Transmission planning in Vermont Past, present and future Docket 7081 workshop By Dean LaForest...
-
Upload
arleen-lester -
Category
Documents
-
view
215 -
download
0
Transcript of Transmission planning in Vermont Past, present and future Docket 7081 workshop By Dean LaForest...
Transmission planning in Vermont
Past, present and futureDocket 7081 workshop
By Dean LaForest
9/19/05
9/19/05 Docket 7081 Workshop Dean LaForest
2
What is transmission planning? Transmission planning examines the need for
changes to the transmission network as load and power sources change through time in an area The transmission network consists of all electric
transmission lines and substations, typically built and constructed at 115,000 volts or above Vermont has an underlying subtransmission network with
significant facilities built and operated at 34,500 and 46,000 volts that often parallel the transmission network
VELCO owns and operates the transmission grid in Vermont, while the Vermont distribution companies own and operate the subtransmission network
9/19/05 Docket 7081 Workshop Dean LaForest
3
9/19/05 Docket 7081 Workshop Dean LaForest
4
9/19/05 Docket 7081 Workshop Dean LaForest
5
What tools and key sets of data are needed and necessary for transmission planning? Need software to model the behavior and performance
of the power system Need accurate model of the power system to capture
existing system performance and predict future system performance Model needs input on network characteristics (t-lines /
transformers), reactive power sources (generators / caps / sync condensers / FACTs devices), real power sources (generators / HVDC), and loads
Model needs sets of this data for each condition examined (load level / generation dispatch, etc.
Need a set of reliability standards against which to measure the system performance and determine whether reinforcements are needed
9/19/05 Docket 7081 Workshop Dean LaForest
6
What are VELCO’s sources for these sets of tools / data?
VELCO uses a widely utilized power flow analysis software, allowing high productivity and data interrogation capabilities
VELCO provides modeling information for the power system network to ISO-NE, who collects information from the rest of New England and the eastern US / Canada
VELCO gets load information from the distribution companies and the DPS for VT, and from the database provided by ISO-NE for areas outside of VT
9/19/05 Docket 7081 Workshop Dean LaForest
7
What are the regional reliability standards? NERC (North American Electric Reliability Council)
Standards found on NERC website (http://www.nerc.com/~filez/standards/Reliability_Standards.html#Transmission_Planning)
These are the minimum level of standards the system must meet
NPCC (Northeast Power Coordinating Council) Standards found on NPCC website (
http://www.npcc.org/criteria.asp) New England by way of the ISO-NE reliability standards is
and must be compliant with these criteria, which are more specific than NERC’s criteria
9/19/05 Docket 7081 Workshop Dean LaForest
8
What are the regional (NPCC) reliability standards?
9/19/05 Docket 7081 Workshop Dean LaForest
9
What are the New England (ISO-NE) reliability standards? ISO-NE’s planning criteria are located at
http://www.iso-ne.com/rules_proceds/isone_plan/index.html
Planning Procedure #3 is the key document
9/19/05 Docket 7081 Workshop Dean LaForest
10
Reliability Standards Evolve
NERC’s Standards will be more stringent, become mandatory, and will include penalties
The FERC will put in place an ERO – and Energy Reliability Organization
9/19/05 Docket 7081 Workshop Dean LaForest
11
The type of system under study matters Vermont system characteristics
Importer of electrical power Two large sources relative to the load Minimal reserves Winter and Summer peaking Sparse transmission network Located at one end of the New England system
9/19/05 Docket 7081 Workshop Dean LaForest
12
Planning design example . . . the problem Question – feed 50 MW of load (Addison county)
from a 50 MW generator (McNeil) 40 miles away Choices
46 kV line (can look like a distribution circuit) Single conductor Double conductor
115 kV line (standard VELCO h-frame) The issues
Provide adequate voltage for customers (within 5% of nominal)
Provide coverage for expected outages
9/19/05 Docket 7081 Workshop Dean LaForest
13
The first test . . . Can 46 kV work?
9/19/05 Docket 7081 Workshop Dean LaForest
14
The first test . . . Can 46 kV REALLY work?
9/19/05 Docket 7081 Workshop Dean LaForest
15
The first test . . . Can 46 kV work with two conductors (or bundled conductors)?
9/19/05 Docket 7081 Workshop Dean LaForest
16
40 miles . . .
9/19/05 Docket 7081 Workshop Dean LaForest
17
The second test . . . Can 115 kV work over 40 miles?
9/19/05 Docket 7081 Workshop Dean LaForest
18
To meet a N-1 design standard (be able to suffer the loss of one element) . . .
9/19/05 Docket 7081 Workshop Dean LaForest
19
VELCO’s design standard for transmission planning . . . Conforms to NERC, NPCC and ISO-NE planning
standards We consider the unavailability of system elements that
have potential long duration outages (more than one load cycle) Highgate DC converter Underground (or underwater) cables Transformers Generators
After system adjustment following first outage, VELCO tests all other potential outages
9/19/05 Docket 7081 Workshop Dean LaForest
20
What has VELCO done in the past for long range transmission planning VELCO’s recently performed long range studies
include the “Twenty Year Plan” (1987), the “Long Range Transmission Plan” (1992), and “A Strategic Planning Study” (2001) Each considered, and included, distribution company
projects / plans and current regional system information Each effort used the latest tools and system models
available The earlier two efforts included examination of power
source location and its influence on transmission expansion Each effort built on the past using better tools, and utilized
a more thorough understanding of the transmission network (with less predictable performance as time went on).
9/19/05 Docket 7081 Workshop Dean LaForest
21
What VELCO projects included analysis of future system
performance? Those projects included the Essex STATCOM (filed June 1999 – docket 6252), the Rutland Region Reliability Project (filed March 2001 – docket 6479), the Northern Loop Project (filed December 2002 – docket 6792) and the Northwest Reliability Project (filed June 2003 – docket 6860)
9/19/05 Docket 7081 Workshop Dean LaForest
22
What peak loads did VELCO experience during these planning efforts? Vermont seasonal peaks
550
600
650
700
750
800
850
900
950
1000
1050
1100
1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006
1980 to 2005
VT
lo
ad max sum
max win
9/19/05 Docket 7081 Workshop Dean LaForest
23
What will VELCO provide to comply with Act 61? VELCO will perform a study examining system performance 10
years from the present (i.e. 2015). The analysis will likely consider: All facilities available, and with one facility out due to a long term
outage Stressed transfer conditions The continued availability of energy from Highgate and how it
might influence transmission system design A reduced load growth scenario and how that might influence the
timing of transmission system reinforcements Proposed in-state generation projects and how they may
influence transmission system design VELCO will provide a draft report early in 2006 and hold public
meetings to promote discussion and elicit comments before publishing a final report by July 1, 2006
9/19/05 Docket 7081 Workshop Dean LaForest
24
What activities will take place within the Long Range Planning process? Involve the Vermont distribution companies (via the Vermont
Utility Planning Group) in review of interim results and proposed solutions Make certain that distribution utility issues / projects are
considered and properly reflected in the analysis Involve ISO-NE through collaborative meetings to review results,
refine modeling of beyond Vermont conditions / assumptions and provide / seek input on the transmission system design necessary to address system deficiencies that do not meet design criteria
Propose a series of alternatives to any discovered system wide deficiency Provide planning grade cost estimates for the alternatives to
allow ranking
9/19/05 Docket 7081 Workshop Dean LaForest
25
Questions?
9/19/05 Docket 7081 Workshop Lawrence Kirby
26
A probabilistic reliability guideline for subtransmission planning, based on the
equal slope criterion
9/19/05 Docket 7081 Workshop Lawrence Kirby
27
costs
be
ne
fits
Conceptual Cost-Benefit Map
Diminishing returns on investment
B
C
Figure 1
A
9/19/05 Docket 7081 Workshop Lawrence Kirby
28
costs
be
ne
fits
Conceptual Cost-Benefit Map
"Most for Less" Planning Philosophy
To
tal b
en
efit
sim
ilar
to o
ption
C
Total cost similar to option A
A
B
C
Figure 2
desired tradeoff occurs near "knee" of curve
9/19/05 Docket 7081 Workshop Dean LaForest
29
Equal Slope Criterion