KEY PROJECT REPORT: YAVUZ SULTAN SELIM BRIDGE The 3rd Bosporus Bridge and the Northern Marmara Motorway will improve transport links between Europe and Asia and cut chronic congestion in Istanbul, Turkey’s largest city - Mike Woof reports TURKEY’S landmark bridge W ork is now well underway on the 3rd Bosporus Bridge and the Northern Marmara Motorway, providing a new link for Turkish city Istanbul and the region as a whole. This enormous bridge and highway project is breaking several records for Turkey in terms of scale, as well as setting a number of international records for engineering. The landmark 3rd Bosporus Bridge, or Yavuz Sultan Selim Bridge, forms the centrepiece of the Northern Marmara Motorway project. The construction work is being carried out by the IC Ictas – Astaldi joint venture, which is handling the project under the build-operate-transfer (BOT) model. The project has an investment value of some US$2.5 billion, the highest amount ever secured for a new project since the Turkish Republic was founded, and with financing being supplied by a group of seven banks. The consortium will operate the link for 10 years, two months and 20 days (which includes the construction period) before transferring it to Turkey’s Ministry of Transportation. The project team is itself highly international and combines Turks from local firm ICTAŞ and Italians from contractors Astaldi, with designers from Belgium, France and Switzerland and a South Korean sub-contractor. Around 5,700 people in all are working on the project, with the majority of the workforce being Turkish. The bridge will be a particularly impressive structure and it, as well as the associated highway and tunnel stretches, will be built to the latest world- class construction and safety standards. The combination of a growing population and Turkey’s strong economy has seen vehicle numbers rise in the city, which suffers chronic congestion and frequent traffic jams, particularly at peak travel times. One of the causes of the congestion comes from the flow of traffic across the Bosporus, which divides the city. At peak travel times, traffic intending to cross the two existing bridges backs up into the city’s major arteries, often reducing vehicle speeds to a crawl. The first bridge over the Bosporus was completed in 1973 and within one year of its opening, traffic volumes over the structure had grown by around 200% according to research. The Fatih Sultan Mehmet Bridge (2nd Bridge) opened to traffic in 1988 and since that time, studies show that the volume of vehicles crossing the two bridges has increased enormously When the new bridge is complete it will be the ninth longest suspension bridge in the world www.worldhighways.com - updated content every working day www.worldhighways.com - updated content every working day 20 World Highways JUNE 2014 KEY PROJECT REPORT BEYKOZ B L A C K S E A SİLE CEKMEKÖY MALTEPE İstanbul SARIYER ARNAVUTKÖY BAŞAKŞEHIR ŞİŞLİ Bosporus Bridge (1st Bosporus Bridge, opened 1973) Fatih Sultan Mehmet Bridge (2nd Bosporus Bridge, opened 1988) Yavuz Sultan Selim Bridge (3rd Bosporus Bridge, expected opening date 2015)

Transcript of TURKEY’Slandmark bridge - TABPI · According to Dr Virlogeux, the bridge features several...

KEY PROJECT REPORT: YAVUZ SULTAN SELIM BRIDGE

The 3rd Bosporus Bridge and the Northern Marmara Motorway will improve transport links between Europe and Asia and cut chronic congestion in Istanbul, Turkey’s largest city - Mike Woof reports

TURKEY’Slandmark bridge

Work is now well underway on the 3rd Bosporus Bridge and the Northern Marmara Motorway, providing a new link for Turkish city Istanbul and the region as a whole. This enormous bridge and highway project is breaking several records for Turkey in terms of scale, as well as setting a number of international records for engineering. The landmark 3rd Bosporus Bridge, or Yavuz Sultan Selim Bridge, forms the centrepiece of the Northern Marmara Motorway project.

The construction work is being carried out by the IC Ictas – Astaldi joint venture, which is handling the project under the build-operate-transfer (BOT) model. The project has an investment value of some US$2.5 billion, the highest amount ever secured for a new project since the Turkish Republic was founded, and with financing being supplied by a group of seven banks. The consortium will operate the link for 10 years, two months and 20 days (which includes the construction period) before transferring it to Turkey’s Ministry of Transportation.

The project team is itself highly international and combines Turks from local firm ICTAŞ and Italians from contractors Astaldi, with designers from Belgium, France and Switzerland and a South Korean sub-contractor. Around 5,700 people in all are working on the project, with the majority of the workforce being Turkish. The bridge will be a particularly impressive structure and it, as well as the associated highway and tunnel stretches, will be built to the latest world-class construction and safety standards.

The combination of a growing population and Turkey’s strong economy has seen vehicle numbers rise in the city, which suffers chronic congestion and frequent traffic jams, particularly at peak travel times. One of the causes of the congestion comes from the flow of traffic across the Bosporus, which divides the city. At peak travel times, traffic intending to cross the two existing bridges backs up into the city’s major arteries, often reducing vehicle speeds to a crawl.

The first bridge over the Bosporus was completed in 1973 and within one year of its opening, traffic volumes over the structure had grown by around 200% according to research. The Fatih Sultan Mehmet Bridge (2nd Bridge) opened to traffic in 1988 and since that time, studies show that the volume of vehicles crossing the two bridges has increased enormously

When the new bridge is complete it will be the ninth longest suspension bridge in the world

www.worldhighways.com - updated content every working day www.worldhighways.com - updated content every working day20 World Highways JUNE 2014

KEY PROJECT REPORT

BEYKOZ

B L A C K S E A

SİLE

CEKMEKÖY

MALTEPE

İstanbul

SARIYERARNAVUTKÖY

BAŞAKŞEHIR

ŞİŞLİ

Bosporus Bridge(1st Bosporus Bridge, opened 1973)

Fatih Sultan Mehmet Bridge(2nd Bosporus Bridge, opened 1988)

Yavuz Sultan Selim Bridge(3rd Bosporus Bridge,expected opening date 2015)

KEY PROJECT REPORT

22 World Highways JUNE 2014

by as much as 1,180%. With traffic levels in Istanbul continuing to grow, along with the city’s population, the need for a third crossing has long been recognised and this was initially proposed in the 1990s.

The design challenges facing the bridge planners have been substantial. Linking the Sea of Marmara and the Black Sea, the Bosporus is one of the world’s busiest waterways and shipping is crucial to the economy of Turkey as well as its neighbours. A key point of the design was that the bridge could not impede shipping along the Bosporus.

Turkey does suffer from earthquakes, with Istanbul lying close to the North Anatolian Fault. A Tsunami triggered by an earthquake devastated the city in 1509, killing an estimated 10,000 people while an earthquake in Izmit as recently as 1999 killed around 18,000 people overall, some 1,000 of whom were in in Istanbul’s suburbs. According to seismologists, Istanbul faces a 60% risk of an earthquake measuring 7.6 on the Richter scale by 2030, and as a result, the structure has also been designed so that it will withstand major shocks.

The structural loads the bridge will have to contend with on a daily basis will also be substantial. The rapid expansion of the vehicle population in the Istanbul area and the large volumes of through traffic moving between the European and Asian sides mean that the link will carry enormous numbers of vehicles on its four lanes. This will include a high percentage of heavily laden trucks and as the bridge also carries two rail lines, it will have to contend with carrying the not insubstantial weight of train traffic as well. The rail link on the bridge will be integrated with the Marmaray and Istanbul Subway to link Atatürk Airport, Sabiha Gökçen Airport, and the planned 3rd airport, transporting passengers from Edirne to Izmit.

To meet the many challenges, the bridge has been designed jointly by French structural engineer Dr Michel Virlogeux, arguably the world’s foremost bridge specialist, and Swiss firm T-Engineering. This project is of key importance worldwide due to the engineering advances the bridge represents and Dr Virlogeux has also emphasised that the risk of earthquakes to the area is well understood and that structure is designed to cope with all anticipated shocks.

According to Dr Virlogeux, the bridge features several innovative points, as well as its enormous load capacity. The central main span is 1,408m long, due to the main towers being placed out of the main channel. The bridge uses inclined suspension cables that run from the 59m wide deck to anchorage boxes in the towers and because of the length of the central span, the 322m high towers will be the highest of any suspension bridge worldwide. Once complete, this will be the first suspension bridge in the world to feature multiple lanes for vehicles and twin train tracks that transition onto a single deck.

Part of the design process has involved carrying out wind tests to ensure that the

1. Enormous cuttings have been made for the roadway leading to the bridge 2. The foundations for the towers are substantial due to the enormous loads the bridge will carry 3. Initially construction of the piers was carried out using sliding formwork but when this reached 200m, a climbing form was used instead 4. The new bridge and motorway link lies in an earthquake zone so engineering ensures the structures will cope with major shocks 5. Cranes have played a crucial role in raising components for the bridge into position 6. While much of the workforce on the project is Turkish, there are also engineering staff from Belgium, France, Italy, South Korea and Switzerland working on the project so discussions between team members can be in English as well as Turkish 7. Overhead view of the mobilisation site on the European side

FACTSBRIDGE DETAILS: l 8 lanes of motorway and 2 lanes of railway are going to be located at the same level on the deck. A product of professional engineering and advanced technology, the bridge will be among the important bridges of the world with its aesthetic and technical features.

l The bridge is going to be built by a team most of whom are Turkish engineers.

l Nearly 7,000 people will be employed in the construction phase, with 500 people involved in the operation phase of the bridge respectively. l It will be the widest suspension bridge in the world with a width of 59metres. l It will be the longest spanning suspension bridge in the world that has a rail system on it, with a main span of 1408metres, and the highest suspension bridge in the world, with the highest tower in the world, at a height of more than 322metres.

PROJECT NAME: The 3rd Bosporus Bridge and The Northern Marmara Motorway OPERATOR: IC İçtas – Astaldi Consortium START DATE: 2013 FINISH DATE: 2015 (Targeted)OPERATION PERIOD: 10 years 2 months 20 days (including construction)INVESTMENT COST: 4.5 billion TL SCOPE OF WORK: Construction of the 3rd Bosporus Bridge and nearly 115km of motorway and linking road between Odayeri – Paşaköy

1.

2.

5.

6.

3. 4. 7.

23World HighwaysJUNE 2014

KEY PROJECT REPORT

www.worldhighways.com - updated content every working day World HighwaysJUNE 2014 a.

bridge will perform as expected. The research has involved the use of a scale model as well as computer models of the bridge, with wind resistance testing work carried out at Nantes in France, as well as in Milan, Italy. Dr Virlogeux participated in the tests, which focussed initially on the apron and tower design, using computer modelling to calculate how the bridge would react in extreme wind conditions.

“An 11m long model has been constructed for the bridge which is in effect approximately 2,000m, together with its towers and anchorage. Experiments have been executed on this model. We have checked the wind’s influence on the construction. This is a standard method which is applied on all important and strategic buildings. Not only on this one,” said Roberto Sorge, who is the design manager of the 3rd Bridge and Northern Marmara Motorway Project.

Focussing on different construction stages for the Yavuz Sultan Selim Bridge, a series of tests have been carried out on the scale model and computer models over a 6-7 month period. During this development work the tests have modelled the structure being subjected to a wind speed of 300km/h. It is worth noting that 130km/h was the highest recorded wind speed in the Istanbul area since records began 40 years ago.

Major progress is being achieved on the bridge towers, which are now more than 67% complete. Once the bridge piers reached a height of 200m, the construction method was changed. Up to that point, sliding formwork was used to raise the height of the piers. However, above that height a climbing form is being used as this method makes it easier to fit the anchorage boxes that will secure the cables. Installing the anchorage boxes presents a major task for the engineering team and these components are crucial to the design as they join the inclined suspension cables to the bridge piers. The design of the bridge calls for 176 anchorage boxes in all for the suspension cables and the four bridge piers will each house 44 anchorage boxes.

Ömer Çeri is responsible for the towers on the European side of the bridge and explained that the first of the anchorage boxes had to be installed at a height of 208m. Because of its size, this had to be lifted in two pieces, with one part weighing 33tonnes and the other 28tonnes, and tower cranes have been used to lift all of the anchorage boxes. The towers are expected to be complete by August 2014 while the bridge itself should be ready by 2015.

Motorway connectionThe motorway construction is as important to the overall project as the bridge and also includes a number of challenging aspects with 67 viaducts in all over its 116km length. The project manager for the 37km E-2 section of the Northern Marmara Motorway, İsmail Tüm, said that Istanbul has a strong need for this new route as it will provide a major improvement in transportation for the area in coming years.

1. The Northern Marmara Motorway project is being constructed to world-class standards 2. Once the anchorage boxes are installed on the towers the cables can then be attached 3-4. Elements for the anchorage blocks were brought to the bridge by ship along the Bosporus and then lifted by a mobile crane onto the transporter to be taken to the towers 5. Once complete, the towers will be the highest for any suspension bridge in the world

1.

4.

5.

3.

2.

KEY PROJECT REPORT

24 World Highways JUNE 2014

KEY PROJECT REPORT

www.worldhighways.com - updated content every working day

KEY PROJECT REPORT

KEY PROJECT REPORT

b. World Highways JUNE 2014

The E-2 section of the motorway project includes 24 viaducts, one ecological bridge, two junctions, 50 outlets and 9 underpasses and 17 overpasses. This section lies between Odayeri and the Yavuz Sultan Selim Bridge itself and Tüm said, “Now we are working on the digging and filling.”

He explained that the highway is being constructed to world-class standards, with graduated slopes and curves to cope with vehicle speeds. The earthmoving portion involves raising or lowering the level for the road bed by as much as 20m in some areas, with this stage of the work carrying on until the end of 2014. Around 30% of the E-2 stretch is now complete, with 39% of the excavation and 26% of the fill work as well as 19% of the concrete pours for the viaducts having been carried out.

Tüm said that the first sections of the road’s asphalt surface will be laid after June, “Our aim is to complete 7-8km asphalting in our region within this year. So we will be able to do our work properly to our target and also in time. We have to start with the asphalting, as it can’t be done in the winter season.”

Tüm added that construction work is now being carried out on the viaducts along the E-2 section. The well-proven incremental launching method is being used for many of the viaducts, with a number due for completion shortly. Improving weather conditions are helping to speed construction and, according to Tüm, the target for the end of 2014 is for 70% of the work on the E-2 stretch to have been completed.

Despite the speed of construction Tüm emphasised that the work is being carried out to high quality standards with materials that meet international standards. And testing is being carried out on a regular basis to ensure that the design requirements are being met also.

Tüm commented that the need for the bridge and the associated highway is acute, due to congestion on the two existing bridges. He pointed out that traffic backing up to cross the existing structures can cause queues up to 20km long on either side of the Bosporus at present, leading to delays and further disruptions right across Istanbul.

Significant progress has been achieved on the ÇavuŞbaŞ Viaduct that will provide a link for the project on the Anatolian side. This viaduct measures 400m in length and will have 22 piers. At the time of writing, 66% of the concrete work for the viaduct had been carried out. The foundations were completed first, allowing construction work to commence on the piers, with the highest being 42m high according to the site manager for viaduct V-35, Adnan Gültekin.

Another of the managers for the section, Eran Erdem said, “Around 100 people are working on this viaduct. We are pouring 150m³ of concrete/day.” Erdem added that the structure comprises 350 precast beams, the largest of which are up to 41m long.

The V35 viaduct should be completed by August 2014 and with this complete, the road

1. European side towers 2.Tower cranes play a vital role for raising components into place 3. Anchorage boxes and inside view of the climbing form system 4. Modern construction tools are being used in this project to maximise quality 5. The structure for the bridge is complex in design and construction 6. Lifting work of the anchor boxes 7. Works performed in the approach viaduct construction and towers at the European side 8. The complexity of the construction job means efficient operations are crucial

1.

4. 5.

8.

6.

3.

2.

7.

KEY PROJECT REPORT

www.worldhighways.com - updated content every working day World HighwaysJUNE 2014 e.d. World Highways JUNE 2014

KEY PROJECT REPORTKEY PROJECT REPORT

on the Asian side will be connected from the Deve Geçidi area to the Northern Marmara Highway.

In addition to the bridge itself, another important portion of the new Northern Marmara Highway Project being built is for the Çamlık tunnel sections, on the Asian side of the Bosporus. Once the tunnel sections are complete, they will feature impressive dimensions with a width of 22m. İbrahim Ataöz is site manager for the Çamlık Tunnel. He explained that the new Austrian tunnelling method (NATM) has been used for excavation of the two tunnels, with the northern drive measuring 600m long and the southern, 700m. Extensive exploratory drilling was carried out prior to the excavation work, so as to provide a comprehensive picture of the conditions and to locate any faults. Because of its size, importance has been placed on providing plenty of support for the tunnel and the project team also pays close attention to site safety.

The NATM method calls for removal of material in six separate stages, due to the width of the tunnel. Once the excavation of each stage is carried out, the tunnel wall is given a temporary shotcrete layer to provide support. The first and second stages are excavated in parallel, with the third and fourth stages then used to break through the shotcreted floor and deepen the initial headings, while temporary shotcrete layers are again used on the floor and sides. The fifth stage first breaks through the shotcrete linings to link the area between the

initial headings, and the sixth is for the removal of the material all the way to the floor.

For the tunnel portals and areas where the ground is soft a pipe proofing method is used, using perforated steel pipes that are 152mm in diameter and 9m long. These pipes are installed with an overlap of 4m and are grouted into position. Where the conditions are better, a lattice structure is used once the first layer of shotcrete is applied. The shotcreting process involves installing a layer of wire mesh first, then spraying with shotcrete. This process is repeated with an additional layer of wire mesh, held in place by shotcrete, and rock bolting (with 9m long bolts) provides additional support. Once the primary support is in place, waterproofing with a polyfelt and a PVC membrane is installed and this is then covered with the final permanent concrete lining shell.

Excavation work is also underway for the T2 RIVA tunnels on the Asian side of the Bosporus, with the work progressing simultaneously from both ends. These links will both carry four lanes of traffic, with one measuring 626m long and the other 564m. Although the excavation phase for one tunnel is now finished, the linings still have to be completed, while the electrics and ventilation systems have yet to be installed. Once all this work has been carried out, the twin tunnels should be finished by the second quarter of 2015. n

ICAwww.3kopru.com

KEY PROJECT REPORTKEY PROJECT REPORTKEY PROJECT REPORT

www.worldhighways.com - updated content every working day

Istanbul has long been a cultural melting pot, sandwiched as it is between Europe and Asia and providing a gateway between both continents. Its history is extensive, the area having been settled as far back as Neolithic times, with various other villages following and the city being founded around 660BC. The city came to prominence during Roman times and has been the capital for not just one, but four separate empires: the Roman, Byzantine, Latin and Ottoman, while it was also the world’s largest city during much of the Middle Ages. Originally called Byzantium,

then renamed Constantinople and in following centuries becoming Istanbul, the city was besieged and invaded on several occasions over a period of 2,500 years. Meanwhile its culture and architecture reflects its complex history and its fusion of European, Asian and Middle Eastern religious, artistic and political influences.

When the ailing Ottoman regime was finally replaced by the Turkish Republic in 1922, Turkey’s charismatic new leader, Mustafa Kemal Atatürk, moved the capital to Ankara, in part to develop his vision for a secular nation.

Istanbul’s importance waned initially but from the 1940s and 1950s, it started regaining its economic role within Turkey, due much to its strategic location. The city’s population began to grow significantly once more in the 1970s and this process has continued ever since. In 1975 Istanbul’s population was around 2.5 million but estimates for the number of residents now put the figure at some 14 million, qualifying it as a megacity. Although Ankara remains Turkey’s seat of government, Istanbul is the commercial centre for the country and accounts for

around 25% of the nation’s gross domestic product.

The growth rate continues, with the city’s urban sprawl spreading as a result. Just how Istanbul’s infrastructure will cope with the population growth in the area is a cause for some debate within Turkey and the need for further investment in public transport links is as acute as for the bridge and motorway. New metro and bus routes are being built along with new housing but Istanbul’s fast expansion continues to place heavy burdens on existing facilities.

Bridging history

KEY PROJECT REPORT

2.

1.

3.

4. 5.

6.

7.

1-3. Artist impressions of the Northern Marmara Highway 4-6. When complete the bridge will be impressive both visually and aesthetically 7. Artist impression of the Çamlık tunnel section, on the Asian side of the Bosporus

Bridge designer Dr Michel Virlogeux’s impressive CV includes other structures such as the Vasco da Gama Bridge in Portugal, and the Pont De Normandie Bridge and Millau Viaduct in France. These three earlier structures have all been landmark projects in their own right. The Vasco da Gama Bridge in Portuguese capital Lisbon spans the Tejo River, and is one of the longest bridges in Europe, measuring 17.2km in length. Meanwhile the 2.143km Pont De Normandie Bridge had, for around five years following its completion, the longest central span of any cable-stayed bridge in the world. And the breathtaking Millau Viaduct has the highest structural height of any bridge in the world, with towers reaching up to 343m high. Dr Virlogeux was awarded the Gustave Magnel Medal in 1999, the award of Construction Engineers Institute in 2005 and also holds a Fritz Leonhardt Award. In addition, he also received an award from the International Association of Bridge and Structure Engineering in 2003 for his contributions to suspension bridge design and has been lecturing in various institutions since 1977, sharing his experience at the École Nationale des Ponts et Chaussées and Centre des Hautes Études du Béton Armé et Précontraint, amongst others.

World HighwaysJUNE 2014 g.xx World Highways JUNE 2014 www.worldhighways.com - updated content every working day

“ Bridge designer Dr Michel Virlogeux’s impressive CV includes other structures such as the Vasco da Gama Bridge in Portugal, and the Normandy Bridge and Millau Viaduct in France”

Dr Michel Virlogeux is undoubtedly one of the world’s foremost bridge engineers

World-class designer Millau Viaduct in France

KEY PROJECT REPORTKEY PROJECT REPORTKEY PROJECT REPORT KEY PROJECT REPORTKEY PROJECT REPORTKEY PROJECT REPORTKEY PROJECT REPORT

Pont De Normandie in France

Vasco da Gama Bridge in Portugal

DR MICHEL VIRLOGEUX

A tight construction schedule calls for night working