TRANSPORT TECHNOLOGY OPTION FOR SMART CAPITAL …
Transcript of TRANSPORT TECHNOLOGY OPTION FOR SMART CAPITAL …
MINISTRY OF ENERGY AND MINERAL RESOURCESDIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY AND ENERGY CONSERVATION
TRANSPORT TECHNOLOGY OPTION FOR SMART CAPITAL CITY :
RENEWABLE ENERGY IMPLEMENTATION
F.X. Sutijastoto
Directore General of NREEC
Jakarta, 26 February 2020
2
INTRODUCTION
RENEWABLE ENERGY DEVELOPMENT POLICY
RE DEVELOPMENT CONCEPT FOR SMART CAPITAL CITY OF INDONESIA
I.
II.
III.
OUTLINE
3
INDONESIA’S CLIMATE CHANGE COMMITMENT
Mitigation action will be conducted through:• Shift fuel subsidy budget to productive
activities (infrastructure)• 23% renewable energy of thwe total national
primary energy mix by 2025;• Waste to energy.
4
PRIMARY ENERGY SUPPLY 2025
GOV REG 79 OF 2014 NATIONAL ENERGY POLICY
Gas
Coal Oil
NRE
Indirect Utilization
Direct Utilization
1. Geothermal PP, 7,2 GW
2. Hydro PP, 17,9 GW
3. Small Hydro PP, 3 GW
4. Bioenergy PP, 5,5 GW
5. Solar PP, 6,5 GW
6. Wind PP, 1,8 GW
7. Others, 3,1 GW
Maximize renewable energy utilization; Reduce fuel-oil consumption and refined oil import
Coal
Gas
2015
Target of RE:Policy
• Maximize Renewable Energy utilization
• Minimize Oil utilization
• Optimize gas and new energy utilization
• Utilization of coal as the main national energy supply
• Utilization of Nuclear Power Plant as the last option
5
MEMR Regulation No. 39K/20/MEM/2019 on Ratification Power Supply Business Plan of PT PLN (Persero) 2019-2028
5
NoRE Power
PlantCapacity 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Total
1 Geothermal MW 190 151 147 455 245 415 2759 45 145 55 4,607
2 Large Hydro MW 154 326 755 - 182 1484 3047 129 466 1467 8,009
3 Mini Hydro MW 140 238 479 200 168 232 27 20 20 10 1,534
4 Solar PV MWp 63 78 219 129 160 4 250 - 2 2 908
5 Wind MW - - 30 360 260 50 150 - - 5 855
6Biomass/
Mun. WasteMW 12 139 60 357 50 103 19 5 15 35 794
7 Ocean MW - - 7 - - - - - - - 7
8 BiofuelThousand
KL520 487 291 167 151 146 154 159 166 175 2,415
Total MW 560 933 1,697 1,501 1,065 2,287 6,251 199 648 1,574 16,714
GENERAL PLAN FOR ELECTRICITY SUPPLY (RUPTL) 2019-2028
6
11,5254,1
511,8845,5
1.392,4
1.745,1
3.534,3 MW
10.33511.256
12.88714.064
15.184
17.421
24.074
0
5.000
10.000
15.000
20.000
25.000
30.000
2019 2020 2021 2022 2023 2024 2025
Hydropower Geothermal Solar PV Bioenergy Wind other RE Market TOTAL
MW
*RUPTL for eksisting power plant untuil 2018, adding project list 2019-2025, with assumption the economic growth 5,5% until 2020 and 6,5% for 2025
Market Creation
RUPTL
RE STRATEGIES IN NATIONAL ENERGY MIX BY 2025
7
SMART & GREEN ENERGY IN THE NEW CAPITAL
www.esdm.go.id Direktorat jenderal ketenagalistrikan @infogatrik Info gatrik InfoGatrik
SMART
&
GREEN
ENERGY
SOLAR
PV
ENERGY
STORAGE
SYSTEM
SMART
METER
(2 WAYS)
PUBLIC
CHARGING
STATIONS
SMART
GRID
• With Assumptions:a. Population transfer : ± 1,5 Mio*)b. Per Capita Consumption : 4,000 kWh**)c. Electricity Needs : 6,000 GWhd. Losses : 10%e. Load Factor : 63%f. Power Production : 6,600 GWh
• Peak Load : 1,196 MW
• If reserve margin is 30%, the electricity supply that needs be prepared is 1,555 MW
Electricity supply needed for the New
Capital City is: 1.55 GW
*) Bappenas
**) - Estimate kWh per capita 4,000 kWh
88
New Capital Electricity Plans: 1,550 MWRE Potential Development in North and East Kalimantan
RE DEVELOPMENT AND ENERGY EFFICIENCY THROUGH SMART
CAPITAL CITY OF INDONESIA
Smart Green City Development Concept
Public
transportation
oriented
50% of the
capital city
for green
space
Renewable
energy and
low carbon
emission
99
RENEWABLE ENERGY POTENTIAL DEVELOPMENT FOR NEW
CAPITAL CITY (RUPTL 2019-2028)
No Province Type Power Plant Capacity (MW) Developer
1 North Kalimantan Large Hydropower Kaltara 1 90.00 PLN
2 North Kalimantan Large Hydropower Kayan 1 600.00 Potential
3 North Kalimantan Large Hydropower Kayan 2 500.00 Potential
4 North Kalimantan Large Hydropower Kayan 3 1,200.00 Potential
5 North Kalimantan Large Hydropower Kaltara 300.00 Potential
6 North Kalimantan Large Hydropower Mentarang 2 240.00 Potential
7 North Kalimantan Large Hydropower Sei Tubu 200.00 Potential
8 North Kalimantan Large Hydropower Sembakung 250.00 Potential
9 East Kalimantan Large Hydropower Kelai 55.00 PLN
10 East Kalimantan Large Hydropower Tabang 90.00 PLN
11 East Kalimantan Large Hydropower Boh 270.00 Potential
12 East Kalimantan Hydropower Long Bangun 20.00 Potential
13 East Kalimantan Large Hydropower Mentarang 1 300.00 Potential
14 East Kalimantan Large Hydropower Tabang 240.00 Potential
15 North Kalimantan Solar PV PLTS Tarakan (Kuota) Tersebar 3.00 IPP
16 East Kalimantan Solar PV PLTS Mahakam (Kuota ) Tersebar 0.70 IPP
17 North Kalimantan Solar PV Tarakan 3.00 Potential
18 East Kalimantan Solar PV Kaltim 0.70 Potential
TOTAL 4,362.40
10
KE TANJUNG / KALSEL
Ext 2LB Kuaro
2018
100%
Grogot
2018
100%
Longikis
2019
88,73%
Ext Petung
2017
100%RLB 7 Januari 2017
Ext
Kariangau arah New
Balikpapan
2019
84,27%
New Balikpapan
2019
75,50%
Industri
Upr Manggarsari
2017
100%
RLB 22 Nov 2017
Senipah
100%
Upr Karang Joang
2019
100 %
RLB 21 Des 2017
Samboja
2019
Upr Harapan Baru
2018
100%
RLB 23 Des 2017
Ext Palaran
2017
100%
RLB 21 Feb 2017
Sanga Sanga
2018
Tengkawang
Ext 2LB Embalut
2018
100%
Ext
Tenggarong
2017
100%
RLB 25 Mei 2017
Ext 2LB
Kota Bangun
2018
100%
Melak
2018
100%
KE BANGKANAI /
KALTENG New
Samarinda
2019
83,60%
Ext 2LB Sambera
2018
100%RLB 9 April 2018
ExtSambutan
100%
Ext Bontang
2017
100%
GISangatta
2017
100%RLB 29 Desember 2017
Sepaso
2019
Maloy
2019
Muara Wahau 2019
60,56%
GI Tanjung Redep
2018
100%
Tanjung Selor
2018
100%
Tidang Pale
2018
100%
Malinau
2018
100%
TalisayanTalisayan
2020
Komam
2019
90,01%
T/L (Konstruksi)
Keterangan :Pembangkit OG
GI
T/L(energize)
GI Rencana
SUTT (Rencana)
GI On Progress
MAHAKAM
SYSTEM
PLTMG/MPP Kaltim
Bontang
IPP Kaltim MT PLTU Tanjung
Selor
57,44%
PLTU Kaltim -
Teluk Balikpapan
PLTU Malinau
(2x3 MW)
72,43%
PLTMG
Tj Selor
83,95%
IPP PLTU Kaltim 4
PLTU Berau
89,66%
Sekatak
2020Juwata
2020 Tarakan
2020
Sepaku
2020
Tanjung Batu/
Derawan
2024
Simangaris
Sebuku
2020Nunukan
2020
Status perijinan :
Survey
Rencana
2018
2019
2017
2019 2017
38/50
2019
100%/46/46/46/46/462019
2024
2019
2019 2019 2019
2019
2019
2020
2020
2020
2020
45,98%/187/105/27/0/2332019
132/3142020 2020
20202020
90,01%/140/138/131/71/140
100%RLB Line 1 : 25 September 2017
RLB Line 2 : 17 November 2017
100%/147/147/147/147/147
93,07%/160/160/160/137/160
100%RLB 21 Desember 2017
PLTMG
Nunukan 2
(10 MW)
34,62%
53/479
Status konstruksi :
(progress)/(tanah bebas)/(pondasi)/(erection)/(stringing)/(jumlah
tower)
Status tanah :
(tanah bebas)/(jumlah tapak tower)
Ijin
PrinsipSKTR Ijin
Lingk
IPPKH
On Going
Selesai
Tidak perlu
0/248
79/368
2020
2019
20202019
Kembang Janggut
2019
GIS Balikpapan
2020
2020
2020
GIS Samarinda
2020
2020
2021
2020
3/3
2019
PLTU
Kaltim 5 (IPP)
IPP PLTU Kaltim FTP 2
IPP PLTGU
Senipah
Kalimantan Utara
29,70%/100/62/0/0/1002019
36,75%/46/40/0/0/6817,65%/27/15/0/0/42
SINGLE LINE DIAGRAM TRANSMISSION SYSTEM FOR EAST KALIMANTAN
1117
MICRO GRID
PASSIVE DESIGN
1
2
Community based Micro Grid with Distributed energy resource
• Micro grid centered by escaped house and public facilities -- Evacuationcenters
• Distributed energy resource introduction as land mark – Energy supply during disaster
Hydro Power for main supply, Roof PV for public facilities /Mega solar /Bladeless wind energy system
• Environmental load reduction within community base
Waste management /water management
Passive design-prioritized building conservation guideline• Green Public buildings
Passive design/Facility with high efficiency equipment/Energy management
• Residential
Passive design/Eco Lifestyle
SMART AND GREEN ENERGY CITY CONCEPT
12
Hydropower development as the
main energy source
Natural / rural area:
Integrated with natural landscapes:
• Forest
• PUPR Dam Reservoir
A P E C L C M T : B a n d a A c e h – F i n a l W o r k s h o p 1 2 0 1 9
NO PROVINCE POWER PLANTCAPACITY
(MW) DEVELOPER COD
1 North Kalimantan Kaltara 1 90 PLN 2025
2 East Kalimantan Kelai 55 PLN 2025
3 East Kalimantan Tabang 90 PLN 2025
4 North Kalimantan Kayan 1 600 Potential
5 North Kalimantan Kayan 2 500 Potential
6 North Kalimantan Kayan 3 1,200 Potential
7 North Kalimantan Kaltara 300 Potential
8 North Kalimantan Mentarang 2 240 Potential
9 North Kalimantan Sei Tubu 200 Potential
10 North Kalimantan Sembakung 250 Potential
11 East Kalimantan Boh 270 Potential
12 East Kalimantan Long Bangun 20 Potential
13 East Kalimantan Mentarang 1 300 Potential
14 East Kalimantan Tabang 240 Potential
TOTAL 4,355
Potential:1. East Kalimantan : 975 MW2. North Kalimantan : 3.380 MW
HYDROPOWER DEVELOPMENT FOR SMART CAPITAL CITY
OF INDONESIA
Hydropower Potential
13
Solar PV Potential Development is
integrated according to
environmental characteristics and
topology
Natural / rural area
Integrated with natural landscapes:
• Forest
• Open Space
• Ex-mining land, dsb
Urban area
• PV Rooftop
• Solar PV for public street lighting
• Public Facilities
A P E C L C M T : B a n d a A c e h – F i n a l W o r k s h o p 1 2 0 1 9
SOLAR PV DEVELOPMENT FOR SMART CAPITAL CITY OF
INDONESIA
NO PROVINCE POWER PLANTCAPACITY
(MW) DEVELOPER
1North Kalimantan
PLTS Tarakan (Kuota) Tersebar
3 IPP
2East Kalimantan
PLTS Mahakam (Kuota ) Tersebar
0.7 IPP
3North Kalimantan
Tarakan 3 Potential
4East Kalimantan
Kaltim 0.7 Potential
TOTAL 7.4
Solar PV Potential (RUPTL 2019-2028):1. East Kalimantan : 1.4 MW2. North Kalimantan : 6 MW
14
Integration of the use of mass public
transportation with functions and spatial
patterns to create efficient urban movements.
INTELLIGENT TRANSPORTATION
SYSTEM
Encourage the use of public
transportation for daily
Electricity based transportation
o LRT, MRT, commuter
o Electric tram
o Electric bus
TRANSPORTATION CONCEPT FOR SMART CAPITAL CITY OF
INDONESIA
Electrical TramElectric Bus
MRT, LRT
Solar PV for street lighting and
traffic light
15A P E C L C M T : B a n d a A c e h – F i n a l W o r k s h o p 1 2 0 1 9
Transit Oriented Development (pedestrian-friendly network) in public transportation area
TRANSPORTATION CONCEPT FOR SMART CAPITAL CITY
OF INDONESIA
Solar PV Charging station forelectric vehicles
Electric car and electric motorcycle for private vehicle
16
Thank You