TRANSMISSION MASTER PLAN FOR RWANDA June 2019...28.65 5,442,254 2019 GoR 9 110kV Nyamugari-Bugesera...
Transcript of TRANSMISSION MASTER PLAN FOR RWANDA June 2019...28.65 5,442,254 2019 GoR 9 110kV Nyamugari-Bugesera...
-
www.reg.rw
TRANSMISSION MASTER PLAN FOR RWANDA
June 2019
-
www.reg.rw
HIGH VOLTAGE TRANSMISSION NETWORK
PURPOSE OF TRANSMISSION PLAN▪ The function of the Transmission Network (110kV and 220kV) is to evacuate power from the Generation stations to
the main substations in the country. The objective is to do this efficiently to minimize losses, enable reliability and
flexibility
▪ To plan and design Internationally Interconnected Transmission lines
▪ To plan and design the network to function under contingency conditions
▪ To plan and design how every significant power plant must have more than one evacuation line in order to optimize
the availability of the power plants at all conditions.
▪ To plan and design how existing lines can be upgraded/maintained without network interference.
CHALLENGES WITH THE EXISTING TRANSMISSION NETWORK▪ Isolated from the Transmission Networks of the neighbouring countries.
▪ Many substations have only one source of supply and some of them don`t have n-1 connections.
▪ All power plants have only one evacuation line each which reduces the availability of the power plants during the
failure of the evacuation line and this may result to the catastrophic circumstance of blackout.
▪ Voltage Drop from Ntaruka switchyard towards Rwinkwavu Substation are very high due to the small size of the
conductor and long distance.
-
www.reg.rw
CONTENTS
▪ Methodology
▪ Planning Criteria
▪ Load Forecast Methodology
▪ Assumptions
▪ Network Development
▪ Load forecast
▪ Recommendations
-
www.reg.rw
Methodology1. Model the existing network using PowerFactory2. Model network with existing loads3. Do load forecast
1. Existing network2. New Electrification3. Bulk loads
4. Simulate existing network with future loads to determine network supply limits
5. Model future networks6. Simulate future loads on future network7. Determine problem areas and test alternative proposals
-
www.reg.rw
PLANNING CRITERIA
-
www.reg.rw
Planning Criteria• All transmission lines in Rwanda must have n-1 supply option (supplied from at least two sources).• All Power Substations in Rwanda must have n-1 supply (at least two evacuation options).• Evacuation of Generation must be able at n-1 conditions (at least two evacuation options).• High Voltage supply and substations must be installed at all Major Cities and Industrial Parks.• All new transmission lines are constructed to allow for two circuits (allow for future growth – use same corridor and
structures).• The transmission network will be operated at 110kV where required until the load justifies the 220kV (reduce reactive
losses) or other reactive compensation is installed for local network conditions.• The 220kV lines used for major international load transfer will be operated on 220kV.• Distribution (15kV and 30kV) must not be on the same transformer as the 220kV network. Distribution must be done from
the 110kV intermediate voltage network (Reliability of the 220kV network may not be compromised).• Transmission Substations must be designed and positioned in accordance with the requirements of the Distribution
Master Plan.• All substations shall have a double HV busbar with split or double MV busbar and coupler breaker to allow operational
flexibility (and availability) of the network.• All new substations must be designed and prepared for two transformers, even if only one is installed initially.• A minimum transformer size of 20MVA must be used for all new Distribution substations.• International Consultants shall follow the REG master plan guidelines for Transmission network development.
-
www.reg.rw
LOAD FORECAST METHODOLOGY
-
www.reg.rw
LOAD FORECAST METHODOLOGY Load Growth Calculations(Maximum Demand vs Years)• Load growth is a combination from different growth types.
LOAD GROWTH CALCULATIONS
1Growth on existing networks (grow to saturation)
(a)Growth of existing consumers
(b)Fill-in connections
2 New Networks connections (S-Curve)
3 Bulk loads (Step input)
-
500
1,000
1,500
2,000
2,500
3,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
12% growth
-
www.reg.rw
• Data is 5 years old. Data is extrapolated
with population growth before use.
1. LOCATE POTENTIAL CUSTOMERS (LOAD)
2. NOW WHERE THE LOAD IS (Feeder,
Substation)
3. SIMULATE LOAD TO IDENTIFY
REINFORCEMENT REQUIREMENTS
LOAD FORECAST METHODOLOGY Capture Potential Customers AND LOAD GEOGRAPHICALLY
-
www.reg.rw
ASSUMPTIONS FOR LOAD FORECAST AND PLANNING
-
www.reg.rw
0 1 2 3 4 5 6 7 8 9 10 11 12 13
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Growth on Existing load LOW 0.0% 4.0% 4.0% 4.0% 4.0% 3.5% 3.5% 3.5% 3.0% 3.0% 3.0% 2.5% 2.5% 2.5%
Growth on Existing load MED 0.0% 5.0% 5.0% 5.0% 5.0% 4.5% 4.5% 4.5% 4.0% 4.0% 4.0% 3.5% 3.5% 3.5%
Growth on Existing load HI 0.0% 6.0% 6.0% 6.0% 6.0% 5.5% 5.5% 5.5% 5.0% 5.0% 5.0% 4.5% 4.5% 4.5%
AssumptionsFor the distribution planning, certain assumptions must be made to calculate load forecast.
• A target of 65% of all customers must be connected on-grid, the remaining 35% off-grid
• The population growth is taken at 3%. That implies that the target connections are growing
every year with 3% and after 100% electrification, the population growth must still be catered for
to maintain the 100%.
• The growth on existing load is divided into 3 categories for urban to rural load. This only
represents the growth of existing networks and excludes new electrification and bulk loads.
-
www.reg.rw
Assumptions (Continued)
• Individual households can take up to 6 years from connection date to saturation load. In most African
conditions, new connections do not take up full capacity at the time of connection, but it saturates after
some time. Taking this into consideration will prevent unnecessary high forecast and wrong generation
planning.
• The average saturation load of new connections after 6 years is 80W per household. (ADMD after
Diversity Maximum Demand = 80W)
Initial Load at 100% (European model)
Initial Load saturates after 6 years (African model)
The same connections and ADMD used in two different ways.
2025
-
www.reg.rw
Assumptions (Continued)
• Method of calculating potential electrification load:
The 48/52% rule for on-grid is used on average for all feeders.
1. Count number of households next to the feeder using GIS Functionality
2. Due to age of Orthophoto's data, add 3% growth from 2014 = 12%
3. Calculate 64% average on each feeder to be connected
4. Do load forecast applying the S-Curve characteristic using PowerFactory functionality.
-
www.reg.rw
TRANSMISSION NETWORK DEVELOPMENT
-
www.reg.rw
Overview of new projects
-
www.reg.rw
List of all Transmission Projects
List of Planned Projects/Transmission Projects 1.xlsxList of Planned Projects/Transmission Projects 1.xlsx
-
www.reg.rw
Transmission Projects with funds
No. Project Name Components Length/Capacity Estimated Cost(USD)
Starting Period
Source of Funds
1 Replacement of a 15MVA 6.6/110 Transformer No1 in Mukungwa Switchyard
Upgrade of Mukungwa Switchyard From 15MVA to 31.5MVA
1,750,000 2019 AFDB/RBF
2 Installation of 110/30kV 20MVA Transformer at Nyabarongo I Switchyard
Extension of Nyabarongo I Switchyard20MVA 1,750,000 2019 FDB/RBF
3 Replacement of 2*15MVA 110/15kV Transformers No 1 and No2) in Gikondo Substation by 2*31.5MVA
Upgrade of Gikondo SSFrom 2*15MVA to 2*31.5MVA
3,500,000 2019 FDB/RBF
4 110kV Gahanga-BugeseraConstruction of Transmission Line, Construction of Bugesera SS
17.5 3,150,000 2019 GoR
5 110kV Bugesera-Bugesera IP Construction of Transmission Line 24 4,780,415 2019 GoR
6 220kV Shango-Bugesera Construction of Transmission Line 34.12 11,987,113 2019 AFDB and ADF
7 220kV Bugesera-RwabusoroConstruction of Transmission Line , Construction of Rwabusoro SS
39.78 29,160,616 2019 GoR
8 110kV Mukungwa-NyabihuConstruction of Transmission Line ,Construction of Nyabihu SS, Construction of Nyabihu Line bay at Mukungwa SS
28.65 5,442,254 2019 GoR
9 110kV Nyamugari-BugeseraConstruction of Transmission Line , Construction of Nyamugari SS 81.25 28,544,928 2019
AFDB and ADF for Transmission Line;GoR for Nyamugari SS
10220kV Symbion Cut-in, Cut-out
Construction of Transmission Line , Construction of Symbion Switchyard
10.5 19,890,000 2019 GoR
11220kV Mamba-Rwabusoro
Construction of Transmission Line, Construction of Mamba Switchyard
21.52 14,822,213 2019 GoR
12220kV Rusumo-Nyamugari
Construction of Transmission Line, Construction of Rusumo Switchyard
2.5 878,305 2019 AFDB and ADF
13220kV Bwishyura-Kigoma-Rwabusoro
Construction of Transmission Line , Construction of Bwishyura SS, Upgrade of Kigoma SS
74 14,282,392 2019 GoR
14 220kV Kigoma-Gisagara-Burundi BorderConstruction of Transmission Line , Construction of Gisagara SS
64 19,601,009 2020 KFW
17 New Gasogi Substation Construction of new Gasogi Substation 2 x 15MVA 23,542,130 2020 JAIKA
15 110kV Nyabarongo II-RulindoConstruction of Transmission Line, Construction of Nyabarongo II Switcyard 16.65 14,995,200 2024 GoR
16 220kV Bwishyura-Kamanyola-Rusizi III Construction of Transmission Line, Consctruction of Kamanyola SS,Consctruction of Rusizi III Switcyard
93 30,353,201 2024 EU
Total 228,429,777
-
www.reg.rw
Planned Transmission Projects N0. Project Name Components Length/Capacity Estimated
Cost(USD)Starting Period
Financial aspects
1 110kV Nyabarongo I-Nyabihu Construction of Transmission Line 46 14,073,091 2020 Needs to be financed
2 Construction of Bugesera Industrial Park Substation
110/30kV substation 2 x 20MVA 9,000,000 2020 Needs to be financed
3 110kVGasogi-Bugesera Construction of Transmission Line 17.8 3,382,000 2020 Needs to be financed
4 110kV Nyamugari-Rwinkwavu Construction of Transmission Line 57.2 10,868,000 2020 Needs to be financed
5 220kV Mamba-Gisagara Construction of Transmission Line 21 4,620,000 2020 Needs to be financed
6 Installation of 220/110kV Transformer at Rubavu SS
Upgrade of Rubavu SS 75/93.8MVA 2,057,819 2020 Planned in future
7 110kV Nyabihu-Rubavu Construction of Transmission Line 40 7,200,000 2021 Needs to be financed
8 110kV Musanze Substation cutt-in cutt-out
Construction of Transmission Line, Constructiomn of Musanze SS
0.596 2X20MVA 9,113,240 2021 Planned in future
9 110kV Rukarara - Huye -Gisagara
Construction of Transmission Line, Extension of Rukarara SS, Construct Huye substation
40.71 19,327,800 2022 Needs to be financed
10 110kV Rwabusoro-Bugesera IP
Construction of Transmission Line 39 7,020,000 2022 Needs to be financed
11 Installation of 220/110kV Transformer at Gisagara SS
Upgrade of Gisagara SS 75/93.8MVA 2,057,819.12 2022 Planned in future
12 110kV Kirehe cutt-in cutt-out Construction of Transmission Line, Construction of Kirehe SS
2 9,380,000 2023 Planned in future
13 110 Nyabarongo I-Muhanga and Muhanga Substation
Construction of Transmission Line, Muhanga 110/30kV SS
20.35 8,866,500 2023 Planned in future
14 Replacement of 2*16.5MVA 6.6/110 Transformers at Nyabarongo I Switchyard
Upgrade of Nyabarongo I Switchyard
From 16.5MVA to 31.5MVA
3,500,000 2024 Planned in future
15 Installation of 220/110kV Transformer at Bugesera SS
Upgrade of Bugesera SS 75/93.8MVA 2,057,819 2025 Planned in future
16 110kV Gicumbi-Nyagatare Construction of Transmission Line 43 8,113,000 2025 Planned in future
17 110kV Gicumbi cutt-in cutt-out
Construction of Transmission Line, Construction of Gucumbi SS
1.54 9,292,600 2025 Planned in future
18 110kV Kigoma-Muhanga Construction of Transmission Line, COnstruction of Muhanga SS
17.59 12,342,100 2025 Planned in future
19 110kV Nyabarongo II-Shango Construction of Transmission Line 26.55 23,732,636.54 2026 Needs to be financed
20 110kV Nyagatare-Gabiro Construction of Transmission Line, Construction of Nyagatare SS
23.87 4,535,300 2026 Planned in future
Total 170,539,725
0
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
35,000,000
40,000,000
45,000,000
50,000,000
2020 2021 2022 2023 2024 2025 2026
USD
Years
Total Yearly Budget
0
20
40
60
80
100
120
140
2020 2021 2022 2023 2024 2025 2026
Km
lin
e
Years
Yearly Line Length
-
www.reg.rw
SHORT TERM NETWORK CONFIGURATION
220kV Lines:Mamba - RwabusoroRusumo-NyamugariMamba-GisagaraShango- Mirama220/110kV Transformations:Rwabusoro 220/110kV 93.8MVARubavu 220/110kV 93.8MVABwishura 220/110kV 93.8MVAShango 220/110kV 93.8MVANyamugari 220/110kV 93.8MVAKigoma 220/110kV 93.8MVA
220kV Line to be operated on 110kVBwishyura-Rubavu-ShangoRwabusoro-BugeseraNyamugari-Bugesera-Shango
Note – Gisagara has no 220/110kV Trf. This must be installed before upgrade to 220kV
PREVIEW OF SHORT TERM NETWORK CONFIGURATION
SHORT TERM NETWORK CONFIGURATION
-
www.reg.rw
Existing Network (2019)Existing Transmission Network is made by the following
Transmission Lines:
➢ 220kV Bwishyura-Rubavu-Shango which is currently
operating under 110kV.
➢ 110kV MururuII-Ntendezi
➢ Ntendezi-Karongi
➢ Ntendezi-Bugarama
➢ Ntendezi-Kibogora
➢ Gishoma Peat to Power-Bugarama
➢ Karongi-Kilinda
➢ Nyabarongo I HPP-Kilinda
➢ Rukarara-Kilinda
➢ Kilinda-Kigoma
➢ Kigoma-Mount Kigali
➢ Kigoma-Gikondo
➢ Gikondo-Jabana SS
➢ Jabana I TPP-Jabana SS
➢ Jabana II TPP-Jabana SS
➢ Ntaruka HPP-Mukungwa I HPP
➢ Mukungwa I HPP-Gifurwe
➢ Mukungwa I HPP-Rulindo
➢ Rulindo-Jabana SS
➢ Jabna SS-Birembo
➢ Birembo-Gasogi
➢ Birembo-Musha
➢ Musha-Kabarondo
➢ Kabarondo-Rwinkwavu
➢ Rulindo-Gabiro-Musha
➢ Jabana-Nzove-Mount Kigali-Gahanga
➢ Ramba-Ndera
-
www.reg.rw
Order Project Name Components Length/Capacity Estimated Cost(USD)
Starting Period
Source of Funds
1 Replacement of a 15MVA 6.6/110 Transformer No1 in Mukungwa Switchyard
Upgrade of Mukungwa Switchyard From 15MVA to 31.5MVA
1750000 2019AFDB/RBF
2 Installation of 110/30kV 20MVA Transformer at Nyabarongo I Switchyard
Extension of Nyabarongo I Switchyard
20MVA 1750000 2019FDB/RBF
3 Replacement of 2*15MVA 110/15kV Transformers No 1 and No2) in GikondoSubstation by 2*31.5MVA
Upgrade of Gikondo SS From 2*15MVA to 2*31.5MVA
3,500,000 2019FDB/RBF
17 Construction of New Gasogi SS Construction of New Gasogi SS 2*15MVA 23,542,130 2019 JAICA
4 110kV Gahanga-BugeseraConstruction of Transmission Line
17.5 3,150,000 2019 GoRConstruction of Bugesera SS
5 110kV Bugesera-Bugesera IPConstruction of Transmission Line 24 4,780,415.35
2019GoR
Construction of Bugesera IP SS 1*20MVA 4,500,000 AFDB6 110kV Shango-Bugesera Construction of Transmission Line 34.12 11,987,113.27 2019 AFDB and ADF
7 110kV Bugesera-RwabusoroConstruction of Transmission Line
39.78 29,160,615.63 2019 GoRConstruction of Rwabusoro SS
8 110kV Mukungwa-Nyabihu
Construction of Transmission Line
28.65 5,442,254 2019 GoRConstruction of Nyabihu SSConstruction of Nyabihu Line bay at Mukungwa SS
9 110kV Nyamugari-BugeseraConstruction of Transmission Line
81.25 28,544,928.29 2019AFDB and ADF for Transmission Line;GoR for
Nyamugari SSConstruction of Nyamugari SS
10 220kV Symbion Cut-in, Cut-outConstruction of Transmission Line
10.5 19,890,000 2019 GoRConstruction of Symbion Switchyard
11 220kV Mamba-RwabusoroConstruction of Transmission Line
21.52 14,822,213.37 2019 GoRConstruction of Mamba Switchyard
12 220kV Rusumo-NyamugariConstruction of Transmission Line
2.5 878,305.48 2019 AFDB and ADFConstruction of Rusumo Switchyard
13 220kV Bwishyura-Kigoma-RwabusoroConstruction of Transmission Line
74 14,282,392 2019 GoRConstruction of Bwishyura SSUpgrade of Kigoma SS
14 220kV Kigoma-Gisagara-Burundi BorderConstruction of Transmission Line
64 19,601,008.70 2019 KFWConstruction of Gisagara SS
Total 187,581,376.09
2019 Ongoing Transmission Projects
-
www.reg.rw
2020 Projects
N0. Project Name Components Length/ Capacity
Estimated Cost(USD)
1 110kV Nyabarongo I-Nyabihu
Construction of Transmission Line
46 14,073,091
2 Construction of Bugesera Industrial Park Substation
110/30kV substation 2 x 20MVA 9,000,000
3 110kVGasogi-Bugesera
Construction of Transmission Line
17.8 3,382,000
5 110kV Nyamugari-Rwinkwavu
Construction of Transmission Line
57.2 10,868,000
6 220kV Mamba-Gisagara
Construction of Transmission Line
21 4,620,000
7
Installation of 220/110kV Transformer at Rubavu SS
Upgrade of Rubavu SS
75/93.8MVA
2,057,819
8220kV Kigoma-Gisagara-Burundi Border
Construction of Transmission Line , Construction of Gisagara SS
64 19,601,009
8New Gasogi Substation
Construction of new Gasogi Substation
2 x 15MVA 23,542,130
TOTAL 87,144,049
-
www.reg.rw
N0. Project Name Components Length/ Capacity
Estimated Cost(USD)
1110kV Nyabihu-Rubavu Construction of Transmission Line 40 7,200,000
2
110kV Musanze Substation cutt-in cutt-out
Construction of Transmission Line, Constructiomn of Musanze SS
0.596 2x20MVA
9,113,240
TOTAL 16,313,240
2021 Projects
-
www.reg.rw
N0. Project Name Components Length/ Capacity
Estimated Cost(USD)
1
110kV Rukarara -Huye - Gisagara
Construction of Transmission Line, Extension of Rukarara SS, Construct Huye substation
40.71 19,327,800
2
110kV Rwabusoro-Bugesera IP
Construction of Transmission Line 39 7,020,000
3
Installation of 220/110kV Transformer at Gisagara SS
Upgrade of Gisagara SS 75/93.8MVA 2,057,819
TOTAL 28,405,619
2022 Projects
-
www.reg.rw
2023 Projects
N0. Project Name Components Length/ Capacity
Estimated Cost(USD)
11110kV Kirehe cutt-in cutt-out
Construction of Transmission Line, Construction of Kirehe SS
2 9,380,000
12110 Nyabarongo I-Muhanga and Muhanga Substation
Construction of Transmission Line, Muhanga 110/30kV SS
20.35 8,866,500
TOTAL 18,246,500
-
www.reg.rw
2024 ProjectsN0. Project Name Components Length/
CapacityEstimated Cost(USD)
1
110kV Nyabarongo II-Rulindo
Construction of Transmission Line, Construction of Nyabarongo II Switcyard
16.65 14,995,200
2
Replacement of 2*16.5MVA 6.6/110 Transformers at Nyabarongo I Switchyard
Upgrade of Nyabarongo I Switchyard
From 16.5MVA
to 31.5MVA
3,500,000
3
220kV Bwishyura-Kamanyola-Rusizi III
Construction of Transmission Line, Consctruction of Kamanyola SS,Consctruction of Rusizi III Switcyard
93 30,353,201
-
www.reg.rw
2025 Projects
N0. Project Name Components Length/ Capacity
Estimated Cost(USD)
1Installation of 220/110kV Transformer at Bugesera SS
Upgrade of Bugesera SS 75/93.8MVA
2,057,819
2110kV Gicumbi-Nyagatare Construction of Transmission Line 43 8,113,000
3
110kV Gicumbi cutt-in cutt-out Construction of Transmission Line, Construction of Gucumbi SS
1.54 9,292,600
4
110kV Kigoma-Muhanga Construction of Transmission Line, COnstruction of Muhanga SS
17.59 12,342,100
TOTAL 31,805,519
-
www.reg.rw
2026 Projects
N0. Project Name Components Length/ Capacity
Estimated Cost(USD)
1110kV Nyabarongo II-Shango
Construction of Transmission Line
26.55 23,732,637
2
110kV Nyagatare-Gabiro
Construction of Transmission Line, Construction of Nyagatare SS
23.87 4,535,300
TOTAL 28,267,937
-
www.reg.rw
No ongoing project planned in this
year, but according to the
development of the Transmission
Master Plan, some new projects may
be started in this year even after.
-
www.reg.rw
0.0
50.0
100.0
150.0
200.0
250.0
300.0
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Rwanda Grid Load Forecast (MW) after Modelling and Simulation with Power Factory
Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030Peak demand (MW) 173.9 188.2 205.1 218.0 236.5 249.5 257.2 264.9 272.5 276.6 280.7 282.7
-
www.reg.rw
RECOMMENDATIONS
➢ The size of 110kV Ntaruka-Mukungwa-Rulindo-Jabana-Birembo-Gasogi-Musha-Kabarondo-Rwinkwavumust be upgraded from ACSR 157/25 to 240/40 to reduce voltage drop.
A second evacuation route for Hakan Peat Power Station to Gisagara is recommended.➢ Since Gisagara Substation will have a dual transformer(220-110/30 i.e 220/30kV or 110/30kV), a new
220/110kV Transformer must be installed before the completion of 110kV Rukarara-Huye-Gisagara➢ 220/110kV Transformers must be installed at Rubavu and Bugesera Substations before upgrading Rwanda
Transmission Network to 220kV➢ A SVC must be installed in 2020 to help stabilize the network from reactive power.➢ All transmission lines must be installed as per these guidelines to ensure efficient power distribution and
reliability for the Rwanda network.
-
www.reg.rw
Thank You