TURBINE DATA

download TURBINE DATA

of 2

Transcript of TURBINE DATA

  • 7/25/2019 TURBINE DATA

    1/2

    BHEL, Hardwar 6.1-0101-97/1

    Steam Turbine Technical DataDescr ipt ion Steam & Casing Temperatures

    Steam Temperatures

    Rated Value,Annual

    Average

    Long-TermValue, Subject

    to Annual

    Average

    400 hrs.Per Year

    80 hrs. Per YearMax. 15 min inIndividual Case Unit

    Main Steam atHP Stop Valve inLet

    537.0 545.3 551.0 565.0 C

    HRH Steam atIP Stop Valve inLet

    537.0 545.3 551.0 565.0 C

    Steam Temperatures

    Rated Value

    Long TermOperation

    80 hrs. Per Year,Max. 15 min. in

    Individual Case

    In SpecialCases at

    No LoadUnit

    HP Turbine Exhaust 337.9 339.9 429.9500.0

    C

    Extraction 6 337.9 339.9 429.9 500.0

    C

    Extraction 5 410.0 415.0 450.0 C

    Extraction 4 297.2 307.2 347.2 C

    Extraction 3 183.8 196.8 243.8 C

    Extraction 2 99.3 119.3 164.3 C

    Extraction 1 75.4 95.4 145.4C

    LP Turbine Exhaust 46.1 70.0 70.0 C

    Long-Term Operation: Upper Limit Value Permissible Without Time Limit.

    These Values Correspond To 600 MW Load With 3% Makeup and 0.1013 bar Back PressureWith all Heaters in Service and Rated Steam Conditions.

    Only Valid For The No Load Period With High Reheat Pressure After Trip-Out From Full LoadOperation. For Individual Case Approx. 15 Minutes.

    The Turbine Is Immediately Re-Loaded Or The Boiler Immediately Reduced To Minimum LoadIf No Load Operation Is Maintained.

    Casing Metal Temperatures

    Wall Temperatures Alarm At Machine Must Be Shut Down At Unit

    HP Turbine Casing Exhaust 485 500 C

    Outer Casing of LP Cylinder 90 110 C

    Spray Water To LP Turbine Must Be Switched On At 900C

  • 7/25/2019 TURBINE DATA

    2/2

    BHEL, Hardwar 6.1-0101-97/2

    Casing Metal Temperature Differences

    Temperature Difference Alarm At Machine Must Be Tripped At Unit

    Between Upper & Lower CasingHalves of HP Turbine, Middle

    90 100 C

    Between Upper & Lower CasingHalves of IP Turbine, Front

    30 45 C

    Between Upper & Lower CasingHalves of IP Turbine, Rear

    30 45 C

    Permissible Differential Temperature between Parallel Steam Supply Lines

    No Time Limitation 17 C

    Short Time Period (15 min) 28 C

    In the Hottest Line the Limitations Indicated for Main and Reheat Steam Temperature must not be Exceeded

    Feed Water Heater out of Service

    Operation With Feed Water Heaters Out of Service Main Steam Flow, Kg/s(Indicative)

    Load,MW

    Extraction A6, A5 (Both Strings Out) 454.95 600

    Output Limit du ring Testing with Automatic Turbine Tester

    Testing of Main Steam Stop and Control Valves < 300 MW

    Testing of HRH Steam Stop and Control Valves 300 MW

    MotoringMotoring is the condition in which the turbine is driven by the generator at rated speed with thestop and control valves closed. In this operating mode, certain turbine components are heated upby wind age power of the blading.To prevent heat-up beyond permissible temperatures, motoring must not be allowed to continuefor longer than one minute. If the condenser low vacuum limit of 0.3 bars is exceeded, motoringmust not be allowed to continue for more than 4 seconds.