Tribal Transportation ProgramUpdate
JULY 23, 2014
Legislative Update◦ Highway Trust Fund status◦ Reauthorization proposals◦ FY15 Appropriations
TTP Safety Funding TTP Bridge Funding
Topics
2 issues at present◦ Highway Trust fund is going broke
We have authority and limitation, just nothing in the account to cash the check with.
DOT is implementing reduced state reimbursements beginning August 1
No effect on TTP except possible Safety funds (app process)◦ MAP-21 expires in 71 days
Best case scenario is legislative fix to both issues; ◦ Both houses have a proposal◦ Extension will be until either December or May (House)◦ Congress in session only for a few more days◦ Midterm elections are in 105 days
Legislative Update
Insolvency of Highway Trust Fund
Requires Congressional action
Not enough cash on hand to support full annual program
Limits amount of cash available to reimburse commitments
2 Issues impacting TTP Expiration of current
highway act (MAP-21)
Requires Congressional action
Extension of Act or reauthorization still requires action on the highway fund insolvency
Unique features of TTP Contracts allow different drawdowns depending on
agreement type 92% of TTP funds are subject to Tribal Shares
So what does this mean?◦ An expiration of the authorizing highway act,◦ Finding funding to support the highway trust fund
account,◦ Resulting in partial funding in FY15 and delays in
program delivery
Legislative Update
FY 14 is final year of MAP-21 Senate Environment and Public Works (EPW)
Committee has passed the “MAP-21 Reauthorization Act”
◦ 6 year Bill◦ TTP
No changes $450 million/year through FY 2020
Reauthorization Proposals
GROW AMERICA ACT Proposal The Administration has sent a Bill to
Congress◦ GROW AMERICA ACT “Generating Renewal, Opportunity, and
Work with Accelerated Mobility, Efficiency, and Rebuilding of Infrastructure and Communities throughout America”
4 year Bill TTP is included with increase in program $$
No change in formula Some change in takedowns Brings HPP back into the primary program
GROW AMERICA - TTP
Authorized Amounts◦ FY15 - $507 million◦ FY16 - $517 million◦ FY17 - $527 million◦ FY18 - $538 million
Takedowns◦ 6% PM&O◦ 4% Bridge◦ 3% Planning◦ 2% Safety; and◦ 7% HPP
GROW AMERICA - TTP 3rd year of transition formula
◦ 40% FY 11 tribal shares with remainder under new MAP-21 statutory formula
Bridge◦ Set aside increase is to provide funding for
inspection and additional projects Planning
◦ Set aside increase is for data collection and other transportation planning activities
HPP◦ Brought back into the program◦ $1.5 million maximum project size
Other GROW AMERICA opportunities SEC. 2008. NATIONALLY SIGNIFICANT FEDERAL
LANDS AND TRIBAL PROJECTS PROGRAM◦ Would provide $150 million/year in funding to
construct, reconstruct, or rehabilitate nationally significant Federal lands and Tribal transportation projects. (NO DESIGN) Projects must have NEPA completed and an estimated
cost equal to or exceeding $25 million. Priority consideration will be given to projects over $50
million◦ Intent is to fund high cost projects that are not able
to be funded through regular programs◦ 2-3 projects/yr.
Other GROW AMERICA opportunities FIXING AND ACCELERATING SURFACE
TRANSPORTATION (FAST) GRANTS◦ A competitive program designed to achieve National
transportation outcomes Projects must promote the implementation of policies and
procedures that generate long-term, institutionalized changes, and support performance based management. (Basically supports best practices)
Criteria included in proposal Awards of no less than $50,000,000 ($$ amount not
applicable to tribes) $1 Billion over 4 years
TIGER◦ Continues with tribes as eligible applicants◦ Proposed at $1.25 Billion/year
Reauthorization Summary
Act still needs full vote by the Senate Nothing passed yet in the House Remember: SAFETEA-LU expired in ‘09 but
was extended 9 times until MAP-21 was passed in July 2012
DOT will still need an Appropriations Bill for next year before full funding is made available
126 Applications received asking for $27.1 million
Reviewed and selected for award:◦ Education 7 $418,589◦ Enforcement/EMS 8 $1,701,290◦ Engineering 12 $5,415,625◦ Safety Plan 49 $615,000◦ Other Safety Planning 6 $390,495◦ Total Funded 82 $8,540,999
◦ Not Funded (Not Q) 44 $18,538,285
FY14 TTP Safety Funding - Tentative
FY 14 Construction – 8 BIA/Tribal - $5.5 M
6 non BIA/Tribal - $2.6 M
Engineering - 4 BIA/Tribal - $152 K 1 non BIA/Tribal - $64K
TTP Bridge Program (deficient TTP bridges)