Transmission line design project proposal

22
Upgrading the 69 kV transmission line between Demerara and Berbice A Proposal Submitted by Selwin Collier Electrical Engineering Faculty of Technology University Of Guyana January 30 th , 2015

description

Final year electrical engineering project proposal

Transcript of Transmission line design project proposal

  • Upgrading the 69 kV transmission line between

    Demerara and Berbice

    A Proposal Submitted by Selwin Collier

    Electrical Engineering

    Faculty of Technology

    University Of Guyana

    January 30th, 2015

  • 2

    Summary/Abstract

    This proposal is merely based on the upgrading of the 69kV transmission line between Demerara

    and Berbice. The design and construction of the previous transmission line between Demerara and

    Berbice has experienced an appreciable increase of loads in Berbice resulting in inconsistencies in

    transferred power. These inconsistencies are causes for concern since there are plans to incorporate

    the future Amaila falls project on this very network for the transfer of power to Berbice. Through

    the use of calculations, modeling and operational data, identifying the transfer capability of the

    present 69 kV line between Demerara and Berbice would be objectified. The present and future

    Berbice loads would be accessed or developed and the possibility of a new transmission line would

    be designed with specific voltage and current carrying capacity to meet the requirements of the

    system over the next 20 years. Further analysis also would include possible route for this new

    transmission line where all designs would be modeled to demonstrate their operational capability.

  • 3

    Table of Contents

    Summary/Abstract ........................................................................................................................ 2

    List of Figures ................................................................................................................................ 4

    Background ............................................................................................................................... 5

    Statement of Problem ............................................................................................................... 6

    Scope of Work ............................................................................................................................... 7

    Overview .................................................................................................................................... 7

    Literature Review ..................................................................................................................... 8

    Transmission Constraints .................................................................................................... 9

    Thermal Constraints ........................................................................................................... 10

    Voltage Constraints ............................................................................................................ 10

    System Operated Constraints ............................................................................................ 11

    Alternative Solutions .............................................................................................................. 13

    Evaluation ................................................................................................................................ 15

    Decision .................................................................................................................................... 16

    Implementation of Work ............................................................................................................ 17

    Facility .......................................................................................................................................... 18

    Schedule ....................................................................................................................................... 19

    Budget .......................................................................................................................................... 20

    Bibliography ................................................................................................................................ 21

  • 4

    List of Figures

    Figure 1 Short Line Transmission................................................................................................... 8

    Figure 2 HVDC and HVAC Transmission systems cost ................................................................ 9

    Figure 3 Transmission-line loadability curve for 60-Hz overhead lines - no series or shunt

    compensation ................................................................................................................................ 13

  • 5

    Introduction

    There has been an increased percentage of load in the Berbice area resulting in a percentage voltage

    drop along the Demerara Berbice transmission link. Other contributions to voltage drops arrived

    from mechanical and electrical factors. With the advent of the hydropower project scheduled to

    come online in the near future, expectations are that this same transmission link would be used to

    continue distributing electrical power to Berbice. Coupled with the existing voltage drop on the

    current transmission system and the expected increase in load demand, expectations are that further

    voltage drops will occur requiring an improved design as well as a proposed new transmission

    link.

    Background

    The first form of transmission link was in 1886 in Great Barrington, Massachusetts where a 1 kV

    alternating current (AC) allocation system was established. AC power at 2 kV, transmitted 30 km,

    was also installed at Cerchi, Italy, the same year. Nikola Tesla, a mechanical engineer, on May 16,

    1888, conveyed a lecture on the topic A New System of Alternating Current Motors and

    Transformers, explaining the equipment which let resourceful generation and use of poly-phase

    (a means of distributing alternating current electrical power) alternating currents. The initial

    transmission of three-phase alternating current using high voltage happened in 1891 at the time of

    the international electricity exhibition in Frankfurt. The quick industrialization in the 20th century

    made electrical transmission lines and grids a significant part of the infrastructure in many

    countries [1]. Guyana took a while but in the late 1980s they had an installed electricity-generating

    capacity of about 168,000 kilowatts, and annual production was some 385 million kilowatt-hours,

    nearly all generated in thermal facilities [2].

    The mining areas of Linden and Everton (Upper Berbice) received power from Alcan and

    Reynolds, both expatriate companies that respectively owned the Mackenzie (Linden) and

    Berbice-based bauxite operations [3] hence establishing the first transmission link to Berbice from

    Linden. 22nd June, 2014 history was made when Guyana Power and Light (GPL) completed the

  • 6

    transmission interconnection of the Demerara and Berbice Interconnected Systems. Overall

    available generation capacity in Demerara and Berbice was then 100.6MW and the peak demand

    was 95MW [4]. Since then there has been an increase in load resulting in low transferred power

    from Sophia to Berbice as well as other contributing factors.

    Statement of Problem

    In the event of the loss of all its power generation in Berbice, and more particularly because of the

    government's proposal to establish the Amaila Falls hydropower facility with cheaper electricity

    supplies, GPL would like to have the transmission capability such that it can supply the entire

    Berbice area from Demerara.

  • 7

    Scope of Work

    Overview

    Research has been done on understanding transmission upgrades and what are the requirements

    for upgrading and possibly redesigning a new transmission link system, for, developing and

    implementing a stable and highly efficient transmission system. Some results indicated that voltage

    drop increases as transmission line length increases. Similarly, the terminating voltage at the

    receiving end may vary above or below the recommended or nominal operating voltage, depending

    on the types of loads connected to the receiving end. The criteria required the receiving-end

    voltages to be maintained within specified bounds (usually 5% of the nominal voltage).

    Customer and utility equipment operates most efficiently when operated near the nominal voltage

    level [5].

    The design of this project would be based on installing a capacitor bank to improve the transferred

    power in the transmission network. The Demerara Berbice transmission link will be modelled

    by creating equivalent circuits. Different sub stations would be represented by bus bars, each

    having varying characteristics such as load, generating and slack bus. Power world and Matlab

    would be used to simulate practical operating conditions and analyze systems parameters.

  • 8

    Literature Review

    Electric power transmission or "high voltage electric transmission" is the bulk transfer of electrical

    energy, from generating power plants to substations located near population centers. This is

    distinct from the local wiring between high voltage substations and customers, which is typically

    referred to as electricity distribution. Transmission lines, when interconnected with each other,

    become high voltage transmission networks [6]. Alternating current (AC) is the main driving force

    in the industries and residential areas, but for the long transmission line (more than 400 miles) AC

    transmission is more expensive than that of direct current (DC) [7]. Other approximations of

    transmission lines are:

    1. Short transmission line (less than 80 km)

    2. Medium transmission line (between 80 and 250 km)

    3. Long transmission line (more than 250 km)

    The longest single line transmission within the Demerara Berbice transmission link is 55.904

    km highlighting that short line approximations are used for carrying out line analysis. Only the

    series resistance and reactance are included for short line approximations. The shunt admittance

    is neglected [8].

    Figure 1 Short Line Transmission

    Current and voltage limits are the two important factors of the high voltage transmission line. The

    AC resistance of a conductor is higher than its DC resistance because of skin effect, and eventually

    loss is higher for AC transmission. The switching surges are the serious transient over voltages for

  • 9

    the high voltage transmission line, in the case of AC transmission the peak values are two or three

    times normal crest voltage but for DC transmission it is 1.7 times normal voltage. High voltage

    direct current (HVDC) transmission has less corona and radio interference than that of high voltage

    alternating current (HVAC) transmission line [7]. In other words, it is safe to use HVAC

    transmission for this identified area of study especially due to cost attached.

    Figure 2 HVDC and HVAC Transmission systems cost

    Transmission lines, however, have been susceptible to many influential factors that determines its

    effectiveness in terms of its ability to transfer power effectively. Some of these factors include

    environmental, electrical, mechanical and economic factors. As a result reliability and congestion

    issues are birthed such as (1) transmission constraints, (2) thermal constraints, (3) voltage

    constraints and (4) system operated constraints [5].

    Transmission Constraints

    As the transmission system has expanded over the years, surplus capacity available on

    transmission lines always seems to be consumed as the system grows or as transmission users find

    more economical ways of meeting system demands. Expansion leads to more usage that leads to

    more expansion. Transmission congestion results when a particular electricity transmission path

  • 10

    cannot accommodate increased power flow. Although the reasons for congestion vary, the

    common consequence is that increased power flow on a particular transmission path is not possible

    without risking system reliability.

    Thermal Constraints

    Line sag caused by exceeding a transmission lines thermal limit can result in a line fault, which

    is an arc between the transmission line and nearby vegetation, structures, or ground. When line

    faults occur, protective transmission line components remove the line from service to protect

    terminal equipment from serious damage. Once the faulted line is removed from service, other

    transmission lines in the system experience increased loads as they compensate for loss of the

    faulted line. Overloading can then occur on these transmission lines, which might exceed thermal

    operating constraints. If not controlled promptly, additional transmission line faults may occur. To

    ensure reliable system operation, a thermal operating constraint (specified in real power, or

    megawatts) is often placed on troublesome transmission lines to control the permissible power

    transfer across the lines. This limit establishes an upper bound on a particular lines transfer

    capability. It is important to note that in some cases, the transfer limit set on a particular line may

    actually minimize the overheating of a different transmission line. Transmission line additions tend

    to alleviate the potential for exceeding transmission line capacity limits, at least until future uses

    of the additional transfer capacity are discovered and new limiting factors are reached.

    System operators understand that, as a short-term workaround, the thermal limit may be exceeded

    in emergency situations. For this reason, transmission lines may also carry an emergency rating

    subject to a length of time that permits a higher transfer limit as long as the length of time the

    transfer is in effect does not exceed the specified period, for example, a 10-min emergency rating.

    In general, thermal constraints are more common in areas where the transmission system is tightly

    interconnected (shorter lines) [9].

    Voltage Constraints

    Primarily as a result of transmission line reactance, the voltage at the receiving end of a conductor

    will be less than the voltage applied on the sending end. Large voltage deviations either above or

    below the nominal value may damage utility or customer equipment. Therefore, operating voltage

    constraints are employed to preserve operating conditions that meet necessary voltage

    requirements. In general, voltage constraints are more typical in areas where transmission lines are

  • 11

    sparse and long [9]. It may be more economical to address voltage constraints by modifying

    existing lines, such as adding capacitance, rather than by adding new transmission capacity.

    System Operated Constraints

    Parallel Flows

    System operators can estimate the impacts of contract flows (those flows defined as point-to-point

    transactions) on parallel paths in the transmission system. These estimates allow operators to adjust

    contract schedules to minimize the likelihood of encountering a transfer limit on system

    transmission lines caused by loop flows. Therefore, specific operating constraints may be in place

    to mitigate the effects of parallel path power flows.

    Operating security

    To ensure system operating reliability, an industry-derived set of standards and procedures has

    been recommended by the North American Electric Reliability Council (NERC). These

    recommendations suggest, for example, that the system should be operated so that it remains

    reliable in spite of disruption of a single system component (e.g., loss of one generator or loss of

    one transmission line). As a result, NERC operating guides tend to limit the maximum allowable

    operating capacity of a transmission line to a value less than its actual thermal limit to ensure

    available capacity in the event of a nearby transmission line outage. Similarly, NERC guidelines

    call for a generation margin to assure that sufficient generation remains on-line in the event of a

    generator outage. Likewise, operating guides exist to limit system effects caused by other types of

    conditions that affect system stability. All of these operating conditions are recommended as a

    means to improve overall system reliability while underutilizing specific system components. In

    addition, all system operators follow preventive operating guidelines to assure overall system

    integrity and reliability.

    System and Voltage Stability

    Because loads constantly change, small variations in frequency occur as the mechanical power at

    generator turbines adjusts to variations in electrical power demand. As long as frequency variations

    are small (i.e., small-signal stability), the interconnected system remains synchronized. The system

    will continue to operate in a stable manner unless the variations continue to gain in magnitude and

  • 12

    oscillate at low frequencies. These oscillations can lead to more threatening voltage and frequency

    problems that may lead to instability and potentially to cascading outages.

    Larger oscillations occur when system components are removed from service because a fault or

    disruption occurs. For example, frequency variations caused by a generator that goes off-line tend

    to be larger in magnitude than small-signal oscillations caused by load variations. Larger frequency

    swings provide more potential for uncontrolled swings that could lead to steady-state instability.

    Preventative measures are needed to minimize the likelihood of system instability, which could

    lead to widespread system outages. A system that lacks transient stability can produce these

    operating characteristics if corrective measures are not exercised to eliminate the condition.

    Voltage instability occurs when the transmission system is exposed to large reactive power flows.

    As previously described, large reactive power flows on long transmission lines result in voltage

    drops at the receiving end of the line. Lower voltage causes increased current, which causes

    additional reactive losses. The end result is voltage collapse, which can damage equipment and

    cause additional outages, if left unresolved.

    In general, long transmission lines are stability limited, not thermally limited [9]. Generally,

    depending on the system conditions, equipment enhancements to add more reactive power or

    additional transmission lines can relieve steady-state and voltage stability problems.

    Moreover, in practice, power lines are not operated to deliver their theoretical maximum power,

    which is based on rated terminal voltages and an angular displacement = 90 across the line.

    Figure 3 shows a practical line loadability curve plotted below the theoretical steady-state stability

    limit. This curve is based on the voltage-drop limit VR/VS 0:95 and on a maximum angular

    displacement of 30 to 35 across the line (or about 45 across the line and equivalent system

    reactances), in order to maintain stability during transient disturbances. The curve is valid for

    typical overhead 60-Hz lines with no compensation. Note that for short lines less than 80 km long,

    loadability is limited by the thermal rating of the conductors or by terminal equipment ratings, not

    by voltage drop or stability considerations [8].

  • 13

    Figure 3 Transmission-line loadability curve for 60-Hz overhead lines - no series or shunt

    compensation

    Alternative Solutions

    There are a variety of approaches that may provide incremental improvements to transfer

    capability [5]: -

    1. Permit Higher Line Operating Temperatures: - This approach is not generally

    recommended for extended periods of time, higher line operating temperatures may be

    permissible as line ratings are increased. However, increased sag and insulator integrity

    may be compromised. This alternative should be used with caution and should not be

    viewed as a permanent solution to a thermal line limit.

    2. Improve Transmission Line Real-Time Monitoring: - The actual temperatures occurring

    on transmission lines depend on the current, as well as on ambient weather conditions, such

    as temperature, wind speed, and wind direction. Because the weather affects the dissipation

    of heat into the air, an effort to monitor environmental conditions can result in higher line

    loading, if ambient conditions permit. When actual monitored values are used to establish

  • 14

    line ratings, generic ratings based on nonspecific environmental conditions that are often

    very conservative can be avoided.

    3. Uprate Substation Equipment: - Just as thermal limits define maximum current flow values

    on transmission lines, equipment located at the terminating ends of a transmission line also

    have maximum current limits. In some situations, the limiting capacity may be linked to

    the equipment capabilities at the substation and not to the transmission line. If this is the

    case, the equipment at the substation can be replaced with larger components to increase

    the effective transfer limit of the line and its associated equipment.

    4. Re-conductor Existing Transmission Lines: - To mitigate underrated transmission lines,

    the actual line conductors can be replaced with larger conductors to increase the transfer

    limit of the transmission line. Sometimes, multiple conductors are bundled together to

    obtain this improvement. As long as existing tower structures are adequate to support the

    additional weight of the new conductors, this alternative is useful to increase transfer

    capability. In some situations, this alternative may be cost-effective even when tower

    structures and insulators require modifications.

    5. Install Phase-Shifting Transformers: - Loop flows can have a significant effect on

    designated transfer limits. One method to reduce loop flows is to uses phase-shifting

    transformers to help direct flows to transmission lines with sufficient transfer capability.

    As a result, transfers that take place on transmission lines that are not part of the primary

    flow path are lessened so that transfer limit violations are not attained. Although phase-

    shifting transformers are costly and consume additional energy.

    6. Install Capacitors for Reactive Power Support: - In situations where voltage support is

    problematic, capacitor banks can be used to increase the reactive power at a system bus to

    return voltage levels to nominal operating values. This method of increasing reactive-

    power support is often used to minimize voltage support problems and improve system

    stability.

    7. Design a new transmission line: - Transmission lines may reach the point of no return

    whereby upgrades to existing transmission lines may not be too effective. Hence, the

    implementation of a new transmission line is advised. In other scenarios where new designs

    may be very effect but not necessary due to the status of the current transmission line are

    not advised. This is mainly due to the financial impact new design inflicts.

  • 15

    Evaluation

    Solutions Time Efficiency Risk Level Cost

    Short

    Term

    Long

    Term

    Permit Higher Line

    Operating Temperatures

    1 Low High Cheap Costly

    Improve Transmission

    Line Real-Time

    Monitoring

    3 Low Medium Cheap Cheap

    Uprate Substation

    Equipment

    4 Medium Low Costly ----

    Re-conductor Existing

    Transmission Lines

    5 High Low Costly Costly

    Install Phase-Shifting

    Transformers

    4 Low Low Costly ----

    Install Capacitors for

    Reactive Power Support

    4 High Low Costly ----

    Design a new

    transmission line

    5 High Low Costly ----

    Table 1 Decision Matrix

    Time: - 0 means very little time

    5 means requires allot of time

    Time was rated from 0 to 5 for every possible alternative solution.

  • 16

    Decision

    The primary objective of this project does not lead to a definitive decision. The research invested

    in this project is to explore all possibilities associated with not just upgrading the current

    transmission line between Demerara and Berbice but through parameters manipulation be able to

    establish a close to ideal transmission line to facilitate primarily the eventual implementation of

    the Amaila Falls hydro project. This in itself may most likely lead to the design of a new

    transmission line.

  • 17

    Implementation of Work

    The upgrade to the 69 kV transmission link will be designed and modelled using the

    MatLab/Simulink software as well as the Power World software. The processes that needs to be

    undertaken in order to complete this design are as follows:

    Obtain all the systems parameter information as it relates to the present transmission link

    between Demerara and Berbice

    Develop an equivalent circuit of the network

    Developing an equivalent model makes model the entire system very simple cause

    you generally sum all the main parameters such as Load, Generation etc.

    Model equivalent circuit using Matlab and Power World simulation softwares

    Apply various load ratings on transmission line to analyze system behavior

    Doing the following allows us to understand the actual capability of the system. We

    would then have an idea exactly where maximum voltage drop occurs in the system

    as well as how to implement solutions.

    Improve system conditions by applying various alternatives solutions for the improvement

    the systems stability and efficiency

    The objective at this point of the project is to improve the maximum power transfer

    capabilities of the present transmission line.

    Maximum load will be applied to the line in order to observe reactions after system

    improvements

    Carryout various calculations to develop further solutions based on forecast load demand

    for next twenty (20) years for loads in Berbice.

    The concept of developing a new transmission line beckons at this point of the

    project.

    Analysis will be done to identify if the present transmission line can withstand

    future load capacities applying considerations for electrical, mechanical,

    environmental and economic factors.

    Design new transmission line

  • 18

    Facility

    This project design will be done in an Integrated Development Environment (IDE) which is a

    software application that provides comprehensive facilities to computer programmers for software

    development Schedule. The computer softwares that would be used are the MatLab/Simulink and

    the Power World software.

  • 19

    Schedule

    Gantt chart

  • 20

    Budget

    Items Cost

    Printing $5000

    Transportation $10000

    Total $15000

  • 21

    Bibliography

    [1] InnovateUS, "What are the limits on Electricity Transmission?," 2013. [Online].

    Available: http://www.innovateus.net/science/what-are-limits-electricity-transmission.

    [Accessed 17 January 2015].

    [2] A. Khan, "History," 1 January 2015. [Online]. Available:

    http://www.guyana.org/Handbook/history.html. [Accessed 17 January 2015].

    [3] GPL, "Our History," 17 January 2015. [Online]. Available:

    http://www.gplinc.net/about/history. [Accessed 17 January 2015].

    [4] S. Editior, "Demerara, Berbice power systems connected for first time," 24 June 2014.

    [Online]. Available: http://www.stabroeknews.com/2014/news/stories/06/24/demerara-

    berbice-power-systems-connected-first-time/. [Accessed 1 January 2014].

    [5] J. C. Molburg, J. A. Kavicky and K. C. Picel, "The Design, Construction, and Operation

    Of Long-Distance High-Voltage Electricity Transmission Technologies," Arronne

    National Laboratory, Illinois, 2007.

    [6] CC-BY-SA, "Electrical Power Transmission," Princeton University, 23 January 2015.

    [Online]. Available:

    http://www.princeton.edu/~achaney/tmve/wiki100k/docs/Electric_power_transmission.ht

    ml. [Accessed 24 January 2015].

    [7] K. Meah and S. Ula, "Comparative Evaluation of HVDC and HVAC Transmission

    Systems," IEEE Xplore, Wyoming, 2008.

    [8] J. D. Glover, M. S. Sarma and T. J. Overbye, Power System: Analysis and Design,

    Connecticut: Global Engineering, 2012.

  • 22

    [9] A. R. Burgen and V. Vittal, Power Systems Analysis, New Jersey: Prentice-Hall Inc.,

    1986.

    [10] Artsofte, "Reactive Power Compensation Devices," SverdlovElektro Group, 2015.

    [Online]. Available: http://svel.ru/en/catalog/ukrmsvel?id=53. [Accessed 26 January

    2015].