TRIBUNE - ITA-AITES · 2013. 5. 30. · TRIBUNE n°30 - ITA- AITES - Apr il 2006 6 2.2 Geology ......

35
N° 30 - AVRIL 2006 - ISSN 1267-8422

Transcript of TRIBUNE - ITA-AITES · 2013. 5. 30. · TRIBUNE n°30 - ITA- AITES - Apr il 2006 6 2.2 Geology ......

  • N° 30 - AVRIL 2006 - ISSN 1267-8422

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 3

    TRIBUNEITA newslet t er

    la let t re de l'AITES

    SoyanggangDam Auxiliary Spillway(copyright Samsung)

    Barrage Soyanggang tunnel de déchar-ge (copyright Samsung)

    2.500 copies of this issue have been printed

    BUREAU EXÉCUTIF ET COMITÉ DE RÉDACTION

    EXECUTIVE COUNCIL AND EDITORIAL BOARD

    H . P a r k e r U S AA . M . Muir Wood U KA . A s s i s B r a z i lK . O n o J a p a nM . K n i g h t s U KH . Wa g n e r A u s t r i aY. E r d e m Tu r k e yM . B e l e n k i y R u s s i aE . G r ø v N o r w a yF. Grübl G e r m a n yY. L e b l a i s F r a n c eF. Vu i l l e u m i e r S w i t z e r l a n dC . B e r e n g u i e r

    Directeur de la publication :Claude Berenguier

    I TA-AITES - c/o EPFL- Bat GC -Station18 - CH-1015 L A U S A N N E

    ✆+41-216932310, ✍ + 4 1 - 2 1 6 9 3 4 1 5 3Édité par ACROTÈRE :

    BP24775 - F-31047 TO U L O U S E✆+33-561494894, ✍ + 3 3 - 5 6 1 4 9 0 5 2 2

    a c r o t e r e @ w a n a d o o . f rImprimé par Imprimerie Te c h n i p r i n tZ I Albasud - F-82000 MONTA U B A N

    Crédits photos :Nations membres de l'AITESPublicité : A C R O T È R EDépôt légal : Avril 2006

    ITA accepts no responsibility or liability with regard to thematerial on this newsletter. This material: •is information of a general nature only which is not intendedto address the specific circumstances of any particular indivi-dual or entity;• is not necessarily comprehensive, complete, accurate or upto date;• may not be ITA position, specially signed articles areunder the responsability of their authors• is not professional or legal advice (if you need specific advi-ce, you should always consult a suitably qualified professio-nal).

    SOMMAIRE • CONTENTS

    Focus sur la Corée 4 Focus on Korea

    Résumés des présentations de 15 WTC’06 Open Session la séance publique WTC’06 Abstracts

    Rapports 2005 des Nations 18 Member Nations 2005 Membres reports

    Rapports 2005 des "Prime 36 ITA "Prime Sponsors 20045 Sponsors" de l’AITES reports"

    Training Session in Istanbul during the WTC’05

  • Focus on Korea

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 5

    1 . G E N E R A L ASPECTS OF TUNNELLING INKOREA

    Underground development in Korea allows the full utilizationof potential of a site. For planners, underground space pre-sents opportunities to facilitate transport routes, utilities andother infrastructure, allowing the development of better envi-ronment on the ground surface. Therefore, making a full useof underground space remains one of the greatest challengesfor the future in Korea since over 65% of the Korean penin-sula is mountainous terrain.

    In geological aspect, the predominant rock types in Korea aregranite, granitic gneiss, and gneiss. In most cases, joints andfissures are prominent, which make it difficult for tunnelengineers to develop an economical as well as a safe tunnel-ling. In some parts of the peninsula, sedimentary rocks andtheir metamorphic derivatives are also found. As the dimen-sions of newly planned tunnels are becoming longer andwider, the site investigation demands intensive geophysicalsurveys (such as seismic and electrical, among others) inclu-ding borehole logging in the design stage.

    Currently, as shown in Figure 1(a), a total length of tunnelsand utilities up to 2005 are approximately 1,597km excludinglife line tunnels such as electric power line tunnels and com-munication cable tunnels. However, the total length of tun-nels and utilities is expected to be about 2,311km by 2020 asshown in Figure 1.1(b).

    It should be noted that most tunnels were excavated in hardrock formation by drilling and blasting method, while mecha-nised tunnelling methods have also been widely adopted inKorea in recent years.

    Modern tunnelling technologies in Korea have been rapidlydeveloped in short period of time. Due to the social demandson the construction of transportation infrastructures, tunnel-ling has been concentrated on the road, subway and railway.However, various demands on the use of underground spacessuch as waste isolation, recreational facilities and strategicspaces will be foreseen in the near future.

    In the following, some of the on-going examples of under-ground space development projects will be presented andbrief explanation on the design procedures employed in the

    projects will be made:• Railway tunnel: Young-Dong tunnel project• Urban subway tunnel: Busan and Seoul subway tunnel pro-jects• Road tunnel: Neungdong tunnel project• Flood control tunnel: Soyanggang Dam spillway tunnel pro-ject• Rock caverns and utilities: Yeosu oil storage complex,Gonjiam food storage, Yangyang underground power plant,electric power cable tunnels

    These tunnel and underground utility projects in Korea willbe introduced in next sections.

    2. CONSTRUCTION OF A RAILWAY TUNNEL INTHE YOUNG-DONG ROUTE

    2.1 IntroductionConstruction of the “Sol-An” tunnel connectingDongbaeksan station and Dokye station at Young-Dong rail-way route (see Figures 2.1 and 2.2) is briefly described in thisSection. When this tunnel is completed, it will be the longesttunnel in Korea with the length of 16.2km. The tunnel site islocated in a complex geological area with faults, cavities andcoal seams. During construction of the second adit, geophy-sical survey using the electrical resistivity and GPR (GroundPenetration Radar) methods was carried out to locate thefaults, cavities and coal seams. The geophysical investigationresults along with the in-situ boring test results were used toupdate the tunnel reinforcement design. In addition, seismicreflection methods (TSP, HSP) were also used at the junctionpoint between the second adit and main tunnel in order todetect discontinuities around the tunnel.

    Project title: Young-Dong Route Relocation Contract period: 21 December 1999 ~ 8 September 2007Project budget: 312,593 million won in 1999Project location: Backsan-Dong, Taeback-City to Dogae-Eup, Samcheok-City, Gangwon-DoConstruction works:

    - Main tunnel: L=16km+240m (Cut & Cover: 320m, NATM: 15km+920m)Inclined shaft: L=2km+100m (No.1: 1km+510m, No.2:590m)Rail: L=23km+483m (Main line: 17km+774m, Specialline: 1km+168m, Multi line: 4km +541m)

    Figure 2.1 Tunnel location in a Gangwon province

  • Focus on Korea

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 6

    2.2 GeologyThe proposed tunnel alignment passes through the geologicalformations ranging from Cambrian age to Triassic age. Anestimated lithology is intercepted by the alignment of the tun-nel including conglomerates, quartzite, sandstone, shale,limestone and coal seams. Volcanic rocks of Cretaceous ageare also exposed in the project area, but these rocks are expec-ted to be located above the proposed invert level (Figure 2.3).

    2.3 Geophysical exploration• Electrical resistivity method: the 2nd adit (A1 line shown inFigure 2.4)The test results show the weak zone at the second adit area,as shown in Figure 2.5. The loosening zone was formed dueto mining and settlement associated with the shaft collapse.

    Table 2.1 Main construction contentsSections Main Inclined shaft Vertical shaft Total

    Excavation (m3) 1,094,000 126,000 11,000 1,231,000Shotcrete (m2) 61,000 6,000 1,000 68,000Rock bolt (ea) 81,000 3,000 1,000 85,000Concrete lining (m2) 141,000 16,000 2,000 1 59,000

    Figure 2.2 Railway tunnel route map

    Figure 2.8 Interpretation of discontinuities along the tunnel line byHSP/TSP

    Figure 2.4 Geological survey lines

    Figure 2.6 3D discontinuities (STA.106K 640 to the left side)

    Figure 2.7 3D discontinuities (STA.106K 640 to the right side)

    Figure 2.5 Test result from A1 line(2nd adit cross-section)

    Figure 2.3 Geological map

  • Focus on Korea

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 7

    • Seismic reflection method (TSP/HSP)The HSP survey confirmed the presence of the coal layers inthe rock mass. In addition, many discontinuities were foundin the section between STA. 106k 720 and STA. 106k 820.

    3. URBAN TUNNELLING

    3.1 Shield tunnelling in KoreaMost of subway tunnels in Korea have been constructed bythe cut-and-cover method or NATM until late 1990s.However, these tunnel construction methods caused severalproblems such as noise, ground vibration and traffic conges-tion. Thus, public attention and demand of shield tunnellingtechnique were increased to minimise the above negative pro-blems. In addition, most of urban subway tunnel projectsfaced an inevitable situation of driving underneath river andadjacent to existing buildings as well as foundations withoutany damage.

    In the late 1990s, two subway tunnels in Busan subway lineII (section 230) and three subway tunnels in Gwangju subwayline I (section 1) were launched by using slurry shield TBMin the diameter of 7.28m and EPB (Earth Pressure Balanced)shield TBM in the diameter of 7.38m. These Busan andGwangju subway tunnels were completed on February in2002 and July in 2003, respectively. Recently, 2nd tunnelamong 4 tunnels in the Seoul subway line IX (section 9) hasbeen completed employing the slurry shield TBM as shownin Figure 3.1. In addition, several subway tunnels in Seoulincluding the Seoul subway line VII (sections 3 and 4) and theBundang line between Wangsimlee and Seollong (section 3)are scheduled to be bored by the shield TBM.

    3.2 Constraints and difficulties in shield tunnellingGeneral shield tunnelling operations take place in the single

    soil layer such as London Clay and Bangkok Clay as well as inthe single rock layer. Consequently, the level and alignment ofshield machine for the soil and TBM for the rock can be arran-ged in a planning stage of the project. However, in Korea,shield machine should advance through a mixed geological for-mation of soil and rock in order to meet both of the economicand the geometric requirements. Most of subway tunnels aredesigned in the depth of 20m, as shown in Figure 3.2.During the construction of Busan Subway Line II(section230) using the bentonite slurry shield TBM, severalconstraints and difficulties were encountered due to the geo-logical fluctuations of soil layer, mixed surface layer and hardrock layer. These geological fluctuations affected to the shieldTBM operation and the advance rate of machine during theexcavation of tunnel. In addition, unusual abrasion form ofroller disk and the distorted cutter mount were observed (seeFigure 3.3). Those negative effects led to the reduction of thenet advance rate from 0.9 m/hr down to 0.15m/hr and unex-pected stop of machine. The construction of Gwangju subwayline I (section I) was encountered similar problems due to thegeological fluctuation and extremely hard rock.

    Figure 2.9 Construction site views

    Temporary facilities

    Backfill grouting Shotcreting Tunnelling working face

    Lattice girder Tube umbrella with grouted steel pipe

    Figure 3.2 Geological profiles of two subway tunnels

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 8

    Focus on Korea

    Figure 3.1 Tunnel construction and shield TBM

    Figure 3.1 Tunnel construction Figure 3.3 Negative effects during the shield tunnellingand shield TBM

    (a) Unusual abrasion forms of roller disk (b) Distorted cuttermount

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 9

    Focus on Korea

    3.3 Alternative plan for overcoming constraints anddifficultiesIn order to overcome the difficulties of geological fluctua-tions, several alternative plans were adopted. For example, inBusan Subway Line II and Gwangju subway line I, old flattype of cutter head with 14 inch disk cutters was replaced bynew dome type of cutter head with 17 inch disk cutters asshown in Figure 3.4. These cutters well dealt with the geolo-gical fluctuations of soil, mixed face layer, and hard rock. InSeoul subway line IX, a dome type with 17 inch alloy weldeddisk cutters combining strength and resilience was used.

    In addition, to avoid any damage to the existing undergroundand surface structures, special measures inside of the shieldTBM and cement-grouting from the surface were taken andalso extensive surveys were carried out. As a result of thealternative plans above, net advance rate in Tunnel B ofBusan subway line _ (section 230) was recovered up to 0.5m/hr (Figure 3.5(a)) and the tunnel construction was success-fully completed on schedule. So far all phases of the tunnelconstruction in the Seoul subway line IX (No. 1 and 2, sec-tion 9) are on schedule with fast net advance rate shown inFigure 3.5(b).4. Neungdong road tunnel

    4. NEUNDONGROAD TUNNEL

    4.1 IntroductionThe Neungdong tunnel is a part of the state road 24 extensionproject and the tunnel connects Joongsan with Sangbook. Atotal length of state road extension project is 8.663km, whichincorporates 6 bridges (555m), a tunnel and 2 interchanges.The Neungdong tunnel is 4.58km long and has two paralleledlanes. This tunnel may become the longest tunnel in SouthKorea within category of road tunnels. The objective of thetunnel work is to provide more direct and easier commutationbetween two cities (Ulsan and Milyang) in southeast area ofKorea (Figure 4.1). This tunnel will pass through the sandfault layer and national heritage of the Ice Valley.

    Client Busan National Territory Management Office

    Contract Value US$ 129,000,000Total Length 4.58km two lane, width: 20mConstruction PeriodJune 2000 – June 2006Location Ulsan, Korea

    Figure 3.4 Komatsu dome type cutter head

    Figure 4.1 Location and layout of Neungdong tunnel

    Figure 3.5 Net advance rate of two subway tunnels

    (a) Busan subway line 2 (section 230)

    (b) Seoul subway line 9 (section 9)

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 10

    Focus on Korea

    4.2 Construction method selected by geological characte-risticsGround investigation was carried out by various field tech-niques. A number of analyses were also performed to mini-mize influences on the fault layer and the surrounding envi-ronment as follows:• Ventilation system was selected to analyze how the IceValley (National heritage 224th) is negatively influenced bythe exhaust gas in the tunnel.• A slope of Colluvial deposit area was modified to the sloperate of 1:1.8, which was involved with a collapse of the slopeat the beginning of tunnelling. In addition, a technical planwas established for the area of Talus which was supposed tobe influenced by blasting.• Raise climber method was selected for driving vertical shaft,based on equipment performance tests and drilling verticalboreholes in which ventilation systems are installed.• Position of fault layer was found by the boring test data.Consequently, a temporary invert and the half-section exca-vation method for the existing fault layer are applied duringthe mechanical tunnelling.• In order to find positions related to the poor foundation andcrushing layer, the physical survey (specific resistivitymethod, image E/M survey) was carried out. In addition,those positions were thoroughly investigated by TSP and 3Dinstrumentation to establish the contingency plans during thetunnelling.

    4.3 Design ConsiderationsFigure 4.2 shows a schematic design diagram along theNeungdong tunnel alignment.

    (1) Cross section of tunnelEnlargement of the tunnel shoulder as 2.0m width based onthe continuity of earth work was considered. The commonduct considering the operation of the future integrated mana-gement system was planned. And also, the evacuation passa-ge system for vehicles and people in case of fire was planned.Maintenance and design of the drainage system for separatingsewage and waste-water was considered.

    (2) Tunnel entranceEnvironment-oriented design for the underground substationand the harmony of surrounding scenery after the completionshould be considered at the planning stage. In this project, aminimization of the glaring effect on the tunnel portal struc-ture at evening sunset time was employed in the design of thetunnel entrance (Figure 4.3).

    (3) Study of stability associated with the tunneling methodParametric study has been performed to decide the reasonabletunnel analysis and design. From this, three-dimensional fini-te element analysis according to the type of tunnel supportwas carried out to calculate stability and safety factor of thetunnel. Figure 4.4 shows drilling work in the blast hole at thetunnel face.

    (4) Ventilation systemOptimum ventilation system including vertical shaft and jetfans was adopted for the long tunnel. For this, numericalsimulation was initially performed for the Ice Valley relatedto the vertical shaft (Figure 4.5), electrostatic precipitator andinclined shaft. In addition, investigation of borehole up to260m depth at the vertical shaft was carried out and optimumconstruction method (Raise Climber) was selected throughthe comparative analyses

    Figure 4.2 Design aspects of Neungdong tunnel

    Figure 4.3 Construction of tunnel portal

    Figure 4.4 Drilling of blast hole

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 11

    Focus on Korea

    (5) The scheme of passing through the fault layerLogical construction method ensuring the stability of tunnelsfor passing through the sand fault layer at the end of tunnelwas adopted and the following plan for the investigation ofthe fault layer was set up:• TSP 202 (long distance prediction)• Devilog system / investigating boreholes in parallel advan-ce (short distance check-up)

    (6) Construction and instrumentation plans• Construction plan:- Minimizing the removal of excavated soils to the beginningof tunnel through placing concrete lining simultaneously- Planning construction method upon consideration of hazardanalyses• Instrumentation and monitoring plans:- Utilizing a precise instrumentation for the maintenance inthe fault layer- As-built-data-base for instrumentation and monitoring infor-mation during construction

    (7) Design of waterproofing and drainageDrainage water from the tunnel was to be separately treatedfor the purpose of the prevention of environmental contami-nation on the tunnel.

    (8) Non-toxic shotcrete accelerator• Improvement of the constructability by creating better wor-king environment in the tunnel• Prevention of the workers’ damage resulting from usingpowdered cement mineral accelerator• Prevention of the surrounding environmental contamination

    5. A U X I L I A RY S P I L LWAY T U N N E L O FSOYANGGANG DAM

    5.1 IntroductionThe Soyanggang multipurpose dam was completed in 1973.It is the biggest central core type rockfill dam in Asia with thegross storage capacity of 2,900,106m3, flood control capacityof 500,106m3, and flood water level of elevation 198.0m.However, due to recent abnormal precipitation during rainyseason, two great floods almost reached to the design floodwater level. This situation demands a review on the floodcontrol capacity of the dam. Since the design standard modi-fied in 2001 has considered the maximum credible flood ins-tead of floods with specific return periods related to theabnormal precipitation, the current spillway does not have asecure disposal capacity against the maximum credible flood.Therefore, the auxiliary spillway plan was setup to improvethe long-term flood control capacity (Figure 5.1). A generalaspect of the project is as follows:

    5.2 Geological featuresThe project site is located in the north-eastern part ofKyonggi province. The typical rock types are schist andgneiss, also silicate and granite are frequently found. A largescale of folding structure is found at Gamagol valley and twosets of strike-moving fault zone govern the geological fea-tures of the site. Mica schist dominates the upper part of tun-nel and quartz schist does the lower part tunnel. A small scaleof Jurassic granite and Pre-Cambrian granite gneiss is alsoobserved (Figure 5.2).

    Figure 4.5 Construction of vertical ventilation shaft

    Figure 5.1 General section profiles

    • Construction period: 30 August 2004 – 12 February 2007• Location: Book-Myun, Chuncheon city, Gangwon Province• Auxiliary Spillway: Mild-slope (14degree) spillway tunnel(L1=1,276.4m, L2=1 ,206.4m) and Water gate (B=14.7m ,H=14.0 m)• Facilities: access road to wharf and museum, etc.

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 12

    Focus on Korea

    The values of RMR and Q are decided from rock cores andlaboratory tests. When the coring was unavailable, the RMRand Q values were decided from the correlation between rockmass classification and geophysical characteristics, such asresistivity method and elastic wave survey. Overall rockmasses at the site is fair (grade 1~2) except for the part ofupward tunnel where fault zones are crossing through the por-tal of the lower part tunnel.

    5.3 Details of designCross sections of the tunnel at the inflow and discharge areaare varied smoothly for the water flow. For these transitionsections, a single arch type tunnel is applied with shotcretethickness of 15cm and concrete lining of 70~150cm. Generalsections have a 2R horseshoe-shaped cross section with a dia-meter of 14m, shotcrete thickness of 15 cm and concretelining of 40~60cm. The drill and blasting method is appliedwith the appropriate modification on the support system andmultiple excavation step method according to the variation ofsoil conditions. For an intake section, rockbolts are installedafter the excavation of pilot tunnel prior to the excavation ofthe upper half part of the section (Figure 5.3). Long bench cutis used for the efficiency of vehicle operation and operationcycle.

    Tunnel stability analyses were performed through a series ofexaminations, such as statistical analysis for rock mass clas-sification, structural analysis, and verification of tunnel sup-port system. Structural analyses considering potential loa-ding factors, such as deterioration of the first support systemfor the tunnel lining were carried out.

    6. ROCK CAVERNS AND UTILITIES6.1 Essential prototypesUnderground space in rock masses has widely been used inKorea for various utility caverns and tunnels such as crude-oilstorage caverns, LPG storage caverns, food storage caverns,pumped storage power plants, electric power tunnels, watersupply reservoir tunnels and waterway tunnels. Since the oilcrisis in 1970s, Korean government has constructed largevolume of oil storages up to 60 days capacity to ensure stablesupply of petroleum. Large-scale underground oil and gasstorage caverns in Korea have become one of the typicalmodels in technological contributions to the rock enginee-ring.

    6.2 Oil and gas storage cavernSince the very first product oil storage cavern was built in1977- 1982 in the south-eastern area of Seoul, 10 more oiland gas storage caverns were constructed in Korea. Thecapacity of first one is 1.5 Million BBLand another extendedcavern with the capacity of 1.5 Million BBL was built nearthe first one in 1994. Three crude oil storages were construc-ted in the southern coast of Korea during 1981-1997 and ano-ther one is under construction to extend the former storage.These projects were derived by government for strategic sto-rage of crude oil. Private company had performed feasibilitystudy in Ulsan city.

    Figure 5.2 Geological features

    Figure 5.3 Excavation steps

    Figure 6.1 Alignment of U-1 crude oil storage complex in Yeosu (U-1extension construction is underway)

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 13

    Focus on Korea

    From 1984, a LPG storage cavern containing pressurizedbutane and propane was brought into service in Yeosu andfive more LPG storage caverns were built in Ulsan,Pyeongtaek and Incheon. Commercialization of LPG storagehas been led and achieved by private companies.

    6.3 Food storage cavernAccording to the growing demand for the space in urbanareas, cavern for food storage was tried in 1995. Pilot cavernfor cold and chilled storage was excavated in Daejon and thefirst commercial food storage cavern was built in 1996 inGonjiam. The cavern is used as cold storage of imported beefnow.

    6.4 Underground pumped storage power plantThree underground pumped storage power plants are beingoperated in Korea and three more plants are under construc-tion. The first one started service in 1980 after seven years ofconstruction in Chungpyeong. The capacity of Chungpyeongplant is 400MW. Two more 600MW power plants wereconstructed in Muju and Samrangjin afterwards. Sanchungpower plant (capacity of 700MW) has finished the construc-tion recently and Yangyang and Chungsong plants are underconstruction.

    6.5 Electric power openingsOne of the most increasing utility tunnels in Korea is the elec-tric power cable tunnel. More than 20 electric power cabletunnels were constructed during the last two years and 10more tunnels are under construction in Seoul now. The exca-vations were carried out by various methods such as shieldTBM, TBM and NATM

    7. CONCLUSIONS

    Tunnel and underground utility projects in Korea will be gra-dually increased throughout 21st century and so called“mega” projects such as undersea tunnels and very long tun-nels can be easily foreseen due to local situation in Korea.The state-of-the-Art technologies on the geophysical surveytechniques and the auxiliary reinforcement methods in diffi-cult geologic conditions are the most significant engineeringgoals to be achieved in Korea, while environment-friendlydesign approaches are the social issue to be accomplished.

    In this regard, the international cooperation among ITAnations and tunnel experts is highly expected and we look for-ward to hearing from you soon!

    Figure 6.2 Final piping works afterexcavation of Pyeongtaek LPG storage

    Figure 6.3 Gonjiam food storage cavern

    Figure 6.5 Underground pumped storage power plant

    Figure 6.4 View of Yangyang underground power plant afterconcreteworks (W:H:L=26:56:115m)

  • WTC'06 Open Sessionabstracts

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 15

    RISK MANAGEMENT ONTUNNEL PROJECTIntroductionIn the past 10 years or so there have been a number of wellpublicised tunnel construction failures. In the subsequentreporting on the reasons for the failures there appears in manycases to have been a lack of proactive management of therisks during the project. Proactive management meansconstantly assessing the risks to tunnel projects during theplanning,design and construction phases and implimentingprior plans for mitigation, reduction and removal of the risksbefore they occur. The publicity and consequential effectsmean that the public,funders, regulators and insurers willhave reduced confidence in our industry. This must be a mat-ter of concern to ITA.

    In recognition of these events ITA set up and has recentlypublished guidance reports on managing risks during theplanning, design and construction phases of a tunnelling pro-ject dealing with technical,safety and contractual matters.Working Groups 2, 3 and 5 have been proactive in this res-pect. You will hear from the speakers representing these 3WGs and they will point out key issues and developments indealing with Risk Management of Tunnel Projects.

    In parallel with the ITA initiatives the International Insurers(ITIG) have developed a new Code/Framework that seeks tofacilitate and ensure the use of formal Risk Managementtechniques on tunnel projects. They seek to make it a condi-tion that Insurances will only be given to a tunnel project pro-viding that the Insurer is satisfied --through regular audits --that Risk Management principles are being applied by all par-ties--client, designer and Contractor. The speaker from ITIGwill explain the recent requirements. In addition the BritishTunnelling Society recently co authored a Code of Practisethat promotes the use of recognised Risk Management tech-niques for tunnel projects. The recent ITIG Code/Frameworkis based on that document which was publised in 2003.

    Finally we have a speaker who will provide a regional pers-pective of risk on tunnel projects.

    The Open Session should be educative for those not aware ofrecent developments on the application of Risk Managementin our industry and you are encouraged to ask questions anddiscuss your own experience .Martin Knights - ITA VicePresident

    I TA GUIDELINES FOR T U N-NELLING RISK MANAGE-MENTThe presentation will focus on the document prepared recent-ly by Working Group 2, titled “Guidelines for TunnellingRisk Management”. It will provide the background for thepreparation of the Guidelines and give an overview of thedocument and its main recommendations.

    Traditionally, risks have been managed indirectly in tunnel-ling projects through the engineering decisions taken duringthe project development. Based on recent developments, itcan be claimed that present risk management processes canbe significantly improved by using systematic risk manage-ment techniques throughout the tunnel project. By using thesetechniques, potential problems can be clearly identified at anearly stage of the project, so that appropriate risk mitigationmeasures can be implemented in a timely manner.

    The presentation will describe the different steps of the riskmanagement process, from the early planning phases of atunnelling project until completion. The use and scope of arisk policy and a risk management strategy will be addressed.

    It will be highlighted that the risk management strategy mustinclude a definition of the risk management responsibilities ofthe various parties involved and a short description of the

  • TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 16

    WTC'06 Open Sessionabstracts

    activities to be carried out at different stages of the project inorder to achieve the objectives, together with a definition ofmethods to be used for follow-up on results obtained throughthe risk management activities.

    Some examples of risk matrices and the practical use of a riskregister of some form will be presented.

    The presentation will highlight that the use of risk manage-ment from the early stages of a project, where major decisionssuch as choice of alignment and selection of constructionmethods can be influenced, is essential. Søren Degn Eskesen(Reporter) – Eric Leca (WG2 Animateur)

    MANAGING RISKS INT U N N E L P R O J E C T S :ENSURING THE A P P R O-P R I ATE CONTRACTUALA P P O RT I O N M E N T O FCONSTRUCTION RISKS.The Contractual arrangements for underground constructionprojects should set out the obligations and liabilities for theprudent management of underground construction risks.

    Understandably the substance of contracts are often drivenby the interests of the financial aspects of projects – focussingupon income streams and resources allocation. The more fun-damental harsh realities of construction risks are often onlydealt with by comparatively unsophisticated means.

    The systematic consideration of the many construction riskissues within the original project documentation directlyimpacts upon the management of construction risks, as wellas minimising uncertainty with regards to their managementduring the construction phase.

    Over the last 30 years members of the ITA WG 3 -Contractual Practices group developed a range of contractualpropositions. Careful re-evaluation of these has revealed thatthey only related to a small proportion of the vast range ofpotential construction risk issues which should be dealt within construction contracts.

    A new framework has been developed which provides gui-dance on the substance of the many matters to be consideredin contractual arrangements – and not to specify how thecontracts should be drafted.

    This new framework captures the broad range of subjects inwhich there are likely to be relationships between parties andhighlights the need for consideration of their responsibilities,rights and obligations. The framework can be applied to the

    wide variety of different contractual practices that areemployed world wide and is well suited to the many newforms of contracts emerging.

    By using the framework parties to an underground construc-tion project can better ensure that the most appropriate appor-tionment for construction risks are actually implemented -minimising conflict and ambiguity with respect to the mana-gement of construction risks - and thereby minimising theresultant risks in underground construction projects. D . A r n o l dDix - Animateur ITA WG3 – Contractual Practices / M a r t i nS m i t h , Vice Animateur ITA WG3 – Contractual Practices

    O C C U PAT I O N A L H E A LT HAND SAFETY R I S KMANAGEMENT IN TUNNELWORKS.The paper provides an overview of occupational health andsafety risk management set hopefully within the perspectiveof the wider international tunnelling community.

    It briefly discusses hazard identification, sources of risk andrisk assessment. Sources of guidance on the hazards of under-ground construction are given. The paper suggests that whil-st underground construction can present risks to thoseconstructing the works, some risks such as those arising fromground collapse may be greater to those on the surface above

    than to those in the tunnel.It summarises recentresearch into third partyrisks with which theauthor has been involved.

    The paper identifies thevarious parties to a tunnel-ling contract and outlinestheir role or potential rolein health and safety riskmanagement. A l t h o u g hthe phrase “health andsafety is widely used, thepaper recognises thatoccupational health isoften neglected. Welfare is

    another issue linked with occupational health and one whichif addressed properly can make a contribution to health riskreduction.

    Competence and training are essential parts of any risk reduc-tion strategy and comment is made on this matter. D. R.Lamont. Animateur ITA WG5 - Health and Safety in Works.

  • WTC'06 Open Sessionabstracts

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 17

    THE CODE OF P R A C T I C EFOR RISK MANAGEMENTO F T U N N E L WORKS –FUTURE T U N N E L L I N GINSURANCE FROM T H EINSURERS’ POINT OF VIEWFor many years now, engineering insurers have repeatedlyhad to cope with major losses in the tunnel construction sec-tor. The question of the insurability of such projects has beenon the agenda for quite some time. Munich Re and other insu-rers and reinsurers have therefore set themselves the task ofgetting together with representatives of the international tun-nel construction industry in order to discuss and launch mea-sures that are capable of promoting safety and hence loss pre-vention.

    As a result of the increasing number of major tunnel losses,(and following a similar successful initiative in the buildingindustry) a working group was set up in London with the taskof developing a code of practice for the risk management oftunnel construction projects. The working group comprisedrepresentatives of the UK construction industry and construc-tion underwriters from the leading insurers and reinsurers ofthe London market. The original document prepared for theUK market was presented to the public in September 2003and an international version has now been officially releasedby ITIG, the International Tunnel Insurance Group of whichMunich Re is a leading member.

    The purpose of this “Code of Practice for Risk Managementof Tunnel Works” is to create a set of rules which is acceptedby all the parties involved in the planning procurement andconstruction process and which addresses the systematic

    identification, assessment, allocation, and handling of risksinvolved. It is proposed to make the application of the Code,which, in the form of an endorsement, shall become an inte-gral part of construction insurance policies for tunnel pro-jects, and contribute towards optimum risk management forall phases of tunnel projects.

    This will be an important milestone in the improvement ofsafety standards of tunnel construction risks and thus contri-bute to them being made insurable on a profitable basis in thefuture. Heiko Wannick. Construction Underwriter & RegionalRisk Engineer Senior Consultant Tunnelling & DamConstruction - Munich Reinsurance Company

    KOREAN RISK MANAGE-M E N T PRACTICES : AC O N T R A C TOR’S PERSPEC-TIVE (SK E&C)In Korea, the construction industry has changed radicallysince the past financial crisis in 1997; companies are facedwith higher risks and uncertainties than ever before.Regulations and legislation on the environment, sustainabili-ty and safety on sites have placed more responsibility onorganizations. Clients/Owners expect more, most important-ly, they do not want surprises, and are more likely to engagein litigation when things go wrong. For construction industry,it is most important to secure more profitable project in bidphase and to minimize the risk under the construction stagesince project profit is fully determined at the stage ofcontracts and negotiation. The key strategy for constructionindustry, the ‘Order Amount’ determines Profit at contractand negotiation, and ‘Risk Management’ through long termcan increase revenue at project execution. Hence, the successof project management in construction industry depends onprecise prediction of risks and risk hedge planning, andprompt response to contingency plan throughout the marke-ting and project execution phase.

    This paper describes one of Korean risk management systemsdeveloped by SK E&C, as a contractor’s perspective. Thissystem provides a complete integration of project life cyclefor marketing and operating functions to make winning profi-table projects by minimizing operation risks y s t e m a t i c a l l y.Woong-Suk Yoo1 - Vice-President, SKEngineering & Construction Co., Seoul, Korea

    Meteor, Paris

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 18

    AUSTRALASIA

    Australia is now represented in ITA by the AustralasianTunnelling Society (ATS). In fact, to better promote theindustry the National committee altered the name fromAustralian Underground Constructiuon and Tu n n e l l i n gAssociation (AUCTA) to the Australasian Tunnelling Society(ATS). This was accompanied with changing the logo toreflect harmony with the ITA. This society is jointly sponso-red by Engineers Australia (EA) and The Australian InstituteMining and Minerals (AUSIMM)

    The society consists of a National comittee and various ‘subgroups’called chapters. These are

    • Victoria• New South Wales• Queensland• Western Australia• New Zealand

    The main facts during 2005 are as follows :• ATS conducted our triennial conference during April

    2005. Ther were over 250 registrants to the conference.-• New Zealand joins ATS as a chapter-• ATS Sponsored flights, accommodation and registra-

    tion to 26 student members to enable them to attend the trien-nial conference that was conducted in April of 2005.

    • ATS proactively cooperates witrh NSW Governmentsafety regulators to assist draft Safety code for woring condi-tions in underground structures-

    • Sub committee prepared production of marketingvideo aimed at students (Years 10-11-12 -13-14) to enticethem to consider careers in the underground constructionindustry.

    • The ATS is overahuling the website• The ATS is arranging the publication and editing of a

    hard cover technical book relating to the cutting of Hard Rockauthored by David Sugden

    Tunnelling and underground construction projects are boo-ming in Australia with current major projects including: :1 In the Sydney suburb, the Lane Cove motorway tunnelconsisting of twin tunnels comprising 3.6 Km of excavationeach2 Mitcham to Frankston motorway in the State of Victoria,comprising 45 Km of freeway, 1.6 Km of 3 lane tunnels and80 bridges.3 Sydney Cross City motorway tunnel comprising twin 2.1Km of main tunnel with a total of 8.5 Km of tunnelling4 Epping to Chattswood rail tunnels that comprising of 12Km of twin 7m diameter TBM bored tunnel and four sta-tions.5 The preparation of tenders for a 5m diameter x 6.8 Kmlong hard rock hydro electricty project for Southern Hydro inthe State of NSW.

    6 Tenders have closed for the first stage of the Trans Apexroad tunnel system for the Brisbane city council in Queens-land. This comprised twin 3 lane tunnels of 12 m diameterand 4.5 Km long in hard but fractured rock.7 The Perth City Rail tunnel under the CBD in Western Aus-tralia. This consists of a total of 2.6 Km of cut-and-cover andEPB TBM tunneling. The EPB machine will excavate twotunnels at 6.9 m diameter 800 meters long each in saturatedsands.8 Expressions of interest for the Sydney de-salination watertreatment project that could consist of up to 20 Km of 4mdiameter tunnels9 The Alkimos waste water project for a Perth Suburb inWestern Australia consisting of both cut and cover and pipejack and EPB tunneling for 5.1 Km10 Plans are being developed by Energy Australia to excavtea 5 m diameter x 2.5 Km long tunnel under the CBD of Syd-ney for the transmission of high tension power.11 Hobsons Bay a Melbourne suburb is relocating a mainsewer. This will be an inverted siphon of finished 2.7 m dia-meter and approximately 600 meters long by EPB machine.12 Cairns to Western Tablelands in Queensland has comple-ted a study to construct a twin tunnel for vehicular traff i c .This will consist of 7Km of excavation in hard rock

    AUSTRIA

    The Austrian national committee of ITA has been repre-sented at the World Tunnel Congress 2005 in Istanbulwith approximately 10 attendees. The most important conference concerning tunnelling in 2005was the traditional Geomechanics Colloquium in October2005 organized by the Austrian Society for Geomechanicswhich was followed by about 800 national and internationalattendees. In 2006 the most important conferences concerning tunnel-ling will be the “Betontag 2006” (30. – 31. March 2006), the“Safety and Aerodynamics conference for tunnelling” in Graz(15. May 2006), the “Tunneltag 2006” in Salzburg (11.October 2006) and the “Geomechanik Kolloquium” inSalzburg (12. – 13. October 2006).

    Essential work has again been done in the ITA workinggroup Nr.19. Two meetings with international contri-bution took place in Istanbul in May 2005 and one more mee-ting was held parallel to the STUVA in Leipzig in November2005. On the basis of these results the ITAWG Nr.19 will pre-pare a meeting during the ITA conference in Seoul in April2006.

    During the year 2005 a various number of projectsconcerning tunnelling was started in Austria. Concer-ning tunnel design the next design stage of the Brenner BaseTunnel was started on 1st of January 2005; the consortium

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 19

    PGBB which is a joint venture of Geoconsult (A), RaumUm-welt (A), Wisserodt Consulting (D) and SWS (I) won the ten-der for the approval design stage. For special fields like aero-dynamics, tunnel safety, vibrations and cost estimations sub-consultants HBI Härter (CH), Matousek (CH), Rutishauser(CH) and ITB (I) are joining the joint venture. Besides tunnel design several tunnel projects for metro, rail-way and motorway routes are under construction.In the capital of Austria the metro in Vienna is growing byanother two sections which are called U2/1 and U2/4. Furthermore the “Wiental-Sammler” – a project for sewage collec-tion is under construction within the heart of Vienna.Starting with the railway tunnels the biggest projects at themoment are the following mentioned ones.Between Steiermark and Kärnten the tunnel project named“Koralm” is now under construction with its exploratory tun-nels; the contractors STRABAG, Swietelsky, Bögl, A l p i n eand BEMO are involved.Along the high speed railway route connecting Vienna and St.Pölten the tunnel projects Perschlingtal and Wienerwald arealso under construction. PORR and Bilfinger+Berger havestarted their tunnel boring machine at Wienerwald tunnel; atthe tunnelsite of Perschlingtal STRABAG is also doing thejob with a tunnel boring machine.At the Lainzer tunnel the lot LT44 is under construction byÖSTU-Stettin, Hinteregger and Haider; lot number LT31 andLT33 which are mined sections of the Lainzer tunnel are pre-pared to start its construction. At the Unterinntal route, which is the northern access to the Bren-ner Base Tunnel, the variety of the tunnel construction is verywide; in these regions cut and cover sections, but also mined tun-nels in some parts with the use of compressed air, following thevery difficult alignment in this region, had to be chosen. Further more in 2005 tunnelling startet to connect the Arlbergmotorway tunnel and the very old Arlberg railway tunnel bysafety tunnels. The next lines give a rough summary of the biggest road tun-nel projects in Austria which are now under construction:Following the S35, which is connecting Bruck and Graz, atunnel near Mixnitz could be opened for traffic in 2005. Themotorway connection between Bruck and Graz should beready in 2008. Therefore another two tunnels have to be builtalong this route. Looking at the S6 only one more tunnel, called Ganzsteintunnelnear Mürzzuschlag, is missing to fully connect Bruck and Vi e n-na with a motorway connection. Tunnelling for the 2nd tube ofGanzsteintunnel is foreseen to be started at the end of 2005. Going from the eastern part of Austria to Salzburg, the tunnelHenndorf is under construction. Following the heavy traffic along the A10 – Tauernautobahnduring every holiday season it was decided to build thesecond tubes of Katschberg- and Tauerntunnel. The construc-tion of the second tube of Katschberg was started in 2005.

    Going even more to the western part of Austria, let’s stop inTirol, were the construction of the second tube of the Roppe-ner-Tunnel will be started at the beginning of 2006.Due to the heavy rainfalls in August 2005 a tunnel with alength of approximately 450 meters, which is called Tu n n e lGfell, had to be constructed in the area of the entrance to thePaznauntal in very short time this year. Looking to Vorarlberg, the most western part of Austria, Tun-nel Achrain is under construction.

    BELGIUM

    In 2005, the General Assembly has been held on 24.03.2005with visit of the urban underground storm bassin at placeFlagey in Brussels. • Participation in the General Assemly ofITA and the World Tunnel Congress in Istanbul ,• Visit of thecivil works for the High Speed Train in Antwerp on1 9 . 0 5 . 2 0 0 5 ,• Studyday on 17.11.2005 “Underg r o u n dPerspectives in Belgium : Utopias or Realities ?”

    The Underground work construction is as follows inBelgium :Significant projects under construction in Belgium :• High speed train Brussels - Antwerp - Amsterdam : installa-tion of equipments in the tunnel under the city of Antwerp(total : 1800 m)• High speed train Brussels – Liège – Köln : installation ofequipments in the tunnel under the hill of Soumagne (total :1500 m)• Half-submersed tank for liquid gaz in Zeebrugge (diameter90 m)Significant projects under design in Belgium :• Rail-connexion of the airport of Brussels to the high speedrailway network : 2 bored tunnels of 1100 m, cut-and-coversection of 1000 m• Deep underground disposal of high level radioactive waste :gallery 250 m long, 220 m deep• Closing of the motorway around Antwerp : tunnel under theriver Scheldt : 1000 m, possibly included in a storm barreer• Railway-tunnel “Schuman-Josaphat” for creating a secondNorth-South link through Brussels and better connecting theEuropean headquarters to the airport : built in-situ, 1250 m• Railway-tunnel “Liefkenshoek” under the river Scheldt inAntwerp : bored tunnel (5570 m + cut-and-cover sections 500m and 1075 m) or immersed tunnel (3450 m + cut-and-coversections 2700 m and 1075 m)• Section Charleroi-French border of the motorway E 420 : sec-tion of 13 km including 3 cut-and-cover tunnels (total 1700 m)• Test cave for nuclear reactor : 70 x 47 x 43 mOther possible significant projects in Belgium :• Shortcut in the motorway around Brussels : bored tunnel(single tube with 2 traffic levels, cars and public transportbusses, multimodal approach) : around 10.000 m length

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 20

    BRAZIL

    The Brazilian Tunnelling Committee (CBT) is an opensociety, with 105 members (8 corporate and 97 individualmembers). In 2005, CBT and ITA organised the InternationalSymposium on Waterproofing of Underground Structures,sponsored by Sika. The symposium, held in Sao Paulo andgathering 225 participants, was very successful and its pro-ceedings are published in the ITA website.

    In 2005, CBTcontinued its task to promote mirror ITA WGsin Brazil. Five Brazilian mirror groups have been quite acti-ve (WG-06, WG-12, WG-15, WG-18 and WG-19). TheBrazilian mirror WG-06 has been participating in the discus-sions of the new Brazilian standards on Fire Protection inUnderground Structures. Moreover, the highlight news for theBrazilian tunnelling community was the appointment ofTarcisio Celestino as the new animateur of the ITA WG-12 onShotcrete.

    In 2005, CBTconcluded the catalogue and data collection of120 cases of underground structures in Brazil, all for civilprojects (transport, energy and public utilities), with diametergreater than 3 m, totalling almost 400 km of length and 27million m3 of excavated volume. This material will composethe book "Tunnels in Brazil", written in both Portuguese andEnglish, to be published in the first half of 2006 and distribu-ted inside the ITA family, aiming to present the Brazilianexpertises in tunnelling, inside and outside the country.Financial resources totalling 100,000 Euros have been assu-red thanks to the sponsoring of major Brazilian companies.Other important news from the Brazilian tunnelling commu-nity is that the Federal University of Bahia (UFBA), takingadvantage of the Salvador Metro construction, promoted in2005, the first Master Course on Tunnelling for professionals(civil and mining engineers and geologists). The course is aone-year programme, totalling 400 h of classes in differenttopics related to tunnelling and underground structures. Thefirst edition of the course gathered 20 students, who will com-plete their activities in mid 2006.

    The year of 2005 was very busy for underground works inBrazil, especially those related to mass transit systems inmajor cities. The Sao Paulo Metro continued the works ofLine 2 Extension (more 5 km of tunnels to be completed in2006) and started Line 4 (13 km long fully underground tobe completed in 2008). The Rio Metro continued to expandthe system in Copacabana, towards one more station (1 kmof tunnels). The Brasilia Metro concluded the last tunnel ofLine 1 (1.2 km long, built by the doorframe method), expan-ding the system from 32 to 40 km long. Besides subway tun-nels, several hydroelectric power plants were resumed thisyear and are presently under construction, with hydraulicschemes predominantly underground. The Irape Hydroelec-tric Power Plant, with all major civil works completed in2005, encompasses 9 km of tunnels and a volume of 2 mil-lion m3 of underground structures. The San Francisco Riverdiversion project, despite all environmental debates, wasapproved by governmental bodies and should start soon. Itincludes the partial diversion of the Sao Francisco Rivertowards the Northeast of Brazil (40 m3/s), aiming to guaran-tee the minimum amount of fresh water to people who livedin that region, as well to agriculture irrigation. This projectincludes hydraulic channels and tunnels, and the selectedalternative encompasses a total length of 60 km of tunnels.

    CANADA

    An annual general meeting is held once per year with theexecutive committee meeting via conference call at leastfour other times throughout the year. Local chapter meetingsare held in each region an average of 6 times per year. TACalso holds a national conference every second year with thenext conference scheduled for the September 2006 inVancouver, British Columbia. Also, of note is that the RETC(Rapid Excavation and Tunnelling Conference – www.sme-net.org ) which is held every two years and attracts an avera-ge of over one thousand participants will be held in Toronto,Canada June 10-13, 2007. This will be the first time ever thatthe conference is being held outside of the United States.

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 21

    For additional information on TAC and current and upcomingactivities please go to our website at www.tunnelcanada.ca

    Tunnelling in Canada is undergoing a resurgence withnumerous major projects entering the construction phasein 2005.

    PROJECTS KNOW UNDER CONSTRUCTION OR AWAR-DED INCLUDERichmond•Airport•Vancouver Light Rail Transit, Vancouver,British Columbia• 14 km long alignment from airport to downtown• Sections will be completed by TBM, Drill and Blast and Cutand Cover, at grade construction and elevated construction• Bored Tunnels will be 6.0m diameter• Contractor : SNC Lavalin – SELI Joint Venture• TBM Supplier: LOVATBathurst / Langstaff Sewer, York Region, Ontario• 8.3 km of 3.3m diameter Bored Tunnel• Tunnels will be excavated by TBM• Contractor: McNally AECON Joint Venture• TBM Supplier: LOVATSeymour Capilano Twin Tunnels, Va n c o u v e r, British Columbia• 2 No. tunnels at 7.1 km each• To be excavated by TBM• Bore Diameter of 3.8m• Contractor: Bilfinger Berger• TBM Supplier: Robbins

    Brilliant Expansion Project, Castlegar, BC• Expansion of hydroelectic facility on the Kootenay River• Power tunnel and access tunnels recently completedIn addition to these Municipal Infrastructure projects thereare also several large Hydro Electric projects currently under-way the largest of which is the Sir Adam Beck A d d i t i o n a lDiversion Project for Ontario Hydro in Niagara Falls, Onta-rio. This project was awarded to Strabag of Austria andconsists of 10km of 14m diameter tunnel which will beconstructed with the largest Open Beam Hard Rock TBM yetconstructed which will be supplied by Robbins.

    PROJECTS IN DESIGN• Ninth Line/Sixteen Ave. Sewer Project, York Region,Ontario, Construction tender in 2006• St. John’s Harbour Interceptor Sewer, St. John’s NewFoundland• Hyde Creek Sewer, Coquitlam, British Columbia• Vancouver LRT, Coquitlam Port Moody Extension,

    Vancouver, British Columbia.• Port Mann Tunnel, 1 km of 3.5m Diameter Tunnel, DetailedDesign Stage awarded to Sandwell Engineering, Constructiontender expected in 2007• 2nd Narrows Tunnel, Greater Vancouver, British Columbia,in conceptual design stage, Construction tender expected in2010.All Five Regional Directors (British Columbia, Alberta, Prai-ries, Ontario and Quebec) have indicated a marked increasein the amount of work both ongoing and in the planningstages. This is confirmed by the continued growing presenceof foreign tunnel contractors (from the United States, A s i aand Europe) both bidding and winning projects in Canada.

    The TA C / A C T is looking forward to continued growth in thetunnelling sector for several more years with large infrastructureprojects in the major urban centers and continued developmentof Hydro Electric Power in British Columbia and Quebec. T h i scombined with the surging natural resources sectors and thepush for further development of underground mines will ensurecontinued growth in the tunnelling industry in Canada.

    CZECH REPUBLIC

    The preparation for the WTC 2007 continues, the work ofthe Organising Committee and Scientific Council is in fullswing. The WTC 2007 web pages www.wtc2007.org wereput into service. The Second Bulletin containing the call forabstracts by 15 February 2006 was issued. All premisses nee-ded for the WTC 2007 congress have been booked and co-operation with the STA commenced

    The WG Shotcrete in Underground Construction aimedtheir efforts to the methodology of training and practicalexamination of nozzle operators. They also prepared com-ments on the previously developed “Guidelines for ShotcreteApplication”.

    The field of safety and optimal operation of tunnels is dealtwith by the CTuC “Committee on Safety in Tunnels”, whichcollaborates closely with the Czech Road Association (aPIARC member).

    Also the work on the UPTUN Project belongs among key itemof the collaboration between the two institutions, takingadvantage of the fact that the team gathers representatives ofboth the public and professional spheres.

    WG Conventional Tunnelling continued working under thechair of Mr. Václav Soukup. The WG activity was focused oncollaboration with the WG 19 and preparation of a documentwhich will briefly summarise the NATM application prin-ciples. The distribution of this document is planned for thefirst of 2006.

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 22

    The work on the Prague metro line C extension continuesat a fast pace. The 4.6km long operational section IVC2starting from the current terminus Ládví is under construc-tion. This operational section consists of the Stílov, Prosekand Letnany cut-and-cover stations. The length of mined tun-nels, which are built using the NATM, amounts approximate-ly to 2.3km. The largest railway construction is currently the “N e wConnection” in Prague. It is part of a project of completionof modernisation of the Prague railway intersection; itcontains two double-rail tunnels under Vítkov Hill, over 1kmlong. The works proceed successfully. The construction willmake a significant increase in the commuter railway trafficpossible. Further, railway tunnels Hnevkov and Brezno areunder construction. Apart from that, the first phase of prepa-ration of a nearly 30km long railway tunnel from Prague toBeroun has commanced. Road tunnels:•- final lining is being erected in the highway tunnelsPanenská (about 2km long) and Libouchec (0.5km) on the D8highway near the border with Germany, in the directiontoward Dresden• final lining is being cast in the Valík tunnel on the D5 high-way near Plzen. When the tunnel and adjacent section of thehighway are opened to traffic, the D5 highway from Pragueto Rozvadov at the German border (the direction towardNuremberg) will be completed. • the about 1km long Klimkovice tunnel is being driven onthe D47 highway near Ostrava• the Komoransky and Slivenec highway tunnels on thePrague City Ring Road are under preparation, as well as thetechnologically difficult tunnel Blanka on the City CircleRoad. This tunnel passes under urban development and theVltava River. Excavation of an exploration gallery for thistunnel is being finished.

    DENMARK

    The Danish Society for Tunnels and Underground Workshas arranged 5 member meetings during the year 2005. Inaddition it organized a technical visit to the New Theater atthe harbour front of Copenhagen. Members of the societyhave participated in ITA General Assembly in Istanbul andtwo working groups.

    The next phase (4) of the Copenhagen Metro Ring waspolitical decided at the end of 2005. The project willrequire an investment of 2 billion euros to be financed by thecities of Copenhagen and Frederiksberg, the State and userscharges. The new line will be approximately 15 km long andinclude 17 stations. The design will start in 2007.

    A tunnel for pedestrians under the Copenhagen Harbour cros-sing nearby the New Opera House is still waiting for the

    Copenhagen Municipality to decide on financial issues.

    A bored service tunnel as part of an updating of theCopenhagen power stations has been contracted to MTHøjgaard at the early spring 2005. The tunnel will be a seg-ment lined tunnel with an inner diameter of 4.20 m and has atotal length of 3.8 km. The mining method will be closedmode TBM with an EPB shield supplied by Herrenknecht.Time frame is preparation of shafts 2005- 2006 and start ofmining in mid 2006. The TBM should start in mid 2007 andthe project is planned to be finished by the beginning of 2009.Consultants: COWI.

    A serious proposal for a 12 km road tunnel linking the motor-way system at the north with the motorway system at thesouth of Copenhagen has in September 2005 been tabled forthe Copenhagen Municipality. The alignment follows theCopenhagen Harbour front throughout and will thereforeoffer only minor disturbance of the city and its current traffic.The tunnel is proposed as an immersed type tunnel with 4lanes plus emergency lanes, all to motorway standard. Thecost is estimated to be close to 3 billion euros. The proposalgot a favorable reception from the public as well as local poli-ticians, because it was design to remove a very substantialpart of the road traffic from the center of Copenhagen.

    A new Harbour Tunnel in the city of Aarhus is under plan-ning. The tunnel will be almost 2.5 km long connecting theharbour terminal with the motorway system passing throughthe city center of Denmark’s second largest city. It will be acut-and-cover tunnel with two tubes with 2 lanes each andunidirectional traffic. The final planning will go out for poli-tical and public hearing at the end of 2006. Consultants: CarlBro Group.

    The proposed new road link between the Nordhavn andLyngbyvej located north of Copenhagen has been decided bythe political system at the end of 2005. The project contains a458 m long tunnel and two access tunnels 190 m and 159 mlong to a cost of 180 million euros. The project is expected totake 5 years to complete.

    EGYPT

    ETS held 8 local presentations for its members on differenttunneling topics during year 2005 .• An international Symposium on Utilization Of UndergroundSpace will be held in Sharm El Shiekh on 6-7 November2006 ( see ETS website )

    Extension of the line no. 2 Cairo metro by about 3 km hasbeen completed . This extension has two stations (SakiatMekki and El-Monibe ). This makes the total length of theline 22 km. out of which 15 km.are underground. It was inau-gurated by end of January 2005 . (see ETS website )

    • The total length of Greater Cairo Metro Line 3 is 30.5 Km

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 23

    of which nearly 28.5 Km is underground section. The routeextends from Cairo Airport to Imbaba and Mohandeseen ( seeETS website). The length of the branch to Mohandeseen is 3Km, which shall be constructed as an underground section.The line crosses the River Nile twice. The planned capacity ofthe line when completed is 2.1 million passengers / day. Thetender documents for stage I & II of line 3 are under prepara-tion, stage I starts from Attaba to Abbasia section, stage IIstarts from Abbasia to Heliopolis. All this parts are under-ground, the total length of stage I is 4.3 km and that of stageII is 6.2 km. The design of stage I is taking into considerationthe safe crossing at two major underground structures, name-ly the line 2 bored tunnel at Attaba and the waste-water spinetunnel north of Attaba, the station will be constructed by thecut and cover method.•The transportation study for Greater Cairo Area had beenfinished proposing 6 lines of metro till 2022. Three furthermetro lines are recommended in this in addition to the alrea-dy 3 basic lines [lines 1 & 2 being finished , line 3 under ten-dering ].

    • Currently, there are many road tunnels projects under stu-dying to solve the crossings in many cities other than Cairo asin Sharkia, Ismailia and Ein El-Sokhna

    FINLAND

    During 2005, different events to contribution of rock engi-neering with drill-and-blast method took place inFinland• Management and coordination of in 2002 started, 5-yearsR&D program named “The competitiveness of RockEngineering” • Participation and cooperation in European ConstructionTechnology Platform, ECTP in focus area Underg r o u n dconstruction.

    Finnish people are participating in four working groups:WG6, WG12, WG18, WG20At the moment in Finland there are plenty of undergroundworks under planning or under construction. In the citycentre of Helsinki the construction works of a new under-ground buss terminal have been nearly carried out. The firstphase of the Kamppi project, including buss terminals andunderground car parking was completed in the beginning ofJune 2005: The entire Kamppi complex will open in March2006. There are number of new underground car parkingprojects with 300 - 600 parking places each under way orunder planning in different city centres of Finland. In 2005the new 500 cars underground parking cavern for VTT in thecity of Espoo was taken in use.

    In 2005 excavation works of a 1,5km long road tunnel anda 13,5 km long railway tunnel for the land traffic connec-tions of Vuosaari harbour in Helsinki has been continued. In

    Savio railway tunnel: Vuosaaren satamahanke there are 5different tunnel contracts with drill and blast method underconstruction at same time and the excavation works of thetunnels will be carried out in spring 2006. The harbour pro-ject construction has been started for a new, modern harbourin Helsinki with cargo traffic due to move there from theWest and North harbours in 2008. From environmental rea-sons the land traffic connections will be built underground.Vehicular traffic will be placed in a tunnel to cross the Natu-ra conservation area underground. Railway traffic will beplaced in tunnels to bypass the many city and dwelling areasu n d e rground so minimizing the negative environmentaleffects of the harbour traffic.

    There are several road tunnel projects under constructionin Finland. For instance 7 twin-tube motorway road tun-nels, total length 5,2 km, has been included in the last 50 kmlong part of the new motorway line of E 18 between Helsin-ki and Turku. The contract agreement of the whole projecthas been made and it is based on life cycle model includingconstruction works and 25 years financing and operation per-iod, too. Construction works has been started during 2005:www.tiehallinto.fi.

    In the city centre of Helsinki a new 5 km long utility tunnelincluding district heating and district cooling pipes andmany kind of electricity and telecommunication cables botha district cooling store in rock are under construction. A new,2,5 km long city centre service tunnel for service traffic ofdifferent stores and shopping centres has just been designedand construction works will be started during 2006. In thecity of Turku excavation works for a new underground wastewater treatment plant are ongoing. The total excavation volu-me is 450 000 m3.

    During 2004 the excavation works of Onkalo project,concerning the final disposal of used nuclear fuel inbedrock has been started in Olkiluoto, in western coast ofFinland. This underground research and construction projectwill be continued several years in future.

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 24

    FRANCE

    En 2005, s’est tenu à Chambéry le congrès “Les tunnels,clés d’une Europe durable”. Ce congrès a regroupé 451participants et 151 exposants. L’intégralité des présentationset discussions de la table ronde consacrée à la spécificité destunnels longs et les conséquences sur les difficultés deconception, réalisation et exploitation est publiée dans lenuméro Novembre-Décembre de la revue “Tunnels etOuvrages Souterrains”

    L’Assemblée Générale Extraordinaire du 15 décembre aentériné le changement de nom de l’Association, qui àdater du 1er janvier 2006 devient “L’Association Françaisedes Tunnels et de l’Espace Souterrain”

    Il y a eu 20 groupes de travail actifs, regroupant environ 300participants. Trois recueils thématiques franco-anglais ontété publiés à l’occasion du congrès de Chambéry. Ils concer-nent : les tunneliers et les voussoirs, l’étanchaité et la réhabi-litation. Toutes les versions anglaises des recommandationssont disponibles sur le site de l’AFTES; les versions fran-çaises seront progressivement mise sur le site à partir dusecond semestre 2006.

    Les princiapux travaux souterrains en 2005 : • adjudicationdu tunnel des Grands-Goulets (1,7 km, Drôme), • chan-tiers des galeries de reconnaissance et descenderies du tunnelde base de la LGV Lyon-Turin (descenderies de Modane et deSt Martin La Porte en chantier) • achèvement du tunnel deSchirmeck, • travaux de rénovation du tunnel MauriceLemaire (Ste Marie aux Mines), • divers collecteurs en régionparisienne, • travaux du tunnel du Perthus (Perpignan-Figueras), • achèvement du tunnel du Sinard..

    GERMANY

    DAUB - The German Tunnelling Committee is a registe-red non-profit restricted association with up to 30 mem-bers coming from owners, scientific institutions and consul-tants as well as from contractors. The results of 2 workinggroups active in 2005 and dealing with safety in tunnelling,and dimensioning of shield machines are/will be published inthe international journal "Tunnel". Annual contacts are heldwith the National Groups of Austria and Switzerland..

    DAUB run 6 working groups during 2005:• Safety in tun-nelling jointly with the Austrian and the Swiss NationalTunnelling Committees • Certification of tunnelling experts• Asbestos in tunnelling • Non-reinforced inner shell liningDimensioning of shield machines • Financing of tunnels viaPPP/BOT-projects.

    These working groups are of temporary nature and will beclosed as soon as they have finished their special task.Members of these working groups are mostly also membersof DAUB, but specialists from outside are also involved insome cases.

    The results of the working groups are published in technicaljournals, preferably in "Tunnel", but sometimes also in theGerman handbook of tunnelling (edited annually). Examplesare mentioned above.

    The following major tunnelling projects were running inGermany during 2005: • New ICE high speed lines (250to 300 km/h): between Karlsruhe and Basel; partly upgradedand partly replaced, integrating two major bored tunnel pro-

    Galerie de Modane Bochum Rapid Transit System

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 25

    jects of 9 and 6 km respectively in length. Each tunnelconsists of two parallel single tubes with about 10.5 m exca-vation diameter. Inauguration is planned for 2011 to improvethe traffic connections between Northern and SouthernEurope via Lötschberg and Gotthard base tunnels inSwitzerland. • DB project Stuttgart 21 putting the aboveground main station underground by simultaneously turningit over 90 ° in plan view; this project involves besides the newunderground main station nearly 40 km single/double tracktunnels; intensive design work was started in 1997. Firstconstruction works started during 1998. After an intermedia-te slow down the project was reactivated in late 2001. Theentire project will be finished around 2010.

    General details on tunnelling in Germany can be seen in thetable below according to the latest statistics conducted bySTUVA.

    GREECE

    The Greek Tunneling Society has been fully functional forabout ten (10) years and has an active membership of twohundred eighty one (281). The members are mainly profes-sionals coming from: a) Tunnel owners/client organizations,b) Consulting Engineers, c) Tunnel and General Contractors,d) Tunnels materials Suppliers, e) Universities etc, who areactively involved in tunneling and underground works inGreece and overseas.

    The public activities of the GTS in 2005 have been the follo-wing:

    a) The bimonthly circulation of the newsletter to all its mem-bers with news about GTS, ITA and useful information ontunneling.b) The compilation of the “Registry of the Greek RoadTunnels”, where some thirty two tunnels have been registe-red, out of which twenty six are twin tunnels and six aresingle bore two directional tunnels.c) A one-day symposium, organized in May 2005, and refer-ring to “The analysis and dimensioning of the final lining oftunnels” with papers referring to theory and practical casestudies. The proceedings are available in greek language. Atranslation in English of the proceedings is underway.d) A celebration of the 10 years of the Greek TunnellingSociety with the organization of a lecture presented by Prof.P. Marinos on the “Base Tunnels of the Alps or the New Eraalpine tunnels”, on the 7th of November 2005.e) A one-day technical visit and the official celebration ofSanta Barbara’s day, organized on the 4th of December 2005,with fifty participants. Visits to the Knimida road tunnel ofPATHE under construction and the bauxite mine museum“VAGONETO” have been paid before the annual SantaBarbara lunch.

    GTS actively supports four working groups with conti-nuous and intermittent participation, namely: • WGContractual practices, • WG Shotcrete, • WG ConventionalTunneling, • WG Mechanised Tunneling.

    The following major tunneling projects have been underprogress in Greece, in the year 2005:• Road tunnels of the Egnatia Odos Motorway Project.Twenty five twin road tunnels of total length of about thirtythree km under construction and four twin road tunnels oftotal length of six km under design. • The Patras-Athens-Thessaloniki (PATHE) Motorway Project. Six twin road tun-nels of total length of twenty one km under design/construc-tion. • Other national road tunnels of total length of 3,2 Kmunder construction and 6,4 km under design. • New PlannedMotorway Tunnels of the six mega highway projects to beundertaken by concession BOT contracts which are undertender procedure. These contain some twenty five twin roadtunnels of total length of the order of thirty five km.• AthensMetro extension lines. Two lines with tunnels of total lengthof 9 km under construction and extension of other three lineswith tunnels of total length of twenty one km under tenderdesign. The successful tenderers for two contracts have beenalready announced. • Thessaloniki Metro line. One line withtunnels of total length of twelve km under tender procedure.The successful tenderer has been already announced. •Thessaloniki Road Immersed Tube Tunnel , 3,2 km longunder tender procedure. The successful tenderer has beenalready announced. • The 17,5 Km long Acheloos river diver-sion tunnel to Thessaly Plain, 6m final diameter underconstruction. Has been excavated 9,5km. The related Sykia

    Type in operation under plannedof tunnel constructionmetro 641 26 82railway 487 20 247road 204 39 146Total 1,332 85 475

    Katzenberg Railway Tunnel

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 26

    dam hydraulic tunnels (headrace, tailrace, drainage etc) underconstruction. • Messohora Hydroelectric Project of the PublicPower Corporation various tunnels (access road and long drai-nage tunnel under a village) under construction. • IlarionHydroelectric Project of the Public Power Corporation varioustunnels (headrace, spillway, drainage etc) under construction.• Heraklion Main Trunk Sewer, Tunnel of length of 2.2 kmwith shafts • Rail Tunnels of the Greek Railway UpgradingProject., Three tunnels with total length of nine km under ten-der procedure and another twelve tunnels of total length oftwenty three km under design.

    It is expected that tunnelling boom will continue (with slightslower rate though) in 2006 with the continuation ofconstruction of : a) the Egnatia Motorway Project, b) thePatras-Athens-Thessaloniki-Evzoni (PATHE) MotorwayProject, c) the hydro dam construction projects (Messohora,Ilarion Sykia, Triantafyllia, Papadia, Aposelemis etc), d)Athens Metro lines extension Projects, e) Thessaloniki Metrostarting works, e)The Heraklion main trunk sewer, and the ten-dering of a)the new railway upgrading lines tunnels and b) thesix mega motorway concession projects with affair number oftunnels.

    HUNGARY

    During the year 2005, two seminars with the introductionof ten invited foreign companies on special technicswhere organized as well as 2 sitevisits were hold in Hungaryand one in Vienna on U2 tunnelling. Gus KLADOS (our mem-ber) has got an Award from the BTS for his tunnelling works.and the Hungarian Association is preparing a Proposal forinviting ITA-AITES-2009 to Budapest

    News about the Metro network: The reconstruction workof the 35-years-old 2nd Metroline went on and theworks on three stations and running tunnels between themwere completed in 2005. These reconstruction works aregoing on in 2006 and 2007, as well, and further stations willbe taken under work. Keleti Station will get a 2nd exit (withescalators), as a necessity of the transfer connection for theMetro line No 4. (It is in the final stage of construction).During 2005 was issued the new international Design-Buildtender for the entire tunnelling work and in tree issues the sta-tion tenders. It is the biggest tunnelling-work after theconstruction of Metro line No3. Other tenders for the rest ofthe stations of the Metro line No. 4. will be issued during theyear 2006. Tunnel-construction works will be launched in thesecond part of this year.• Lifts will be built in for every existing metrostation, and inthe future all new metrostation will be supplied with lifts, hel-ping handicapped and old people’s moving.• Having became a member of EU there are more projects on

    which will be built tunnels, as well. • It is on the preparation of the Regional Express Rail (M5), aswell. It will connect Buda North Region and Pest SouthRegion to the citycentre and will give transfer possibility forall other metroline. It is questioning, whether let havy rail runon it or not.• Hungarian road projects are concidering the TEN-T corri-dors in Europe, for creating a traversable European transportnetwork . Construction of autorute M6 is underway, on its sou-thern part will be built tunnels, as well, which are being underplanning.• Tunnels will be necessary to the orbital motorway (M0), itslength will be about 4-6 km.• Also 5-9 km tunnels will be necessary for by-pass roadsunder the capital-city Budapest to dump traffic on the city-centre surface alike on Pest and Buda side. • The construction of Underground Storage Facilities inHungary for low- and intermediate radiation radioactive wastedisposal went on with the construction of an access tunnel.Our association reviewed the work at the site following a pro-fessional day.

    Hungary is connected to the EU, now it makes possiblethe sustainable development through its prosperousconstruction providing more modern infrastructure. A m o n gothers this is why will be tendered the ITA - A I T E S - 2 0 0 9WTC to invite it to Budapest.

    ICELAND

    The Icelandic Tunnelling Society which represents the ITANational Groupof Iceland is an inde-pendent group oftunnelling professio-nals with corporateand ordinary mem-bers. The NG boardheld regular mee-tings and memberswere heavily invol-ved in planning,design and construc-tion management andsupervision of largehydro and road tun-nel projects.

    The constructionof the major tun-nelling works ofKarahnjukar hydroproject continued inthe year 2005. T h e

    Karahnjukarpowerhouse station

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 27

    excavation of the powerhouse complex was completed andsome 25 km of the 50 km TBM tunnels have been excavated.The 1,3 km Almannaskard road tunnel was opened for trafficin June after a record breaking progress with conventionaldrill and blast excavation. The 5,9 km Faskrudsfjördur roadtunnel was opened for traffic on schedule in September.Further underground hydro and road projects are in the desi-gn process and one 10,6 km long road tunnel will be tenderedin the first half of 2006.

    INDIA

    Two conferences have been organized during year 2005 :DE V E L O P M E N T O F HY D R O PO W E R P R O J E C T S – AProspective Challenge , 20-22 April 2005, Shimla ThisConference including a special session on ‘ Small HydroPower Development ‘ was organised by the Central Board ofIrrigation and Power jointly with Himachal Pradesh StateElectricity Board in association with the Adhering Committeeof ITA (India) from 20-22 April 2005 at Shimla (HP). 175delegates from Bhutan, Nepal and from across the country,participated in the conference. 33 presentations, includingthree from Bhutan, on the various topics concerning develop-ment of hydropower projects, such as Hydro Power Policiesand Development Strategies, Hydrology and Planning,Design Aspects, Instrumentation and Electro-Mechanical &Hydro-Mechanical Equipment, Small Hydro PowerDevelopment, Environmental Issues and Private SectorParticipation, Construction Aspects, Silting & SedimentationProblems and Rehabilitation & Resettlement, were madeduring the conference. The Hon’ble Chief Minister,Government of Himachal Pradesh, Shri Virbhadra Singh,inaugurated the conference on 20th April 2005. SAFETY INCONSTRUCTION 30-31 May 2005, Chandigarh The aboveseminar was jointly organised by the Central Board ofIrrigation and Power (CBIP), The Institution of Engineers(India), Punjab,Chandigarh State Centre & Safety andQuality Forum IEI) in association with the A d h e r i n gCommittee of ITA (India) from 30-31 May 2005 atChandigarh.The seminar was inaugurated by Shri K.C. Pant,Former Defence Minister, Govt. of India and Ex-DeputyChairman, Planning Commission. There was excellent res-ponse both from authors and participants. More than 100delegates from various government organizations, manufac-turers and academic institutions participated in the seminar.Seven Keynote addresses were delivered by the eminent engi-neers in the field during the seminar: 15 papers were presen-ted by the various experts pertaining to Safety in Constructionin 4 technical sessions i.e. “Power projects”, “Roads & rail-ways”, “Buildings & construction projects” and “Safety inconstruction and related issue”. A proceedings volume,containing all the technical papers discussed during the twodays deliberations, was brought out. At the end of the semi-

    nar a CD containing all the power point presentations presen-ted by the various authors during the two deliberations wasdistributed to all the participants present during the seminar.The seminar was sponsored by National Thermal PowerCorporation Ltd. and Punjab State Electricity Board

    The General Body Meeting of the Committee was conve-ned on 6th July 2005 at New Delhi under theChairmanship of Shri Yogendra Prasad, President of theCommittee & Ex. CMD, National Hydro Electric PowerCorporation Ltd., Faridabad, Vice PresidentsDr.T.Ramamurthy, Former Prof.IIT Delhi and Shri ManguSingh, Chief Project Manager, Delhi Metro Rail CorporationShri G.N.Mathur, Secretary General of the A d h e r i n gCommittee of ITA (India) welcomed the members andrequested for their active participation in the activities of theCommittee and informed the General Body that he has atten-ded the meeting of ITA General Assembly held at Istanbul,Turkey on May 8-11, 2005, wherein he made a presentationfor holding World Tunnel Congress in India at New Delhi, inSeptember 2008. The ITA General Assembly approvedIndia’s proposal to hold the 2008 ITA Congress in India. Thetheme of the Congress is ‘ Underground Facilities for BetterEnvironment and Safety’General assembly will also be heldalong with the Congress.

    The General Body suggested the following topics for orga-nising the workshop / Training Course for the year 2005-2006. • Training Course on “Underground excavation by rockblasting” 6-9 June 2006, J&K. • Workshop on “RockMechanics and Tunnelling Techniques”

    PRACTICES ADOPTED FOR TUNNELLING OFDELHI METROOn July 2005 the entire Metro Corridor from Vishwa Vidya-laya to Central Secretariat has been commissioned alongwith the K.P. Depot in two phases. The first segment wasopened for revenue services on 19.12.2004 from Vi s h w aVidalaya to Kashmere Gate including K.P. Depot and the restof the portion has been made available for public on02.07.2005 from Kashmere Gate to Central Secretariat. Thissegment is very important link between two main link of theDelhi Metro i.e. Shahdara to Rithala and from BarakhambaRoad to Dwarka.

    The underground section comprises of 10 stations in whichthe station construction has been done by cut and covermethod either by adopting bottom up construction sequenceor top-down/semi top-down construction sequence exceptthe Chawri Bazar Station. The Chawri Bazar station has beenconstructed below ground through two shafts viz. Hauz Qaziand Amar Cinema. The Chawri Bazar Station is situated in adensely populated area having dilapidated buildings. T h econstruction of this station has been completed without anydamage to surface construction.

  • Member Nations Report 2005

    TRIBUNE n°30 - ITA- AITES - Apr i l 2 0 0 6 28

    The tunnelling in between the stations has been done eitherby cut and cover method or by using tunnel boring machinesfor the rocky strata as well as in alluvium (Delhi silt). Tw oEarth Pressure Balance machines have been deployed forexecuting tunnelling in alluvium portion i.e. from KashmereGate to Delhi Main, New Delhi to Rajiv Chowk and fromRajiv Chowk to Patel Chowk. The rock TBM has beendeployed for construction of tunnels between Delhi Main toChawri Bazar but due to poor progress of rock TBM one ofthe earth pressure balance machine has been modified fordoing tunnelling in rocky strata from Delhi Main to ChawriBazar. To meet the project schedule NATM tunnels has beendone from New Delhi to Chawri Bazar Station, which wassupposed to be done by using rock tunnel boring machines.

    The completion of the above underground section has beendone nine month ahead of schedule. The commissioning ofthis segment given boost to the city and made the dream ful-filled for the commuters.

    ITALY

    Società Italiana Gallerie is an open association (approxima-tely 700 members), that promotes, coordinates and spreadsthe results of studies and researches in underground works. Itpublishes the “Gallerie e grandi opere sotterranee/Tunnels andlarge underground works” magazine (in Italian and English).

    At Istanbul, during the ITA World Tunnel Congress, morethan 10 Italian Representatives attended the variousWorking Groups Session and two of them are Animateurs ofWG.

    The next few years is a good period in Italy for the deve-lopment of large infrastructure projects involving a lot oftunnelling works both conventional and mechanized.1) An important mega project will be at the Final DesignStage: the 52Km-long Base Tunnel and the 12Km-long Bus-soleno Tunnel on the Ly o n - Turin new railway link betweenItaly and France, where 2 exploration tunnels on the Frenchside are already under construction and the contract for the upto 10Km-long Venaus exploration tunnel on the Italian sidehas just been awarded by LTF and construction of this tunnelwill start very soon.

    2) Works for the Milan-Genoa high speed railway line willstart; the project comprehends two tunnels respectively 9 and30 Km long.

    3) Two macro-lots for the new motorway Umbria-Marchewill be at final design stage: the Quadrilatero 1 macro-lotcomprehends tunnels for 28 Km, the Quadrilatero 2 macro-lotcomprehends tunnels for 16 Km.

    4) More than 18 Km of tunnels are under construction for themodernisation of the Salerno-Reggio Calabria motorway.

    5) Many big urban transformation projects shall be realized:

    • The design and build contract for the Passante di To r i n oProject (an underground railway section in the center ofTurin) has just been tendered;

    • The design and build contract for the Passante di Bologna(railway) Project is under construction with EPB machines;

    • The design and build contract for the Passante di Palermo(railway) project has already been awarded;

    • The contracts for the design and construction of Line C(17Km long) and Line B1 (6Km) of Rome Metro are in theprocess of tendering.

    • The important metro line of Brescia is under Constructionwith an EPB machine.

    • The new section of the Milan metro to reach the new “Fieradi Milano” with an EPB machine was finished.

    Many other large-diameter railway and road tunnels are eitheralready under construction or in the phase of constructionprocurement.

    Th