TTU SYSTEM CIP PORTFOLIO - texastech.eduBOR Approved Capital Projects Campus Projects Budget Cost...
2
TTU SYSTEM CIP PORTFOLIO April 2010 – October 2016
Transcript of TTU SYSTEM CIP PORTFOLIO - texastech.eduBOR Approved Capital Projects Campus Projects Budget Cost...
![Page 1: TTU SYSTEM CIP PORTFOLIO - texastech.eduBOR Approved Capital Projects Campus Projects Budget Cost +/-TTU/TTUS 44 $ 692,732,249 $ 678,072,726 -$ 14,659,523 HSC 9 $ 160,871,838 $ 160,590,678](https://reader035.fdocuments.us/reader035/viewer/2022071213/604180cc41d8b7225d24a3c1/html5/thumbnails/1.jpg)
TTU SYSTEM CIP PORTFOLIOApril 2010 – October 2016
![Page 2: TTU SYSTEM CIP PORTFOLIO - texastech.eduBOR Approved Capital Projects Campus Projects Budget Cost +/-TTU/TTUS 44 $ 692,732,249 $ 678,072,726 -$ 14,659,523 HSC 9 $ 160,871,838 $ 160,590,678](https://reader035.fdocuments.us/reader035/viewer/2022071213/604180cc41d8b7225d24a3c1/html5/thumbnails/2.jpg)
BOR Approved Capital ProjectsCampus Projects Budget Cost +/-
TTU/TTUS 44 $ 692,732,249 $ 678,072,726 -$ 14,659,523HSC 9 $ 160,871,838 $ 160,590,678 -$ 281,160
HSC EP 2 $ 98,900,000 $ 97,972,256 -$ 927,744ASU 7 $ 77,240,000 $ 75,363,826 -$ 1,876,174TOTAL 62 $ 1,029,744,087 $ 1,011,999,486 -$ 17,744,601
-2%(Cost Avoidance / Debt Reduction)