FLOWCHART FOR TROUBLED PROJECTS
STARTRealise Requirements (Properly)
YES
NO WILD ENTHUSIASM (AGAIN?)Insanity? "New Broom Sweeps Clean" syndrowm
INSANITY - SAME AS LAST JOBDefine Success/Failure/'Trouble"
DEJECTIONMechanism for Escalation?
REALISE REQUIREMENTS (Better late than never) YESIs 'Complete' defined?
NO
DISILLUSIONMENTCHAOS / CONFUSION
BARGAINING Success/Failure Criteria Defined?NO DENIAL
Shooting Messengers leads to 'heads downYES culture
SEARCH FOR GUILTY
Political Projects DENIAL AMBITIOUS PROJECTS Realisation of RequirementsYES
NO NO SHOCKAccusations of 'negativity'Beware 'the sky is falling'
YES
Nerve to say "NO" ANGER"Too big to Fail" "Throw Resources to fix" syndromeMoral Fortitude of Leadership tested
NO
YES Realise Requirements
BARGAINING
DENIAL / ANGER
DEPRESSIONExternal HERO seeks glory
NOYES DEPRESSION / ANGER
NO DENIAL SHOCKANGER
BARGAININGYES
PROMOTION OF NON-INVOLVED
REALISATION OF REQUIREMENTS
Project team defensive ACCEPTANCESacking of innocent Alignment
NEED FOR PROJECT / BUSINESS CASE
PROJECT EXECUTION (Execution Plan, M&C, Reports/Escalation Criteria, Change Control)
PROJECT PLANNING (Baseline, Sequence, Dependency, Constraint, Risk, WBS/OBS/CBS/TBS)
ASCERTAIN REMEDIATION REQUIRED PLUS BUDGET (Time/Cost/People)
PROJECT INITIATION (Project Charter, Authority, Procurement Model) / Funding)
CLOSE OUT PROJECT
ABANDON
ISSUE REPORT TO PM/PD
FORMULATE RECOVERY PROJECT TO BE IMPLEMENTED & EXECUTED
DEVELOP RECOVERY PLAN, PRIORITIES, PEOPLE, TIME/COST, TRAINING
INTERIM REVIEWS OF REPORTS, COMPLIANCE WITH GOALS, TEAM EVALUATION, EXECUTION.
ASCERTAIN ASPECTS TROUBLED (Planning, Scope, Quality, Comms, Risks, Team, Client)
DEFINE REQUIREMENTS FOR RECTIFICATION / ACTION PLAN
SEEK AUTHORISATION FOR CHANGE/FURTHER WORK
LESSONS LEARNED, FEEDBACK TO ONGOING PROJECTS, ORGANISATIONAL LEARNING
AMEND PROJECT DOCUMENTATION / ORGANISATION (WBS/OBS/CBS/TBS/RBS, schedule, org structure)
TRAINING SESSIONS, ORGANISATIONAL ALIGNMENT, ASSISTANCE AS REQ'D
PROJECT REFORMULATION STRATEGY + DEALING WITH EXISTING PROJECT
ALTERNATIVE DELIVERY MECHANISMS (Rescope, Repackage, Re-contract)
FINALISE RECOVERY PLAN/STRATEGY
INCEPTION PLAN (Communicate to relevant parties, training sessions, organisational change)
MODIFY AS REQUIRED
VERIFY REVIEW & RECOMMENDATIONS - Root Causes & possible solutions
CONSULT 'RELEVANT' STAKEHOLDERS / PROJECT TEAM MEMBERS (Task Force?)
COMPLETE?
TROUBLED?
Is Project Recoverable in current context?
Essential Project?
OK?
Acceptable to Project Sponsor?
OK?
Business Case review req'd?