Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In...
Transcript of Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In...
![Page 1: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/1.jpg)
Tullamarine Landfill
Community Meeting18 October 2017
![Page 2: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/2.jpg)
Recently Completed Activities
� Groundwater sampling at new wells completed,
letter report currently being prepared
� Snap shot of In Situ parameters on all groundwater
boreholes completed, report currently being
prepared
� Groundwater sampling, all boreholes, completed
� Review of Bore Network Depths, data sent to Auditor
� Stormwater connection design concept completed,
consultation commencing
![Page 3: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/3.jpg)
Tullamarine Planned Activities
� Ambient Air Testing [Underway]
� Install Landfill Gas Extraction Wells on Mound 3
[Design Phase]
� Next groundwater technical review [Late 2018 / Early
2019], Technical Review for Auditor Review [TRAR]
Grey = task underway; Blue = task commencing
![Page 4: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/4.jpg)
Email Question 1
Q1. In July 2015, at the invitation of Kieren, Julie Law
and I attended the obtaining of water samples from
bores on the Buffer land. To date the report arising
from that testing has not, I believe, been presented to
the community. When can the community expect to
receive that report? Over two years is an inordinately
long time.
A1. The groundwater results are assessed holistically
every 3 years. The next assessment report will be
completed in 2018 for all sampling completed in the
period late 2014 to December 2017.
![Page 5: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/5.jpg)
Email Question 2
Q2. In November 2016 a number of bores were
installed in the housing area east of the dump. When
can the community expect the preliminary results from
that testing? It is nearly 12 months. Ample time to
have results.
A2. The results have been incorporated into a letter
report. The report is currently being reviewed and will
be made available in the next four weeks.
![Page 6: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/6.jpg)
Tullamarine Stormwater Connection
![Page 7: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/7.jpg)
Protecting Moonee Ponds Ck and
Growling Grass Frog
![Page 8: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/8.jpg)
Original Concept
Concrete Pipe [0.75 m to 1.0 m diameter]Concrete Pipe [0.75 m to 1.0 m diameter]
Concrete Pits/Formwork
![Page 9: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/9.jpg)
New Concept
Hard Edge
Wetlands
Soft Edge
Wetlands
Pipe and Open
Channel Swale
Pipes Smaller or Replaced with Open Channel / Swale / Rock
No change to Creek connection.
![Page 10: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/10.jpg)
Defined Wetland
![Page 11: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/11.jpg)
Pipe and Grass Swale
![Page 12: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/12.jpg)
Wetland Example
Constructed Wetlands
Handbook, Melbourne
Water, July 2017
![Page 13: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/13.jpg)
Stormwater Management & Grass
EstablishmentExisting Stormwater System
![Page 14: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/14.jpg)
North Wall Landscaping
May 2012
May 2013
Designed by Western
Plains Flora
![Page 15: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/15.jpg)
Mound 1
Gas Collection
Manifold
Leachate Well
Drainage Swale
![Page 16: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/16.jpg)
Kangaroos on Mound 3
![Page 17: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/17.jpg)
Echidnas near the Flare
![Page 18: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/18.jpg)
Benefits
� Improved water quality
� Increased habitat
� Increased biodiversity
� Softer design
� Opportunity to work with Melb Water / Friends
Groups / Council
� Savings?
![Page 19: Tullamarine Landfill Community Meeting - Microsoft · 18/10/2017 · Email Question 2 Q2. In November 2016 a number of bores were installed in the housing area east of the dump.](https://reader036.fdocuments.us/reader036/viewer/2022070801/5f027cf77e708231d40482c3/html5/thumbnails/19.jpg)
Thank you for your time.