Turbine Erection

131
26 May 2012 PMI Revision 00 1 TURBINE ERECTION

description

ntpc

Transcript of Turbine Erection

Page 1: Turbine Erection

26 May 2012 PMI Revision 00 1

TURBINE

ERECTION

Page 2: Turbine Erection

26 May 2012 PMI Revision 00 2

HP Turbine IP Turbine

Page 3: Turbine Erection

26 May 2012 PMI Revision 00 3 LP Turbine

Brg

Page 4: Turbine Erection

26 May 2012 PMI Revision 00 4

Salient Features Of Turbine Erection

• The fore most activity before taking up the work is the safe working conditions. Thus we should first assemble temporary railing and covers before the start of the job

• Remove construction material & sweep the foundation well. A proper foundation is of utmost importance for proper operation of the machine. A hammer test is to be carried to detect any flaw / void in the concrete layer. An ultrasonic testing of the TG deck should also be carried out if possible. No looseness below the base plates is acceptable

Page 5: Turbine Erection

26 May 2012 PMI Revision 00 5

Page 6: Turbine Erection

26 May 2012 PMI Revision 00 6

Salient Features Of Turbine Erection (Contd.)

• FOUNDATION CHECK: check accuracy of size, elevation & axiality of foundation for conformance the erection drawing

• Check all contact surfaces & openings for turbine, generator etc., Holes for anchor bolts. Record final dimensions & make a protocol

• Check, mark & record main reference point (absolute floor level) for height against building wall or foundation pillar

Page 7: Turbine Erection

26 May 2012 PMI Revision 00 7

Page 8: Turbine Erection

26 May 2012 PMI Revision 00 8

Page 9: Turbine Erection

26 May 2012 PMI Revision 00 9

Page 10: Turbine Erection

26 May 2012 PMI Revision 00 10

Salient Features Of Turbine Erection (Contd.)

• BASE PLATES & BEARING PEDESTALS :

LAYING The base plates are designed to transfer uniformly all forces & vibrations caused by the operation of the machine.The pedestal are aligned as the deflection curve of the rotor. The base plates are leveled with help leveling screws provided below the base plate

Page 11: Turbine Erection

26 May 2012 PMI Revision 00 11

Page 12: Turbine Erection

26 May 2012 PMI Revision 00 12

Page 13: Turbine Erection

26 May 2012 PMI Revision 00 13

• ANCHOR BOLTS FOR BASE plates:they are long through bolts for fastening the machine / base plates to the foundation. They are stretch elongated by specified length by the help of the bolt tensioning device.Normally diagonally opposite two bolts are tightened & locked subsequently

Salient Features Of Turbine Erection (Contd.)

Page 14: Turbine Erection

26 May 2012 PMI Revision 00 14

Page 15: Turbine Erection

26 May 2012 PMI Revision 00 15

Page 16: Turbine Erection

26 May 2012 PMI Revision 00 16

• ANCHOR BOLTS FOR BASE plates:they are long through bolts for fastening the machine / base plates to the foundation. They are stretch elongated by specified length by the help of the bolt tensioning device.Normally diagonally opposite two bolts are tightened & locked subsequently

Salient Features Of Turbine Erection (Contd.)

Page 17: Turbine Erection

26 May 2012 PMI Revision 00 17

Page 18: Turbine Erection

26 May 2012 PMI Revision 00 18

Page 19: Turbine Erection

26 May 2012 PMI Revision 00 19

Page 20: Turbine Erection

26 May 2012 PMI Revision 00 20

Page 21: Turbine Erection

26 May 2012 PMI Revision 00 21

Page 22: Turbine Erection

26 May 2012 PMI Revision 00 22

Page 23: Turbine Erection

26 May 2012 PMI Revision 00 23

Page 24: Turbine Erection

26 May 2012 PMI Revision 00 24

Page 25: Turbine Erection

26 May 2012 PMI Revision 00 25

Page 26: Turbine Erection

26 May 2012 PMI Revision 00 26

Page 27: Turbine Erection

26 May 2012 PMI Revision 00 27

Salient Features Of Turbine Erection (Contd..)

• ALIGNMENT :align the base plates in zero position as per the deflection curve. The location is fixed in longitudinal & transverse axes using plumb & piano wires.The levels are fixed using the leveling instrument such as the dumpy level or by scale & water tubes and final levelling is done by the help of precision spirit level.Normally bearing pedestal #4 acts as the zero level for the turbine.The base plates & pedestals are then tightened with spanners for taking up the grouting

Page 28: Turbine Erection

26 May 2012 PMI Revision 00 28

Page 29: Turbine Erection

26 May 2012 PMI Revision 00 29

Salient Features Of Turbine Erection (Contd..)

• Grouting: The grouting of the base plates & pedestals is carried using shrink free grouting cement which is intended to ensure uniform transmission of mass and vibration of the machine on the foundation.The activity is carried with great care as the operation behavior of the machine depends largely on workmanship while carrying out the assembly of the load bearing components

• Bolt tensioning:

Page 30: Turbine Erection

26 May 2012 PMI Revision 00 30

Page 31: Turbine Erection

26 May 2012 PMI Revision 00 31

Salient Features Of Turbine Erection (Contd..)

• COUPLINGS: coupling on turbine shaft are generally rigid couplings.

The couplings are used to connect two shafts to form a shaft

assembly. The couplings are so designed so as to perform the

following two functions:

• a)the dimensions & design is such that it is capable of transmission of

all torque encountered during its service.

• b) The coupling must not influence the smooth running of the shaft

assembly

Page 32: Turbine Erection

26 May 2012 PMI Revision 00 32

Page 33: Turbine Erection

26 May 2012 PMI Revision 00 33

Page 34: Turbine Erection

26 May 2012 PMI Revision 00 34

Page 35: Turbine Erection

26 May 2012 PMI Revision 00 35

Page 36: Turbine Erection

26 May 2012 PMI Revision 00 36

Page 37: Turbine Erection

26 May 2012 PMI Revision 00 37

SALIENT FEATURES OF TURBINE ERECTION (CONT)

• After carrying out the coupling check and performing the adjustments necessary in the shaft position, the coupling of the shafts is carried out. Check for concentricity / radial alignment before carrying out the the coupling. Also measure the clearance between the spigot & recess. This should be well within the specified limit s of 0.08mm or else it shall give a lot of problem while doing the alignment of the rotors. There after carry out the axial alignment of the rotors

Page 38: Turbine Erection

26 May 2012 PMI Revision 00 38

SALIENT FEATURES OF TURBINE ERECTION (CONT)

• While coupling ensure the concentricity of the coupling holes of the two coupling. This shall minimize the requirement of reaming & honing. A run out check at the shaft journal is necessary to ensure a good coupling. It may be noted that even a run out of 0.03mm at journal area will eventually lead to vibrations of 30 microns.A higher run out is an indication of improperly connected coupling. It is imperative to locate the cause of the improper connection& to eliminate them by appropriate measures

Page 39: Turbine Erection

26 May 2012 PMI Revision 00 39

SALIENT FEATURES OF TURBINE ERECTION (CONTD..)

• CASING GUIDES: The casing guides are used to link the turbines & bearing casing together in such away that turbine casing can expand freely in desired direction when heated. Prior to installation of the turbine casing, check their mating surfaces& t6hose of bearing casing for perfect condition. Permanent casing guide keys are fixed with required clearance after the final alignment of rotor and casings. Ensure a thin layer of molykote on keys while installing. The thickness of keys& the clearances are to be recorded in the log-sheets

Page 40: Turbine Erection

26 May 2012 PMI Revision 00 40

Page 41: Turbine Erection

26 May 2012 PMI Revision 00 41

SALIENT FEATURES OF TURBINE ERECTION (CONTD..)

• CASING SUPPORTS :The position of all outer casing & that of inner casing of LP turbine are fixed horizontally by casing supports. When the turbine casing rests on the bracket supports the casing is at proper elevation wrt turbine shaft

• The HP &IP turbine casing are supported in the turbine axis by two front & two rear bracket supports standing on the support blocks of the pedestals.The support are free to slide during the thermal expansion

Page 42: Turbine Erection

26 May 2012 PMI Revision 00 42

Page 43: Turbine Erection

26 May 2012 PMI Revision 00 43

•BEARING PEDESTALS The Function of the Bearing Pedestal Is To:

-Support the Rotors -Connect HP & IP to Form One Unit -Support HP & IP Turbine Sections

-Center the Turbine Sections • THRUST BEARING takes care of the uncompensated residual thrust

• FRONT BEARING PEDESTAL houses the main oil pump for lube oil & control oil. The over speed trip device is also installed in this pedestal

• AXIAL MOVEMENT : those pedestals which are not fixed point are designed to take care of thermal expansion. The movement is based in the length of the turbine section and the casing temperatures

• Setting of spacer bolt clearance

• Checking of radial & axial clearance on the right & left hand sides

Page 44: Turbine Erection

26 May 2012 PMI Revision 00 44

The Erection any equipment is a complete & systematic process which is well conceived before start of the job. It involves detailed planning about the content and the scope of work that needs to done. The complete technical specification of the equipment, its Layout, the foundations, and the Terminal points have to be defined before the start of the work. It is well said, that a work well planned is half done. Thus while award of the work the complete technical specifications are frozen in detail during pre award discussions with the Engineering and the Contract services.

Page 45: Turbine Erection

26 May 2012 PMI Revision 00 45

-The complete erection of a TG is a long drawn process requiring more that 30 months of work. -Thus the sequence of supplies and their dates of dispatches are decided before hand. -Similarly the dates of readiness of the Foundations is also decided before hand. -The Terminal points are also decided before the Final award of the contract i.e. NTPC scope(Customer Scope) which generally are free construction power supply, water supply, Civil foundations, EOT Crane (optional) with operators, Compressed air, Area lighting, accommodation land, storage area, DM water etc. -The rest of the work is in the scope of the equipment

supplier. - This includes Supply, Storage, Erection, Testing & Commissioning and Trial operation of the equipment.

Page 46: Turbine Erection

26 May 2012 PMI Revision 00 46

Pert Networks

• The contractor is required to submit a PERT network indication the major mile stone dates

• The three types viz. L1, L2 & L3 networks are submitted by the contractor which is reviewed & finalized after incorporating the comments of the owner. L3 is the complete detailed network which is normally used at site for each commitment

• Similarly the supplies are also decided as per the milestone dates and any slippage from the committed date is subject to LD to be levied by the owner. This is levied @ 1/2 % per week’s delay subject a maximum ceiling of 5 %

Page 47: Turbine Erection

26 May 2012 PMI Revision 00 47

Handing Over Of Fronts

• The fronts are handed over to the contractor after due

checking of the soundness & dimensional check of the elevation & pocket, insert sizes and their location after a joint protocol

• It is essential to provide weather proof TG hall along with crane girder which includes side wall cladding, railway siding, approach ladders / staircase, adjoining floors etc

Page 48: Turbine Erection

26 May 2012 PMI Revision 00 48

CONSTRUCTION OF TG DECK

• The TG deck is supported on steel / RCC columns. A vibration isolation system is provided on the column to isolate the deck vibrations from the columns

• After the layout of steel inserts on the form work/ shuttering, the TG deck is constructed by a process of non stop casting in order to provide monolithic structure. The cement setting is delayed by adding certain additives to the concrete mixture. The curing is carried out for a period of 28 days after which it is

released for erection of the equipments

Page 49: Turbine Erection

26 May 2012 PMI Revision 00 49

Page 50: Turbine Erection

26 May 2012 PMI Revision 00 50

Page 51: Turbine Erection

26 May 2012 PMI Revision 00 51

Page 52: Turbine Erection

26 May 2012 PMI Revision 00 52

Page 53: Turbine Erection

26 May 2012 PMI Revision 00 53

Page 54: Turbine Erection

26 May 2012 PMI Revision 00 54

Page 55: Turbine Erection

26 May 2012 PMI Revision 00 55

Page 56: Turbine Erection

26 May 2012 PMI Revision 00 56

Page 57: Turbine Erection

26 May 2012 PMI Revision 00 57

Page 58: Turbine Erection

26 May 2012 PMI Revision 00 58

Page 59: Turbine Erection

26 May 2012 PMI Revision 00 59

Page 60: Turbine Erection

26 May 2012 PMI Revision 00 60

Page 61: Turbine Erection

26 May 2012 PMI Revision 00 61

Page 62: Turbine Erection

26 May 2012 PMI Revision 00 62

Page 63: Turbine Erection

26 May 2012 PMI Revision 00 63

Page 64: Turbine Erection

26 May 2012 PMI Revision 00 64

Page 65: Turbine Erection

26 May 2012 PMI Revision 00 65

Page 66: Turbine Erection

26 May 2012 PMI Revision 00 66

Page 67: Turbine Erection

26 May 2012 PMI Revision 00 67

Page 68: Turbine Erection

26 May 2012 PMI Revision 00 68

Page 69: Turbine Erection

26 May 2012 PMI Revision 00 69

Page 70: Turbine Erection

26 May 2012 PMI Revision 00 70

Page 71: Turbine Erection

26 May 2012 PMI Revision 00 71

Page 72: Turbine Erection

26 May 2012 PMI Revision 00 72

Page 73: Turbine Erection

26 May 2012 PMI Revision 00 73

Page 74: Turbine Erection

26 May 2012 PMI Revision 00 74

Page 75: Turbine Erection

26 May 2012 PMI Revision 00 75

Page 76: Turbine Erection

26 May 2012 PMI Revision 00 76

Page 77: Turbine Erection

26 May 2012 PMI Revision 00 77

Page 78: Turbine Erection

26 May 2012 PMI Revision 00 78

Page 79: Turbine Erection

26 May 2012 PMI Revision 00 79

Page 80: Turbine Erection

26 May 2012 PMI Revision 00 80

Page 81: Turbine Erection

26 May 2012 PMI Revision 00 81

Page 82: Turbine Erection

26 May 2012 PMI Revision 00 82

Page 83: Turbine Erection

26 May 2012 PMI Revision 00 83

Page 84: Turbine Erection

26 May 2012 PMI Revision 00 84

Page 85: Turbine Erection

26 May 2012 PMI Revision 00 85

Page 86: Turbine Erection

26 May 2012 PMI Revision 00 86

Page 87: Turbine Erection

26 May 2012 PMI Revision 00 87

Page 88: Turbine Erection

26 May 2012 PMI Revision 00 88

Page 89: Turbine Erection

26 May 2012 PMI Revision 00 89

Page 90: Turbine Erection

26 May 2012 PMI Revision 00 90

Page 91: Turbine Erection

26 May 2012 PMI Revision 00 91

Page 92: Turbine Erection

26 May 2012 PMI Revision 00 92

Page 93: Turbine Erection

26 May 2012 PMI Revision 00 93

Page 94: Turbine Erection

26 May 2012 PMI Revision 00 94

Page 95: Turbine Erection

26 May 2012 PMI Revision 00 95

Page 96: Turbine Erection

26 May 2012 PMI Revision 00 96

Page 97: Turbine Erection

26 May 2012 PMI Revision 00 97

Page 98: Turbine Erection

26 May 2012 PMI Revision 00 98

Page 99: Turbine Erection

26 May 2012 PMI Revision 00 99

Page 100: Turbine Erection

26 May 2012 PMI Revision 00 100

Page 101: Turbine Erection

26 May 2012 PMI Revision 00 101

Page 102: Turbine Erection

26 May 2012 PMI Revision 00 102

Page 103: Turbine Erection

26 May 2012 PMI Revision 00 103

Page 104: Turbine Erection

26 May 2012 PMI Revision 00 104

Page 105: Turbine Erection

26 May 2012 PMI Revision 00 105

Page 106: Turbine Erection

26 May 2012 PMI Revision 00 106

Page 107: Turbine Erection

26 May 2012 PMI Revision 00 107

Page 108: Turbine Erection

26 May 2012 PMI Revision 00 108

Page 109: Turbine Erection

26 May 2012 PMI Revision 00 109

Page 110: Turbine Erection

26 May 2012 PMI Revision 00 110

Page 111: Turbine Erection

26 May 2012 PMI Revision 00 111

Page 112: Turbine Erection

26 May 2012 PMI Revision 00 112

Page 113: Turbine Erection

26 May 2012 PMI Revision 00 113

Page 114: Turbine Erection

26 May 2012 PMI Revision 00 114

Page 115: Turbine Erection

26 May 2012 PMI Revision 00 115

Page 116: Turbine Erection

26 May 2012 PMI Revision 00 116

Page 117: Turbine Erection

26 May 2012 PMI Revision 00 117

Page 118: Turbine Erection

26 May 2012 PMI Revision 00 118

Page 119: Turbine Erection

26 May 2012 PMI Revision 00 119

Page 120: Turbine Erection

26 May 2012 PMI Revision 00 120

Page 121: Turbine Erection

26 May 2012 PMI Revision 00 121

Page 122: Turbine Erection

26 May 2012 PMI Revision 00 122

Page 123: Turbine Erection

26 May 2012 PMI Revision 00 123

Page 124: Turbine Erection

26 May 2012 PMI Revision 00 124

Page 125: Turbine Erection

26 May 2012 PMI Revision 00 125

Page 126: Turbine Erection

26 May 2012 PMI Revision 00 126

Page 127: Turbine Erection

26 May 2012 PMI Revision 00 127

Page 128: Turbine Erection

26 May 2012 PMI Revision 00 128

Page 129: Turbine Erection

26 May 2012 PMI Revision 00 129

Page 130: Turbine Erection

26 May 2012 PMI Revision 00 130

Page 131: Turbine Erection

26 May 2012 PMI Revision 00 131

THANK YOU