TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán •...
Transcript of TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán •...
![Page 1: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/1.jpg)
TransCanada Pipeline Projects
with a Focus on the Unique Execution Challenges in Mexico
![Page 2: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/2.jpg)
Overview
TransCanada Today
• Overview
TransCanada Project Portfolio
• Near Term and Longer Term
TransCanada in Mexico
• Overview
Topolobampo Project
• Land, Permitting, Indigenous, Construction, Safety & Security
Closing
![Page 3: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/3.jpg)
• One of North America’s Largest Natural Gas Pipeline Networks
• 91,500 km of pipeline
• 653 bcf of storage capacity
• 23 bcf/d; ~25% of continental demand
• Liquids Pipeline System
• 4,300 km of pipeline
• 545,000 bbl/d; ~20% of Western Canadian exports
• One of the Largest Private Sector Power Generators in Canada
• 12 power plants, 6,200 MW
TransCanada Today
![Page 4: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/4.jpg)
TransCanada Project Portfolio
• Near Term ~$20B under execution
• Mexico $3.4B
• United States $7.5B
• Canada $9.1B
• Longer Term ~$30B under development
![Page 5: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/5.jpg)
TransCanada in Mexico
• Four revenue-generating pipelines
• Topolobampo • Tamazunchale
• Mazatlán • Guadalajara
• Three new projects
• Tula ($0.6B) – 275 km NPS 36
• Villa de Reyes ($0.6B) – 299 km NPS 36
• Sur de Texas ($2.2B, 2.6 Bcf/d):
• Offshore 690 km NPS 42
• Onshore 70 km NPS 42/36
![Page 6: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/6.jpg)
Topolobampo Project
• Scope
• 570 km NPS 30 (670 MMCFD)
• 2 Compressor Stations (15 and 24MW)
• 3 Meter Stations
• 3500 workers peak, 22MM hours total
• Schedule
• 2013 to 2017
• Prime Contractor
• Saipem (Subcontractors GDI/FlowTex)
• Key Challenges
• Land acquisition and permitting
• Indigenous consultation
• Construction
• Safety and Security
![Page 7: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/7.jpg)
Topolobampo Project - Land Acquisition and Permitting
• 2014 Mexico Energy Reform
• Change of law in the midst of execution
• Land acquisition and indigenous consultation process defined
• Land and Permitting – Complex
• Civil Law and Agrarian Law overlap
• 52 “Ejidos” (communally owned land)
• Acquisition process labour intensive, no eminent domain option
• 845 land parcels acquired in insecure area
• Permitting - under-resourced agencies
• NGO influence
![Page 8: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/8.jpg)
Topolobampo Project - Indigenous Consultation
• 68 indigenous groups in Mexico representing 21% of Mexican population
• One of the first projects in Mexico to go through new indigenous consultation process led by government
• Government resourcing constraints
• Consultation process involved 119 communities
• Ejido governance and approval issues
• 152 community projects:
• Educational centers
• Medical centers
• Electrical installations
• Water installations
• Recreational facilities
![Page 9: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/9.jpg)
Topolobampo Project – Community Projects
![Page 10: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/10.jpg)
Topolobampo Project – Construction
![Page 11: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/11.jpg)
Topolobampo Project - Construction
• Mountain
• 144 steep slopes (>25 degrees, 90-300m)
• 46% rock terrain, 200km blast rock
• Access
• 100km access roads
• 10km helicopter stringing
• 6 camps and 1 fly camp
• Special Construction
• 150m rock cliff raised bore
• Geotechnical
• Chinipas HDD
![Page 12: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/12.jpg)
Topolobampo Project - Construction
• Raised-boring
• 150 meter rock cliff
• Used in mining to excavate subsurface tunnels without blasting
![Page 13: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/13.jpg)
Topolobampo Project - Construction
![Page 14: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/14.jpg)
Topolobampo Project - Construction
• Geotechnical
• Millions of hours dedicated to geotechnical works
![Page 15: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/15.jpg)
Topolobampo Project - Construction
• Chinipas HDD
• Isolated, insecure location
• 2 section pull, extreme access constraints each side
![Page 16: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/16.jpg)
Topolobampo Project - Safety & Security
• World class safety performance
• 0 fatalities
• 22 million hours, 9 million hours without lost time incident
• LTIF 0.08
• TRIF 0.46
• VIF 1.56 (80 million kilometers driven)
• Security concerns - Sinaloa and Chihuahua States
• Community engagement and local opportunity
• Indigenous support
• Security management plans, intelligence gathering, and strict adherence to procedures
• Visibility
• State government and state police support
![Page 17: TransCanada Pipeline Projects - IPLOCA...• Topolobampo • Tamazunchale • Mazatlán • Guadalajara •Three new projects •Tula ($0.6B) – 275 km NPS 36 •Villa de Reyes ($0.6B)](https://reader033.fdocuments.us/reader033/viewer/2022051811/601de9846a8f0863ff577915/html5/thumbnails/17.jpg)
Closing
World Class Project with Industry Leading Safety Performance
Success in Mexico? External Stakeholders, Risk Management
Patience and Determination. Portfolio and Long Term Approach
Opportunity
Thank you!