Past, current, and future of the central European corridor for aquatic ...
Transport Rhine-Alpine Corridor Presentation of the corridor work plan by the European Coordinator...
-
Upload
arlene-clark -
Category
Documents
-
view
214 -
download
0
Transcript of Transport Rhine-Alpine Corridor Presentation of the corridor work plan by the European Coordinator...
TransportTransport
Rhine-Alpine Corridor
Presentation of the corridor work plan by the European Coordinator
Mr Pawel Wojciechowski
Hearing in the European Parliament,Brussels, 13 October 2015
TransportTransport
Corridor characteristics (1)
● 5 Member States and Switzerland
● 13 urban nodes
● 11 airports
● 8 seaports
● 22 inland ports
● 20 Rail-Road Terminals
TransportTransport
Corridor characteristics
(2)The freight modal split (cross-border traffic in 2010)
•54% - inland waterways•34% - road•12% - rail
TransportTransport
Corridor process in 2014 - 2015
• 4 Corridor Forum meetings with gradually increasing number of stakeholders
• 2 working group meetings (IWW/Ports, Regions)
• Several bilateral meetings and missions along the corridor by the former and the new European Coordinator
• Corridor meeting during the TEN-T Days in Riga in June 2015: presentation of the corridor work plan to a wider
TransportTransport
Main outputs so far
Corridor study with detailed analysis of the corridor, including a multi-modal transport market study
TENtec maps illustrating compliance of corridor infrastructure with TEN-T standards
List of projects planned to be implemented along the corridor by 2030
...which led to:
A corridor work plan presented by the European Coordinator and unanimously approved by all MS in May 2015
TransportTransport
Corridor work plan: agreed priorities
1. Improving compliance with the TEN-T requirements, mostly for rail (including ERTMS) and inland waterways;
2. Implementing the large rail cross-border projects between NL-DE, DE-CH and CH-IT;
3. Promote innovative solutions (RIS, ITS, deployment of LNG infrastructure;
4. Reduce external effects of transport, in particular the rail noise pollution;
5. Maintain existing infrastructure in good condition, in particular road and inland waterways;
6. Investing in ERTMS along the corridor.
Mainz
Ghent Albertkanaal
Zeebrugge
Nijmegen
Amsterdam
Rotterdam
Duisburg
KölnBrussels
Antwerpen
Frankfurt M.
Mannheim/ Ludwigshafen
Karlsruhe
Strasbourg
Milano
Genova
Urban nodesDüsseldorf
Liege
Novara
Airports
Maritime ports
Inland ports
Rail - Road terminals
Vlissingen
Moerdijk
Utrecht
Basel
Bern
Mulhouse
Chiasso
Aarau / Birrfeld
Rekingen
Zürich
Railways
Roads
IWW
Mertert
Koblenz
TransportTransport
High investment needs
● 175 projects (including 30 in Switzerland) have been identified which would be needed for the development of the Rhine-Alpine Corridor until 2030
● Estimated total volume of investments of around 60 billion EUR
● Examples of key projects:o Karlsruhe-Basel: >6 billion EURo Zevenaar-Emmerich-Oberhausen: >2 billion EUR o Chiasso-Milano: >1.4 billion EUR
TransportTransport
Project list
Corridors shall facilitate the coordinated implementation of the Core Network
List of CEF in Annex I, part I, with pre-identified projects
List of projects resulting from the work on the Corridors is obviously longer: more detailed sectioning, studies and works
The long list has a focus up till 2030, date of completion of the Core Network
The CEF Annex runs up till 2020
There is no direct link between the two lists: being in the long list is not a guarantee for financial support and vice-versa
TransportTransport
Recommended CEF funding per corridor
TransportTransport
Rhine – AlpineCEF funding per section/mode
TransportTransport
Thank you for your attention