamese  reunification  crystalized  these differences.  South  Vietnam  found  support  from  the USA, while  the  PRC  and USSR backed  North  Vietnam.  Thailand  was  closely  allied  with  the  USA.  Lao  PDR, supposedly  neutral, was  closely  supported  by USA  and  South  Vietnam.  Cambodia, also  apparently  neutral,  had  closed  ties  with  the  PRC.  From  the  Committee’s inception,  the  USA  played  a  dominant  role  in  the  Mekong  waters  cooperation, invoking  the  MC  as  mean  for  setting  peaceful  political  relations  in  the  region. 

                                                        13 In  1956,  the  ECAFE  published  a  report  advocating  numerous  large  dams  projects  in  the  LMB. Currently, the ECAFE is known as the United Nation Economic and Social Commission for Asia and the Pacific (ESCAP) (Yu, 2002; Makim, 2002).  14 The “Boundary Treaty between the Union of Burma and the People’s Republic of China” (Morgera, 2011). 

Page 20: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   20 

American  officials  and  engineers15 were  directly  involved  in  planning  hydrologic activities.  The  American  backing  was  also  part  of  a  wider  geopolitical  strategy  to channel  aid  funds  to  economic  development  projects  and  thus  counteract  the communist expansion (Sneddon et al., 2006; Bakker, 1999).  

 Despite  ideological  tension  and  conflicts,  Lao  PDR,  Cambodia,  Thailand  and  South Vietnam  agreed  to  work  together  for  the  sake  of  sub‐regional  Mekong  water development, under  the condition of only approving unanimously every activity  to be undertaken  in  the basin.  In 1970,  the MC released an  indicative basin plan that proposed 17 potential large mainstream dams by 2000 (MRC, 2010). In 1975, the MC approved the “Joint Declaration of Principles for the Utilization of the Waters of the Lower Mekong Basin”. This declaration promulgated specific rules and principles for water  use  and  gave  veto  power  to  riparian  nations  over  activities  to  divert water from the mainstream (Hirsch, 2006; Makim, 2002).   From  its  inception  to  1975,  the  MC  focused  its  work  in  planning  a  cascade  of mainstream large dams from northern Lao PDR to southern Cambodia. Nonetheless, none materialized,  primarily  due  to  political  reasons  rather  than  technical  or  even financial (Hirsch, 2010). According to the MRC (MRC DB, 2009), seven tributary dams were built during this period in Thailand and Lao PDR, of which four are considered large dams. The first of them was built in 1966 on the Nam Pong River, province of Khon Kaen, district of Ubonrat, Thailand. The Ubol Ratana dam cost US$17,42 million and has an installed capacity of 25.20 MW. In 1971, the Nam Ngum 1 hydroelectric project was built  in the province of Vientiane, district of Keo oudom, Lao PDR.  It  is the  largest  dam built  during  this  period with  a  total  cost  of US$97 million  and  an installed  capacity  of  148.70  MW.  Its  main  purpose  was  to  supply  electricity  to Thailand (Hirsch, 2010). Following, two other dams were achieved in 1971 and 1972 in Thailand,  the Sirindhorn dam  (US$13,6 million and 36 MW) and  the Chulabhorn dam  (US$14,6  million  and  40  MW)  respectively  (MRC  DB,  2009).  Multilateral institutions  such  as  the World  Bank  supported  financially  the  realization  of  these hydropower and irrigation projects.   

2.1.2 Geopolitical hitches to MC progress: 1975‐1991  From  1975  to  1991,  LMB  countries  faced  a  difficult  period  punctuated  by  various disruptive events. Following the end of the Vietnam War in 1975, Lao PDR, Cambodia and Vietnam endured political regime shifts. From 1975 to 1979, the Khmer Rouge took  political  and  military  control  of  Cambodia.  Meanwhile,  regional  leadership dispute between Thailand and Vietnam was fierce (Makim, 2002). The USA stopped its  financial  support  for  the  MC  due  to  several  economic  embargoes16 .  Other Bilateral Development Agencies (BDA), in particular from Scandinavian and Japanese 

                                                        15 Staff came from both the United States Bureau of Reclamation and Army Corps of Engineers. Few months  before  the  creation  of  the  MC,  the  US  government  released  influential  reports  to  draw attention on the substantial hydropower and irrigation potential of the Mekong (MRC, 2010a).  16 Embargoes were  imposed  on  Cambodia  (removed  in  1992),  Vietnam  (removed  in  1994)  and  Lao PDR (removed in 2004) (MRC, 2010a). 

Page 21: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   21 

governments,  replaced  this  financial  gap  and  maintain  support  to  this  day  (MRC, 2010).   In this context, the Committee’s activities were partially halted. The 1975 declaration was  impeded  by  these  politically  disruptive  events.  The  Committee  did  not  meet during  1976  and  1977  and was  on  the  brink  of  failure  of  the  cooperation  process started two decades earlier  (Hirsch, 2006). But,  in January 1978, Vietnam, Thailand and Lao PDR signed a declaration to establish an  interim body and thus promote a continuation  of  the  discussion.  The  Interim Mekong  Committee  (IMC)  maintained interval activities17 until 1991, as it was not possible to plan basin‐wide development without the Cambodian government (MRC, 2010a).   Indeed,  dam  development  slowed  down  during  this  period.  In  approximately  20 years  (1972‐1991), only  two small‐scale dams were built  (MRC DB, 2009).  In 1982, the Huai Kum dam (1,18 MW/ S$7,28 million) was built in the Chaiyaphum province, Kaset Sombun district, Thailand. Then,  in 1990,  the Dray Hlinh 1 dam (12 MW/NA) was built  in the Dak Lak province, Dak Nong District, Vietnam (MRC DB, 2009). This decline in hydropower development in the Mekong Basin was over with the end of the  Cambodian  civil  war  in  1991.  The  pacification  of  the  region  brought  a  new favourable framework for promoting discussion and basin‐wide planning.  

2.1.3  Regionalization and economic development in the post Cold war context: post 1991 

 In December 1991,  the collapse of  the USSR precipitated the cessation of  the Cold War, following the USA‐USSR détente process started in the late 1980s (Hirsch, 2006; Makim,  2002). Meanwhile,  the Cambodian  civil war  officially  came  to  an  end with the signature of the Paris Peace Accords in 1991 (Sneddon et al., 2006). The Mekong sub‐region development opportunities revived as main political and military hurdles were eliminated. For the international community, the Mekong River arose again as symbol of peaceful cooperation with possibilities for rapid economic growth due to, among  other  things,  its  potential  for  hydropower  and  irrigation  (Sneddon  et  al., 2006).  Few  years  earlier,  in  1988,  Thai  Prime  Minister  Chatichai  Choonhavan expressed  this  renewed  interest  in  transforming  the  region  from a  battlefield  to  a market place (Hirsch, 2006; Makim, 2002).  According  to  the  Asian  Development  Bank  (ADB),  the  Greater Mekong  Sub‐region (GMS)  encompasses  the  six  Mekong  riparian  countries:  the  Yunnan  Province  of China, Myanmar, Lao PDR, Thailand, Cambodia and Vietnam.  It accounts about 326 million inhabitants (Yu, 2002; ADB, 2012). The restoration of a basin‐wide planning in changing  regional  geopolitics  relations  has  been  strongly  promoted  by  the  Asian Development  Bank  (ADB).  In  1992,  the  six  members  entered  into  an  economic cooperation  program  supported  by  the  ADB:  the  GMS  initiative.  This  cooperation program  includes  nine  priority  sectors:  energy,  trade,  investment,  transport,                                                         17 Mostly consisting  in data collection.  In 1987, the IMC released a revised basin plan that proposed less hydropower development than the 1970 plan (MRC, 2010a). 

Page 22: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   22 

telecommunications,  agriculture,  environment,  human  resource  development  and tourism. A set of economic corridors was also established  to  facilitate North‐South and East‐West commercial activities (see Appendix II) (Krongkaew, 2004). Trade and investment  are  important  components  to  improve  commercial  relations  between members. The GMS initiative fosters large loans and co‐financing between members. In  addition,  it  enhances  private  sector  involvement  and  improves  competitiveness (Yu, 2002). With no appropriate energy  supply  in  the GMS, MDBs  such as WB and ADB advocated regional power trade as a main strategy for economic development. The Mekong River plays a  central piece  for  this  regional  cooperation. All members have  their  own  interest  in  harnessing  the  Mekong  waters  energy,  e.g.  producing electricity  for  Thailand  or  earn  revenues  from hydroelectricity  selling  for  Lao  PDR. This  includes the construction a sub‐regional  interconnected transmission network. It is included in the GMS framework (Krongkaew, 2004).   Other  signs of economic  integration  intensification were  the Vietnam admission  to Association of Southeast Asian Nations (ASEAN) in 1995, then joined by Lao PDR and Burma in 1997, and finally by Cambodia in 1999. ASEAN was established in 1967 by Thailand,  Indonesia, Malaysia,  Philippines  and Singapore.  The  ten member  states18 are  gathered  under  the  motto  “One  Vision,  One  Identity,  One  Community”.  The central  mission  of  the  association  is  to  accelerate  economic  growth  and  social progress  through  active  collaboration  and  mutual  assistance  between  member states19 (Krongkaew, 2004; ASEAN, 2010).  In 2004, ASEAN heads of State agreed to improve economic integration and cooperation amid the poorer nations of the MRB: Myanmar,  Cambodia,  Lao  PDR  and  Vietnam.  The  MRC,  ADB’s  GMS  and  ASEAN actively  cooperate  to  identify  and  support  development  opportunities  in  the MRB (Karki, 2005; MRC, 2010a).   Almost  twenty  years  after  the  GMS  initiative  launched,  the  MRC  (2010a)  praises large  benefits  of  this  economic  cooperation  and  extensive  investments  in  the region20 .  Improved  road  connectivity  and  power  infrastructures  have  provided numbers of direct and spill over benefits for LMB countries (MRC, 2010a). Previous statements present views of the MRC and may not reflect other opinions, e.g. from subsistence farmers (Hirsh, 2006).   In April 1995, Thailand, Lao PDR, Vietnam and Cambodia21 signed the Agreement on the  Cooperation  for  the  Sustainable  Development  of  the  Mekong  River  Basin (“Mekong  Agreement”)  (Hirsch,  2006).  The  MC  became  the  Mekong  River Committee (MRC) and kept a similar mandate in terms of planning and development of  water  resources  in  the  LMB.  Although  the  MRC  promotes  equitable  and reasonable use of the Mekong River (MRC, 2010a), the veto power accorded to each 

                                                        18 Brunei Darussalam joined the ASEAN in 1984 (ASEAN, 2010). 19 In 1992, the six original members of ASEAN agreed to set up a free trade area (AFTA) (Krongkaew, 2004).  20 Between 1992 and 2008, more than US$3 billion were invested in the area.  21 Cambodia  asked  for  its  re‐admission  in  1991.  Despite  Thailand  opposition,  negotiations  led  to Cambodia reintegration with the signing of the 1995 Agreement (MRC, 2010a). 

Page 23: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   23 

member  state  in  1975  was  abandoned.  This  salient  change  allows  each  nation  to build  large  dams  without  approval  of  other  countries.  Only  the  Procedure  for Notification,  Prior  Consultation  and  Agreement  (PNPCA,  introduced  in  the  1995 Mekong Agreement) is required before a new dam is built (Lee, 2009; MRC, 2010a; Grumbine  et  al.,  2012).  The MRC  turned  out  to  be  the  foundation  of  further  dam development  for  the  LMB.  Despite  absence  of  Myanmar  and  China22 in  this  new agreement,  large hydropower projects and bilateral power trade perspectives have developed a better economic collaboration between the six riparian countries.  From 1990 up to now, 28 hydropower dams were built in the LMB (MRC DB, 2009) and  4  in  the  UMB  (MRC,  2010a).  Figure  5  distinctly  shows  the  hydropower development boom in the LMB. 

 Figure 5: Cumulative installed hydropower capacity (MW) in the LMB 

(based on data from MRC DB 2009) (Yunnan and Burma dams are not included in this picture)  

2.2 Financial context evolution   In  the  new  world  order  succeeding  the  end  of  the  Cold  War,  Southeast  Asian countries experienced a gradual shift from highly centralized to open market based economies  (MRC,  2010a;  Baird,  2011).  While  strengthening  regional  economic integration  and  political  cooperation  in  the  1990’s,  the  power  industry  sector was reshaped  by  structural  adjustment  programs  (SAP)  promoted  by  international financial  institutions  (Makim, 2002; Yu, 2002). Also, powerful central control states shaped their economies and supported such reforms. It is the case of Thailand that became a tiger economy during the last decade (along with Indonesia, Malaysia and Philippines)  and  suffered  substantially  during  the  financial  crisis  in  1996  (MRC,                                                         22 The PRC and Myanmar became dialogue partners in 1996(MRC, 2010a). 

5 000 

10 000 

15 000 

20 000 

25 000 

30 000 

1965 

1967 

1969 

1971 

1973 

1975 

1977 

1979 

1981 

1983 

1985 

1987 

1989 

1991 

1993 

1995 

1997 

1999 

2001 

2003 

2005 

2007 

2009 

2011 

2013 

2015 

2017 

2019 

2021 

Cumulative installed hydropower capacity (MW) in the LMB 

Existing dams 

Planned dams 

Page 24: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   24 

2010a).  As  a whole,  it  has  resulted  in  substantial  changes  in  the manner  in which power facilities are financed, built, owned and operated (WCD, 2001).  

2.2.1 Reform process in the power sector  According to western oriented  international  financial  institutions,  the core purpose of power sector reform, gradually implemented in South‐east Asia since the 1980s, is to design a suitable  industrial  framework that enlarges competition, accountability, innovation and efficiency opportunities. These structural changes usually materialize in  deregulation,  privatization  and  public  spending  cuts,  fostering  optimum profitability  and  competitive  tariffs  required  by  electric  utilities  (Ingco,  1996;  Yu, 2002; Williams,  2006).  The  usual  first  step  is  to  break  the  classically  state‐owned electricity utility  into smaller entities.  It  involves restructuring power generation by creating  independent  power  producers  (IPP)  that  compete  against  each  other through the market. When possible, electricity distribution is divided into a number of concession zones. Then the regulatory authority compares each company based on  performance  criteria  and  fixes  individual  tariffs  and  targets.  The  transmission network  usually  remains  centralized  for  practical  reasons.  Furthermore,  these reforms  aim  at  attracting  private  financial  funds  for  system expansion  and  service quality improvement (Ingco, 1996; WB, 2000; WCD, 2001).   To  encourage  private  sector  involvement  in  energy  development  projects, appropriate  forms  of  project  financing were  established. Under  pressure  from  IFIs (such  as  the  IMF,  WB  or  ADB),  private  sector  participation  in  hydropower development was stimulated in terms of research, design, investment, construction, operation, transmission and distribution through the establishment of new forms of contracts  (such  as  Built‐Own‐Transfer  (BOT),  Built‐Own‐Operate  (BOO),  Built‐Own‐Operate‐Transfer  (BOOT) 23  and  Joint  Venture)  (Yu,  2002).  These  mechanisms encourage  large  infrastructure  project  and  public‐private  partnerships  with  long‐term arrangements. They allow stakeholders to recover their  initial  investment and operational and maintenance expenses (WCD, 2001).   Since  the  emergence  of  an  energy  market  system  in  the  early  1990s,  the  GMS countries  have  gradually  transformed  their  energy  policies  and  restructured  their power  sectors.  Yu  (2002)  has  identified  and  listed  the  evolution  of  energy  utility structures  in  each  GMS  member  states.  The  most  important  changes  for  each country’s utilities are described in Appendix III.  The objectives  and  implications of  such  reforms were diverse.  For  instance,  in  Lao PDR,  the deregulation of  the power  sector was designed principally  for  the export market.  The  government  of  Lao  (GoL)  in  1986  introduced  the  New  Economic Mechanism, whose objectives were, among others,  to  foster private  investment  in power  projects  and  increase  revenue  from hydroelectricity  sales.  The Hydropower Office was created  to plan and  implement hydropower generation plants aimed at supplying energy to neighbouring countries. This new entity was separate from the                                                         23 Further in the text, all similar contracts will be commonly named BOOT. 

Page 25: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   25 

historical state‐owned utility, Électricité du Laos (EdL), which remained in charge of the national electricity market. Both institutions are dependent on the Department of Electricity. The Foreign  Investment Management Committee manages all private investments, negotiates terms of concessions and acquires support from all national bodies involved. In addition, as the banking and legal system represented a concern for investors, during the 1990s, the GoL started a series of reforms concluding in the Foreign Investment Law (WB, 2000), minimizing risks and optimizing profitability for foreign investors.   

2.2.2 Drivers of structural reforms  Before structural reforms, the power sector worldwide was generally centralized in state  utilities  who  managed  electricity  supply  and  distribution.  However,  by  the 1980s and the 1990s, many developing country utilities experienced a lack of capital resulting in decreased public service quality (supply shortage, worsening equipment, transmission  loss 24 )  (Barnett,  1992;  Williams,  2006).  International  financial institutions,  especially  the  IMF,  argued  that  state‐owned  utilities  were  in  need  of structural  reforms.  External  macroeconomic  factors,  such  as  economic  crisis, precipitated actual  implementation of these reforms. The essential external driving force  was  finance.  Impacts  of  such  reforms  over  growing  economies  are controversial (Ingco, 1996; Williams, 2006; Dreher, 2006).   Following the oil crisis in the 1970s and the accumulation of financial burden (foreign debt,  inflation  and  budget  deficit)  in  the  1980s,  developing  countries  fell  prey  to economy‐wide SAP. Within  this  global economic  context, many developing nations were anxious about  the  future of  their power sectors. Even when electricity public companies were profitable,  they were worried about  the  incapacity of public debt financing  to provide  capital  needed  in  future power  infrastructure  investments,  as power  demand  was  forecasted  to  rise  substantially.  Consequently,  the  absolute necessity  for  alternative  sources  of  funds  became  the  central  driving  force  of  the power  sector  reform  in  developing  countries.  Foreign  Direct  Investment  (FDI), encouraged by growing  interest  in energy from international  firms and commercial lenders in new market opportunities, turned into a mean to fill this financial gap. The IMF and  the WB strongly  supported  these visions.  Their  SAP  loan policies adopted the  neoliberal  dogma  of  the  “Washington  Consensus”  (Yu,  2002;  Williams,  2006; Baird, 2011).  In  1994,  the  ADB  adopted  a  new  lending  policy  that  required  liberalization  and reforms prior to new power sector  loans (Williams, 2006). The Asian financial crisis hit  Southeast  Asian  economies  from  mid‐1997  to  1998.  The  crisis  caused  two opposed outcomes on power  sector  reforms.  First,  several Asian countries  such as Thailand  prompted  their  reforms  as  a  result  of  stabilization  loan  conditionality imposed by the IMF and the WB. Second, the Asian Crisis provoked a sudden drop in 

                                                        24 For example, in Vietnam in 1998, 19% of the electricity produced was lost through transmission and delivery (Yu, 2002).  

Page 26: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   26 

FDI that had increased extensively in response to reforms since the beginning of the 1990s (Baumüller, 2009; MRC, 2010a).   

2.2.3 Implications for hydro‐development   The power sector privatization stemming  from structural program adjustments has resulted  in  a  shift  from  public  to  private  control  over  the  development  and ownership  of  new  power  facilities  (WB,  2000).  The  emergence  of  new  financial mechanisms  through  IPP  and  PPP  has  helped  to  set  up  a  financial  structure  that minimizes  the  perception  of  risk  for  financiers.  In  addition,  privatization  of  energy sector  has  provoked  an  increase  in  power  production  to  maintain  profits  of privatized  firms.  Thus  demand  side  management  and  energy  efficiency  are marginalized (Yu, 2002).   For instance, in Lao PDR, little attention is given to off‐grid alternatives, such as pico hydropower  plants  or  solar  systems.  Instead  financial  actors,  along  with governments and multinational companies, promote large‐scale investments in large hydropower  dams  and  grid  electrification.  These  projects  are  usually  financed  and developed  by  foreign  companies  through  BOOT  contracts  (Smits,  2010;  IR,  2012). Furthermore, the promotion of bilateral energy trade has also been stimulated. As a result, Lao PDR have signed a MoU with Thailand and Vietnam, in which they allow to purchase from Lao PDR 3000 MW of hydropower by 2006 and 2000 MW by 2010 respectively.  At  the  same  time,  Lao  PDR  concluded  thirteen  official  contracts  and seventeen  unofficial  arrangements  with  foreign  companies.  Myanmar  identified eight potential large dam export projects for a capacity of 8200 MW (Yu, 2002). The legislative  reforms  engaged  in  Lao  PDR  were  focused  on  enhancing  foreign investment  for  export  hydropower  projects,  as  Lao  PDR  hydropower  potential resources are far larger than its national electricity demand (WCD, 2001).    The 1990s have been a turning point period for hydro‐development in the Mekong Basin and has  resulted  in a changing dam  financing pattern. The 2001  report  from the WCD argues that the reforms arose a number of concerns such as impacts on the poor and on energy efficiency, the loss of sovereignty and societal authority over key development  resources,  the  national  ability  to  regulate  the  power  sector  and concerns of corruption and nepotism (WCD, 2001; IR, 2012). However, these issues are  not  further  discussed  in  this  report  as  they  are  outside  of  the  scope  of  this research.  Following this background historical analysis, the subsequent section deals with the explanatory case study: the Nam Theun 2 dam.         

Page 27: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   27 

3 Case study: the Nam Theun 2 Project Company   Nam  Theun  2  Project  Company  (NTPC)  was  chosen  as  case  study  to  identify  and understand hydropower‐financing  trends  in  the LMB. This project  is  comparable  in size to the eleven dams planned on the Mekong mainstream, although some argue that  is  less  representative  due  to  its  unusual  financing  plan  compared  to  dams already built in the Mekong Basin (key informant from the World Bank, see Appendix IX). The analysis of the complex financial set‐up of NTPC will help further studies to assess and understand the  influence of  financial actors  in  the completion of  future large dams.   NTPC symbolizes  the considerable potential  for hydropower  in Lao PDR (IEC, 2010) and represents a prototype of best project finance deal (EGCO, 2010). Following the financing success of NTPC, the first proposed mainstream dam in the LMB, funded by Thai  banks  and  developed  by  a  Thai  company  (Matthews,  2012),  is  underway.  In September 2010, the GoL informed the MRC of its desire to build the Xayaburi Dam (Grumbine  et  al.,  2012).  The  construction  costs  are  estimated  at  US$  3.8  billion (Stone, 2011).  This project will  need  to mobilize  substantial  funds. Private  lenders’ involvement  will  be  crucial.  NTPC  seems  to  open  doors  to  future  similar  projects aimed at “extracting the blue gold” of Lao PDR.  

3.1 Context and Background  The intention to exploit the hydropower potential of the Theun River and the steep slope  offered  by  the  Nakai  Plateau  is  not  a  new  idea.  The  1st  of  May  1927,  the headlines  in L’Eveil  Economique de  l’Indochine weekly newspaper  read  “Les  Forces hydrauliques de la Nam Theune (Laos)” (“The hydraulic forces of the Nam Theune”). French engineers were already contemplating a multipurpose dam in this area. Their plan was to divert Nam Theun waters toward a 300 meters cliff on the edge of the plateau and  thus create a hydropower plant of 40,000 horsepower capacity  (equal around  30 MW).  This  proposal  aimed  also  at  improving  irrigation,  navigation  and opening  up  this  remote  region.  However,  “well‐informed”  settlers  criticized  this project of electrifying “a savage country where there is nothing to do for a hundred years”25. A final interesting point raised by the article is the potential energy market of  the Siam Kingdom26 (Cucherousset, 1927). Thailand was already considered as a potential  power  export  market.  The  project  never  saw  the  light,  probably  for technical, financial or political constraints.   Approximately  ninety  years  later,  the  Nam  Theun  2  (NT2)  power  facility  is operational.  The  plant  is  situated  in  the  central  provinces  of  Khammuane, Bolikhamxay and Savannakhet, approximately 200 hundred kilometres southeast of Vientiane.  It  is  the  largest  tributary  dam  in  the  Mekong  Basin  with  an  installed                                                         25 In  the  original  text :  «…que  des  gens  dits  « bien  informés »  ont  ridiculisé  l’idée  d’électrifier  le Cammon, pour eux pays sauvage où il n’y a rien à faire avant cent ans » (Cucherousset, 1927). 26 Currently  known as Thailand.  

Page 28: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   28 

capacity of 1,070 MW. The hydropower facility consists of a 39 meters27 high dam, a 450  square  kilometres  reservoir  and  a  power  station.  The  NT2  is  a  trans‐basin diversion hydropower plant, which means water is diverted from its original stream and the power station is not located nearby the dam. Water stored in the reservoir is diverted to the power station through an underground shaft. The station is  located at  the  bottom  of  the Nakai  escarpment  (South‐west  of  the  reservoir,  close  to  the village  of  Gnommalat)  and  benefits  from  a  natural  drop  of  350 meters.  From  the station,  waters  are  discharged  into  a  regulating  pool  and  then  flow  into  a  27 kilometres downstream channel  toward  the Xe Bang Fai River, which drains  in  the Mekong around 150 kilometres south of  the Nam Theun  junction. The project also contains two transmission lines: one 500kV transmission line to the Thai border and one 220kV transmission line to the domestic Lao PDR power grid (World Bank, 2005; MIGA, 2006; Sinha, 2007a; Sinha, 2007b; IR 2008).   To visualize where and how the NT2 project is integrated into the Laotian landscape, the map below shows the hydropower development in the Nam Theun River basin. In Appendix  VI  and VII,  two  other maps  present  the  regional  location  as well  as  a technical schematic representation of the hydroelectric plant.  

                      

 Figure 6: Key existing and proposed dams in the Nam Theun Basin (IR, 2008b) 

 

                                                        27 Sources differ from 39 to 48 meters (same for installed capacity from 1070 and 1075 MW). 

Page 29: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   29 

Although  the project was already contemplated  in  the 1920s,  feasibility  studies on the Nam Theun were actually considered from the 1970s on, when the MC identified the hydropower potential of the Nam Theun. It led to a World Bank feasibility study achieved  by  Snowy Mountains  Engineering  Corp  between  1989  and  1991.  Shortly after, the Government of Lao PDR (GoL) signed an agreement to develop the project and asked the World Bank to contribute to the project financing in 1994. In 1995, the NT2 project became a priority for the GoL (WB, 2005; Sinha, 2007b). In 1997, a first round  of  socio‐environmental  studies  was  produced  but  the  Asian  crisis  delayed temporally  the project development.  In 2000,  the EGAT and the NTPC agreed on a proposed  electricity  tariff.  That was  the  starting  point  for  further  agreements:  the Shareholder Agreement (SA) was signed in 2001, the Concession Agreement (CA) in 2002 and the Power Purchase Agreement (PPA) in 2003. While safeguard documents were finalized,  financing activities continued and reached financial closure  in 2005. On  November  2005,  the  Prime  Minister  of  Lao  PDR,  the  Prime  Minister  of  the Thailand and the Ambassador of France in Lao PDR, along more than 300 local and international officials, celebrated the NT2 construction inauguration. From this date on,  the  construction  moved  forward  and  the  NT2  power  facility  started  its commercial activities in December 2009 (Sinha, 2007b).  With  a  total  cost  of  more  than  53%  of  Lao  PDR  annual  GDP28,  NT2  is  the  most valuable  asset  and  greatest  source  of  foreign  exchange  for  the  GoL.  Over  the concession period, the GoL will benefit from about US$ 2 billion of revenues from its 25%  share  in  the  NTPC.  For  this  purpose,  the  GoL  established  a  special‐purpose company,  the  Lao  Holding  State  Enterprise  (LHSE),  to  become  the  shareholder  in NTPC  (among  others  IPP  projects).  The  Laotian Ministry  of  Finance  owns  100%  of LHSE. Deducting LHSE’s expenses and debt pay‐back,  it will  represent  the principal source of funds for the country’s public finance and is meant to improve its financial resources  aimed  at  poverty  alleviation.  These  development  programs  for  poverty reduction and environmental protection will follow the procedures and rules stated under  the  revenue  and  expenditure management  agreement  signed  between  the Gol and International Development Association (IDA, part of the World Bank group) (ADB, 2005; MIGA, 2006; Sinha, 2007b; IR, 2009).   

3.2 Financial flows and actors  Three  components of  the project are being described here:  (i)  the  shareholders of the  project  company,  (ii)  the  contractual  arrangements  and  (iii)  the  financial structure and actors involved in the project. A special emphasis is given to the third element.  The  Nam  Theun  2  Power  Company  Limited  (NTPC)  has  implemented  the  NT2 hydropower  project.  The  company was  created  on August  27th,  2002,  as  a  limited liability  company  under  Lao  PDR  law,  and  its  registered  head  office  is  located  in Vientiane,  Lao  PDR.  The  firm  was  owned  by  four  parties:  Électricité  de  France                                                         28 Compared to US$ 2,718 billion 2005 Lao PDR GDP (in current US$) (World Bank data).  

Page 30: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   30 

International (EDFI – 35%), Electricity Generating Public Company of Thailand (EGCO – 25%), the Lao Holding State Enterprise (LHSE – 25%) and Italian‐Thai Development Public Company (ITD – 15%).  In 2010,  ITD sold  its shares to EDFI29 and EGCO30. The NTPC bears all the risk related to the project (except political risk) (WWF, 2003; WB, 2005; Sinha, 2007a; MIGA, 2006).   All parties  involved  in the project are bound together by  formal contracts. The key contracts related to the NT2 project are briefly described here after:  

• Shareholders Agreement (SA): signed in 2001 with a duration of 45 years, the SA establishes the rights and obligations of the four shareholders. It provides for the goals, organization, management and operation of NTPC (ADB, 2005; WB, 2005).  

• Concession Agreement (CA): signed in 2002 between the GoL and NTPC with duration of 25 years, the CA grants NTPC to develop, finance, build, own and operate the NT2 hydropower plant; and to pass the project to the GoL at the end of  the concession period. The CA provides  for  the right and obligations for  both  GoL  and  NTPC  (CA,  2005;  ADB,  2005;  WB,  2005).  Under  this agreement NTPC is in charge of the entire water management aspects related to NT2.  Except  for water  release obligations  and  restrictions, NTPC has  the right of using the water stored in the reservoir (Sinha, 2007b). The full CA (a 1000‐pages document)  is confidential,  leaving citizens without access to the dam’s operating cost and liabilities (Probe, 2004).  

• Power Purchase Agreement (PPA): signed in 2003, it stipulates the conditions under which the EGAT and EDL will purchase the electricity produced by the NTPC.    It  is  the central  contract  for  the completion of  the project, ensuring the  future  revenues  of  the  hydropower  plant  on  the  basis  of  a  promise  to buy. EGAT approved to buy 5,636 GWh per year at agreed tariffs on a take‐or‐pay  basis  over  the  concession period.  EDL  agreed  to  purchase  200 GWh per  year.  In  return,  the  NTPC  is  obliged  to make  these  amounts  of  energy available (ADB, 2005; WB, 2005). 

• Head Construction Contract (HCC): signed in 2005 between NTPC and EDF, it is a  turnkey contract.  It  gathers engineering, procurement and construction activities.  EDF  has  subcontracted  four  other  companies  for  civil  works  and electromechanical  installations.  These  firms  are  well‐known:  ITD  from Thailand (also a shareholder in the project), Nishimatsu Contracting Company from Japan, General Electric from the USA and Mitsubishi‐Sumitomo Electric from Japan (ADB, 2005).  

Other  contracts  regarding  staff  management,  technical  services,  implementation arrangements or socio‐environmental management are not described in this report.  The  schematic  representation  in  Appendix  VIII  shows  graphically  the  contractual structure of the NT2.   

                                                        29 In September 2010, EDF acquired 5% extra shares in NTPC (EDF, 2010).  30 In October 2010, EGCO acquired 10% stake in NTPC (EGCO, 2010).  

Page 31: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   31 

So far, the NTPC power facility is the biggest infrastructure investment in Lao PDR. In total,  the  estimated  project  base  cost  US$1.25  billion,  plus  an  additional  US$200 million for contingencies. The costs are attributed as follows: US$722 million for the Head  Construction  Contract,  US$250  million  for  financing  charges,  US$229   development  and  pre‐operating  expenses  and  US$90.5  million  for  environmental and  social  impact mitigation  and  compensation  programs  (ADB,  2005; WB,  2005). The total project cost was funded 28% by equity (US$350 million) and 72% by debt (US$900 million)31. The additional US$200 millions contingent costs are financed half by equity and half by debt (WB, 2005). The Nam Theun 2 dam was created under a BOOT contract.  It means  that  the NTPC has built  the dam and will operate  it  for a concession period of 25 years  from starting commercial operations. After  that,  the dam will be transferred at no cost to the GoL. With this financial structure, the GoL is not entirely exposed to financial risks such as building cost overruns or delays (WWF, 2003; Sinha, 2007b).   In order to assess roles and influence of financial actors over the Nam Theun 2 dam building  process,  financial  actor  profiles  must  be  established.  To  do  so,  a  set  of criteria is identified. It allows distinguishing or clustering each financial actor. Three criteria have been established as follows: 

• Source  of  funds:  sector  (public,  private,  public/private),  country  of  origin, scale (importance of investment) and type (loan, grant, guarantee); 

• Relationship between  financial actors  (temporality  /  common  interest  /  risk allocation); 

• Weighting of objectives.  Source of funds 27 parties have participated in financing the NT2 large‐scale project. The  four  shareholders  directly  finance  the  equity  package.  The  GoL,  through  the LHSE, owns 25% share in NTPC. The LHSE equity participation in the project accounts for  US$87.5 million32.  As  the  GoL  has  limited  capital,  this  package was  funded  by grant,  loans and credit from the IDA (US$20 million loan), the French Development Agency (AFD, €5 million grant), the European Investment Bank (EIB, €40 million loan) and  the  Asian  Development  Bank  (ADB,  US$20 million  loan)  (WB,  2005).  Detailed financing schemes of the equity participation of the three other shareholders are not publicly accessible. It was not found in time for this report.    Financial institutions provide the US$ 1,000 million total debt package through loans to NTPC and/or guarantees to private lenders. The following financial actors are: 

• MDB:  IDA,  ADB, Multilateral  Investment  Guarantee  Agency  (MIGA),  Nordic Investment Bank (NIB), European Investment Bank (EIB); 

• BDA: AFD, PROPARCO, Exim Thailand33; • ECA: COFACE, EKN, GIEK; 

                                                        31 When contingent cost are taking into account, the debt‐equity ratio slightly changes to 69:31. 32 It represents 25% of US$ 350 million equity package, excluding contingent equity.  33 Exim Thailand is not a BDA but assimilate as such. It is a state‐owned bank that provides loans.  

Page 32: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   32 

• Private lenders:  o 9  international  commercial  banks:  ANZ  Investment  Bank,  Bank  of 

Tokyo – Mitsubishi, BNP Paribas, CALYON Financial, FORTIS Bank, ING, KBC, Société Générale and Standard Chartered; 

o 7 Thai  commercial  banks:  Bank of Ayudhya,  Bangkok Bank,  Kasikorn Bank, Krung Thai Bank, Siam City Bank, Siam Commercial Bank, TMB Bank Public Company Limited. 

International  financial  institutions have offered US$ 300 million  in  form of  loans or guarantees. MIGA, IDA and ADB have provided US$ 126 million in debt guarantees to support private financing. ADB, NIB, AFD and PROPARCO have made US$ 144 million in direct loans to NTPC (private part‐owner equity and long‐term private commercial bank debt) (WB, 2005). Exim Thailand has provided a US$30 million loan to NTPC. COFACE, EKN and GIEK have covered private dollar  international  lenders with  total debt  guarantees of US$200 million.  ECA  involvement  aimed at protecting  the nine international commercial bank investments.  Finally, the seven commercial Thai banks have invested US$500 million equivalent in the  form  of  direct  loans  to  NTPC.  These  investments  are  not  covered  for  political risks.  Hereafter, Figure 7 represents the financing structure of NTPC and table 3 resumes the sources of the fund of NTPC.  

 Figure 7: NTPC financing scheme (Sinha, 2007b) 

      

Page 33: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   33 

NTPC Source of funds   Sector / Origin  Scale 

(US$ million / %)  Type 

Equity34 (sponsors) EDFI  Public‐Private / Fr  157.5  10.9%  Core capital LHSE  Public / Lao  112.5  7.7%  Public Grant/Loan EGCO  Public‐Private / Thai  112.5  7.7%  Core capital ITD  Public‐Private / Italy, Thai  67.5  4.7%  Core capital 

Debt (financial actors) MDBs  Public / International  21035  14.5%  Debt guarantees/Direct loans BDAs  Public / Fr, Thai  90  6.2%  Direct loans ECAs  Public‐Private / Fr, Sw, Nw  200  13.8%  Debt guarantees 

Private36  Private / Thai  500  34.5%  Direct loans Total  1,450  100%   

Table 3: NTPC source of funds (adapted from ADB, 2005 and WB, 2005)  Relationships The  international dollar  lenders  requested  to NTPC  the accessibility of  appropriate political risk37 mitigation, both in Lao PDR and in Thailand. This was a condition sine qua non for international dollars investors to lend to NTPC for the project. Therefore, GoL and NTPC asked the World Bank to provide political risk guarantees to cover the international  investment  package  for  NTPC.  According  to  the  WB,  multilateral guarantees were the single realistic solution for such a project. Applying this model of  guarantees  and  limited  direct  loans,  multilateral  and  bilateral  donors  gathered approximately US$ 1, 150 million in limited private funding (WB, 2005). Private Thai baht  lenders  did  not  cover  their  investment  with  political  risk  guarantees.  They financed around one third of the project.   The different actors involved in NTPC are linked in the following ways: 

• The  French  played  an  important  role  in  the  development  of NT2.  Not  only have  French  financial  institutions  supported  the  project,  the  main shareholder and also contractor is the French multinational electric company EDFI.  The  AFD,  PROPARCO,  COFACE  and  French  commercial  banks  have financial  and  institutional  relations.  PROPARCO  is  a  subsidiary  company  of AFD specialized in supporting the private sector. The AFD owns 57% share of PROPARCO. In addition, seven French financial institutions own 27% stakes in PROPARCO.  Société  Générale  and  BNP  Paribas  are  shareholders  and  thus they  both  have  a  permanent  representative  in  the  PROPARCO  board  of 

                                                        34 Contingent  costs  are  financed 50% by equity  and 50% by debt, on a pari‐passu basis. Contingent equity is provided proportionally by the four shareholders and it is included in this table.  35 Guaranteed loans from IDA, MIGA and ADB are supporting $US 126 million of private funding and direct loans of $US84 million from ADB and NIB have been provided to NTPC. 36 Only Thai commercial banks. Dollars commercial lenders are covered under debt guarantees.  37 Political  risks  can  be  shift  in  law  taxes  and  duties  regime,  expropriation,  force majeure  or  other specific  obligations  of  a  sovereign nature.  In  addition,  the  IDA PRG also  insures  investment  against natural force majeure events.  

Page 34: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   34 

directors. Finally, one member of the COFACE is an observer in PROPARCO’s activities  (Proparco,  2012).  These  observations  raise  logically  a  number  of questions regarding conflict of interests that are not addressed in this report. 

• General electric was a subcontractor for the NT2 construction. The company has  around 33%  (Krungsri,  2012)  stake  in  the Bank of Ayudhya  (Middleton, 2011), which has financed part of the NT2 debt package. 

• ING  Bank  and  TMB  Bank  Public  Company  Limited  have  participated  in financing  the private debt package.  ING owns 25%  stakes of  the TMB Bank Public Company Limited (TMB, 2012). 

• BNP Paribas owns Fortis and both have decided to invest in NTPC.    Risks  are  shared  between  the  different  parties  involved  in  the  project.  The construction  risks were  taken by  the Head Contractor, which  then passed  them  to the subcontractors. The completion of transmission line risk was taken by EGAT. The political risks were covered by multilateral bank guarantees for the part of the debt financed  by  international  dollars  lenders.  Even  though  Thai  commercial  bank investment  represent  around  one  third  of  the  total  cost  of  the  project,  these investments are not covered/guaranteed against political risks.   Weighing of objectives The  purpose  of  the  NT2  project  is  to  satisfy  the  Thai  energy  demand  thereby reducing Thailand’s strong dependency on natural gas, and stabilizing energy prices for  consumers  (ADB,  2005).  For  Thailand,  NT2  is  also  a  way  to  avoid  the environmental  and  social  restrictions  on  new  domestic  projects  due  to environmental and social concerns (ECA, 2009). Probe International (2004) however argues that the World Bank, along with the power utility EGAT, have overestimated Thai power demand growth to justify the viability of the project.    According to the ADB (2005),  the economic objective of  the project  is  to “promote economic  growth  in  the  region  by  helping  the  Lao  PDR  develop  its  hydroelectric power  resources  in  an  environmentally  and  socially  sustainable  manner  and  to promote power trade in the GMS” (ADB, 2005, pp. 6). To assess the financial viability of  the  NTPC,  multilateral  banks  have  prepared  financial  projections  over  the concession period (ADB, 2005). Probe International highlighted that the proponents of the project were not able to prove the financial viability of the project. Based on an  economic  analysis  conducted  by  Washington‐based  consultants  in  1997,  the average energy price should be 40% higher than the tariffs negotiated in 2003 in the PPA to cover the project costs (Probe, 2004).  International  lenders  sought  to  secure  their  investment  by  minimizing  risks  and setting  up  the  level  of  interest  rate.  A  borrowing  plan  was  incorporated  to  the financial  plan.  It  fixes  the  interest  rate  associated  with  long‐term  loans.  These documents could not be found for this research.  The normative objective of the financial actors was to enable the GoL “to generate revenues  through  investment  in  hydropower  resources  that  are  used  to  finance spending on priority poverty reduction and environmental programs” (ADB, 2005, pp. 104). The NT2 revenue and expenditure management arrangements intend to insure 

Page 35: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   35 

that  revenues  will  be  spent  with  transparency  and  efficiency.  Multilateral  and bilateral institutions will monitor the effectiveness of the use of the GoL revenues in terms  of  social  and  environmental  programs  (ADB,  2005).  Through  the  Public Financial Management Strengthening Program (PFMSP), the ADB, WB and IMF seek to reform the GoL revenue and spending strategy (ECA, 2009).   The  instrumental  objectives  promoted by  the  financial  actors were  translated  into three  social  and environmental mitigation programs:  the Social Development Plan, the  Environmental  Assessment  and  Management  Plan  and  the  Social  and Environmental Management Framework and First Operational Plan  (ECA, 2009). To evaluate  the  performance  and  quality  of  the  project,  monitoring  and  evaluation arrangements were established. Experts from the MDB/BDA and commercial lenders supervise this multilayered monitoring system (ADB, 2005).   All international commercial banks38 involved in NT2 have committed to the Equator Principles  (Equator  Principles,  2012),  which  should  mean  that  the  project  was  in compliance  with  strict  environmental  and  social  performance  standards. Nevertheless,  International  Rivers  assessed  that  the  Nam  Theun  2  dam  was  in violation of the World Bank safeguard policies (IR, 2009).   Finally, the reputational objectives of the Nam Theun 2 project were enhanced when the project received six awards of best project finance deal by magazine and private bodies  specialized  in  finance.  The  project  is  considered  as  a  financing  prototype model  that  enabled  to mobilize  the  largest  amount  of  capital  through  the  highest number of financing sources in South‐east Asia (EGCO, 2010).    

3.3 Implications for NTPC  The  financing  dynamics  of  the  NT2  project  have  played  a  major  role  in  the establishment of the NTPC. Financial actors have made the completion of the project possible  by  using  different  strategies,  ranging  from  the  incentives  provided  by multilateral  banks  for  drawing  in  private  lenders  in,  to  the  promotion  of  biased overestimations on the financial viability and local spill over benefits.    Although  the  NT2  project  was  established  under  a  BOOT  scheme  with  private ownership,  this  project would  not  have  been  possible without  the  involvement  of international  financial  institutions  such  as  the  WB.  The  participation  of  reliable traditional donors encourages private lenders to enter into project financing. In this way,  MDBs  have  permitted  the  realization  of  the  project  by  facilitating  private investment.  The  NT2  project  financing  used  a  combination  of  large  sums  of  private  capital covered by a set of guarantees provided by  international  financial  institutions. This                                                         38 Considering  that  CALYON  Financial  and  FORTIS  Bank  are  respectively  part  of  Crédit  Agricole  and BNP Paribas, which are members of the Equator Principles.  

Page 36: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   36 

project  is  an example of  the ability of  these  institutions  to mobilize private  capital with a guaranteed private lending ratio of around 1:28 (it means that US$42 million guarantees  accomplished  about  US$1.15  billion  of  private  loans  and  investment). This project is being a showcase to guide and lead the way for future private projects (WB,  2005).  Consequently,  the  NT2  financing  structure  success  may  influence positively  the  economical  feasibility  of  mainstream  dams  planned  and  stimulate investments.   The  CA  negotiations  were  strongly  influenced  by  WB  requirements  in  terms  of obligations  for  all  parties  supporting  the  project,  especially  regarding  social  and environmental measures. The NT2 CA is an exhaustive document compared to other public‐private project of similar extent (WB, 2005). MDBs have influenced the quality of the project by enhancing social and environmental impact mitigation.  According  to  the  WB,  the  NT2  project  financing  is  one  of  the  first  large  funding packages that is conditioned on social and environmental principles, which all donors have endorsed. This means  if  the NTPC does not  respect  social and environmental agreements, multilateral and bilateral  funding would be halted and  it will  lead to a commercial default of the company (WB, 2005; ECA, 2009).  EGAT  negotiated  the  NT2  project  for  its  own  interests  and  those  of  its  subsidiary EGCO (which  is a  sponsor  in NTPC). According  to Probe  International,  the price  for imported  electricity  in  Thailand  will  be  more  expensive  than  the  expansion  of domestic  generation  capacity  (Probe,  2004).  The  Thai  buyer  facility  has  influenced the option of building a dam in Lao PDR rather than in Thailand for its own interests.  Financing  set‐up  is  based  on  recommendations  made  by  the  largest  influential donors such as the WB and the ADB. Their experts advised the Project Company and recipient government on the best practices for financing such a project. The financial advisors also assessed financial projections based on a model especially made for the project. This model intends to show the future performance of the project company during  the  concession  period  on  a  base  case  scenario  (WWF,  2003).  These institutions  are  also  driver  donors  for  the  completion  of  the  project  and  have promoted  benefits  of  such  a  project.  There  was  bias  in  the  financial  viability  as proponents of the project made this feasibility analysis.  The  GoL  applies  royalty  and  income  taxes  on  the  revenues  earned  by  NTPC. Nonetheless, according to the CA, these tax rates are applied at reduced level during the first period of the concession (tax income exemption during the first five years, and then gradually raise from 5% to 30% at the end of the concession) (ADB, 2005; Sinha,  2007b).  The  GoL  financial  incentives  to  draw  foreign  investment  may  be  a threat to the Laotian national sovereignty over its natural resources. One can argue that the GoL is selling off its resources.   Questions  remain  about  the way  contracts  have  been  awarded. No  literature was found  on  the  subject.  The  process  of  awarding  contracts  remains  rather  opaque. Probe  International  states  that  the  NT2  deal  remained  secret  and  without competitive bidding or regulatory oversight in Lao PDR or Thailand (Probe, 2004).  

Page 37: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   37 

 Finally,  lessons  learned  from  NT2  might  reinforce  the  regional  power  system integration  by  providing  economic,  financial,  environmental,  regulatory  and institutional  strategies  to  overcome  development  obstacles  (ECA,  2009),  at  the benefit of financial actors willing to invest in the region.  The Nam Theun 2 case study has identified financial actors leverage of influence. The subsequent Chapters 4 and 5 describe and analyse the trends defined along Chapter 3. This explanatory case study does give valuable insights into the methods used by financial actors to influence the prospective of a project.                                    

Page 38: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   38 

4 Stakeholders and mechanisms of hydropower development  

 4.1 Stakeholders involved 

 The purpose of this section is to provide an overview of actors involved in the 

hydropower  building  process.  It  aims  at  briefly  describing  the  overall  role  of  each player. Following sub‐sections are based on the politicized environment described by Nüsser  (2003)  in  his  critical  review  of  large  dams  through  a  political  ecology perspective  (see  Figure  6  below)  and  the  findings  of  the  case  study  analysis.  The following section will only examine the advocate’s side described by Nüsser  (2003) and applies the conceptual framework described in Figure 4.                             Figure 8: The main actors in the controversial large dam debate (Nüsser, 2003) 

 

4.1.1 National states  According to Nüsser  (2003), hosting countries are amid the most central players  in large dam planning.  Today mostly  constructed  in developing  countries,  large dams are perceived as a symbol of nation building and national industrialization (Cullather, 

Page 39: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   39 

2002; Gonzáles,  2003).  Puissant  state‐owned  regulatory  agencies  and  bureaucratic bodies  usually  support  planning  and  realization  of  such  large  projects.  These institutions  seem  to  have  a  fundamental  self‐interest  to  promote  dam‐building  to maintain  their  authority  and  reputation  (Nüsser,  2003;  Williams,  2006). Governments  with  weak  institutional  frameworks  and  little  organized  public opposition  are  more  attractive  for  investors.  For  instance,  the  lack  of  public resistance to dams makes Lao PDR attractive for private investors (Usher, 1997). The national  state  intervenes  in  hydropower  project  through  their  central  government and  the  public  power  facility,  which  generally  participate  in  financing  equity. Furthermore  as  argued  in  section  2.3.,  energy  market  privatization  has  facilitated private sector participation in financing debt in large dams projects.  In the conceptual framework and along the case study, two roles of the state were identified. States can participate in a large dam project as public utility, shareholder or  both  at  the  same  time  through  different  public  institutions.  The  type  of hydropower  project,  either  domestic  or  export  oriented  (WB,  2000; WWF,  2003), usually determines  the role of  the state.  In  the case of NTPC,  the GoL  through the LHSE played the role of shareholder by funding part of the equity package. The Gol is in need for revenues, has little capacity to invest and thus promotes export projects. Thailand, through EGAT, played the role of public utility. EGAT is the main electricity purchaser (even though EDL is also buying a 5% share of hydroelectricity produced). Thailand  needs  energy  and  promotes  projects  abroad  for  importing  electricity.  In other  cases,  countries  with  energy  needs,  financing  capacity  and  potential hydropower resources might play both roles.   

4.1.2 Multinational companies  Transnational corporations represent the dam‐building industry. They consist mostly of  engineering,  consulting,  manufacturing  and  equipment  supply  companies  and they  are  significant  driving  forces  outward  developing  countries. Many  companies gather  several  of  these  specializations  (Bosshard,  2010).  They  usually  conduct feasibility  studies  and environment  impact  assessments.  This professional  sector  is organized in powerful lobbying associations such as the International Commission on Large  Dams  (ICOLD)  or  the  International  Hydropower  Association  (IHA).  These associations promote expansion of large dams by holding international seminars and conferences.  However,  they  have  difficulty  coordinating  and  developing  common positions due to the heterogeneity of their focus. They also compile their knowledge into  technical  expert  committees  and  gather  all  technical  data  related  to  dams. Technology  transfer  and  successively  economic  development  are  their  main arguments for stimulating dam expansion (Nüsser, 2003; Bosshard, 2010; Baghel et al., 2010). Their overall mission is to promote “sustainable” hydropower and to assist nations  for meeting  their water  and  energy needs  (IHA,  2011).  The  ICOLD  is more specialized  in  setting  up  guidelines  and  standards  to  optimize  dam  building  and operation.    

Page 40: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   40 

Developers  involved  in  the  Mekong  hydropower  development  are  usually multinational  experienced  companies.  Foreign  hydropower  developers  are  often fully or partly  state‐owned utilities  such as Électricité de France  (EDF) or Norway’s Statkraft  Norfund  Power  Invest  (SNPI).  Equipment  suppliers  (like  turbines  and generators)  tend  to  be  massive  private  multinational  companies  such  as  Alstom, Siemens or General Electric (Bosshard, 2010).   Construction contracts were always attributed to traditional foreign firms because of the lack of reliable qualified local companies (WB, 2000). However since 2000, skilled dam companies have been emerging  in developing countries,  such as  in China and India.  For  instance,  with  half  of  the  world’s  large  dams,  China  has  been  able  to strengthen  its  dam  building  industry  and  equipment  supply  chain.  Today,  the Chinese  companies  (and  financiers)  are  playing  a  significant  role  in  Southeast  Asia hydropower development. Synohydro, China Southern Power Grid (CSG), Gezhouba or China International Water and Electric Corporation (CWE) represent main Chinese dam  developers. Many  others  firms  are  involved  in  equipment  supplying.  Chinese dam  industry  is  very  active  in  the MRB.  For  example,  Synohydro  is  involved  in  six dams planned in Lao PDR and Cambodia; CSG in three projects, of which the colossal Sambor mainstream dam planned in Cambodia has an estimated 7,110 MW installed capacity.  Regional  hydropower  developers  are  also  gradually  emerging  from Thailand (such as EGCO, Ratchaburi, GMS Power, ITD, Ch. Karnchang), Vietnam (such as  EVN,  PetroVietnam,  VLPC)  or  from Malaysia  (such  as Megafirst  Corporation  or Gamuda) (Ramamurti, 2004; Liebman, 2005; IR, 2008a; Middleton, 2011). Therefore, the traditional, western dam building industry will experience progressively tougher competition in exploiting hydropower potential in developing countries.   As  identified  in  the  case  study,  multinational  companies  can  play  different  roles. They  can  be  shareholder,  developer/constructor  or  both  at  the  same  time.  For instance,  in  the  case  of  NTPC,  EDFI  is  one  of  the main  shareholders  but  also  the central developer/constructor of the hydropower plant.   

4.1.3 Financial actors   For  this  study,  financial  actors  are  clustered  in  four  categories:  Multilateral Development  Banks  (MDB),  Bilateral  Development  Agencies  (BDA),  Export  Credit Agencies (ECA) and Private Commercial Lenders (PCL). They are the principal actors providing  funds  for dam development. This  study  is not  considering other possible sources  of  funds  such  as  public  domestic  investment  or  private  sponsors 39 . International financial flows from traditional actors are well documented and trends have been  identified. However,  investment data  from  the private  sector  are much harder to access. This section gives a brief overview of the roles played by different type of financial institutions.   

                                                        39 Dam developers can turn into financiers in some cases. See example of EDFI in the NTPC case study (Chapter 3).  

Page 41: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   41 

4.1.3.a Multilateral development banks   During  the  20th  century,  Multilateral  Development  Banks  have  been  the  most important engine of dam development worldwide via direct  investments. Since the beginning of the 1990’s, their support for hydropower has first declined in real terms and  then  took new  forms.  They have  gradually  reduced  their  direct  investment  to destructive  projects  due  to  international  criticisms  from  the  civil  society  and scientific community. Nonetheless, under international political pressure to continue lending, MDBs still play an  important role  in hydropower expansion. They facilitate other  source  of  funds  through  guarantee  and  legitimization  in  order  to  mitigate investment risks. They are still funding debt and equity through loans (Kardam, 1993; Strickland et al., 1998; WCD, 2001; WWF, 2003; WB, 2009a).  The  most  important  multilateral  financial  institutions  are  the  World  Bank  and  its agencies  (IBRD,  IDA,  IFC, MIGA),  the  Inter‐American Development  Bank,  the  Asian Development Bank and the European Investment Bank (WCD, 2001).   

4.1.3.b Bilateral development agencies   Bilateral  Development  Agencies  are  national  agencies  aimed  at  supporting government in developing countries to alleviate poverty. They represent the channel for the Official Development Assistance. BDA and MDB play a similar role. They can be  united  under  the  name  International  Financial  Institutions  (IFI).  Their  financial supports  in  hydropower  development  are  usually  in  the  form  of  equity  grants  or loans  to  the  host  governments,  or  to  the  power  companies.  Although  BDA  are  a rather  a minor  source of  debt  financing,  they  act  as  a  catalyst  for  gathering other sources of funding, like multilateral banks (WB, 2000; ADB, 2002).   The most influent BDA in the Mekong basin are the Japan International Cooperation Agency (JICA), United States Agency for International Development (USAID), Swedish International  Development  Agency  (SIDA),  Agence  Française  du  Développement (AFD) or the Australian Agency for International Development (AusAID) (WWF, 2003; UNEP, 2006).   

4.1.3.c Export credit agencies  Export credit agencies have a facilitating role that helps finance overseas exports of a nation’s goods and services. They are either public‐private or private entities. They generally  provide  guarantees  and  insurances  to  protect  loan  exporters  against political  or  commercial  risks.  Over  the  last  decades,  their  role  in  hydropower development has increased by assisting dam industry exportation. During the 1990’s, they  played  a  substantial  role  in  the  expansion  of  infrastructure  financing  by  the private  sector.  However,  their  involvement  in  dam  building  may  decrease  in  the future  as  they  are  gradually  facing  pressure  to  apply more  sustainable  policies.  In addition,  large  emerging  economies  such  as  Brazil,  India  and  China  have  been 

Page 42: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   42 

developing their own dam industries able to compete with traditional  international hydropower companies (WCD, 2000; WWF, 2003).   

4.1.3.d Private commercial lenders  Private commercial lenders such as commercial banks have always been involved in hydropower  development,  though  private  investors  used  to  be  reluctant  to participate  in hydropower projects that have significant  front‐end costs, a high‐risk profile and  long payback periods. But since the beginning of the 1990’s, worldwide private  sector  investments  in  infrastructure  building  have  substantially  increased. MDB,  BDA  and  ECA  have  been  providing  risk  mitigation  instruments  that  have convinced  private  lenders  to  upscale  their  investments.  In  addition  to  direct participation in debt financing, commercial banks very often play a financial advisor role to establish and negotiate financing plans. Commercial banks are usually highly skilled and experimented in piecing together a large diversity of financial instruments into a reliable financing plan (WCD, 2000; ADB, 2002; WCD, 2001; WWF, 2003). Their advisor role might have a greater influence than their lending activities.    4.2 Hydropower financing mechanisms  Based  on  the  case  study,  the  most  important  contractual  arrangements  between stakeholders  of  a  hydropower  project  were  clearly  distinguished.  In  addition,  the financial flows related to a dam project are described on the base of the depiction of the financial dynamics of the case study and the literature available.  

4.2.1 Contractual arrangements   In  this  section,  four  central  contracts  are  briefly  explained:  (i)  the  Concession Agreement  (CA),  (ii)  the  Power  Purchase  Agreement  (PPA),  (iii)  the  Shareholder Agreement  (SA)  and  (iv)  the  Head  Construction  Contract  (HCC).  Furthermore, complementary contracts will be succinctly described.  Concession Agreement (CA) The CA is the central contract of the hydropower project. It stipulates the conditions under  which  the  dam  company  can  operate  (usually  under  BOOT  schemes).  The average  duration  of  the  CA  is  ranging  from  20  to  30  years.  It  also  specifies  the obligations of the government to the dam company. Habitually, the CA protects the power company against political force majeure event and shifts in law and taxation regimes (WB, 2000; WCD, 2001).   Power Purchase Agreement (PPA) The PPA  is  a  contract  between  the  electricity  utility  and  the dam  company.  It  is  a long‐term agreement to purchase a certain amount of power at pre‐defined tariffs. It also  includes  different  technical  and  financial  undertaking  by  both  parties. 

Page 43: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   43 

Hydropower project financing is strongly dependent on this long‐term arrangement as it provides a long‐run financial outlook of a project (WB, 2000; WCD, 2001).  Shareholders agreement (SA) The  SA  sets  out  the  right  and  obligation  of  the  shareholders  and  stipulates  the objectives,  establishment,  management  and  operations  of  the  power  company.  It usually has a longer duration than the CA (WB, 2000; Sinha, 2007b).   The Head Construction Contract (HCC) The HCC is signed between the Head Contractor and the Power Company. The HC is in charge of the design, the completion of the civil and electromechanical works and the  procurement  of  all  equipment  under  the  supervision  of  the  PC.  The  HCC  is typically a turnkey contract for a fixed price, subject to penalties in case of delay.  Complementary arrangements are listed hereafter: Memorandum of Understanding (e.g. between host  government and dam developer based on energy  consumption forecasts), Royalty arrangements (return revenue to the hosting government for the utilization of  its  natural  resources),  Technical  Services  and Personnel Management Contracts,  Operation  and  Maintenance  Agreement  or  Loan  Agreements  (loan maturity,  repayment  and  rate  of  interest).  This  list  is  not  exhaustive  and  further detailed as it does not fit in the scope of this report.  

4.2.2 Financial flows  Two main types of funding package are used in hydropower financing: (i) the equity package and (ii) the debt package (Briscoe, 1998; WB, 2000; WCD, 2001; WWF, 2003; Williams,  2006).  In  average  the  debt/equity  ratios  for  hydropower  project  are around 70:30 (WCD, 2001). Based on the case study, two distinct periods along the life  cycle  of  a  project  were  identified  based  on  a  turning  point:  the  dam commissioning  date.  Before  commissioning,  financial  flows  come  mostly  from financial  actors  and  shareholders  into  the  power  company;  whereas  after  the beginning of commercial operation, financial flows are reversed, from the electricity buyers  to  the  shareholders  (dividends  and  royalties)  and  financial  actors  (loan repayment,  plus  interests).  The  Figure  9 maps  out  these  financial  dynamics  in  a schematic diagram.  Financing equity On average, equity represents around one third of total  investment. Equity  lenders and  investors  hold  the  share  of  the  power  company.  Holders  of  equity  are  of different  nature.  Generally,  equity  holders  are  the  host  government  and  the multinational  companies. Host government can buy power company shares  thanks to loan and grants provided by MDBs or BDAs. Hosting governments can also directly participate in funding equity when they have the sufficient financial capacity. Private sponsors  provide  participation  in  equity  (typically  multinational  companies). Sponsors  are  usually  public‐private  foreign  hydropower  developer,  multinational engineering  companies,  IPP  and national  private  groups  (Briscoe,  1998; WB,  2000; WCD, 2001; WWF, 2003; Williams, 2006). As private entities,  it  is difficult to assess 

Page 44: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   44 

where  there  capital  comes  from.  In  this  report,  it  is  assumed  that  their  equity participation  is  based  on  commercial  loans  from  private  banks  and  on  their  own capital. Shareholder’s  return on  investment  is around 15‐20% over 40 years  (WCD, 2001; Tractebel, 2005).   Financing debt On average, debt represents around two thirds of total  investment. The public and private donors provide  sources  for  financing debt.  Funds are  raised  in  the  form of direct  loans  to  the  dam  company  and  guarantees  to  commercial  financiers. Most hydropower projects are not feasible without public funding and guarantee support. MDBs used  to be  the most  important  source of  debt  financing.  To  a minor  extent BDAs also provide debt financing in forms of loans and guarantees. ECAs can finance up  to  30%  of  the  total  project  cost  (Briscoe,  1998; WB,  2000; WCD,  2001; WWF, 2003; Williams, 2006). The participation of private lenders is difficult to assess due to opacity of their financial operations. Debt lenders get a return margin over the cost of capital around 2‐3% over approximately 10 years (WCD, 2001; Tractebel, 2005).    The figure below is a global picture that seeks to map out the financing dynamics and actors involved in a hydropower project. The figure is based on the explanatory case study and on the literature accessed along this research. It is representative to many hydropower projects and can be applied in most cases. However, it does not include particular type of financing (e.g. bonds issues, domestic investment) and leaves out some relationships (e.g commercial loans to sponsors). 

Page 45: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   45 

Figure 9: Schematic representation of the main financial flows after and before dam commissioning and the main contractual arrangements 

 

Page 46: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   46 

5 Analysis and generalization: Influence of financial actors   In  order  to  assess  the  role  of  financial  players  in  a  dam  building  process,  three leverage of influence have been identified based on the trends drawn from the case study: (i) the sources of funds, (ii) the relationships between financial actors and (iii) the weighting of objectives. The following analysis and generalization is based on the facts  and  alternative  explanations  described  in  the  case  study.  The  description  of these  aspects  will  help  to  identify  general  implications  over  hydropower development.   

5.1 Shifting source of funds  Funding sources have changed during the course of dam building history, following macroeconomic dynamics and geopolitical events. Even though the type of financial actors  involved  in  dam  financing  remains  relatively  the  same  (see  4.1.3),  some aspects have changed substantially. Major shifts have occurred since the end of the Cold War and today these trends appear to be reinforced. Four changing aspects of dam financing have been selected: (i) sector, (ii) origins, (iii) scale and (iv) financing mechanisms. They are described hereafter.  Shifting sector Declining  involvement  of  public  institutions  and  the  increasing  role  of  the  private sector seem to be confirmed today. This trend was already identified by the end of the 1990’s (Briscoe, 1998; WCD, 2001; WWF, 2003; Baumüller, 2009).  The role of classic western donors and international financial institutions, such as the World Bank, in funding large infrastructures in developing countries is declining since global  criticisms  increased  during  the  last  decades  of  the  past  century.  There  is  a gradual  shift  from  international  public  donors  to  the  private  sector,  through increasing  establishment  of  Independent  Power  Producer  (IPP)  and  Public‐Private Partnerships  (PPP).  Nonetheless,  the  public  sector  continues  to  have  a  large influence  on  new  hydropower  projects,  either  developed  by  the  public  or  private sector.  With  decreasing  involvement  of  the  public  sector  and  the  difficulty  of financing  a  project  entirely  by  the  private  sector,  the  PPP  seems  an  appropriate alternative  according  to  the  2001  report  of  the  WCD  (WCD,  2001;  WWF,  2003; Middleton, 2011).  Furthermore, commercial banks are becoming key financiers and thus major decision makers.  For  instance,  Thai  commercial  banks  are  increasingly  providing  loans  to support  regional  infrastructure  development.  They  regularly  co‐finance  projects  in collaboration  with  international  dollar  banks 40  and  with  the  support  of  IFIs. Nonetheless, the backing of  international financial actors does not seem absolutely necessary  to  achieve  a  project.  As  described  in  Chapter  3,  Thai  commercial  banks financed  around  one  third  of  NTPC  total  investment  without  IFIs  guarantees.  In 

                                                        40 The international dollar banks are all banks that lend money in the US dollar official currency. This is in contrast with regional banks, such as Thai banks that lend money in Thai Baht. 

Page 47: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   47 

addition, Nam Ngum 2 dam41 has been entirely  financed by  three Thai  commercial banks42. Nam Ngum 2 is a large dam completed in 2010 in Lao PDR. With a US$ 760 million total cost,  it has an  installed power capacity of 615 MW. The details on the financing plan remain obscure. The power company is a holding by Thai construction and  energy  firms  (MRC  DB,  2009;  IR,  2009;  Middleton,  2011).  Finally,  only  four commercial Thai banks are financing the US$3.8 Xayaburi project (Middleton, 2011; Matthews, 2012).  Shifting origins In  the Mekong Basin,  the origins  of  hydropower  financing  are  also  changing,  from traditional international lenders to more regional financiers. Intraregional  investments are rising  in the development of  the Mekong Basin. New regional  financial  players  and  developers  are  emerging  from  riparian  robust economies  such  as  Thailand,  Vietnam  and  China.  The  regional  commercial  banks have  accumulated  capital  and  have  strengthened  their  understanding  of  the hydropower sector and the complex financing mechanisms implicated. More widely, regional  economic powers  such  as Malaysia  or  Russia  also play  a  role  in  providing investments  in  the  Mekong  basin  (IR,  2009;  MRC,  2010c;  Middleton,  2011).  For instance, regional banks from Thailand cofinanced one third of NTPC (see Chapter 3).  Shifting scale Over  the  last  decade,  the  rush  to  install  hydropower  in Mekong waters  has  been astonishing  (see  Table  1  and  Figure  3  and  5).  Lao  PDR  is  maybe  the  best representation of this boom with 22 licensed and 60 planned dams, of which 9 are proposed  on  the  Mekong  mainstream  (Matthews,  2012).  The  GoL  has  agreed  to supply 7,000 MW of hydroelectricity to Thailand by 2015. The first mainstream dam planned  in  the  LMB  is  the  controversial  Xayaburi  dam.  If  built,  this  US$3.8  billion project  will  be  financed  by  Thai  commercial  banks  and  developed  by  a  Thai development  company  (Stone,  2011; Grumbine  et  al.,  2012; Matthew,  2012).  This investment will be almost three times bigger than the current largest investment in Lao PDR, the Nam Theun 2 dam (see Chapter 3).    Shifting financing mechanisms Since  the  gradual  establishment  of  power  sector  reforms,  new  financing  schemes emerged  to  foster  private  sector  investments.  Today,  the  BOOT  type  of  financing structure is widely implemented in the Mekong Basin.  The increasing use of BOOT mechanism is a direct incentive for the creation of IPPs, but  also  for  PPPs.  It  has  changed  the  traditional  financing  scheme  used  in  dam projects where public  funds played a central  role. BOOT mechanisms have allowed private investors to get more involved in dam financing in growing privatized energy markets (Usher, 1997). In addition, MDB’s direct investments have decreased under international  pressures  of  environmental  groups.  However,  they  now  provide  the 

                                                        41 Nam Ngum 2 has been developed in a chaotic development context within the Ngum River Basin. 10%  of  Lao’s  population  live  in  the  area.  The  competition  between  the  hydropower,  mining  and logging business is threatening ecosystems and livelihoods of ten of thousand local people (IR, 2009).  42 Krung Thai Bank, Siam City Bank and Thai Military Bank.  

Page 48: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   48 

essential  guarantees  (such  as  the  World  Bank  Partial  Risk  Guarantee)  to  attract commercial  funds.  They  facilitate  foreign  private  investment  by  providing appropriate political  risk guarantees and credit enhancement mechanisms that can be used to prolong the maturity of debt financing (WB, 2001). As seen in Chapter 3, NTPC was created under a BOOT contract and IFIs provided appropriate guarantees.   

5.2 Relationships between financial actors  Diverse types of relations between financial actors have been detected through this research.  These  relationships  might  have  a  great  influence  on  the  future  of  dam projects. The different relationships are divided in two types: (i) mutual support and (ii) risk allocation.  Mutual support Financial actors have established diverse kinds of  interconnections that enable one or another actor to get involved in the project and make profit out of it. Based on the case study, four types of mutual support between financial actors, but also with the dam industry and the host government, have been identified:  

‐ Official financial institutions involvement attracts commercial lenders In many hydropower projects, the participation of international financial agencies is required.  Their  role  is  generally  to  provide  sufficient  guarantees  and  legitimacy  to project  lenders,  especially  from  the private  sector. Here  intervenes  the  concept of temporality  of  financial  actors  input‐output, which  is  defined  in  this  report  as  the chronological  order of  entry or  exit  of  a  financial  player  that  can  influence others. Usually, private lenders wait until internationally recognized financial institutions get involved  in  the project. This  can be  translated  into equity  investments, guarantees from  MIGA,  partial  risk  guarantees  from  the  World  Bank  or  ECA’s  loans  and guarantees (WCD, 2001; Ward, 2010). This was the case for NTPC.   

‐ International investors have shares in regional banks Major Thai commercial banks have drawn strategic international investors after the Asian financial crisis. These banks raised additional capital from foreign investors to recapitalize  their  assets.  These  same  banks  are  today  important  investors  in hydropower development in the Mekong Basin. For instance, Thai commercial banks have  foreign  holders  that  have  interest  in  dam  development:  GE  Capital International  Holding  Corporation43 has  33%  shares  in  the  Bank  of  Ayudhya,  ING Bank from the Netherlands holds 25% stakes in the Thai Military Bank and the Bank of Nova  Scotia  owns  50% of  the  Thanachart  Bank  (IR,  2009; Middleton,  2011;  see also  3.2).  International  strategic  investors  support  these  banks  to  fortify  their business and  thus help  them  to be  independent  from  traditional western banks  in their hydropower investments44. 

                                                        43 It is a subsidiary of General Electric US.  44 I  assume  that  can  be  a way  for  traditional western  banks  to  bypass  international  environmental commitments.  

Page 49: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   49 

 ‐ BDA and ECA promote the exportation of their national dam industry 

Common  interests  exist  between  bilateral  cooperation  activities  and  private industry. Even though Aid has formally been untied for more than ten years (OECD, 2012a), close relations continue to exist between donor agencies and their national private industries45. For example, French cooperation is keener to invest in countries where  French  industries  are  well  positioned  to  obtain  contracts  (personal communication with French Ministry of Foreign Affairs, 16th of May 2012). It can be considered as “diplomatic externalities” in the name of greater state interests. This is further  explained  in  Chapter  3.  Additional  research  on  the  issues  would  be interesting.  For  instance,  correlations  between  the  board  of  directors  of  both bilateral  cooperation  and  hydropower  companies  were  found  when  exploring hydropower development. Further  research on how actors  in bilateral  cooperation overlap private sector hydropower development may be fruitful in shedding light on the close relations between Aid and private sector interests.  The Theun Hinboun dam illustrates these relations quite clearly. Completed in 1998, it has an installed capacity of 210 MW and has cost US$240 million (MRC DB, 2009). The  Nordic  Development  Bank  provided  a  grant  to  the  project.  This  funding  was certainly  facilitated  because  Norwegian  and  Swedish  state‐owned  utilities  were shareholders  in  the  project  (Usher,  1997;  WB,  2000).  In  the  same  way,  French cooperation and dam industry actively participated  in the completion of NTPC (see Chapter 3).  Logically, ECAs support their national dam industry, as it is their central purpose.   

‐ Host governments encourage foreign investments In the Mekong Basin, the race to develop hydropower is the most observable in Lao PDR.  The  GoL  attracts  international  involvement  through  important  investment incentives:  reasonable  tax  holidays,  government  taxes  and  other  impost  waived, withholding tax on net profit repatriated to home countries waived, special rates of import  duty  for  materials,  equipment  and  supplies,  foreign  contractors/labor accepted, concession period of 25‐30 years or even offshore bank account permitted (Powering  Progress,  2012).  The  latter  is  quite  stunning.  These  incentives  raise  a dilemma between the need to attract investors and the loss of  legitimate revenues by selling off natural resources.   Risk allocation  The  identification  and mitigation  of  risks  are  essential  for  structuring  a  successful project‐financing  plan.  From  a  donor  perspective,  risk  can  be  classified  in  three categories  depending on  the  stage of  the project:  development  risks,  construction risks  and  operating  risks.  Usually,  the  highest  risk  for  a  project  is  during  the construction phase. The nature of the risks is different for every project and for each participant  (developers may have different  concerns  than  lenders  for  instance). At every stage, different types of risks can interfere with the project. Hereafter is a non‐exhaustive list of potential risks: commercial (delay and cost overruns usually related                                                         45 Untied  aid  releases  the  country  that  receives  international  aid  from  the  obligation  to  purchase goods and services from the country that supplies the aid.  

Page 50: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   50 

to  environmental  and  resettlement  issues),  political  (expropriation,  laws,  force majeure),  hydrological  (sufficient  water),  environmental  (compliance  with standards),  social  (local/  international  opposition),  regulatory  (legality,  licenses, permits  and  concession)  and  reputational  risks.  Financiers  generally  establish contingency  plans  for  overcoming  risks  (Palmieri,  2010;  Kasikornbank,  2010; PROPARCO, 2010).   Risks  are  borne  by  all  project  participants  in  different  proportion.  Before  the introduction  of  private  sector  incentive  mechanisms  (such  as  BOOT),  the  public sector used to assume most of the risks. With the establishment of PPP and IPP, risks are spread between the public and private partners. These risks are shared between the project participants through a set of legal documents (WCD, 2001). As project finance is highly weighted with debt ‐ usually accounting for 70 to 80% of total financing ‐ commercial lenders are the driving forces in risk mitigation. In many cases,  equity  providers  negotiate  contracts with  the  governments,  but when  debt lenders  enter  in,  they  insist  to  change  terms  of  contracts  that  imply  that  the government  or  the  power  company  must  take  higher  risks.  The  reason  is  that sponsors  get  high  returns  on  their  investment  (around  15‐20%)  whereas  private lenders obtain a small margin (around 2‐3%) over the cost of capital (WCD, 2001). As debt providers’ participation is usually imperative, commercial lenders have a great bargaining  power  to  influence  the  provision  of  contracts  and  therefore  the hydropower project itself.   

5.3 Weighting of objectives   Every  financial  stakeholder  shares  a  set  of  objectives,  with  a  favourite preponderance  function of  their own  interests. During the  financing set‐up  (before financial  closure),  power  relations  and  negotiations  between  financial  actors determine the general  financing configuration of the project. Different  instruments and  conditionality  are  employed  to  reach  these  goals.  The  overall  financing arrangement  for  a  dam  project  reflects  a  mixed  of  these  different  objectives. Depending  on  the  composition  of  this  “recipe”,  the  final  outcomes  of  each hydropower project will be affected (a project might be purely commercial, or more “equitable”  if  it has equal weighting between objectives)  (personal communication with French Ministry of Foreign Affairs, 16th of May 2012).  

5.3.1 Political objectives  Political objectives concern essentially the bilateral and multilateral donors and their relation  with  recipient  countries.  Two  main  components  have  been  identified:  (i) reinforcement of political  relations and  (ii)  loan conditionality on  recipient  country policy reforms. On the on hand, bilateral and multilateral donors seek to enhance political relations with recipient countries. It is not an officially claimed objective. It can be considered as  aid  externality.  In  the  case  of  bilateral  agencies,  grant  or  loan  attribution may 

Page 51: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   51 

strengthen the relations between the donor country and the recipient country. This can lead to a better economic cooperation, for instance.  On  the  other  hand,  international  public  donors  attach  broad  governance conditionality  to  loan  allocation.  This  is  explained  by  the  necessity  of  a  strong enabling  environment  for  investment  with  stable  political  and  macroeconomic conditions and solid  legal and governance  institutions  (Agostino, 2008; Kilby, 2009; Delina, 2011). For instance, investors can condition their aid to the improvement of accountability and transparency mechanisms, to the recognition of human rights or to the reform of the public sector (Temple, 2010). Power sector lending policies have been  promoting  structural  reforms  and  encouraging  private  sector  involvement (WCD,  2001).  The  World  Bank  has  put  considerable  efforts  in  developing  energy market opportunities in its recipient countries (Strickland et al., 1998). For instance, in  the  case  of  NTPC,  IFIs  conditioned  their  loans  to  social  and  environmental principles (see Chapter 3).   

5.3.2 Economic objectives  Any  investment  has  intrinsically  an  economic  component,  mostly  in  terms  of profitability.  All  financial  actors  involved  in  hydropower  projects  share  common economic  objectives,  which  are  to  maximize  profitability  and  to  minimize  risk. Profitability depends on the general competitiveness of hydropower. Volatility of gas and oil prices has made hydropower more economically competitive.  In addition, a predicted increase in dry season flows as a consequence of the Lancang dam cascade make  hydropower  in  the  lower mainstream Mekong more  attractive  for  investors (Lee,  2009;  PROPARCO,  2010).  The  potential  energy  market  is  based  on  the prediction  of  rising  energy  demand  in  the  region.  Minimization  of  risk  is  also  a determining factor in evaluating expected economic returns. Risks are usually shared among  different  actors  (see  5.2).  Economic  objectives  take  different  forms depending on the type of financial actors involved.  The MDBs  economic  objectives  have  influenced  hydropower  projects  by  favouring large supply projects over small‐scale alternative projects. The World Bank has been focusing on supply‐side investments in the power sector. The main reason explaining the supply side bias  in the bank’s policy  is the economic argument:  if prices reflect actual costs, the market will function efficiently. The pressure to lend is also a factor for  applying  a  supply‐side  policy.  The  Bank  seeks  to  develop  large  projects where they can lend substantial amounts of money, without consuming too much staff time in managing smaller projects (IR, 2012). As a consequence, the World Bank tries to avoid  demand‐side  or  energy  efficiency  projects.  In  addition,  the  Bank  imposed  a minimum economic internal rate of return (around 10%) to any project financed by the Bank at the expense of the quality of a project. The main objective of the World Bank  is  to  develop  a  project  for  financing,  not  really  to  solve  a  problem.  These economic policies prevent the creation of alternative development solutions (Usher, 1997; Strickland et al, 1998; IR, 2012).  

Page 52: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   52 

A correlation between  the presence of  foreign companies  in  recipient  country and bilateral aid allocation is likely to exist, though it is not totally official. With the end of  the dam era  in  the North during  the second half of  the 20th century, developed countries started to export their technology to the South. Bilateral aid has supported dam  industry  exportation  in  developing  countries,  formerly  through  subsidies  and currently  via  loans  to  the  project  company.  It  has  helped  these  companies  to  find new  market  opportunities  by  creating  competitive  advantage  in  international tenders (Usher, 1997). Even though aid untying has been officially implemented for more  than  ten  years  now,  BDAs  still  display  bias  in  favour  of  projects where  their national industry has good opportunities to win contracts (personal communication with French Ministry of Foreign Affairs, 16th of May 2012). For instance, the French cooperation agency (AFD) and the main electric multinational company contributed actively in NTPC.  ECAs main  activity  is  to  support  the  exportation  of  goods  and  equipment  through loans  and  guarantees.  Their  official main  objective  is  to  facilitate  and  insure  long‐term  infrastructure  investment. For example, COFACE, EKN and GIEK have covered private dollar international lenders in the NTPC project.   Private  lenders  have  reacted  intensely  to  the  new  opportunities  in  power infrastructures. Even after a decline  in private  investment following the 1997 Asian Crisis,  private  hydropower  investments  are  continuing  their  rising  trend  (Briscoe, 1998; WCD, 2001). Investors, especially private lenders and sponsors, seek to get the highest margin possible. In that sense they can influence the terms of contracts. The more  investor  participation  is  necessary  for  the  realization  of  a  project,  the more bargaining power these  investors will have to orientate the project  legal document in  their  favour.  For  instance  in  NTPC,  a  borrowing  plan  was  incorporated  to  the financial plan in order to set up the level of interest rate (see Chapter 3).  

5.3.3 Normative and Instrumental objectives  Normative  objectives  play  a  significant,  rhetorical  role  in  legitimizing  the construction of hydropower plants. Generally, they can be related to concepts such as  sustainable  development  and  economic  growth.  Specifically,  they  encompass notions  of  environmental  protection  and  poverty  alleviation.  These  normative objectives  are  typically  translated  into  instrumental  objectives.  For  instance, environmental protection related to a dam  is addressed through an Environmental Impact  Assessment  and  poverty  reduction  is  addressed  through  social  programs. Dam proponents commonly emphasize the normative benefits for local communities and the necessity to mitigate social and environmental impacts.    The  main  objectives  of  bilateral  and  multilateral  banks  are  to  promote  economic growth  and  poverty  reduction  by  funding  projects  through  loans  and  grants, providing  policy  advice  in  developing  countries,  and  financing  the  private  sector through  debt,  equity  and  guarantee  on  behalf  of  the  international  community (Temple, 2010; Delina, 2011). IFIs face a dilemma providing large dams as a mean to alleviate poverty. Actually, these projects aid the rich at the detriment of the poor. 

Page 53: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   53 

IFIs  promote  dams  as  a  solution  to  improve  rural  electrification  for  instance. However,  the  power  produced  usually  goes  to  urban  or  industrial  centres  (Usher, 1997; IR, 2012). Other financial actors such as ECAs and private lenders increasingly point out  their desire to  improve their  financing activities. Sustainable hydropower financing is rising through the implementation of internal policies and guidelines (see section 5.3.4).  To reach the normative objectives promoted by dam proponents, different types of instruments  are  used  to  assess,  evaluate  and  monitor  the  potential  social  and environmental  impacts  related  to  the  construction  of  a  dam.  This  usually materializes  in  safeguard  documents  such  as  Environmental  Impact  Assessment, Sustainable  Impact Assessment and Resettlement Programs. These documents aim at  planning  mitigation  measures  to  compensate  impacts  on  the  livelihoods  of affected communities, biodiversity or erosion  for  instance  (WCD, 2001; ADB, 2002; Hirsch, 2010; MRC, 2010a).   Donors usually finance EIA and other safeguard documents. There is a trend of pro‐dam EIA made by biased consultants. Consultancy firms are hired by donor to realize impact assessment of a proposed dam project, making the firms much more likely to provide an EIA that reflects positively for the donors who funded the study. They are not accountable to the public and thus evolve  into a grey zone between the public and  private  sector.  These  impact  assessments  are  based  documents  for  financial actors to decide whether or not to finance such a project (Usher, 1997; IR, 2012).     The adoption of WCD recommendations may increase the up‐front costs, but it can reduce  the project’s  risks.  Therefore  the project may be better  accepted and  so  it will be easier  to  finance (WCD, 2000). Thus, sustainable  financing can be seen as a mean to legitimize hydropower development.   Others  normative  objectives  refer  to  issues  of  accountability,  corruption  (Hillman, 2004), public participation or human rights (Doig et al., 2005; Furuoka, 2005). These concerns are not further developed in this report.   

5.3.4 Internal objectives  In  this  report,  internal  objectives  consist  of  the  improvement  of  financial  actor financing  policies  and  the  implications  for  hydropower  development.  Obviously, donors  have  other  types  of  internal  objectives,  but  they  are  not  covered  in  this report. Over the past twenty years,  financial players have enhanced their desire to finance sustainable dam projects (UNEP‐DDP, 2004).   Internal  review  processes  have  been  reinforced  in  large  traditional  financial institutions. For instance in the 1990’s, the World Bank introduced new policies and guidelines  for  improving  sustainable  development  practices  and  addressing  social issues. The WB has assigned an external Inspection Panel to be sure that WB’s staff comply  with  the  bank’s  policies  and  procedures.  Nonetheless,  performance  gaps between  policy  guidelines  and  program  implementation  remain  an  issue.  For 

Page 54: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   54 

example,  the  WB  imposed  a  “green  conditionality”  on  loans  related  to  Narmada Sardar  Sarovar  dam  project.  The  Indian  government  preferred  to  reject  the remaining World Bank loans as they felt their sovereignty threatened (Kardam, 1993; WCD, 2001).   ECAs social and environmental guidelines are diverse and their application remains irregular. Nonetheless, the Export Credit Group46 from the OECD has the mandate to develop  common  guiding  principles  to  address  resettlement  and  environmental problems (WCD, 2001).   The private sector  is  increasingly concerned with the necessity to apply sustainable policies in financing dams. Many commercial banks have committed to international standards  such  as  Equator  Principles,  HSAF  Protocol,  UNPRI,  WCD  standards,  IFC Performance Standards, WB safeguard policies (Oxfam, 2010). Many regional private banks  are  also  gradually  establishing  Corporate  Social  Responsibility  (CSR)  and Corporate Governance policies as guidelines for their financing activities.  The  Equator  Principles  were  established  in  2004  by  an  international  group  of financial  institutions. They  include a  set of  rules and guidelines  that  support banks identifying  and  managing  a  collective  and  reliable  assessment  of  social  and environmental  concerns  across  industries  and  regions.  These  principles  are  in  line with  similar policies  from the ADB,  the EIB and OECD ECA. 67  financial  institutions have adopted the Equator Principles, which commit  them to abandon a  loan  if  the borrower cannot comply with these principles. Using such standards, members can reduce their exposure to reputational risks and get greater access to finance projects (IR, 2009; ANZ, 2010; Allen & Overy, 2010). International commercial banks such as HSBC, ING or Bank of Nova Scotia have agreed with Equator Principles. But still they bypass  international  sustainable  financing  agreements  by  investing  in  important regional commercial banks, which afterwards  invest  in dams. For  instance,  ING  is a strategic investor in Thai Military Bank, which was involved in Nam Ngum and NTPC financing (Middleton, 2011; see Chapter 3).  Regional commercial banks such as Thai banks are increasingly keen to invest in dam building in the Mekong Basin. However, they are gradually perceiving the necessity to  apply  sustainable  policies  to  avoid  dam  project  abandonment  due  to  rising criticism. CSR can  represent a  first  step  toward better  financing practices. CSR  is  a business  model  that  contributes  to  the  social  and  economic  development  of stakeholders (ANZ, 2010). Although Thai commercial banks refer more and more to CSR  in  their  reports,  they  still  need  to  implement  thorough  reforms  in  that  sense. Sustainable banking can be a mean to minimize risk and thus create new investment opportunities (Middleton, 2011). Social or environmental risk can become a financial risk. For  instance,  serious  impact on  the environment must be cleaned up and can compromise future project opportunities. It can also affect the reputation of a bank. Reputational risk is a rising concern for banks.   

                                                        46 The  full  title  of  this  group  is  « Working  Party  on  Export  Credit  and  Credit  Guarantees »  (OECD, 2012b). 

Page 55: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   55 

Even  though  financial  actors  tend  to  improve  their  financing  policy,  there  are  a numbers of contradictions to international commitments.   

5.4 Implication for hydropower development   This  section  seeks  to  analyse  the  linkages  between  the  leverage  of  influence described  previously  and  the  actual  consequences  on  hydropower  development. This  investigation  does  not  pretend  to  depict  all  implications;  rather  it  gives directions for further research. This investigation presents the following findings.   Financial actors have an influence on diverse aspects of a hydropower project. Three concepts have been identified for this study: (i) the feasibility, (ii) the quality and (iii) the performance.  The  feasibility of  a project determines whether  a project  can be achieved  economically,  technically  and  environmentally.  The  quality  of  a hydropower  project  is  defined  by  the  least  possible  impacts  on  local  communities and  environment.  The  performance  of  the  project  encompasses  technical  and financial attainment. The variance of  these outputs can be determined at different stages of the project cycle: (i) negotiation, (ii) planning and design, (iii) construction and  operation  and  (iv) monitoring  and  reporting.  Several  dynamics  allow  financial actors to drive a project in one direction or another. These are (i) the availability of capital,  (ii)  the weighting of  objectives  and  (iii)  the bargaining power by  clustering and advising.   Financial  actors  can  influence  the  feasibility  of  a  project  by  overestimating commercial  benefit  of  large  dams.  They  usually  praise  hydropower  as  a  clean  and cheap  energy without  considering  costs  related  to  siltation47 (especially  in  tropical countries)  and  decommissioning.  Above  all,  the  high  cost  of  dramatic  ecosystem changes  is  repeatedly  underestimated.  Expected  energy  demand  is  also  often overestimated  (Usher,  1997).  By  ignoring  or  underestimating  the  costs,  financial actors can reduce long‐term commercial risks. Furthermore, as private actors have a shorter  perspective  than  recipient  governments,  they matter  less  about  long‐term financial efficiency of a project  (WCD, 2001). The financial viability of a project can also  be  biased  as  specialized  banks  advise  the  power  company  for  setting  up  the financing  plan.  The  study  of  the  NTPC  case  described  these  aspects  (costs underestimation, benefits overestimation and biased financial viability) (see 3.3.).  Financial  and  technical  performance  is  optimized  to  insure  highest  returns  with minimum risks. For instance, financiers can influence the choice of the construction company  to  avoid possible  problems during  the  construction.  They  logically  prefer that experienced firms carry out civil work to minimize this risk. Public equity tenders might be biased.  IFIs  can  still  influence  the  social  and  environmental  quality  by  imposing mitigation and  compensation  requirements  (see  3.2).  Nonetheless,  their  role  in  hydropower                                                         47 Siltation  is  the  phenomenon  by  which  a  dam  reservoir  fills  up  with  silt  and  loses  production capacity.   

Page 56: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   56 

financing seems to have decreased. Commercial banks have the ability to  influence clients to comply with sustainability objectives as they play a central role in financing transactions  (ANZ,  2010).  Therefore,  they  can  also  ignore  sustainable  policy compliance.  

 Along  the  project  cycle,  financial  actors  use  diverse  leverage  of  influence.  During negotiations,  limited  cost‐benefit  analysis  (purely  economic,  without  considering social and environmental costs) promotes and justifies the choice of one option over other  alternatives.  In  addition,  international  banks  advise  financing  scheme  (ANZ, 2010)  and  public  benefits  are  usually  overestimated,  while  public  costs  are  often underestimated.  During  the  planning  and  design  stage,  feasibility  studies  and safeguard  documents  can  be  biased  as  they  are  commissioned  and  financed  by proponents and investors of the project. Terms of key contractual arrangements (CA, PPA, HCC, SA) may be adjusted in favour of the financiers. For instance, to maximize their  returns,  financial  players  tend  to  influence  release  rights  in  the  Concession Agreement in order to optimize hydroelectricity production and make higher profits (see  3.2.)  ‐  even  though  this  can  result  in  intolerable  and  hazardous  cycles  of downstream  flows  (WCD,  2001).  During  the  construction  and  operation  phases, financial actors may control the level of impact mitigation as they advise the power company  financing  scheme.  During  monitoring  and  reporting,  financial  actors  can achieve the overall evaluation of the project. It is in their own interests to prove the viability of their model in order to promote future similar development. For instance, NTPC  received  six  awards  of  best  finance  deal  (see  Chapter  3).  At  the  end  of  the concession, BOOT mechanisms  raise questions about  the  financial  capacity of host countries to bear the costs of equipment replacement or siltation (WB, 2000).   As  described,  financial  actors  play  a  significant  role  in  hydropower  development. They  exert  different  types  of  influence  at  diverse  levels  of  a  project.  Due  to  large opacity  of  hydropower  financing,  these  dynamics  are  not  simple  to  discern. However, they  indubitably have major  implications for the course of a hydropower project.  The  final  subsequent  section  presents  the  conclusions  and recommendations drawn from this investigation.                

Page 57: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   57 

6 Conclusion and recommendations   This thesis sought to analyse the role of financial actors in hydropower development. The main objectives were to map out the financial actors and dynamics, to identify leverage  of  influence  and  to  characterize  how  hydropower  investments  translate into claims over the landscape.    To  a  limited  extend,  this  investigation  enabled  an  understanding  of  the  dynamics behind hydropower financing and the analysis of the leverages of influence exerted by financial actors. The main findings of this report are summarized hereafter:  

⇒ Capital accumulation needs spatial fix Large dams require substantial investments. While large capital reserves need to be invested  in  physic  assets.  Large  hydropower  projects  represent  suitable infrastructures to fill the appetite of commercial lenders (Sinha, 2007b). Additionally, the  source  of  funds  is  changing  and  tends  to  scale‐up  and  speed‐up  hydropower development  within  a  path  dependency.  As  a  result,  large  dams  close  doors  to alternative energy sources (Smits, 2010) and remain destructive for the environment and  local  communities.  Therefore,  whether  devaluation  is  to  be  avoided,  means must  be  found  to  absorb  the  surplus  capital.  This  can  be  achieved  in  various manners.  The  most  relevant  for  this  research  is  “the  making  use  of  pre‐existing hitherto  untapped  markets  or  the  creation  of  new  markets”  (Ahlers,  2005:236).  Hydropower infrastructure investment is one of such spatial fix.   ⇒ Electrification as an externality 

The  normative  and  instrumental  objectives  in  terms  of  poverty  alleviation  and environmental protection are negligible compared to the overall economic purpose of  a  large  dam.  Although  electricity  poverty  is  a  central  argument  of  large  dam proponents  (WB,  2009a;  IHA,  2011),  the main  goals  of  governments  and  financial actors  are  to  create  foreign  currency  for  the  recipient  country  and  supply  the regional  power  demands  of  urban  or  industrial  centres  (Usher,  1997;  IR,  2012). Financiers  overestimate  public  benefits  to  promote  dam  building.  Except  local mitigation impacts usually assumed by the power company, the revenues earned by the  host  government  should  provide  national  spill  over  benefits  (IR,  2012).  The ethical  argument of  “electricity  for  the poor” made by dam proponents  to explain the  renewed  interest  in  hydropower  (WB,  2009a;  IHA,  2011)  is  misleading.  Other demand‐side  alternatives  exist  and  work  efficiently.  Local  communities  would  be better  served  by  investments  in  cheaper  and  cleaner  off‐grid  technologies  (Smits, 2010;  IR,  2012).  In  many  rural  areas  in  Lao  PDR  and  Cambodia,  micro  hydro  and photovoltaic represent a least‐cost strategy for rural electrification (Probe, 2004). 

 ⇒ Principle of sustainability legitimize hydropower 

Sustainable hydropower financing is increasingly a central concern for investors. Best financing  practices  apparently  aim  at  improving  the  quality  of  a  project.  The adoption of WCD recommendations may increase the up‐front costs, but it can also reduce  financial  and  reputational  risks  for  investors.  As  the  project may  be  better accepted, it will be easier to finance (WCD, 2000). As a lead dams specialist from the 

Page 58: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   58 

World  Bank  explained  at  a  MRC  conference,  a  well‐prepared  project  with appropriate  risk  management,  stakeholder  involvement,  attention  to  socio‐environmental concerns and competent developers firms will find finance (Palmieri, 2010). Therefore,  if financiers adopt more ethical standards, while setting up trivial compensation measures, they may have more opportunity to invest in large projects. Sustainable hydropower  financing  is a double‐edged sword: higher quality projects will be better accepted and thus financed, while large dams have inevitable adverse impacts. This point raises the question of the definition of sustainability.  ⇒ Threatened sovereignty over natural resources 

Recipient countries with weak regulations and institutions may lose the control over their  landscape48.  Also  power  sector  deregulation  transferred  resources’  control from  public  to  private  donors,  whose  commercial  priorities  tend  to  prefer  certain form of energy production (WB, 2000), e.g. large dams. First, hydropower loans are generally  conditioned  by  national  policy  reforms  (for  instance,  expenditure management  policy  for  NTPC).  Then,  the  sovereignty  of  the  host  country may  be threatened by foreign direct  investment and the type of financing mechanism used which  might  not  respect  national  laws  (Usher,  1997).  Hydropower  owners  have extensive rights, but also obligations, reflected in the CA. For instance they can be in charge  of  the  full  water  management  of  the  basin  (see  Chapter  3).  By  giving concession to private companies, recipient countries can lose the actual control over their  natural  resources.  It  is  a  disguised  type  of  neoliberal  colonization  translated into water grabbing (Kay, 2012). In other words, the capitalist rationale, that argues that  resources would be better  allocated by market  forces,  rather  than wasted by incompetent public sector (Ahlers, 2010), also dispossesses communities of essential river  water  services.  We  assist  to  a  rapid  transformation  of  landscape  through  a intense  capitalist  accumulation  by  dispossession  and  enclosure  of water  resources (Ahlers,  2010).  Finally,  host  countries  even  reduce  their  sovereign  rights  with incentive measures to encourage foreign investment in their country. In that sense, they  indirectly  sell  off  their  natural  resources  to  investors  through  hydropower investments.  In 2001, the WCD recommended host governments to keep control over the project set‐ups to guarantee the projects return economic benefits to the country coherent with acceptability at the local level (WCD, 2001).   A set of secondary conclusions is recapitulated as follows:  

Reputational objective in terms of scale and complexity  The  notion  of  financial  reputation  may  have  great  consequences  over  the  future development of large‐scale projects. In that sense, financial actors do not based their financing activities on the quality of the energy product, but instead on the financial product.  They  promote  the  success  of  dealing  with  extensive  and  complex investment,  involving  great  numbers  of  investors.  Thus,  they  learn  lessons  to overcome  development  obstacles  that  can  consequently  be  used  in  similar  large‐

                                                        48 In the Mekong basin, this is applicable to Lao PDR and Cambodia (and maybe Myanmar).  

Page 59: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   59 

scale project in the region. They sell their expertise. Money may be made primarily through the financial transaction and power generation may even be secondary.   

Obscurity in hydropower financing Details  on  financing  arrangements  are  unclear  (IR,  2009).  For  instance,  borrowing plans  and  concession  arrangements  for NTPC  are  not  transparent  (see Chapter  3). The approval of large dam projects can be so ambiguous that even policy‐makers are not  sure  of  the  limits  of  the  arrangements  (Usher,  1997).  Without  doubt, hydropower financing is nebulous. This investigation has experienced countless data accessibility  deadlocks,  such  as  interest  rate  dynamics,  conditionality  over expenditure management,  private  loan  and  sponsor  equity  funding  arrangements. Details  on  financing  schemes  and  relationships  between  dam  proponents  are difficult to excavate due to this lack of public information, despite substantial capital involved  and  the  huge  temporal  and  scalar  dimensions  of  these  projects.  For instance in the case study excavation, specified data on the Concession Agreements (e.g.  extensive  water  rights,  obligations  of  host  country),  private  loans  conditions (e.g. evolution of interest rates), level of competitiveness (e.g. contract awarding not fully transparent), sponsors’ involvement (e.g. origins of funds and conditionality) or untied aid  (e.g.  relations with French aid agency and French dam  industry) are not fully accessible.   

Private sector involvement decreases public accountability  Since  the  1990’s,  worldwide  private  sector  investments  in  infrastructure  building have substantially  increased  (WCD, 2001; ADB, 2002). With an  important  financing capacity and ability to raise capital rapidly, private actors tend to play a determining role  in  hydropower  development.  For  instance,  they  usually  advise  the  power company  on  how  to  set  up  a  financing  scheme  and  thus  determine  the  financial feasibility  of  a  project  and  the  level  of  their  interest  rates.  Increasing  investment from the private sector decreases the level of accountability and transparency in the financing  process.  Also  with  complicated  financial  schemes  such  as  NTPC,  it  is difficult  to  understand  exactly  what  happens.  Under  the  BOOT  system,  it  is more difficult  to  monitor  social  and  environmental  impacts  because  foreign  private investors have neither a mandate to reduce poverty nor public institutions to which they are officially accountable (Usher, 1997). Therefore, private sector  involvement does not enhance the accountability or the quality of a project.   

IFIs are gradually changing role Multilateral and bilateral financial institutions are no longer in the driver’s seat, even though they still remain essential as catalysts for drawing in as well as covering other investors. On the one hand, IFIs have gradually reduced their direct participation in dam building. They now facilitate other investors. On the other hand, the emergence of  new  sources  of  funding  has  disrupted  the  traditional  hydropower  financing approach of the 20th century. For instance in financing NTPC, Thai commercial banks’ direct  loans  accounted  for  one  third  of  the  project’s  total  costs  without  financial guarantees.  Powerful  regional  investors  are  increasingly  involved  in  hydropower projects with no need of the conventional support of the  international community. 

Page 60: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   60 

The  forthcoming  hydropower  development  will  confirm  the  accuracy  of  this outcome.   Globally, this research has gathered and collated a large quantity of information that gives  a  global  picture  of  hydropower  financing  processes.  It  has  raised  number  of critical questions that would need further excavation. Policy recommendations and scientific research proposals are given hereafter:  Policy recommendations 

‐ Feasibility  studies  and  Safeguard  documents  should  be  in  charge  of  host government and Include all costs; 

‐ All  public  deals  should  be  fully  transparent  (e.g.  concession,  public  tender) and Improve accountability of private sector by setting stricter rules; 

‐ Governments  should  foster  the  implementation  of  small‐scale  off‐grid alternatives by providing incentives to attract new forms of investment;  

Scientific research recommendations ‐ Decision‐making legitimacy of hydropower PPP/IPP;  ‐ Implication of extensive water rights and national sovereignty;  ‐ Feasibility and effectiveness of demand‐side alternative solutions;  ‐ Extent of public capital managed by private sector; ‐ Link between water grabbing and land grabbing.  

  

To conclude, a new  large‐dam era  is  rising,  in which  financiers are decisive players motivated  by  their  necessity  to  find  untapped  market  prospects.  Following  an improper model of development, benefits remain in few hands while dramatic costs are  borne  by  the  public.  The  poorest  people  are  subsidizing  the  lifestyle  of  the richest.  If  completed,  future  large  dams  will  damage  substantially  biophysical systems affecting livelihoods of millions of people.                  

Page 61: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   61 

Bibliography  

ADB  (2002):  “Volume  II:  Regional  issues  and  emerging  trends:  environmental,  socio‐economic and institutional”. Stockholm Environment Institute.  

ADB  (2005):  “Report and  recommendation of  the president  to  the board of directors on a proposed loan to the Lao People’s Democratic Republic for the Greater Mekong Subregion: Nam  Theun  2  hydroelectric  project”.  Retrieved,  5th  May  2012, http://www2.adb.org/Documents/RRPs/LAO/rrp‐lao‐37734.pdf.  

ADB  (2012):  “Greater  Mekong  Subregion”.  Website  consulted  the  13th  May,  2012,  on http://www.adb.org/countries/gms/main  

Agostino,  M.  (2008):  “World  Bank  Conditional  Loans  and  Private  Investment  in  Recipient Countries”. World Development Vol. 36, No. 10, pp. 1692–1708.  

Ahlers  R.  (2005):  “Stickiness  of  territory  and  fluidity  of  water:  entitlement  structures  to water  in  the  age  of  contemporary  globalisation.  The  case  of  neo‐liberal  water  reforms  in Mexico.” PhD Dissertation, Cornell University, Ithaca. 

Ahlers, R.  (2010): “Fixing and nixing: The politics of water privatization”. Review of Radical Political Economics 42(2), pp. 213 –230. 

Ahlers, R.  (2011): “Temples of modernity:  the technological  fix of  the 20th century”. Paper presented at the Association for American Geographers Annual Meeting, April 14‐16 2011, Seattle, Washington. 

ANZ  (2010):  “Sustainable planning and  financing  ‐ The Equator Principles”. Presentation at the MRC Summit 2010 by the Australian and New Zealand Banking group Ltd. Retrieved, 6th Juy,  2012,  from  http://www.mrcsummit2010.org/Presentations/3‐2_Ian‐Mathews‐equator‐principles.pdf.  

ASEAN  (2010):  “Overview”.  Retrieved,  13th  May  2012,  from http://www.aseansec.org/about_ASEAN.html.  

Baghel, R. and Nüsser, M. (2010): “Discussing large dams in Asia after the World Commission on Dams:  Is a political ecology approach  the way  forward?”. Water Alternatives,  3  (2), pp. 231‐48. 

Baird,  I.  G.  (2011):  “Turning  land  into  capital,  turning  people  into  labour:  primitive accumulation and  the arrival of  large‐scale economic  land  concessions  in  the  Lao People’s Democratic Republic”. New Proposals: Journal of Marxism and Interdisciplinary Inquiry, Vol. 5, No. 1 (November 2011), pp. 10‐26. 

Bakker, K. (1999): “The politics of hydropower: developing the Mekong”. Political Geography 18 (1999), pp. 209‐232. 

Barnett, A. (1992): “The financing of electric power projects in developing countries”. Energy Policy April 1992, pp. 326‐334.  

Page 62: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   62 

Baumüller,  H.  (2009):  “Sustainable  development  impacts  of  investment  incentives  in Southeast Asia”.  International  Institute  for Sustainable Development  (IISD). Retrieved  from http://www.iisd.org/tkn/pdf/competing_business_southeast_asia.pdf.  

Bosshard,  P.  (2010):  “The  dam  industry,  the  World  Commission  on  Dams  and  the  HSAF process”. Water Alternatives 3(2), pp. 58‐70.  

Briscoe,  J.  (1998): “The financing of hydropower,  irrigation and water supply  infrastructure in  developing  countries”.  A  background  paper  for  the  UN  Commission  on  Sustainable Development.  Retrieved,  19th  April  2012,  from http://siteresources.worldbank.org/INTWRD/926910‐1112690201445/20434194/TheFinancingofHydroPowerforUNCommission.pdf.  

Callender,  T.  (2007):  “Environmental  Impacts  of  Trade  Liberalization  in  the  Hydropower, Mining and Construction Materials  Sectors of  the  Lao PDR”. Rapid  trade and environment assessment.  IUCN  Lao  PDR.  Retrieved,  20th  April  2012,  from http://www.iisd.org/pdf/2008/rtea_lao_hydro_mining_construction.pdf.  

CA  (2009):  “Nam  Theun  2  hydroelectric  project  ‐  Summary  of  the  concession  agreement between  the  government  of  the  Lao  PDR  and  Nam  Theun  2  power  company  limited”. Retrieved,  20th  June  2012,  from http://siteresources.worldbank.org/INTLAOPRD/Resources/2935821092106399982/492430‐1092106479653/SummaryofCA.pdf.   

Cucherousset,  H.  (1927):  “Les  Forces  hydrauliques  de  la  Nam  Theune  (Laos)”.  L’Eveil Economique de  l’Indochine, Dimanche 1er Mai 1927, Numéro 516, pp. 1‐2. Retrieved, 10th May 2012, from http://gallica.bnf.fr/ark:/12148/bpt6k5561716f/f9.image.r=sauvage  

Cullather, N. (2002): “Damming Afghanistan: Modernization in a Buffer State”. The Journal of American History, Vol. 89, No. 2, History and September 11: A Special Issue (Sep., 2002), pp. 512‐537.  

Delina, L., L. (2011): “Asian development Bank’s support for clean energy”. Climate Policy 11, pp. 1350‐1366.  

Doig,  A.  and  Marquette,  H.  (2005):  “Corruption  and  democratisation:  the  litmus  test  of international donor agency intentions?”. Futures 37, pp. 199–213.  

Dreher,  A.  (2006):    “IMF  and  Economic  Growth:  The  Effects  of  Programs,  Loans,  and Compliance with Conditionality”. World Development Vol. 34, No. 5, pp. 769–788. 

ECA (2009): “The potential of regional power sector integration ‐ Nam Theun 2 ‐ Generation Case  study”.  Economic  Consulting  Associates.  Retrieved,  10th  June  2012,  from http://www.esmap.org/esmap/sites/esmap.org/files/BN004‐10_REISP CD_Nam%20Theun%202‐Generation.pdf.  

EDF  (2010):  “Rapport  financier  2010”.  Groupe  Electricité  de  France.  Retrieved,  27th  June 2012, from http://www.edf.com/html/RA2010/pdf/EDF2010_fin_full_vf.pdf 

 

Page 63: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   63 

EGCO  (2010):  “Press  released”.  Retrieved,  16th  May  2012,  from http://www.egco.com/en/corperate_com_press_detail.asp?press_id=151&iYear=2010.  

Equator  Principles  (2012):  “Members  and  Reporting”.  Retrieved,  18th  July  2012,  from http://www.equator‐principles.com/index.php/members‐reporting/members‐and‐reporting.  

Furuoka, F. (2005): “Human Rights Conditionality and Aid Allocation: Case Study of Japanese Foreign Aid Policy”. Perspectives on Global Development and Technology, Volume 4, issue 2, pp. 125‐146.  

González, A.  (2003): “La controverse mondiale a propos des grands barrages: d’une réalité hétéropique a la construction d’un espace restraint de representation (la World Commission on Dams)”. Regards Sociologiques, n°25/26. 

Grumbine, R., E. and Xu, J. (2011): “Mekong hydropower development”. Science magazine, 332, pp. 178‐179.  

Grumbine,  R.,  E.,  Dore,  J.  and  Xu,  J.  (2012):  “Mekong  hydropower:  drivers  of  change  and governance challenges”. Frontiers in Ecology and the Environment 2012; 10(2), pp. 91–98.  

Hillman, A., L. (2004): “Corruption and public finance: an IMF perspective”. European Journal of Political Economy Vol. 20, pp. 1067–1077. 

Hirsch,  P.  and  Jensen,  K.,  M.  (2006):  “National  Interests  and  Transboundary  Water Governance in the Mekong”. Australian Mekong resource centre. Retrieved, 18th May 2012, from http://sydney.edu.au/mekong/documents/mekwatgov_mainreport.pdf.  

Hirsch,  P.  (2001):  “Globalisation,  regionalisation  and  local  voices:  the  Asian  Development Bank  and  re‐scaled  politics  of  environment  in  the  Mekong  region”.  Singapore  Journal  of Tropical Geography, 22(3), pp. 237‐251.  

Hirsch, P. (2010): “The changing political dynamics of dam building on the Mekong”. Water Alternatives, 3 (2), pp. 312‐23. 

Ingco, S., P. (1996): “Structural changes in the power sector in Asia – Improving profitability”. Energy Policy, 24(8), pp. 723‐733.  

IEA  (2010):  “Renewable  energy  essentials:  Hydropower”.    International  Energy  Agency. Retrieved,  14th  June,  2012,  from http://www.iea.org/papers/2010/Hydropower_Essentials.pdf  

IEC  (2010):  “A  world  of  opportunity  –  Hydro  energy  around  the  Globe”.  International Electrotechnical  Commission.  Retrieved,  19th  April,  2012,  from http://www.iec.ch/etech/2010/pdf/etech_2010‐12_LR.pdf.  

IHA (2011): “Advancing Sustainable Hydropower”. 2011 Activity Report of the International Hydropower  Association.  Retrieved,  19th  April,  2012,  from http://www.hydropower.org/downloads/ActivityReports/2011‐12_Activity_Report‐web.pdf.  

Page 64: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   64 

IR (2008a): “The new great walls – A guide to China’s overseas dam industry”. International Rivers.  Retrieved,  3rd  April,  2012,  from http://www.internationalrivers.org/files/attached‐files/new_great_walls_report.pdf.  

IR (2008b): “Nam Theun 2 hydropower project: Risky business for Laos”. International Rivers. Retrieved,  10th  April,  2012,  from  http://www.internationalrivers.org/files/attached‐files/ir_nt2_factsheet_june08lowres.pdf.  

IR  (2008c):  “New  financiers  and  the  environment  ‐  Ten  perspectives  on  how  financial institutions  can  protect  the  environment”.  International  Rivers.  Retrieved,  4th  June,  2012, from http://www.banktrack.org/download/new_financiers_and_the_environment/newfinanciers_english.pdf.  

IR  (2012): “Infraestructura para quién? Una critica de  las estrategias de  infraestructura del grupo de los 20 y el Banco Mundial”. International Rivers. Retrieved, 4th August, 2012, from http://www.internationalrivers.org/files/attached‐files/infraestructura_para_quien.pdf.  

Kardam, N. (1993): “Development Approaches and the Role of Policy Advocacy: The Case of the World Bank”. World Development, Vol. 21, No. 11, pp. 1773‐1786.  

Karki, S., K., Mann, M., D. and Salehfar, H. (2005): “Energy and environment  in the ASEAN: challenges and opportunities”. Energy Policy 33, 499‐509. 

Kasikornbank  (2010):  “Risk  assessment  in  hydropower  financing”.  Presentation  at  Centara Grand,  Bangkok,  Thailand,  on  24th  of  September  2010.  Retrieved,  7th  July,  2012,  from http://wwf.panda.org/what_we_do/where_we_work/greatermekong/our_solutions/hydropower_roads/sustainable_hydropower_financing/  

Kay,  S.  and  Franco,  J.  (2012):  “The  global  water  grab  –  a  primer”.  Transnational  Institute (TNI),  The  Netherlands.  Retrieved,  4th  April,  2012,  from  http://www.tni.org/primer/global‐water‐grab‐primer.  

Kilby,  C.  (2009):  “The  political  economy  of  conditionality:  An  empirical  analysis  of  World Bank loan disbursements”. Journal of Development Economics 89, pp. 51–61. 

Krongkaew, M.  (2004):  “The  development  of  the  Greater Mekong  Sub‐region  (GMS):  real promise or false hope?”. Journal of Asian Economics 15, 977‐998.  

Krungsri  (2012):  “Investor  Relations  ‐  Major  shareholders  structure”.  Retrieved,  4th  July, 2012, from http://www.krungsri.com/en/investor‐relation.aspx?cid=44.  

Lee, G. and Scurrah, N.  (2009):  “Power and  responsibility  ‐  The Mekong River Commission and  Lower Mekong mainstream dams”.  A  joint  report  of  the Australian Mekong Resource Centre,  University  of  Sydney  and  Oxfam  Australia.  Retrieved  from http://sydney.edu.au/mekong/documents/power_and_responsibility_fullreport_2009.pdf  

Li, Z., He, D. and Feng, Y. (2011): “Regional hydropolitics of the transboundary impacts of the Lancang cascade dams”. Water International, 36:3, 328‐339. 

Page 65: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   65 

Liebman, A.  (2005): “Trickle‐down hegemony? China’s “Peaceful  rise” and dam building on the Mekong”. Contemporary Southeast Asia 27, no. 2, 281‐304.  

Makim, A. (2002): “The Changing Face of Mekong Resource Politics in the Post‐Cold War Era: re‐negotiating  arrangements  for  water  resource management  in  the  Lower Mekong  River Basin (1991‐1995)”. Working Paper No. 6, Australian Mekong Resource Centre University of Sydney. 

Matthews,  N.  (2012):  “An  analysis  of  the  winners  and  losers  of  Thailand’s  hydropower development in Lao PDR”. Water Alternatives, Vol.5, Issue 2, pp. 392‐411 . 

Mehtonen, K. (2008): “Do the downstream countries oppose the upstream dams?”. Kummu, M., Keskinen, M. & Varis, O. (eds.): Modern Myths of the Mekong, pp. 161‐173.  

Middleton,  C.  (2011):  “Regional  banks,  regional  investments  and  regional  responsibilities: Strengths,  shortcomings  and  trends  of  Thai  commercial  banks’  corporate  governance  and CSR  policies”.  Presentation  at  “Know  your  power”  MEE  Net  Conference,  Thursday  19th January  2011.  Retrieved,  5th  July,  2012,  from http://www.meenet.org/images/power/81329728151_file.pdf.  

MIGA  (2006):  “Hydropower  in  Asia:  the  Nam  Theun  2  project”.  Multilateral  Investment Guarantee  Agency.  Retrieved,  4th  May,  2012,  from  http://www.miga.org/documents/NT206.pdf.  

Mills,  A.,  J.,  Durepos,  G.  and  Wiebe,  E.  (2010):  “Encyclopedia  of  case  study  research”. Thousand Oaks (CA): SAGE Publications. 

Morgera,  E.  (2011):  “Mekong  River”. Max  Plank  Encyclopedia  of  Public  International  Law. Retrieved, 5th April, 2012, from www.mpepil.com. 

MRC  (1995):  “Agreement  on  the  cooperation  for  the  sustainable  development  of  the Mekong  River  Basin  5  April  1995”.  Retrieved,  20th  May,  2012,  from http://ns1.mrcmekong.org/agreement_95/agreement_95.htm.  

MRC  (2003):  “Biodiversity and  fisheries  in  the Mekong River Basin”. Mekong development Series  n°  2.  Retrieved,  2nd  June,  2012,  from http://www.mrcmekong.org/assets/Publications/report‐management‐develop/Mek‐Dev‐No2‐Mek‐River‐Biodiversityfiisheries‐in.pdf.  

MRC  (2010a):  “State  of  the  basin  report  2010”.  Retrieved,  5th  April,  2012,  from http://www.mrcmekong.org/assets/Publications/basin‐reports/MRC‐SOB‐report‐2010full‐report.pdf.  

MRC  (2010b):  “Strategic  environmental  assessment  of  hydropower  on  the  Mekong mainstream  –  Summary  of  the  final  report”.  Retrieved,  5th  April,  2012,  from http://www.mrcmekong.org/assets/Publications/Consultations/SEA‐Hydropower/SEA‐FR‐summary‐13oct.pdf.  

MRC (2010c): “Overview of hydropower development in the Mekong”. Presentation by Haas, L. J. M., MRC Initiative on Sustainable Hydropower at SPLASH meeting, 14‐15 August 2010, 

Page 66: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   66 

Vientiane,  Lao  PDR.  Retrieved  from  http://www.splash‐era.net/downloads/mekong_workshop/Pres02_Haas_Hydropower_Status.pdf.  

Nüsser,  M.  (2003):  “Political  ecology  of  large  dams:  a  critical  review”.  Petermanns GeographischeMitteilungen, 147, pp. 20‐27. 

OECD  (2012a):  “Untying  Aid:  the  right  to  choose”.  Retrieved,  the  20th  July  2012,  from http://www.oecd.org/dac/untyingaidtherighttochoose.htm#definition.  

OECD (2012b): “Working Party on Export Credit and Credit Guarantees”. Retrieved, the 20th July 2012,  http://www.escr‐net.org/docs/i/427906.  

Palmieri,  A.  (2010):  “Water  infrastructure  risk  management”.  Presentation  at  Sustainable hydropower financing in the Mekong River Basin, 23‐24 of September 2010, by a lead dams specialist  from  the  World  Bank.  Retrieved,  14th  July,  2012,  from http://wwf.panda.org/what_we_do/where_we_work/greatermekong/our_solutions/hydropower_roads/sustainable_hydropower_financing/.  

Powering  Progress  (2012):  “Legislation  and  Financial  incentives”.  Retrieved,  6th  July,  2012, http://www.poweringprogress.com/index.php?option=com_content&view=article&id=51&Itemid=54.%20Consulted%20the%2013th%20of%20June,%202012.  

Probe  International  (2004): “Ten reasons why the World Bank should not  finance the Nam Theun  2  power  company  in  Lao  PDR”  by  Ryder,  G.  Retrieved,  17th  April,  2012,  from http://journal.probeinternational.org/?s=Ten+reasons+why+the+World+Bank+should+not+finance+the+Nam+Theun+2+power+company+in+Lao+PDR+  

Proparco  (2010):  “Promoting  Sustainable  Private  Sector  Development  ‐  Financing  tools presentation”.  Retrieved,  28th  July,  2012,  from http://www.afd.fr/webdav/site/afd/shared/PORTAILS/PAYS/LAOS/Breve%20Seminaire%20Nov%202011/Proparco%20Seminaire%20LaoV2.pdf.  

Proparco  (2012):  “Actionnariat  ‐  Une  plateforme  Nord/Sud  d’investisseurs  pour  le développement”.  Retrieved,  19th  July,  2012,  from http://www.proparco.fr/Accueil_PROPARCO/PROPARCO/Actionnaires.  

Ramamurti,  R.  and  Doh,  J.,  P.  (2004):  “Rethinking  foreign  infrastructure  investment  in developing countries”. Journal of World Business 39, pp. 151–167. 

Sinha,  S.  (2007a):  “Nam  Theun  2  (NT2)  Hydroelectric  Project”.  Prepared  for  the  Indian Institute  of  Management.  Retrieved,  20th  April,  2012,  from http://www.ppiaf.org/sites/ppiaf.org/files/documents/toolkits/Cross‐Border‐Infrastructure‐Toolkit/Cross‐Border%20Compilation%20ver%2029%20Jan%2007/Resources/Sinha%20‐%20Case%20Study%20Nam%20Theun.pdf.  

Sinha,  S.  (2007b):  “Project  finance  Structuring:  Case  study  –  Nam  Theun  2”.  PowerPoint presentation prepared  for  the  Indian  Institute of Management.  Retrieved,  20th April  2012, from www.ppiaf.org.  

Smits, M. and Bush, S., R. (2010): “A light left  in the dark: The practice and politics of pico‐hydropower in the Lao PDR”. Energy Policy 38, pp. 116–127. 

Page 67: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   67 

Sneddon, C. and Fox, C. (2005): “Rethinking transboundary waters: A critical hydropolitics of the Mekong basin”. Political Geography 25, pp. 181‐202.  

Stone,  R.  (2011):  “Mayhem  on  the  Mekong”.  Science  Magazine,  Vol.  333,  pp.  814‐818. Retrieved, 18th April, 2012, from www.sciencemag.org.  

Strickland, C. and Sturm, R. (1998): “Energy efficiency in World Bank power sector policy and lending New opportunities”. Energy Policy, Vol. 26, No. 11, pp. 873—883. 

Swyngedouw,  E.  (2007):  “Technonatural  revolutions:  the  scalar  politics  of  Franco’s  hydro‐social dream for Spain, 1939‐1975”. Transactions of the Institute of British Geographers, NS 32, pp. 9‐28. 

Temple,  J.,  R., W.  (2010):  “Aid  and Conditionality”. Handbook of Development  Economics, Volume 5, pp. 4415‐4523.  

TMB  (2012):  “Share  information  ‐  Major  shareholders”.  Retrieved,  19th  July  2012,  from http://www.tmbbank.com/ir/share‐info/major‐shareholders‐en.php.  

Tractebel (2005): “Financing hydropower development in emerging power markets ‐ Lessons of experience of Brazil”. The World Bank Group ‐ Energy lecture series 2005, Jan, 24th 2005. Retrieved,  19th  June,  2012,  from http://www.globalclearinghouse.org/infradev/assets%5C10/documents/Tractebel%20(Baehr,%20Biebuyck)%20%20Financing%20Hydropower%20Development%20in%20Emerging%20Power%20Markets_Lessons%20from%20Brazil%20(2005).pdf.  

UNEP,  Snidvongs,  A.  and  S‐K.  Teng  (2006): Mekong  River,  GIWA  Regional  assessment  55. University of Kalmar, Kalmar, Sweden. 

UNEP‐DDP  (2004):  “Financing  dams  and  sustainable  development  –  Proceedings  and submissions”. Issue‐based Workshop no. 3, London, UK. 

Usher,  A.  D.  (1997):  “Dams  as  aid:  a  political  anatomy  of  Nordic  development  thinking.” London: Routledge. 

Vaidyanathan, G. (2011): “Remaking the Mekong”. Nature, 20th October 2011, Vol. 478, pp. 305‐307.  

Ward, M (2010): “The main report of the private sector investment project”. Retrieved, 2nd  July,  2012,  from http://www.gtriplec.co.nz/assets/Uploads/papers/psi_final_of_main_report_full_version_31_may.pdf.  

Williams,  J.,  H.  and  Ghanadan,  R.  (2006):  “Electricity  reform  in  developing  and  transition countries: A reappraisal”. Energy 31, pp. 815–844. 

World  Bank,  Head,  C.  (2000):  “Financing  of  private  hydropower  projects”.  Energy Mining Network,  Washington  DC.  Retrieved,  5th  April,  2012,  from http://www.chrishead.co.uk/pdfs/3‐Financing‐of‐Private‐HydropowerProjects.pdf.  

Page 68: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   68 

World  Bank  (2005):  “Project  finance  and  guarantees  –  IDA  guarantees  paves  renewed interest in private hydropower – the Nam Theun 2 Project”. Retrieved, 4th April, 2012, from http://siteresources.worldbank.org/INTGUARANTEES/Resources/Lao_NamTheun2_Note.pdf 

World  Bank  (2009a):  “Directions  in  hydropower”.  Retrieved,  27th  June,  2012,  from http://siteresources.worldbank.org/INTWAT/Resources/Directions_in_Hydropower_FINAL.pdf.  

World  Bank  (2009b):  “Directions  in  hydropower:  scaling  up  for  development”.  Water Working  Note,  n°  21,  June  2009.  Retrieved,  27th  June,  2012,  from  http://www‐wds.worldbank.org/external/default/WDSContentServer/WDSP/IB/2009/06/22/000333038_20090622001502/Rendered/PDF/490170NWP0Box31directionshydropower.pdf  

World  Bank  (2010):  “Overview”.  Retrieved,  7th  April,  2012,  from http://siteresources.worldbank.org/INTLAOPRD/Resources/293582‐1092106399982/492430‐1092106479653/nt2_projectbrief_09‐23‐10.pdf.  

World  Commission  on  Dams  (2000):  “Dams  and  Development  –  A  new  framework  for decision‐making”. The report of the WCD. Earthscan Publications Ltd, London and Sterling.   

World Commission on Dams (2001): “Trends in the financing of water and energy resources projects”.  Thematic  Review,  Economic  and  Financial  Issues  III.2.  Retrieved,  6th  April,  2012, fromhttp://www2.wii.gov.in/eianew/eia/dams%20and%20development/kbase/thematic/tr32main.pdf.  

WWF (2003): “Policies and practices in financing large dams”. Research paper II prepared for WWF  International  Living  Waters  Programme.  Retrieved,  4th  April,  2012,  from www.profundo.nl/files/download/WWF0304.pdf.   

WWF  (2010):  Link  to  the  conference  presentations  Retrieved,  14th  July,  2012,  from http://wwf.panda.org/what_we_do/where_we_work/greatermekong/our_solutions/hydropower_roads/sustainable_hydropower_financing/.  

Yu, X. (2002): “Regional cooperation and energy development in the Greater Mekong Sub‐region”. Energy Policy 31, pp. 1221‐1234.                 

Page 69: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   69 

Appendixes • Appendix I: Boundaries of the Mekong River Basin (UNEP, 2006) 

  

Page 70: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   70 

• Appendix II: Greater Mekong Sub‐region Economic Corridors49  

                                                          49 Source  from http://www.amchamvietnam.com/1621, consulted 19th of May, 2012.  

Page 71: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   71 

• Appendix III: Main changes in the power utilities of MRB riparian’s countries ‐ Thailand ‐ There are three state‐owned power agencies: the Electricity Generating 

Authority  of  Thailand  (EGAT)  established  in  1969,  the  Metropolitan  Electricity Administration (MEA) and the Provincial Electricity Authority (PEA). The EGAT is in charge  of  the  majority  of  electricity  supply.  The  MEA  is  in  charge  for  the distribution in Bangkok and the PEA for the rest of the country. The main changes with  the  reform  are  the  promotion  of  independent  power  producers  (IPP)  in  a competitive  energy market  (with  the  IPP  Law  in  1996)  and  easier  access  to  the transmission  system  (Williams,  2006).  The  EGAT  remained  the  main  authority with  the  responsibility  for  hydropower  production  and  transmission  and  for national and international power purchases. The MEA and the PEA have also been restructured, notably  in smaller subsidiary companies. The Government planned to split policy from regulatory functions. 

‐ Vietnam – Electricity of Vietnam  (EVN) was created  in 1995.  It  is a  state‐owned entity  in  charge  of  all  electricity  services  in  the  country.  It  regulates  three  old, fully‐integrated  electricity  utilities.  Since  2004,  the  Vietnamese  government  has started a process of partial distribution facility privatization (IR, 2008b). 

‐ Lao PDR – Electricité du Lao (EDL) was created in 1961 (1959 on EDL website!!). It is  a  state‐owned  utility  in  charge  of  national  power  supply.  Due  to  insufficient power  infrastructure,  its  supply  is  limited  to  the  capital  Vientiane  and  main provincial municipalities.  The  utility  facilitates  and  coordinates  transmission  for IPP projects. EDL was planning to create a separate company specialized in power export projects,  in particular  to Thailand and Vietnam.  In 2005,  the Lao Holding State  Enterprise  was  established  to  hold  part  of  IPP  project.  In  addition,  the government has adopted legislation to enhance BOT and BOO projects.  

‐ Cambodia – Electricité du Cambodge (EDC) was created in 195850 as a state entity. It is responsible for national electricity supply (although limited to the capital city and  the  main  provincial  towns).  Since  the  end  of  the  1990s,  IPPs  have  been encouraged  to  get  involved  in  power  generation.  In  2001,  the  government established  a  separate  body  in  charge  of  regulating  generation  and  supply facilities: the Electricity Authority of Cambodia (EAC).  

‐ Myanmar – Myanmar Electric Power Enterprise (MEPE) was created in 198951 as a state  entity.  It was  a  fully  integrated power utility  for  the whole  country.  Since 1994, the government has encouraged private investments by taking over existing facilities  or  by  investing  in  greenfield  projects  under  BOT  or  joint  venture agreements.  

‐ Yunnan Province – The Yunnan Provincial Power Corporation (YPEPC) is in charge of all electricity services in the province. The Provincial Government holds it. As in other parts of China,  the Yunnan province has unlocked  its power sector  to use foreign  capital  and  technology  through  the  establishment  of  joint  ventures  and partnerships mechanisms. 

                                                        50 Consulted, the 24th of May, on http://www.edc.com.kh/about.html  51 Consulted, the 28th of May, on http://www.eac.gov.kh/index.php.  

Page 72: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

• Appendix IV: Existing, under construction, licensed and planned dam in the Lower Mekong basin (adapted from the MRC DB, 2009)  

Project Name 

Commission Year 

Ref  Year 

Construction 

Period 

Condition Code 

Purpose Code  Province  Country  Installed 

Capacity Dam Height 

Live Storage 

Budget  (US$ 

million) 

Persons 

Resettled 

X_UTM  Y_UTM 

Nam Pung  1965  1965  1.80  EG  PARFC  Sakon Nakhon  Thailand  6.30  41.00  0.16  4.40  391049  1876352 Ubol Ratana  1966  1960  2.70  EG  PARFC  Khon Kaen  Thailand  25.20  35.10  1.70  17.42  247321  1855420 Xelabam  1969  1968  2.00  EG  P  Champasak  Lao PDR  5.00  3.70  0.80  2.00  0  598517  1689753 Nam Dong  1970  1970  1.00  EG  P  Luangprabang  Lao PDR  1.00  10.00  0.01  0.35  0  196250  2194403 Nam Ngum 1  1971  1971  3.00  EG  P  Vientiane  Lao PDR  148.70  75.00  4,700.00  97.00  240971  2050802 Sirindhorn  1971  1966  3.40  EG  PARFC  Ubon Ratchathani  Thailand  36.00  42.00  1.13  13.60  545091  1680985 Chulabhorn  1972  1969  2.80  EG  PARFC  Chaiyaphum  Thailand  40.00  70.00  0.14  14.60  141996  1831085 Huai Kum  1982  1978  4.00  EG  PARF  Chaiyaphum  Thailand  1.18  35.60  0.02  7.28  157490  1816184 Dray Hlinh 1  1990  1990  3.00  EG  P  Dak Lak  Viet Nam  12.00  7.00  1.50  0.00  815988  1403385 O Chum 2  1992  1993  3.00  EG  P  Ratana Kiri  Cambodia  1.00  10.00  0.12  3.60  712152  1525754 Xeset 1  1994  1990  3.00  EG  P  Saravane  Lao PDR  45.00  18.00  0.30  51.00  0  642177  1742990 Pak Mun  1994  1994  4.40  EG  PARF  Ubon Ratchathani  Thailand  136.00  17.00  0.13  248.08  2000  550440  1690214 Nam Ko  1996  1996  2.00  EG  P  Oudomxay  Lao PDR  1.50  6.00  0.00  6.70  0  199081  2301087 Theun‐Hinboun  1998  1994  4.00  EM  P  Borikhamxay  Lao PDR  210.00  27.00  15.00  240.00  0  453188  2018984 Houayho  1999  1993  4.00  EM  P  Attapeu  Lao PDR  150.00  76.50  649.00  166.00  0  678784  1647357 Nam Leuk  2000  2000  4.00  EG  P  Vientiane  Lao PDR  60.00  46.50  228.20  84.50  0  287487  2037096 Lam Ta Khong P.S.  2001  1994  5.80  EG  P  Nakhon Rachasima  Thailand  500.00  40.30  0.29  613.60  128247  1639777 Yali  2001  1992  7.00  EG  PAFN  Gia Lai  Viet Nam  720.00  71.00  779.02  456.12  8475  800970  1574365 Nam Ngay  2002  2000  2.00  EG  P  Phongsaly  Lao PDR  1.20  26.93  0.67  9.00  0  207913  2413272 Nam Mang 3  2004  2004  4.00  EG  PA  Vientiane  Lao PDR  40.00  28.00  45.00  63.00  1200  267483  2030962 Se San 3  2006  2003  5.00  EG  P  Gia Lai  Viet Nam  260.00  69.50  3.80  236.32  0  790936  1573571 Se San 3A  2007  2003  4.00  EM  P  Gia Lai  Viet Nam  96.00  35.00  4.00  101.34  607  786216  1561278 Dray Hlinh 2  2007  2003  3.00  EM  P  Dak Lak  Viet Nam  16.00  7.00  1.50  16.57  153  815988  1403385 Plei Krong  2008  2003  5.00  EG  PAF  Kon Tum  Viet Nam  100.00  71.00  948.00  178.77  5851  808070  1594998 Se San 4A  2008  2005  2.00  EG  P  Gia Lai  Viet Nam  0.00  31.50  7.50  14.00  0  766031  1541933 

Page 73: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   73 

Nam Theun 2  2009  2002  5.00  CM ‐‐> E  PA  Khammuane  Lao PDR  1,075.00  45.00  3,378.40  1,250.00  5500  494867  1990103 Xekaman 3  2009  2004  4.00  CM ‐‐> E  P  Sekong  Lao PDR  250.00  99.00  108.54  266.00  0  750291  1708110 Xeset 2  2009  2005  4.00  CG ‐‐> E  P  Saravane  Lao PDR  76.00  26.00  9.30  135.00  0  636051  1708688 Se San 4  2009  2004  5.00  CG ‐‐> E  PFA  Gia Lai  Viet Nam  360.00  74.13  264.16  335.76  0  769635  1545660 Buon Tua Srah  2009  2004  4.00  CG ‐‐> E  PAF  Dak Lak  Viet Nam  86.00  83.00  522.60  135.96  2215  831096  1360187 Buon Kuop  2009  2003  5.00  CG ‐‐> E  PAF  Dak Lak  Viet Nam  280.00  34.00  14.74  299.88  96  818133  1386524 Sre Pok 3  2009  2005  4.00  CG ‐‐> E  PF  Dak Lak  Viet Nam  220.00  52.50  62.58  266.89  899  810242  1411871 Sre Pok 4  2009  2005  3.00  CI ‐‐> E  P  Dak Lak  Viet Nam  70.00  25.00  10.11  49.44  354  801321  1424936 Sre Pok 4A  2009  2009  5.00  CG ‐‐> E  P  Dak Lak  Viet Nam  64.00  0.10  105.82  859472  1427862 Nam Ngum 2  2010  2005  5.00  CM ‐‐> E  P  Vientiane  Lao PDR  615.00  181.00  2,994.00  760.00  5759  265206  2075154 Nam Lik 2  2010  2005  4.00  CM ‐‐> E  P  Vientiane  Lao PDR  100.00  101.40  826.00  149.00  0  196112  2080852 Nam Ngum 5  2011  2005  4.00  CM  P  Luangprabang  Lao PDR  120.00  104.50  251.00  196.50  994  249766  2142163 Xekaman 1  2011  2007  4.00  CM  P  Attapeu  Lao PDR  290.00  110.00  1,683.00  343.60  1094  730948  1655582 Xekaman‐Sanxay  2011  2007  4.00  CM  PAR  Attapeu  Lao PDR  32.00  28.00  0.00  39.80  0  727564  1647618 Upper Kontum  2011  2008  4.00  LM  P  Kon Tum  Viet Nam  250.00  73.00  122.70  327.82  1363  848214  1629069 Theun‐Hinboun expansion  2012  2007  4.00  LM  P  Borikhamxay  Lao PDR  222.00  27.00  15.00  185.00  0  453188  2018984 Theun‐Hinboun exp. (NG8)  2012  2007  4.00  LM  P  Borikhamxay  Lao PDR  60.00  67.00  2,262.00  163.00  0  461120  2021271 Xe Kong 3up  2012  2007  3.00  PP  PAR  Sekong  Lao PDR  144.60  41.50  95.09  168.27  1080  690508  1700928 Xe Kong 3d  2012  2007  3.00  PP  PAR  Sekong  Lao PDR  91.10  25.90  168.38  112.90  240  705804  1611734 Nam Tha 1  2013  2007  4.00  LM  P  Bokeo  Lao PDR  168.00  93.65  675.50  333.62  8249  70336  2244561 Nam Long  2013  2007  2.50  LM  P  Luangnamtha  Lao PDR  5.00  12.00  0.13  11.87  0  74732  2319984 Xepian‐Xenamnoy  2013  2007  5.00  LM  P  Attapeu  Lao PDR  390.00  75.00  885.00  607.13  800  672158  1661999 Xe Katam  2013  2006  2.50  LM  P  Champasak  Lao PDR  60.80  41.40  115.00  120.24  0  675367  1672841 Don sahong  2013  2007  4.00  LM  P  Champasak  Lao PDR  360.00  10.60  115.00  673.30  66  603648  1543250 Nam Ou 1  2013  2007  3.00  LM  P  Luangprabang  Lao PDR  180.00  65.00  10.00  247.11  3080  217672  2227927 Nam Ou 3  2013  2007  4.00  LM  P  Luangprabang  Lao PDR  300.00  72.00  13.50  330.21  560  256774  2292709 Nam Ou 5  2013  2007  3.00  LM  P  Phongsaly  Lao PDR  108.00  55.00  11.20  175.37  910  224515  2371738 Nam Ngum 3  2014  2006  5.00  LM  P  Vientiane  Lao PDR  440.00  220.00  979.00  684.70  523  276369  2111554 Nam Theun1  2014  2007  4.00  LM  P  Borikhamxay  Lao PDR  523.00  177.00  2,549.20  816.00  6844  409606  2030017 Xekong 4  2014  2007  6.00  LM  PC  Sekong  Lao PDR  300.00  169.00  3,100.00  815.40  4458  691304  1716150 Nam Kong 1  2014  2007  4.00  LM  P  Attapeu  Lao PDR  75.00  86.90  505.00  159.14  1612  686555  1607769 

Page 74: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   74 

Nam Ou 2  2014  2007  3.00  LM  P  Luangprabang  Lao PDR  90.00  55.00  8.40  145.43  700  233512  2256507 Nam Ou 4  2014  2007  3.00  LM  P  Phongsaly  Lao PDR  75.00  47.00  9.20  105.64  630  238715  2339225 Nam Ou 6  2014  2007  3.75  LM  P  Phongsaly  Lao PDR  210.00  108.00  363.00  311.99  210  209572  2411148 Nam Lik 1  2014  2007  3.00  LM  P  Vientiane  Lao PDR  54.00  36.50  6.80  96.10  0  223505  2060585 Nam San 3  2014  2008  4.00  LM  P  Xiengkhuang  Lao PDR  48.00  75.00  121.70  152.50  2832  359692  2117342 Nam Beng  2014  2008  3.50  PP  P  Oudomxay  Lao PDR  30.00  37.70  97.90  59.60  104944  2210529 NamNgiep 1  2015  2001  5.00  LM  P  Borikhamxay  Lao PDR  260.00  151.00  1,191.80  366.20  1609  343657  2062533 Nam Ngiep‐regulating dam  2015  2001  3.00  LM  PR  Borikhamxay  Lao PDR  16.80  21.00  4.70  29.70  0  348964  2062613 

Nam Ou 7  2015  2007  4.60  LM  P  Phongsaly  Lao PDR  180.00  147.00  1,134.00  419.74  490  216712  2445277 Nam Feuang 1  2015  2007  3.50  PP  P  Vientiane  Lao PDR  28.00  77.00  30.00  67.20  0  168940  2093777 Nam Feuang 2  2015  2007  3.00  PH  P  Vientiane  Lao PDR  25.00  5.00  65.00  0  178626  2120230 Nam Feuang 3  2015  2007  3.00  PH  P  Vientiane  Lao PDR  20.00  4.80  54.00  0  194173  2131966 Lower Se San2 + Lower Sre Pok 2  2016  2008  6.00  PH  PCF  Stung Treng  Cambodia  480.00  45.00  379.40  773.45  4809  271652  1416151 Xe Kong 5  2016  2007  5.00  PP  P  Sekong  Lao PDR  248.00  213.70  1,355.50  417.00  440  706157  1767309 Nam Pha  2016  2008  5.00  PP  P  Luangnamtha  Lao PDR  147.20  139.10  2,738.00  257.00  480  44775  2310201 Nam suang 1  2016  2008  4.00  PP  P  Luangprabang  Lao PDR  40.00  47.30  87.60  82.50  220154  2219579 Nam Suang 2  2016  2008  5.00  PP  P  Luangprabang  Lao PDR  134.00  145.00  2,014.70  284.30  253265  2229786 Mekong at Pakbeng  2016  2008  5.00  PP  PN  Oudomxay  Lao PDR  1,230.00  62.10  442.40  1,338.90  1670  95886  2202818 

Mekong at Luangprabang  2016  2008  5.00  PP  PN  Luangprabang  Lao PDR  1,410.00  68.00  734.00  1,705.00  6580  203961  2223354 

Mekong at Xayabuly  2016  2008  5.00  PP  PN  Xayabury  Lao PDR  1,260.00  53.00  224.70  1,405.70  1720  164624  2131869 Mekong at Paklay  2016  2008  5.00  PP  PN  Xayabury  Lao PDR  1,320.00  54.50  383.50  1,359.80  1780  132334  2029715 Mekong at Sanakham  2016  2008  5.00  PP  PN  Vientiane  Lao PDR  1,200.00  38.00  106.10  1,194.00  1650  119928  1989035 Nam Nga  2017  2008  4.00  PH  P  Luangprabang  Lao PDR  97.84  4.72  1,565.10  177.30  207876  2245168 Mekong at Sangthong‐Pakchom  2017  2008  5.00  PH  PNA  Vientiane  Lao PDR  1,079.00  55.00  217.23  1,619.06  642  187571  2015292 Mekong at Ban Kum  2017  2008  5.00  PP  PNA  Champasak  Lao PDR  1,872.00  53.00  402.90  2,804.36  1122  562424  1704775 Mekong at Latsua  2018  2008  5.00  PH  PNA  Champasak  Lao PDR  686.00  22.00  530.00  1,200.00  0  565674  1694030 Xe Pon 3  2018  2007  4.00  PH  P  Saravane  Lao PDR  75.00  35.00  368.00  145.70  600  698398  1803788 Xe Kaman 2A  2018  2007  4.00  PH  P  Attapeu  Lao PDR  64.00  63.50  3.70  104.30  0  761536  1683972 Xe Kaman 2B  2018  2007  4.00  PH  P  Attapeu  Lao PDR  100.00  85.00  216.80  158.00  0  762667  1690442 Xe Kaman 4A  2018  2007  4.00  PH  P  Attapeu  Lao PDR  96.00  60.00  16.50  145.00  0  770908  1684909 

Page 75: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   75 

Xe Kaman 4B  2018  2007  4.00  PH  P  Attapeu  Lao PDR  74.00  61.40  21.20  115.70  0  771792  1698512 Dak E Mule  2018  2008  5.00  PH  P  Sekong  Lao PDR  105.00  103.20  154.00  251.00  0  721665  1720974 Nam Khan 2  2018  2007  4.00  PH  P  Luangprabang  Lao PDR  140.00  155.00  528.00  218.50  220377  2178775 Nam Khan 3  2018  2007  4.00  PH  P  Luangprabang  Lao PDR  47.00  90.00  860.50  97.50  3353  268616  2189158 Nam Ngum 4A  2018  2007  4.00  PH  P  Xiengkhuang  Lao PDR  54.00  65.00  332.30  96.11  0  289577  2151654 Nam Ngum 4B  2018  2007  3.50  PH  P  Xiengkhuang  Lao PDR  54.00  25.00  1.70  118.40  0  274131  2148487 Nam Ngum, Lower dam  2018  2008  3.50  PH  PAR  Vientiane   Lao PDR  90.00  17.20  243.00  242.00  0  288794  2005872 Nam Pot  2018  2007  3.00  PH  P  Xiengkhuang  Lao PDR  22.00  30.00  45.10  55.00  0  317227  2116054 Nam Phak  2018  2007  3.00  PH  P  Oudomxay  Lao PDR  5.10  25.00  1.90  26.70  0  190221  2327320 Xe Lanong 2  2018  2007  4.00  PP  P  Saravane  Lao PDR  20.00  65.00  79.20  66.23  0  678874  1773681 Nam Phak  2018  2008  4.00  PP  P  Champasak  Lao PDR  75.00  40.00  34.97  102.00  0  617721  1673557 Houay Lamphan  2018  2007  4.00  PH  P  Champasak  Lao PDR  60.00  55.00  128.20  147.70  600  660379  1698887 Nam Khan 1  2019  2007  4.00  PH  P  Luangprabang  Lao PDR  101.77  64.10  805.00  166.00  214298  2185025 Nam Pay  2019  2008  4.00  PH  P  Vientiane  Lao PDR  62.00  56.70  52.30  76.00  200  263335  2114638 Nam Mang 1  2019  2007  4.00  PH  P  Borikhamxay  Lao PDR  51.00  81.40  551.40  196.40  0  344093  2051340 Nam Pouy  2019  2008  4.00  PH  P  Xayabury  Lao PDR  43.73  102.60  498.60  71.00  0  157605  2099061 Nam Poun  2019  2008  4.00  PH  P  Xayabury  Lao PDR  84.87  76.00  339.00  138.30  126667  2045311 Nam Ngao  2019  2008  3.00  PH  PA  Oudomxay  Lao PDR  20.00  69.00  434.00  53.10  150982  2232492 Nam Chian  2019  2008  4.00  PH  P  Xiengkhuang  Lao PDR  148.00  68.80  8.30  180.00  0  346530  2119292 Nam Hinboun 2  2019  2007  3.00  PH  P  Khammuane  Lao PDR  13.00  33.00  25.60  48.20  0  463880  2004764 Xe Bang Fai  2019  2007  4.00  PH  PR  Khammuane  Lao PDR  107.00  28.00  228.00  600  510207  1906002 Sambor  2020  2005  10.00  PP  PCN  Kratie  Cambodia  3,300.00  35.00  2,000.00  3,940.00  5120  629939  1500324 Nam Ngieu  2020  2008  3.00  PH  P  Xiengkhuang  Lao PDR  30.40  31.20  18.80  42.40  0  348744  2122563 Nam San 3B  2020  2007  3.00  PH  P  Xiengkhuang  Lao PDR  38.00  45.00  11.70  80.90  0  352777  2111463 Nam San 2  2020  2007  3.00  PH  P  Borikhamxay  Lao PDR  60.00  60.00  1,946.40  122.30  2930  374443  2077643 Nam Pok  2020  2007  3.00  PH  P  Phongsaly  Lao PDR  2.60  22.30  5.10  17.20  0  221660  2366770 Nam Hinboun 1  2020  2008  4.00  PH  PR  Khammuane  Lao PDR  45.00  38.00  1,224.00  82.00  1200  447780  1972133 Xe Neua  2020  2008  4.00  PH  P  Khammuane  Lao PDR  60.00  28.00  624.00  144.00  800  595778  1917440 Nam Theun 4  2020  2008  3.00  PH  P  Borikhamxay  Lao PDR  30.00  122.00  806.50  140.00  0  476023  2065224 Nam Mouan  2020  2007  4.00  PH  P  Borikhamxay  Lao PDR  110.00  128.00  1,960.00  274.00  1200  422140  2075018 Xe Bang Hieng 2  2020  2007  3.00  PH  P  Savannakhet  Lao PDR  16.00  55.00  642.90  74.00  2700  638174  1863376 

Page 76: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   76 

Xe Set 3  2020  2007  3.00  PH  P  Saravane  Lao PDR  20.00  12.00  3.54  26.40  0  636671  1703621 Xedon 2  2021  2007  4.00  PH  PA  Saravane  Lao PDR  54.00  46.00  1,743.00  298.00  613849  1737298 Xe Bang Nouan  2021  2007  4.00  PH  P  Savannakhet  Lao PDR  18.00  65.00  1,477.00  88.60  860  601324  1756197 Xe Lanong 1  2021  2007  4.00  PH  P  Savannakhet  Lao PDR  30.00  75.00  373.74  123.40  0  667357  1797995 

Nam Kong 2  2021  2007  4.00  PH  P  Attapeu  Lao PDR  74.00  72.10  139.60  124.50  0  733880  1627388 

Xe Nam Noy 5  2022  2007  3.00  PH  P  Sekong  Lao PDR  20.00  55.00  8.80  52.60  0  678826  1677323 Xe Xou  2022  2007  4.00  PH  P  Attapeu  Lao PDR  63.39  62.10  1,714.00  121.40  733880  1627388 Battambang 1  ? 2005  5.00  PH  PCAF  Battambang  Cambodia  24.00  49.50  1,040.00  56.69  4350  271327  1375582 Battambang 2  ? 2005  4.00  PH  PC  Battambang  Cambodia  22.00  50.00  110.00  72.20  609991  1391481 Stung Treng  ? 1995  8.00  PH  PCN  Stung Treng  Cambodia  980.00  22.00  70.00  2,280.00  9160  602356  1498360 Pursat 1  ? 2007  3.00  PP  PCAF  Pursat  Cambodia  100.00  51.50  690.00  188.25  234  312883  1356846 Pursat 2  ? 1995  3.00  PH  PC  Pursat  Cambodia  10.00  40.00  295.00  59.60  349147  1358482 Lower Se San 3  ? 1995  6.00  PH  PCF  Ratana Kiri  Cambodia  243.00  75.00  3,120.00  704.00  706486  1557981 Prek Liang 1  ? 1995  4.00  PH  P  Ratana Kiri  Cambodia  35.00  90.00  110.00  146.00  742352  1573055 Prek Liang 2  ? 1995  4.00  PH  P  Ratana Kiri  Cambodia  25.00  90.00  180.00  124.00  744072  1580450 Lower Sre Pok 3  ? 1995  6.00  PH  PCF  Ratana Kiri  Cambodia  204.00  50.00  5,310.00  812.00  721546  1481202 Lower Sre Pok 4  ? 1995  6.00  PH  PC  Mondul Kiri  Cambodia  143.00  70.00  2,700.00  504.00  765258  1442862 Stung Sen  ? 1995  4.00  PH  PCA  Preah Vihear  Cambodia  23.00  38.00  2,890.00  80.00  526652  1470529 Duc Xuyen  ? 2002  4.00  P  AFP  Dak Lak  Viet Nam  49.00  88.00  413.41  82.63  755  837025  1344475 

LEGEND Characters in red have been modified from the original table

General / Commission Indicate the actual or expected year of commissioning of the first generating unit of the project

General / Condition Indicate the status of the project with a two letter code as follows: First Letter E existing project under operation C project under construction

Page 77: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   77 

L project not under construction but licensed for development P planned project Second Letter when the first letter is E, C or L. Define ownership as follows: G project owner is government, public electric utility or state company I project owner is independent power producer M project owner is a partnership of government and IPP Second Letter when the first letter is P. Define level of study as follows: H project is at a level of hydroelectric master plan or inventory (cursory study only) P project is at a level of prefeasibility (preliminary investigations, rough drawings) General / Purpose Use a string of letters separated by / to express, in order of priority, the purposes for which the project is conceived: P power production A agriculture / irrigation W water supply to local municipalities or local population C flood control N navigation R recreation F fisheries development Cost / Reference Project Budget

The budget for all engineering, procurement and construction (EPC) activities related to the project. This budget normally does not include a number of items that are listed in the following columns. If included these will be noted in the appropriate columns.

Units: millions of United States dollars at the price reference level

Page 78: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

• Appendix V: Location map of hydropower project in the LMB 

Page 79: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   79 

 • Appendix VI: Nam Theun 2 hydroelectric project overall map (ADB, 2005) 

 

• Appendix VII: Schematic representation of the NT2 power facility (WB, 2010)  

    

Page 80: Turning water into capital: Political ecology of financing ......Turning water into capital: Political ecology of financing hydropower development The influence of financial actors

Vincent Merme ‐ ERM MSc Thesis   80 

• Appendix VIII: Contractual structure of NT2 (MIGA, 2006)                    

   

• Appendix IX: Key informants  

‐ Policy  Officer,  Development  Strategies Department  of  the  French  Ministry  of Foreign Affairs, Paris, France; 

‐ Database Manager, at the Mekong River Commission Secretariat, Information and Knowledge  Management  Program  Technical  Support  Division,  Phnom  Penh, Kingdom of Cambodia; 

‐ Program  Officer,  at  the  Mekong  River  Commission  Secretariat,  Information Management Initiative on Sustainable Hydropower, Vientiane, Lao PDR; 

‐ PhD researcher at University of Sydney, on Energy Transitions in Thailand and the Lao PDR, Sydney, Australia; 

‐ PhD  researcher  at  King’s  College  of  London,  on  the  water  and  energy  nexus focuses on hydropower decision making in the Mekong Basin, London, UK; 

‐ Junior researcher at UNESCO‐IHE and Policy officer at Ministry of Foreign Affairs, Delft, The Netherlands; 

‐ Professor at the UNESCO‐IHE and Lead water Resource Specialist at International Bank for Reconstruction and Development (World Bank), Delft, The Netherlands.