TREX-45036
-
Upload
osdocs2012 -
Category
Documents
-
view
217 -
download
0
Transcript of TREX-45036
-
7/28/2019 TREX-45036
1/48
Risk Register and Action Tracking Sheet for E&P Projects
This workbook is the property of BP Exploration. It has been designed to fulfil the minimum specifica
Quick Start
Enter data in: 1. SETUP Enter risk categories & personnel. Customise the Probability-Impact G
2. REGISTER Describe and analyse project risks and opportunities3. ACTIONS Define and track actions in response to risks
The grey-tabbed worksheets contain output only
Cells like this are for typing in free text
Cells like this are also for free text, but contain useful default values
Cells like this have pull-down menus (which you can customise)
Cells like this are protected because they contain calculations
Initial Workbook SetupUse this workbook for tracking your project risks (threats and opportunities) and the actions which result.To prepare the workbook for use in your project, complete the following steps:
1. Clear the example entries from the REGISTER and ACTIONS sheets (only clear columns with yellow a2. Fill in the Project Name at the top of the REGISTER sheet.3. Customize the SETUP sheet as follows:
(a) Decide which quantifiable measures of project impact (eg Cost, Schedule, Reserves) you are going(b) In cells C14 to C20, input the total Project Cost, Duration etc.(c) In cells D14 to D20, enter the percentage of Project Cost, Duration etc. above which the impact of a(d) In cells G5 to G22, enter the "Categories" you will use to classify your risks. Give each one a short
(e) In cells M5 to M54, list the project personnel (or job positions) who will play a formal role in the risk(f) For each person, indicate whether they can: (i) Own, Accept or Update risks in the Register, (ii) be(g) If you wish, you can change the titles and definitions in the olive cells to match your lo
Inputs and OutputsEnter and analyse your risks in the REGISTER sheet. The "Data Check" column will show "Error!" when t
Tip: When analysing risks as a team, it may be useful to give each team member a print out of the ReferTo enter an action, type the risk number into column A in the ACTIONS sheet, then enter the action detail
Outputs are as follows:
(a) "Pre-PIG" and "Post-PIG" matrices show the Probability-Impact grid before and after risk response.(b) "Boston Square" or "Risk Manageability Matrix".
Each matrix can be toggled between 9 and 20/30 risks-per-cell using the "Expand" and "Shrink" maIf a matrix cell has more risks than spaces, the number of risks not shown will appear in the bottomThe matrices will show only risks from categories for which "Show?" is set to "yes" in column I on th
(c) Charts - a simple breakdown of risks and actions(d) "Print" Summary. This is a fixed-format summary of the full Register worksheet, suitable for printing
ProtectionThe workbook is protected against inadvertent changes, but can be unprotected using Tools->Protection-The AutoFilter buttons at the top of the columns in the REGISTER and ACTIONS sheets won't work wh
Simplifying & Customizing the RegisterMost risk management processes don't require an entry in every column of the REGISTER and A
You can hide optional columns using the Group (-) buttons at the top of each sheet. Clear the conteYou can also hide sheets you are not using (eg. the "Boston" or "Post-PIG" sheets).
You can enlarge matrix cells as follows: Tools->Protection->Unprotect Sheet, select cell columns, Format
To avoid empty columns on the "Print" report, use the Tools-Protection-Unprotect Sheet command, and h
Importing data from Common Process on-Line (CPoL)If you prefer to manage you risks within CPoL, you can still use this workbook to produce Risk Matrix out
-
7/28/2019 TREX-45036
2/48
Feedback on this workbook and requests for enhancements are always welcome
Facilitating a Risk Management Meeting
Initiate
Get familiar with the tool (eg. Risk Register) you are going to use to record the session. Plan the session by dividing it into distinct sections (Identification; Analysis; Response) Consider adding a section on Opportunities.At the start of the session, explain to the team:
o The deliverable (eg. a Register populated with identified and analysed risks)o The scope of the risks (eg. drilling, D&C, wells, project, technical, HSE etc.)o How much time youve got, and how it will be sub-divided
Consider appointing a time-keeper.Identify If you have written inputs (eg. a risk register from a similar project), choose your moment Use a combination of techniques, eg:
o Start with five minutes for individuals to write down riskso Brainstorm risk headings (eg. rig, personnel, well planning, operations, security etc).o Work through headings in turn.
Help the team define events, not outcomeso Risk event template: Event X may happen, causing an impact on Y.o Bad risk: Completion cost overruno Good risk: Inadequate completion cost estimate causes cost overrun
Dont let the team get sidetracked into analysis or response.Assess
If you havent done it already, agree cost and schedule impact levels with the team Clarify the risk acceptability criteria with the team (eg. Risks rated or
-
7/28/2019 TREX-45036
3/48
Are you planning to reduce the probability, the impact, or both ?
Will the reduction be a little (one square) or a lot (two squares) ?
ControlAgree how the team will keep the risk register up-to-date between meetings.Agree the date, subject and attendance for your next meeting. Make the risks visible put them on a poster and put it on the wall.Learn Make a note of:
o what worked and what didnto what were the sticking pointso people who should have been present and werent, and vice versao things you could have done before the session to better prepare yourself or the team.
If youve got something to share about your process, share it with Hugh Williamson, D&C
For a synopsis of Risk Management best practice as it applies to wells projects, go to the
-
7/28/2019 TREX-45036
4/48
Version 8.04
ions of the Risk Management Guidelines for Major Projects
id
nd blue headers)
to use, and enter these in cells A14 to A20.
risk will be defined as "Very High".bbreviation and indicate whether you want to show these risks on the matrices.
anagement process. Put their initials in the "Abbrev." column.esponsible for carrying out or providing assurance on actions.al definitions.
he REGISTER entries don't correspond to the entries in the SETUP sheet.
nce Sheets.
cro buttons.right space.e SETUP sheet.
.
>Unprotect Sheet. Be sure to re-protect the sheet when you have finished your edits.ile the sheets are protected : unprotect, then filter, then re-protect.
TIONS sheets.
nts of each column before you hide it.
->Column->Width. The default column width is 10.
ide any unused columns.
uts. Instructions are on the "From CPoL" worksheet.
http://global.bpweb.bp.com/http://global.bpweb.bp.com/ -
7/28/2019 TREX-45036
5/48
: Hugh Williamson, EPTG Sunbury
for introducing them carefully you want to stimulate, not stifle, the discussion.
after response cannot be accepted by the team and must be escalated).
works.
ulting in a given impact
hich reduce the risk in different ways (probability, impact, contingency etc)
mailto:[email protected]?subject=Generic%20Risk%20Registermailto:[email protected]?subject=Generic%20Risk%20Register -
7/28/2019 TREX-45036
6/48
Risk Management Specialist.
D&C Risk Management website
http://upstream.bpweb.bp.com/ept/content/page.asp?id=1836http://upstream.bpweb.bp.com/ept/content/page.asp?id=1836 -
7/28/2019 TREX-45036
7/48
Risk Register for Project: Macondo
R/O
no.
Data
Check
Risk
orO .
Category Risk/Opportunity Name Event Descriptio
1 OK T NDS Well ControlPotential well control problem: ris
2 OK T NDS Complex overburden Multiple shallow water flow units
3 OK T NDS PP/FG uncertainty
Drilling into pressure ramps unexproper mud weight or shoe test closs, and stuck pipe which lead
4 OK T NDS Wellbore stabilityDrilling through any salt/sedimenencounter problems with shales the well bore
5 OK T NDS Tight hole, stuck pipeOffset well (Rigel) encountered pat 8900'.
6 OK T NDSMass Transport Deposits(MTD)
Can be shallow water flow units wabout 500 ft in deepwater settingpressured. May have quite variaideal strata to set casing shoe. depth of csg shoes with respect identified geophysically and in of
7 OK T NDS Reduced wireline programLoss of data or limited data colle
8 OK T NDS Lost CirculationLost circulation indentified in thecost.
9 OK T NDS Narrow PPFG window
Isabela had a narrow PPFG windweight and hole conditions are nwell may begin to experience suformation or the well may flow ba
11 OK T NDS HurricaneHurricanes and storms often excrig must unlatch and move to saf
General
-
7/28/2019 TREX-45036
8/48
Risk Action Tracking for Project: Macondo
R/O
no.
Risk
or
Opp.
Category Risk Name Description
Risk / Opportunity
-
7/28/2019 TREX-45036
9/48
Pre-Response Probability-Impact Grid for: Macondo
NDS.14 Shallow
water/gas flows
NDS.15 Lost drill
center/respud
Plan.18 BOP
Issue
Plan.21 Annular
Pressure Build-up
NDS.2 Complex
overburden
NDS.5 Tight hole,
stuck pipe
Plan.20 Shock &
Vibration
NDS.1 Well
Control
NDS.3 PP/FG
uncertainty
NDS.7 Reduced
wireline program
NDS.17 Shallow
depletion
Plan.23
Expandable
Issues
NDS.9 Narrow
PPFG windowNDS.11 Hurrican
Plan.22
Compaction
NDS.4 Wellbore
stability
NDS.6 Mass
Transport
Deposits (MTD)
NDS.8 Lost
Circulation
NDS.16 Gumbo
Attack
NDS.13 Hydrate
buildup on
wellhead /
connector
S Very Low Low Moderate
Frequency / Probability
V. High Risk must be reduced or eliminated. High
Mod. ALARP: Reduce risk where cost-beneficial. V. Low
VeryHig
High
Medium
Low
ImpactLevel
-
7/28/2019 TREX-45036
10/48
Boston Square: Macondo Date
NDS.11 HurricaneNDS.12 Loop and
Eddy currents
Plan.18 BOP
Issue
Plan.21 Annular
Pressure Build-upNDS.1 Well
Control
NDS.3 PP/FG
uncertainty
NDS.9 Narrow
PPFG window
NDS.14 Shallow
water/gas flows
NDS.2 Complex
overburden
NDS.5 Tight hole,
stuck pipe
Plan.23
Expandable
Issues
NDS.7 Reduced
wireline program
NDS.16 Gumbo
Attack
NDS.8 Lost
Circulation
NDS.17 Shallow
depletion
Plan.20 Shock &
Vibration
Plan.22
Compaction
NDS.4 Wellbore
stability
NDS.6 Mass
Transport
Deposits (MTD)
NDS.13 Hydratebuildup on
wellhead /
connector
S Low Medium High
Manageability
V.Low
.
Low
Mod.
H
igh
(Pre-Response)RiskRating
-
7/28/2019 TREX-45036
11/48
Post-Response Probability-Impact Grid for: Macondo
NDS.15 Lost drill
center/respud
NDS.14 Shallow
water/gas flows
Plan.18 BOP
Issue
Plan.21 Annular
Pressure Build-up
NDS.2 Complex
overburden
Plan.20 Shock &
Vibration
NDS.3 PP/FG
uncertainty
NDS.5 Tight hole,
stuck pipe
Plan.23
Expandable
Issues
NDS.1 Well
Control
NDS.9 Narrow
PPFG window
NDS.12 Loop and
Eddy currents
NDS.17 Shallow
depletion
NDS.11
Hurricane
NDS.6 Mass
Transport
Deposits (MTD)
NDS.13 Hydrate
buildup on
wellhead /
connector
NDS.16 Gumbo
Attack
S Very Low Low Moderate
Frequency / Probability
V. High Work cannot proceed. High Obta
Mod. Review within team before proceeding. V. Low Man
VeryHig
High
Medium
Low
ImpactLevel
-
7/28/2019 TREX-45036
12/48
Risk* Summary for: Macondo Date 12-Apr-13
* includes opportunties
4
7
6
0
0
4
8
10
0
0
0 5 10 15
V. Low
Low
Mod.
High
V. High
No. of Risks* by RatingPre-Response
Post-Response
0 2 4 6 8 10 12 14
Chuck Bondurant
Donald Charles
Binh Van Nguyen
Chris Casler
Tomieka Searcy
Pierre Depret
Mark Hafle
Jonathan Bellow
Bobby Bodek
Jasper Peijs
David Sims
George Gray
Craig Scherschel
Team
Marty Albertin
Trent Fleece
Gabe Wilson
Risk* Ownership and ActionsRisks Owned
Actions
0 5 10 15 20
Active
Dormant
Accepted
Closed
No. of Risks* by Status
0 5 10 15 20
HSSEPlanning
SidetrackingSalt Interval
Salt ExitSub Salt
CoringEvaluation
PPFGWeather/Loop
Csg & CmtngWell Control
Rig EquipmentDWOP
BHA/DH EquipInitial Ops
Well Exit OpsNDS
No. of Risks* by Category
0 0.5 1
Country & Reg.
Market & Comm.
H, S & E
Tech. Challenge
Defn. & Complexity
Oper'ty & Ramp-up
No. of Risks* by Category
-
7/28/2019 TREX-45036
13/48
-
7/28/2019 TREX-45036
14/48
Risk Register for Project: Macondo Date: 20-Jun-09
Risk#
Risk/Opport.
Category Risk Name Event Description / Impact
Owner
RiskStatus
Actions
1 T NDS Well ControlPotential well control problem: risk of losing the wellbore inan uncontrolled situation
MH Accptd 0
2 T NDS Complex overburden Multiple shallow water flow units, faults & potential gas. CS Accptd 0
3 T NDS PP/FG uncertainty
Drilling into pressure ramps unexpectedly or without propermud weight or shoe test can cause a kick, fluid loss, andstuck pipe which lead to possible loss of hole section and/orwell. Kicks identified in the offsets.
MA Accptd 0
4 T NDS Wellbore stabilityDrilling through any salt/sediment interface may encounterproblems with shales sloughing/slumping into the well bore
MH Dorm. 0
5 T NDS Tight hole, stuck pipeOffset well (Rigel) encountered problems with stuck pipe at8900'.
MH Accptd 0
6 T NDS Mass Transport Deposits (MTD)
Can be shallow water flow units when buried deeper thanabout 500 ft in deepwater settings, may be over pressured.May have quite variable soil properties. Not ideal strata to
set casing shoe. Evaluate the setting depth of csg shoeswith respect to the depth of MTDs identified geophysicallyand in offset wells. Have pump and dump mud ready to killSWF while drilling riserless.
BVN Accptd 0
7 T NDS Reduced wireline programLoss of data or limited data collection as a result of wellproblems or borehole environmental conditions.
T Accptd 0
8 T NDS Lost CirculationLost circulation indentified in the offsets. Risk to time andcost.
MH Active 0
9 T NDS Narrow PPFG window
Isabela had a narrow PPFG windows (Miocene): if mudweight and hole conditions are not monitored carefully thewell may begin to experience substantial losses to theformation or the well may flow back
MA Accptd 0
10
11 T NDS HurricaneHurricanes and storms often exceed tolerances, and the rigmust unlatch and move to safer conditions.
T Accptd 0
12 T NDS Loop and Eddy currentsLoop and eddy conditions occur almost throughout the yearin many GoM deep water areas. Delays caused by highcurrent velocities can be very costly.
T Accptd 0
13 T NDSHydrate buildup on wellhead /connector
Potential for hydrate buildup around connectors preventingunlatching.
MH Accptd 0
14 T NDS Shallow water/gas flowsUncontrolled shallow water and gas flows prior to riserinstallation could undermine and crater the drill center. Seecomplex overburden
MH Accptd 0
15 T NDS Lost drill center/respudWellhead Subsidence, stuck pipe, surface fracture, TOSrubble zone: potential risk for collapse/squeezing of allconductors
MH Accptd 0
16 T NDS Gumbo Attack Gumbo due to pump and dump. MH Accptd 0
17 T NDS Shallow depletion Evaluate potential for depleted zones. MA Accptd 0
18 T Planning BOP Issue Potential for the BOP stack to cause NPT on the well. TF Accptd 0
19 T Planning Zonal Isolation Risk of a good cement job on the 9-7/8 Production String MH Active 0
20 T Planning Shock & Vibration Risk of down hole tool failures due to shock and vibration. MH Accptd 0
Risk Description
-
7/28/2019 TREX-45036
15/48
21 T PlanningAnnular Pressure Build-up
Risk of casing failure during the production phase of the well. MH Accptd 0
22 T Planning Compaction Casing failure late in life due to reservoir compaction. MH Active 0
23 T Planning Expandable Issues Risk of tubular exspansion failure. MH Accptd 0
24
25
26
27
2829
30
31
32
33
34
35
36
37
38
39
40
4142
43
44
45
46
47
48
49
50
51
52
53
5455
56
57
58
59
60
61
62
63
64
65
66
6768
-
7/28/2019 TREX-45036
16/48
69
70
71
72
73
74
75
76
7778
79
80
81
82
83
84
85
86
87
88
89
9091
92
93
94
95
96
97
98
99
100
101
102
103104
105
106
107
108
109
110
111
112
113
114
115
116117
118
-
7/28/2019 TREX-45036
17/48
119
120
121
122
123
124
125
126
127128
129
130
131
132
133
134
135
136
137
138
139
140141
142
143
144
145
146
147
148
149
150
151
152
153154
155
156
157
158
159
160
161
162
163
164
165
166167
168
-
7/28/2019 TREX-45036
18/48
169
170
171
172
173
174
175
176
177178
179
180
181
182
183
184
185
186
187
188
189
190191
192
193
194
195
196
197
198
199
200
-
7/28/2019 TREX-45036
19/48
Instructions for Importing Risk Data from CPoL1.Create Excel risk report from CPoL2. Copy all the data from the CPoL report and paste into the bordered box below (us3. Ensure that the "Data Check" column shows "OK" for all imported risks
If the Data Check shows "Error!", the entry in one of the orange columns does not a
4. Click on the green macro button (left). The matrices should now be plotted.
Note: The "Data Check" on the REGISTER sheet may still show Error!s. Further edits to thProject n/a Risk Name Owner Risk Event Status
Risk Data Check
1 OK2 OK
3 OK4 OK5 OK6 OK7 OK8 OK
9 OK10 OK11 OK
12 OK13 OK14 OK15 OK16 OK
17 OK18 OK19 OK20 OK21 OK22 OK23 OK
24 OK
25 OK26 OK27 OK28 OK29 OK30 OK31 OK
32 OK33 OK34 OK35 OK36 OK37 OK
38 OK
39 OK40 OK41 OK42 OK43 OK44 OK45 OK
46 OK
ReplaceRegisterData with
CPoL Data
-
7/28/2019 TREX-45036
20/48
47 OK48 OK49 OK50 OK51 OK52 OK
53 OK54 OK55 OK56 OK57 OK58 OK59 OK60 OK
61 OK62 OK63 OK64 OK65 OK66 OK
67 OK68 OK69 OK70 OK71 OK72 OK73 OK74 OK
75 OK76 OK77 OK78 OK79 OK80 OK
81 OK82 OK83 OK84 OK85 OK86 OK87 OK88 OK89 OK
90 OK91 OK92 OK93 OK
94 OK95 OK
96 OK97 OK98 OK99 OK
100 OK101 OK102 OK
-
7/28/2019 TREX-45036
21/48
103 OK104 OK105 OK106 OK107 OK108 OK
109 OK110 OK111 OK112 OK113 OK114 OK115 OK116 OK
117 OK118 OK119 OK120 OK121 OK122 OK
123 OK124 OK125 OK126 OK127 OK128 OK129 OK130 OK
131 OK132 OK133 OK134 OK135 OK136 OK
137 OK138 OK139 OK140 OK141 OK142 OK143 OK144 OK145 OK
146 OK147 OK148 OK149 OK
150 OK151 OK
152 OK153 OK154 OK155 OK156 OK157 OK158 OK
-
7/28/2019 TREX-45036
22/48
159 OK160 OK161 OK162 OK163 OK164 OK
165 OK166 OK167 OK168 OK169 OK170 OK171 OK172 OK
173 OK174 OK175 OK176 OK177 OK178 OK
179 OK180 OK181 OK182 OK183 OK184 OK185 OK186 OK
187 OK188 OK189 OK190 OK191 OK192 OK
193 OK194 OK195 OK196 OK197 OK198 OK199 OK200 OK
-
7/28/2019 TREX-45036
23/48
Paste Special-Values to preserve the formatting).
ppear in the SETUP sheet. Edit the SETUP sheet accordingly.
e SETUP sheet will fix these.Category n/a Impact Type Impact level Probability n/a
KEY:
Pre-Mitigation
Data is copied but
not checked
Data is copied and
checked vs SETUPData is not copied
-
7/28/2019 TREX-45036
24/48
-
7/28/2019 TREX-45036
25/48
-
7/28/2019 TREX-45036
26/48
-
7/28/2019 TREX-45036
27/48
Impact Type Impact Level Probability n/a ByAccepPost-Mitigation
-
7/28/2019 TREX-45036
28/48
-
7/28/2019 TREX-45036
29/48
-
7/28/2019 TREX-45036
30/48
-
7/28/2019 TREX-45036
31/48
Date Manageabilitytance
-
7/28/2019 TREX-45036
32/48
-
7/28/2019 TREX-45036
33/48
-
7/28/2019 TREX-45036
34/48
-
7/28/2019 TREX-45036
35/48
Risk Rating Matrix - customize the matrix in the SETUP worksheet
One or morefatalities
Damage long-term and/orextensive
_Outrage.
Prosecution.Possible loss of
operating license
Commended byNGO at
internationallevel. Globalrecognition
> 10 $M > 12.75 days> 0.1 oProjec
Productio
Serious injury orDAFWC.
HiPo
Short-termdamage within
facility boundary
Long-term and/orextensive
improvement
Involvement ofregulator
Commended byNGO at national
level.Recognition
within country
3 - 10 $M3.4 - 12.75
days
0.03 - 0.1Projec
Productio
Recordableinjury, first aid,
seriousoccurrence
Rapid on-siteclean-up
Short-termimprovementwithin facility
boundary
Complaints fromlocal community
Commended byNGO at local
level.Recognitionwithin area
1 - 3 $M 0.85 - 3.4 days0.01 - 0.0
ProjecProductio
No impact No impact Minorenhancement
Minimal impact
recognised
positivecontributionwithin BP
< 1 $M < 0.85 days < 0.01 oProjecProductio
Probability
Very Low
Low
Moderate
High
ManageabilityLow
MediumHigh
Could only occur as the result of multiple, independent system or control failures.Future occurrence is thought most unlikely.No comparable occurrence is known.
Prob-
Project Management Team can control probability and / or impact. Risk reduction measures will be highly cost-effect
Reputation:
OpportunitiesSchedule Producti
Project Management Team can only influence impact. Risk reduction measures are unlikely to be cost-effective.
Project Management Team can influence probability and / or impact. Risk reduction measures will be roughly cost-n
ImpactLeve
lCould result from a plausible combination of system or control failures.
Would probably occur if the system were to be operated for long enough. Comparableevents are known to have occurred in the past.
Could result from the failure of a single system or control.Could be expected to occur if this operation were repeated regularly.Comparable events are within the team's direct experience.
Uncontrolled.Will occur whenever circumstances are unfavorable.Comparable events are frequent.
ImpactLevel
Type of Impact
Health & SafetyEnvironment:
ThreatsCost
Environment:
Opportunities
Reputation:
Threats
-
7/28/2019 TREX-45036
36/48
Risk Register Set-Up Sheet
Probability Abbrev Categories
Very Low VL AbbrevLow L HSSE HSSE
Moderate M Planning PlanHigh H Sidetracking ST
Impact Type Salt Interval SIHealth & Safety Saf. Salt Exit Sext
Environment: Threats Env (T) Sub Salt SsubEnvironment: Opportunities Env (O) Coring Core
Reputation: Threats Rep (T) Proj. Top Evaluation EvalReputation: Opportunities Rep (O) Value Level Unit PPFG PPFG
Cost Cost 100 10% $M Weather/Loop Currents WeaSchedule Sch. 85 15% days Csg & Cmtng Csg
Production Prod. 10% mbd Well Control WCntrlReserves Res. 15% MMbbl Rig Equipment REquip
NPV NPV 10% $M DWOP DWOPBHA/DH Equip BHA/EqInitial Ops IOps
Impact Level Well Exit Ops WEOpsLow L NDS NDS
Medium MHigh H Abbrev
Very High VH Class #1 (threats) T
Risk Rating Pre Post Class #2 (opportunities) OV. Low VL 4 4
Low L 8 7Mod. M 10 6 Cost 10High H 0 0 3
V. High VH 0 0 1
Manageability Schedule 12.75
Low L 3.4Medium M 0.85
High H Production 0
Risk Status 0
Active Active 3 0Dormant Dorm. 1 Reserves 0
Accepted Accptd 18 0Closed Closed 0 0
NPV 0
Action Status 0
Pending 0Under Review 0 0
Completed 00
0 0
0
0
-
7/28/2019 TREX-45036
37/48
-
7/28/2019 TREX-45036
38/48
-
7/28/2019 TREX-45036
39/48
yes
People
Show ? Count Abbrev
yes 0 1 Chuck Bondurant CB yes 0 yes 0 yes 0 yes
yes 6 2 Donald Charles DC yes 0 yes 0 yes 0 yesyes 0 3 Binh Van Nguyen BVN yes 1 yes 0 yes 0 yesyes 0 4 Chris Casler CC yes 0 yes 0 yes 0 yesyes 0 5 Tomieka Searcy TS yes 0 yes 0 yes 0 yesyes 0 6 Pierre Depret PD yes 0 yes 0 yes 0 yesyes 0 7 Mark Hafle MH yes 13 yes 0 yes 0 yesyes 0 8 Jonathan Bellow JB yes 0 yes 0 yes 0 yesyes 0 9 Bobby Bodek BB yes 0 yes 0 yes 0 yes
yes 0 10 Jasper Peijs JP yes 0 yes 0 yes 0 yesyes 0 11 David Sims DS yes 0 yes 0 yes 0 yesyes 0 12 George Gray GG yes 0 yes 0 yes 0 yesyes 0 13 Craig Scherschel CS yes 1 yes 0 yes 0 yes
yes 0 14 Team T yes 3 yes 0 yes 0 yesyes 0 15 Marty Albertin MA yes 3 yes 0 yes 0 yesyes 0 16 Trent Fleece TF yes 1 yes 0 yes 0 yesyes 0 17 Gabe Wilson GW yes 0 yes 0 yes 0 yesyes 16 18
19
20
21
22
23
24
10% 25
3% 26
1% 27
15% 28
4% 29
1% 30
10% 31
3% 32
1% 33
15% 34
4% 35
1% 36
10% 37
3% 38
1% 390% 40
0% 41
1% 42
0% 43
0% 44
1% 45
46
47
Risk
AcceptaRisk Owner?
Responsible for
Actions?
Assurance on
Actions?
-
7/28/2019 TREX-45036
40/48
48
49
50
-
7/28/2019 TREX-45036
41/48
-
7/28/2019 TREX-45036
42/48
Register
Updates?
0 yes 1 1 1 1 1 1 1 1 1 1
0 yes 2 2 2 2 2 2 2 2 2 20 yes 3 3 3 3 3 3 3 3 3 30 yes 4 4 4 4 4 4 4 4 4 40 yes 5 5 5 5 5 5 5 5 5 50 yes 6 6 6 6 6 6 6 6 6 60 yes 7 7 7 7 7 7 7 7 7 70 yes 8 8 8 8 8 8 8 8 8 8
0 yes 9 9 9 9 9 9 9 9 9 90 yes 10 10 10 10 10 10 10 10 10 100 yes 11 11 11 11 11 11 11 11 11 110 yes 12 12 12 12 12 12 12 12 12 120 yes 13 13 13 13 13 13 13 13 13 13
0 yes 14 14 14 14 14 14 14 14 14 140 yes 15 15 15 15 15 15 15 15 15 150 yes 16 16 16 16 16 16 16 16 16 160 yes 17 17 17 17 17 17 17 17 17 17
ce?
-
7/28/2019 TREX-45036
43/48
17 17 17 17 17
Chuck Bondurant Chuck Bondurant Chuck Bondurant Chuck Bondurant Chuck Bondurant
Donald Charles Donald Charles Donald Charles Donald Charles Donald Charles
Binh Van Nguyen Binh Van Nguyen Binh Van Nguyen Binh Van Nguyen Binh Van Nguyen
Chris Casler Chris Casler Chris Casler Chris Casler Chris Casler
Tomieka Searcy Tomieka Searcy Tomieka Searcy Tomieka Searcy Tomieka Searcy
Pierre Depret Pierre Depret Pierre Depret Pierre Depret Pierre Depret
Mark Hafle Mark Hafle Mark Hafle Mark Hafle Mark Hafle
Jonathan Bellow Jonathan Bellow Jonathan Bellow Jonathan Bellow Jonathan Bellow
Bobby Bodek Bobby Bodek Bobby Bodek Bobby Bodek Bobby Bodek
Jasper Peijs Jasper Peijs Jasper Peijs Jasper Peijs Jasper Peijs
David Sims David Sims David Sims David Sims David Sims
George Gray George Gray George Gray George Gray George Gray
Craig Scherschel Craig Scherschel Craig Scherschel Craig Scherschel Craig Scherschel
Team Team Team Team Team
Marty Albertin Marty Albertin Marty Albertin Marty Albertin Marty AlbertinTrent Fleece Trent Fleece Trent Fleece Trent Fleece Trent Fleece
Gabe Wilson Gabe Wilson Gabe Wilson Gabe Wilson Gabe Wilson
-
7/28/2019 TREX-45036
44/48
-
7/28/2019 TREX-45036
45/48
AlertLite E&P Risk Categories
Count
C Country and Regulatory 0 C Country and Regulatory
C01 Experience of Operating in Province 0 E Market/Commercial ContextC02 Political Stability 0 H Health, Safety & EnvironmentC03 Security of Proprietary Information 0 T Technical ChallengeC04 Currency Risk (versus US $) 0 X Project Definition & Execution ComplexityC05 Fiscal Policy/Tax etc. 0 Y Operability/Production Ramp-upC06 Safety & Security of Personnel 0C07 Regulatory Environment(Federal & local) 0C08 Local Culture 0C09 Employment/Local Sourcing Expectations 0C10 Infrastructure 0C11 Group Reputation 0C12 Ethical Conduct 0
C13 Expropriation/Revenue security 0E Market/Commercial Context 0E01 Partner Alignment 0E02 Partner Funding Constraints 0E03 Development of Product Markets 0E04 Sources of Value Complexity 0E05 Feedstock & Product Values 0E06 Product Differentials 0E07 Managing Exec. Mgmt. Perf. Expectations 0E08 Brand Issues 0E09 Competitor Threats to Economic Success 0E10 Feedstock Source/Product Offtake Agmts. 0E11 Terms Uncertainty 0
H Health, Safety & Environment 0H01 Safety of Design 0
H02 Emmisions/Spills 0H03 Environmental Sensitivities 0H04 Waste Management 0H05 Differing Partner Standards 0H06 Health Sensitivities 0H07 Construction Safety 0T Technical Challenge 0T01 Subsurface Delineation/Complexity 0T02 Recovery Factor 0
T03 GOR/GCR/Water Prodn/Fluids Injection 0
T04 Reservoir Fluids Characteristics 0T05 Well Productivity 0T06 Terrain/Topography/Water Depth 0T07 Seismology/Soil/Met-Ocean Conditions 0T08 Facilities Concept (Choice/Knowhow/Stretch) 0T09 Drilling Complexity 0T10 Completions Complexity 0T11 Mid-Stream/Export 0X Project Definition & Execution Complexity 0
-
7/28/2019 TREX-45036
46/48
X01 Availability of Key Skills 0X02 Early Team Alignment (incl. Partner Staff) 0X03 Modification/Revamp content 0
X04 Scheduling Basis Risk (to First Production) 0X05 Estimating Basis Risk 0X06 Work Fronts / Key Interfaces 0
X07 Quality of Design Basis/Definition 0X08 Remoteness/Access/Logistics Complexity 0X09 Climatic Weather Windows 0X10 Contractor / Vendor Sourcing 0X11 Rig/Instln. Vessels Availability 0X12 Labour Market 0X13 Project Strategy Development 0Y Operability/Production Ramp-up 0
Y01 Availability of Experienced Operations Staff 0Y02 Operating Cost Risk 0Y03 Systems Availability(eg Plant/Export/Wells) 0Y04 Level of New Technology Equipment Items 0
Y05 Sparing Philosophy (Critical Items) 0Y06 Operability of Design 0Y07 Tech.Integrity (incl.QA/QC) 0Y08 Decommissioning Philosophy 0Y09 Planned Rate of Ramp-up 0
-
7/28/2019 TREX-45036
47/48
-
7/28/2019 TREX-45036
48/48
Country & Reg. 0
Market & Comm. 0H, S & E 0Tech. Challenge 0Defn. & Complexity 0Oper'ty & Ramp-up 0