Trans mission T - ceati.com · include project collaboration opportunities yielding ... overall...

34
T & D Trans m ission Distribution Annual Review & 2017/2018

Transcript of Trans mission T - ceati.com · include project collaboration opportunities yielding ... overall...

T&D

Transmission Distribution

Annual Review&

2017/2018

2 CEATI 2017/18

We wish to thank our 2017 participants andlook forward to your continued support in 2018

Addressing Critical Needs in the Electricity Industry

The electricity industry continues to undergo fundamental changes, which are shaping how engineering work is performed and energy services are provided. Low load growth, over-capacity, and future market uncertainty are creating pressures on the availability of capital and the reduction of operating costs to address issues of aging infrastructure. As electrical utilities are looking to replace and refurbish assets, the need to perform effective condition assessment, risk management activities, and strategic asset management planning arises.

These concerns are amplified by an increasing loss of internal technical expertise. As senior engineers retire and new engineers are brought in, the need to retain institutional memory and provide training guidance becomes ever more critical.

As electrical utilities are forced to upgrade and replace their aging infrastructure, many experience challenges in keeping pace with the flood of emerging technologies entering the market. It is both time consuming and capital intensive to find, test, and evaluate these technologies, but choosing the wrong one can lead to performance and financial consequences.

Finally, considering high energy demands along with increasing pressure to reduce greenhouse gas emissions and mitigate the effects of extreme weather events, the electric utility sector is faced with the unique challenge of providing energy services which are both cleaner and more reliable. Advancements in sustainability for all will require innovative approaches and rethinking business as usual.

COMPANY OVERVIEW

OUR PROGRAM MODELThe CEATI Program Model provides electrical utilities with a cost-effective vehicle for sharing experiences and addressing issues pertinent to their day-to-day operations, maintenance, and planning. In addition to serving as a strong technical resource tool through more than 20 focus areas across generation, transmission, distribution, and utilization, CEATI programs include project collaboration opportunities yielding practical deliverables with which organizations can leverage their expenditures.

CEATI 2017 /18 3

OUR PARTICIPANTS

Participation Map

For more information regarding our Programs, Events and Publications, visit www.ceati.com

Alberta Electricity System OperatorAlectraAlgonquin Power & Utilities CorpAltaLinkATCO GroupBC HydroBrookfield Renewable PowerCapital PowerColumbia PowerEnbridge Gas DistributionENMAX PowerEnWin UtilitiesEPCORFortisAlbertaFortisBCFortisOntarioGreat Lakes PowerHydro One NetworksHydro OttawaHydro-Québec

FirstEnergy CorporationFirstLight PowerFlorida Power & LightGeorgia Transmission CompanyGrant County PUDHetch Hetchy Water & PowerIdaho Falls PowerIdaho Power CompanyLewis County PUDLG&E and KU Services CompanyLiberty UtilitiesMinnesota PowerNational GridNational Rural Electric Cooperative Assn.New York Power AuthorityNorth American Electric Reliability CorpNorthern California Power AgencyNorthwestern EnergyOakridge National Lab / Dept. of EnergyOncorPacific Gas and ElectricPacificorpPlacer County Water AgencyPortland General Electric

Environment AgencySevern Trent WaterE.On New Build and Technology

EnergiforskVattenfall AB

Electricité de France SHEM RTE France

Israel Electric Company

TEPCO Power Grid

Meridian EnergyMercury

Transpower New ZealandTrustPower (Damwatch)

Hydro TasmaniaPowerlink QueenslandSnowy Hydro

Fortum Generation ABUniper Energy

Ghana Grid Company

Independent Electricity System OperatorManitoba HydroMaritime ElectricNalcor EnergyNational Research CouncilNatural Resources CanadaNew Brunswick PowerNewfoundland and Labrador HydroNewfoundland PowerNorthland PowerNorthwest Territories Power CorporationNova Scotia PowerOakville Hydro Electricity DistributionOntario Power GenerationRio Tinto AlcanSaskatoon Light & PowerSaskPowerToronto HydroTransAltaTransCanada PipelinesYukon Energy

AESAmerenAmerican Electric PowerAmerican Transmission CompanyArizona Public ServiceAvangrid NetworksAvista UtilitiesBonneville Power AdministrationCalifornia Dept. of Water ResourcesCentral Hudson Gas & ElectricCentralia City LightChelan County PUDCMS EnergyCon EdisonDenver WaterDouglas County PUDDuke EnergyEagle Creek Renewable EnergyEast Bay Municipal Utility DistrictEmpire DistrictEnel Green Power North AmericaEnergy KeepersEugene Water and Electric BoardExelon

Landsvirkjun

Public Service Electric and GasPuget Sound EnergySalt River ProjectSacramento Municipal Utility DistrictSan Diego Gas and ElectricSeattle City LightSeneca GenerationSnohomish PUDSouthern California EdisonSouthern CompanyTacoma PowerTennessee Valley AuthorityTrans Bay CableTri-State Generation & Transmission Assn.Tucson Electric PowerU.S. Army Corps of EngineersU.S. Bureau of ReclamationWestern Area Power AdministrationYuba County Water Agency

ELIAEngie

Chilquinta Energia

SwissGrid

ticipation M2018

ESB

HISTORY OF UTILITY PARTICIPATION

4 CEATI 2017/18

Part

icip

ants

Year

A key benefit to program participation is the ability to leverage the experience and knowledge of the CEATI team and other expert participants. CEATI facilitates on-demand networking & information sharing in the form of group-specific Requests for Information (RFI) as well as regular face-to-face business meetings and conference calls with other members. All shared information and presentations are catalogued and made available on the MyCEATI Participant Portal.

C E A T I A T W O R KNetworking & Information Sharing

We have 130utility participants

worldwide

Industry Benchmarking is another significant component of the CEATI program model, allowing participants to stay informed of the latest developments and emerging technical issues. CEATI provides a closed-door forum, allowing participants to freely exchange information with other like-minded professionals and establish best industry practices in an efficient and cost-effective manner.

Industry Benchmarking

CEATI also offers technical training on focused topics of high operational relevance to participants. Our conferences, webinars, and technical seminars foster professional development as well as technical skills to a rapidly changing workforce. Past conference proceedings, training documentation, and webinar recordings are made available through the MyCEATI Participant Portal.

Technical Training

We create a networkof utility & industry

experts

CEATI 2017 /18 5

T H E V A L U E I NP A R T I C I P A T I O N

CEATI’s Collaborative Projects bring participating organizations, contractors, and consultants together to work across all phases of a project’s life-cycle, from technical conceptualization to final deliverables. Participants are given the flexibility to only support projects that are relevant to their organization, meaning there is never a “black hole” associated with where funding is allocated. Furthermore, by splitting overall costs with other interested parties, these collaborative projects result in highly-leveraged funding opportunities. Participants can then shape the scope of work to meet their needs, select the contractor team, and act as project monitors to further guide project development. Meanwhile, CEATI’s turn-key manage-ment system covers all aspects, ensuring a smooth process from project initiation to final deliverables.

Collaborative Projects

The website’s intuitive design and navigation allows program participants to quickly see upcoming events, easily access a list of reports and their statuses, as well as gain access to past conference proceedings, survey results, and webinar recordings. Designed to help ease the burden of information dissemination, all employees from participating utilities have access to the portal, providing direct access to the latest information. Finally, the portal also features an advanced search en-gine which ranks results based on relevancy scores and supplies only the most pertinent technical documents.

MyCEATI Portal & Electronic Library

The MyCEATI Portal is a library of utility-driven

benchmarking reviews

information exchangestraining webinars

& custom sponsored reports

CEATI Programs offer unparalleled return on investment through a platform of collaborative learning and from understanding the past successes and errors of others; this is all done while addressing industry knowledge gaps through cost-sharing. CEATI’s highly leveraged projects are funded by world leading utilities, helping lighten the burden of undertaking the initiative alone.

Unparalleled Return on Investment

6 CEATI 2017/18

conference proceedings

TRANSMISSION &DISTRIBUTION

8 SEAMStation Equipment Asset Management

10 TLAMTransmission Line Asset Management

12 TODEMTransmission Overhead Line Design & Extreme Event Mitigation

14 G&LGrounding & Lightning

16 TUCIGTransmission Underground Cables

18 PSPOPower System Planning & Operations

20 IPSIGInfrastructure Protection & Security

22 DLAMDistribution Line Asset Management

24 PQATPower Quality & Advanced Technologies

26 SGSmart Grid

28 P&CProtection & Control

30 VMVegetation Management

32 SAMPStrategic Asset Management

CEATI 2017 /18 7

PROGRAMS

Group Overview

Station Equipment Asset Management

The mission of the Station Equipment Asset Management Program (SEAM) is to disseminate the shared experiences and lessons learned regarding the life cycle management of station assets, which includes issues like purchas-ing (specifications, quality control, etc.), designing, installing, commissioning, maintaining, and operating the assets, as well as the disposal and planning for future changes/trends in the utility industry. The group assists participat-ing utilities in maximizing the safety, reliability, and efficiency of their station assets while minimizing costs and complying with applicable regulations, laws, and industry standards in order to produce the required reporting to applicable authorities.

2017 Spring Industry Conference: Innovations in Developing Stations of the FutureBuilding on the success of the 2016 conference, CEATI’s Station Equipment Asset Management Interest Group (SEAM) participants further explored areas of innovation in topics related to the development of future stations and ongoing maintenance. Technological developments in information technology, automation, and design improvements raise exciting possibilities and opportunities for a reconfigured electrical grid, enabling more effective monitoring and maintenance techniques while ensuring the reliability of supply, the sustainability of operations, and the affordabil-ity of electric service for customers. To enable smarter, more efficient, and cost-effective operation of station facil-ities, new station designs must now consider interoperability and monitoring capability to fully utilize these new technologies and associated telecommunications, information technology, security systems, and infrastructure.

2017 Collaborative Projects

• Guide to Risk Management for Station Equipment and Apparatus• Evaluating the Advanced Substation Monitoring Capabilities of Digital Fault Relays, Fault Recorders, Power Quality Monitors, and PMU Equipment – Phase II• Settings Application Guide for Different Types of Monitors – Phase I• Best Practices in Station Equipment Commission Testing• Guide to Developing Utility Asset Management Plans for Each Asset• Understanding the Key Factors, Weightings & Prioritization Factors of Health Indices• Systematic Approach to Evaluate and Compare Asset Renewal and Capacity Upgrade Projects• Enhanced Diagnostics and Condition Assessment of LTCs

This report is a documented roadmap for developing a plan for the total life cycle of an asset. It provides the necessary guidance to elucidate key questions that occur when cre-ating AM plans for each asset and for determining when a specific asset warrants replacement by factoring in con-dition, remaining life, application, and reliability impacts.

Highlighted Projects 2017Guide to Developing Utility Asset Management Plans

for Each Asset

This project provides a comprehensive summary of the best practices in testing, as well as to discuss the activ-ities and guidelines needed for a successful commis-sioning of electrical stations and their associated appa-ratus and systems. The developed commissioning plans should provide directions for the commissioning process during construction and installation; they should also provide resolutions for issues such as scheduling, roles/responsibilities, assignment of duties, lines of commu-nication and reporting, approvals, and coordination.

Best Practices in Station Equipment Commission

Testing

Topics & Issues

1. Substations of the Future2. Maintenance Practices3. Condition & Risk Assessment4. Strategic Management5. Procurement & Installation

8 CEATI 2017/18

Ken Kopechanski, P. Eng, is a registered Profes-sional Engineer in Ontario. With over 35 years of experience, he is an expert in the operation, maintenance, construction, commissioning, and rehabilitation of generating, transmission, and distribution facilities.

Technical Advisor

SEAM2018 Collaborative Projects

• Guide for Loading of In-Service Aged Power Transformers• Best Practices for On-Site Condition Assessment of High Voltage Instrument Transformers• Design Guide for Station Buswork: Accommodating Additions, Substitutions & Growth of Capacity• Design Guide for Station EMI Protection• Criteria for Spare Equipment & Parts - Part II• Guide for Asset Replacement Strategies with an Asset Management Plan Leveraging a Risk Based Approach - Phase II• Best Practice Guidelines for Transformer & Station Fire Protection, Spill Containment and Spills Management• Grid Scale Energy Storage Implementation and Applications at Substations• Online Monitoring Partial Discharge Analysis of Substation Transformers• State-Of-Art Review of Mobile Substations

This is a best practice guide for the loading of in-service aged power transformers by discussing not only the clas-sic hot-spot temperature, but also moisture, furan, CO/CO2 ratio and trend, oil quality (such as dielectric withstand), cooling system, bushing, conservator, and the actual age of the transformer. This project will also research, devel-op, and determine the life expectancy and the loss of life curves for aged transformers by considering the afore-mentioned factors. This guide will provide technical infor-mation that will allow utilities to make better decisions to improve their current transformer loading practice and to estimate the remaining life of transformer insulation.

Highlighted Projects 2018Guide for Loading of In-Service Aged Power

Transformers

This project will provide a comprehensive summary of best practice testing, activities and guidelines for success-ful on-site condition assessment of high voltage instru-ment transformers for rated voltage of 69kV up to 500 kV. The study will cover condition assessment of both oil-filled and new dry-type instrument transformers. This guide will clarify the application and effectiveness of inspection and test methods as well as the pros/cons of each test for inspecting HVITs. It will also help to avoid, identify, and eliminate developing issues with instrument transformers.

Best Practices for On-Site Condition Assessment of

High Voltage Instrument Transformers

CEATI has been a great format for us for “”benchmarking our practices and standards.

- Richard BenefielSenior Consulting Substation Strategy Engineer

Pacific Gas & Electric Company

CEATI 2017 /18 9

• Changes in Maintenance Practices and/or Philosophies

• Technology Changes / Innovations in Maintenance Practices

• Health Indicators / Predictors / Risk Identifiers for Maintenance Practices

• Innovations to Improve Reliability / Availability and/or Expected Lifecycle / Resiliency of Station Equipment

• Innovations in Performance Measurement and Performance Indicators in Station Maintenance

• Feeding, Tracking, Reviewing, and Analyzing Data for AM Programs

Sessions

Transmission Line Asset ManagementGroup OverviewThe objectives of this program are to bring together transmission system operators to exchange information on asset management practices and techniques and to facilitate collaboration that will optimize the management of overhead transmission line assets. Key focus areas of the group include asset life extension in order to defer the need for major capital expenditures, the refinement and development of prudent and effective asset management practices, and the maintenance techniques needed to reduce life cycle cost and to maintain the performance of the transmission lines system.

In 2017, two of CEATI’s Asset Management programs hosted an international industry conference. The strategies discussed included health indexing, risk assessment practices, work prioritization, conditionassessment practices, new technologies, and datarequirements.

• Asset Management and the Importance of Managing Condition

• Condition Based Maintenance Strategies for T&D Lines, Highlighting the Benefits, Costs, and Risks

• How to Develop Health Indices & Assess the Likelihood of Failure

• Work Prioritization, Diagnostics, Risk Analysis, and Degradation Curves including a Deep Dive into Health Indices

• Condition Assessment for Various Components including Techniques and Technologies

• The Full Process Cycle from Data Collection to Use and the Creation of Gap Fillers for Failure Curve Models

• New Technologies and Industry Trends

2017 Highlighted Projects

Guidelines for Transmission Line Pole and Tower Steel Capacity Based on Corrosion Degradation

The objective is to determine practical guidelines that asset managers can use to determine what would be considered an acceptable degree of metal loss on steel pole structures and tower members including the buried sections of the towers and poles.

Standardization of OHTL Inspection Data Collection (Mobile Applications)

This project creates industry standard specifications and requirements for OHTL inspection mobile/field data collection that, if followed, will provide the information needed by utilities to support both day-to-day line maintenance func-tions and longer term asset management functions.

Guidelines for Managing Transmission Line Clearances

The objective of this project is to create an industry best practices guide and a decision tree by identifying practical solutions for maintaining transmission line clearances that improve safety, reliability, and compliance while reducing the total cost of transmission operations.

• Condition Assessment of Transmission Line Concrete Foundations

• Standardization of OHTL Inspection Data Collection (Mobile Applications) - Phase 1

• Information Required to Manage the Life Cycle of Transmission Line Assets/Components

• Guidelines for Transmission Line Pole and Tower Steel Capacity Based on Corrosion Degradation

• Guidelines for Managing Transmission Line Clearances

• Live Transmission Line Maintenance Techniques for Locations with Restricted Clearances and for Major Rebuilds

2017 Collaborative Projects

Conference Themes

2017 T&D Asset Management Conference

10 CEATI 2017/18

TLAM

Technical AdvisorGeorge Juhn is a professional engineer with 28 years of experience in the electrical utility industry, most of which was spent at Ontario Hydro/Hydro One. His areas of expertise include maintenance planning, field operations, transmission and distribution asset management, line design, rate applications, and regulatory proceedings.

maintenance planning, field operations, transmissionand distribution asset management, line design,rate applications, and regulatory proceedings.

Transmission Line Infrared Inspection Guide

Infrared inspections are used to identify anomalies and confirm the electrical integrity of transmission lines. Inspections are typically performed on all line hardware, conductor, shield wire/OPGW, insulators, splicers, spacers, dampers, bonding, grounding, etc. While many transmission companies commonly use infrared inspections to complement their other inspection programs, a best-practice infrared inspection guide does not exist. This project is intended to provide a guide for the effective use and application of infrared technology for transmission line inspection.

Transmission Line Reliability and Component

Performance Measures and Their Application

This initiative will develop a set of reliability measures for monitoring, recording, and assessing the perfor-mance of transmission lines at 3 levels: 1) the transmis-sion system level, 2) the transmission line level, and 3) the component level. This will allow utilities to effec-tively manage the reliability performance of transmis-sion line assets, and to establish a format for collecting line component failure and outage information to be used in calculating these measures. This project will enable personnel looking after transmission lines to better understand how failure of individual compo-nents impacts overall transmission line and transmis-sion system unreliability, and will allow the analysis of “what if” scenarios in deciding where investments should go to improve system reliability performance and to estimate future performance.

• Infrared Transmission Line Inspection Guide• Condition Assessment of Overhead Transmission

Line Steel Lattice Towers• Transmission Line Inspections and their

Coordination• Transmission Line Reliability and Component

Performance• Standardization of OHTL Inspection Data Collection

- Phase II• Comparison of Glass Fiber Reinforced Polymer (FRP)

Composite Tapered and Constant Cross Section Poles for H-frames & Refurbishing Existing Wood H-frame Structures with FRP Composite Structural Components

• Guideline to Assess the Degree of Damage to TL Wood Poles from Woodpeckers Including Methods of Repair and Deterrents

• Transmission Line Investment Planning for Existing Lines

2018 Collaborative Projects2018 Highlighted Projects

Topics & Issues1. Asset Investment Decisions2. Maintenance & Business Practices3. Optimizing Maintenance 4. Health/Condition Assessment & End-of-Life

Prediction5. Reliability Issues, Evaluations and Solutions6. Technical Standards and Supplements7. Assessment of Promising New Technologies

• Reliability & Security: Planning• Asset Management: Managing Transmission Line

Reliability and Performance• Reliability, Security & Safety in Line Design • Emergency Restoration (Catastrophic Failures): Lines,

Network, Issues & Challenges

Conference Topics

CEATI 2017 /18 11

Transmission Overhead LineDesign & Extreme Event MitigationGroup OverviewThe objectives of this program are to develop and share strategies to deal with overhead transmission line design issues and to mitigate the impact of extreme events, develop benchmarks to increase the utilization of existing lines as well as for designing new lines, understand resiliency issues, address corrosion of transmission components, develop containment strategies against line cascade, and investigate new technologies.

2017 Workshop:

Resiliency Issues in Overhead Line Planning and DesignIn October 2017, two of CEATI’s programs hosted a joint workshop which provided attendees with a better understanding of where the “National Resilience” effort is heading and its impact on the electric power industry.

• NIST Lifeline Resiliency Project• Systems Resiliency to Disaster• Beyond N-1, a More Resilient Electric

Power Transmission Grid• Dynamic Reference Matrix for

Management of High Impact Low Frequency Risks & Basis for Technology Transfer

• Discussion on the Implementation of a Resiliency Program for Overhead Lines

• Station Hardening: Con Edison’s Response to Hurricane Sandy & Related Long-Term Improvements

• Understanding Resilience Issues from a Line Engineer’s Perspective

• EMP Mitigation: Systems and Components

Presentation Highlights

• Guidelines for Compact Line Design• Understanding and Development of a Database for Line

Failures • Guidelines for Optical Ground Wire Technology • Innovative New Structures for Better Public Acceptance • Review of Sensor Technologies in Monitoring Foundation

Movements, Vibration Detection, Insulator Leakage, and Ampacity

• Guidelines for Managing Transmission Line Clearances• State of the Art & Best Practices for Foundations • Review of Glass Fiber Reinforced Polymer (FRP)

Composite Lattice Structures for Transmission Lines

2017 Collaborative Projects

Innovative New Structures for Better Public Acceptance

The objective of this project is to prepare a state-of-the-art report on the use of innovative transmission structures in overhead line design that are more compact, visually acceptable, and have a reduced environmental impact. The report also provides guidelines with respect to cost and benefit of using such innovative aesthetic structures versus conventional structures that are commonly used in the industry.

Review of Sensor Technologies in Monitoring Foundation Movements, Vibration Detection, Insulator Leakage

and Ampacity

The objective of this project is to prepare a state of the art report of current sensor technologies that are available to measure line performance parameters such as ampacity, conductor temperature, aeolian and galloping vibrations, foundation movement, line tension and sag, etc.

2017 Highlighted Projects

Asim Haldar received his Master’s and Ph.D. in Engineering from Memorial University of Newfoundland. He has published over 50 papers and reports on line design and asset management areas, including conductor dynamics, reliability-based optimization, cascade prevention, and condition-based asset management.

Technical Advisor

12 CEATI 2017/18

TODEM

Topics & Issues

1. Extreme Events2. Maximizing Availability/Utilization of Existing

Transmission Lines3. Investigation of New Technologies4. Development of New Transmission Lines -

Constraints: Environmental, Visual, Structural5. Understanding Resiliency Issues and their

Impact on Line Design

Reliability Based Calibration of Overhead Lines – Life Assessment

The objective of this project is to prepare a state of the art report for understanding how the calibration is done with respect to reliability based design format. The methodology will be developed to assess and calibrate the old line design against the new lines, based on RBD design and a methodology to determine the remaining asset life of an old line based on this calibration.

Operating Limit for Conductor Temperature and its Impact on Splices

The objective of this project is to prepare a state of the art benchmarking report for providing guidelines on what op-erational thermal limits should be imposed on various conductor types under normal loading and emergency loading conditions (Traditional ACSR, versus several HTLS conductors). This study will specifically identify the thermal limits and its impact on the performance of splices and its technical life with specific reference to ACCR and ACCC, and will address the impact of conductor temperature on hardware and fittings and their acceptable performance limits.

Best Practices Guide for EHV AC Transmission Lines (230 kV - 765 kV) – Mechanical Issues

This project reviews the current best practices in designing extra high voltage (EHV) overhead lines. This project is carried out in two phases. Phase 1 addresses the electrical aspects while Phase 2 will focus on the mechanical aspects of EHV line design. Both phases will be integrated in a best practices guide for EHV line design.

• Operating Limit for Conductor Temperature and its Impact on Splices

• Reliability Based Calibration of Overhead Lines – Life Assessment

• Galloping Mitigation Using AR Twister and Other Devices

• Guidelines for Qualitative Risk Assessment• Comparative Evaluations of Direct Embedment vs.

Concrete Caisson Foundations for Tubular Steel Pole Structures

• Understanding Line Vibration Issues and its Impact on Splices and Overall Service Life

• Expected Life of High Temperature Low Sag (HTLS) Conductor

• Best Practices Guide for EHV AC Transmission Lines (230 kV - 765 kV) – Mechanical Issues

2018 Collaborative Projects

2018 Highlighted Projects

• Reliability & Security – Planning• Asset Management – Managing Transmission Line

Reliability and Performance• Reliability, Security & Safety in Line Design • Emergency Restoration (Catastrophic Failures) –

Lines, Network, Issues & Challenges

Conference Topics

CEATI 2017 /18 13

Grounding & LightningGroup OverviewThe Grounding and Lightning program takes a broad-spectrum view, providing clarity and understanding to a consortium of international electric power utilities with several common goals that include benchmarking, sharing of information and knowledge on grounding and lightning protection of power systems, and expanding the knowledge base through collaborative projects and development of standards and guides. The group is interested in all aspects of grounding and lightning protection of Transmission and Distribution systems.

The 9th Annual Grounding and Lightning Conference brought together leading subject matter experts from around the world, while providing an exceptional opportunity for networking with industry professionals.

9th Annual Grounding & Lightning Conference

Highlight Presentations

• HVAC Corridors, Substations and Pipeline ICCP Systems• Lightning Overvoltage Protection of Combined Overhead Line and

Underground Cable Distribution Networks• Lightning Protection Approach & Simulation Tool to Quantify the

Probability of Direct Strikes to Areas of Power Plants• Lightning Ground Potential Rise Associated with Large Ground Electrodes• How Can Cell Phone Base Stations be Located Safely Near Transmission

Structures• Identifying AC Interference Concerns and Preventing Inordinate Mitigation

Requirements• Assessment of Ground Grid Performance by Current Injection Testing:

Overland Injection vs. Phase Conductor Injection• Temporary Protective Grounds - Cables & Clamps

Improvements to Fall of Potential Ground Testing

The goal is to investigate the proximity correction method for measuring station ground impedance and to compare its efficiency and accuracy relative to the existing method proposed by IEEE STD 81. This review of methods for measuring station ground impedance will be relevant to generating stations, HV transformer stations, distribution stations, and distributed grounding systems that have solar or wind power developments.

Rating and Placement of Working Grounds

Existing standards on working grounds define current ratings and provide graphs for estimating touch potentials for different working grounds placements to define a safe working zone. Utilities need simple, quantitative tools to calculate the stresses seen by working grounds and by staff when X/R ratios differ from rated values, particularly when applied away from stations along lines and when orientations relative to source conductors differ from pictures in the standards. Additionally, utilities need tools to review ancillary topics such as capacitively and magnetically coupled voltages and currents that affect voltage testing and arcing when installing and removing working grounds. Tools to calculate step and touch voltages and currents when working around vehicles may also prove useful to utilities. The tools for calculation provided through this project for working grounds can be applied to air insulated transformer, distribution, and generating stations at all voltage levels.

Step and Touch Coordination During Substation Expansion

This project will provide an analytical review of the step and touch potentials resulting during various construction and maintenance activities of substation expansion. The study objectives include: 1) Review the hazards resulting from existing construction procedures; 2) Explore a wide range of barriers and procedures to reduce step and touch potentials; and 3) Quantify the efficiency and hazard reduction offered by differing mitigation methods.

2017 Highlighted Projects

14 CEATI 2017/18

G&L2018 Collaborative Projects

Topics & Issues1. Personal Protective Grounding2. Distribution & Transmission System

Grounding3. Lightning Protection & Performance4. Substation Grounding5. Pipelines in Proximity to Electrical

Powerlines and Structures6. Copper Theft from Grounding Systems

• Gradient Control Around Bucket Trucks and Line Stringing Vehicles

• Contribution of Overhead Ground Wires to Substation GPR Reduction

• Testing of Gradient Control Mats• Determination of Minimum Separation Between

Underground Pipelines and Electric Supply Line Structures - Phase 2

• Guide & Method to Determining Utility Contributions to Stray Voltages

• Active Method to Mitigate Induced Voltages in Pipelines • Grounding in Renewable Plants• Externally Gapped Line Arresters• Voltage Induction on Pipelines Caused by Power Line

Harmonic Currents

Guide & Method to Determining Utility Contributions to Stray Voltages

The objectives of this project are to establish a technically sound index that can quantify the respective contribu-tions of utilities’ system and customer loads to the NEV at their interface point, to develop a practical and easy-to-use method to measure the contribution index, and to prepare a guide for utility engineers in order to use the proposed method for troubleshooting stray voltage problems.

Gradient Control Around Bucket Trucks and Line Stringing Vehicles

The objective of this project is to provide an analytical review of the step and touch potentials and configuring an equipotential zone using gradient mats resulting from various construction and maintenance activities around buck-et trucks and feller bunchers with ranges of parameters as follows: transmission and sub-transmission lines over 44 kV;single and multi-circuit lines sharing a tower; steel and wood pole, H-frames, and lattice structures; a range of two-lay-er soil resistivity models, including a low resistivity top layer over rock; and vehicles including bucket trucks and tree fellers, with tires/outriggers and tracks.

Determination of Minimum Separation Between Underground Pipelines and Electric Supply Line Structures

(Ongoing Work in Phases)

Utilities are under pressure to minimize separation between underground pipelines and overhead electric power lines. The objective of this project is to provide an assessment tool for the determination of a safe separation distance between high voltage power line tower/pole footings and underground pipelines. These models should include the following parameters: system voltage, fault current, shield wire characteristics, tower spans, tower footing dimen-sions, soil types, soil resistivity, moisture content, pipeline geometries, and coating characteristics.

2018 Highlighted Projects

Technical AdvisorJohn Williamson is a professional engineer with 36 years of experi-ence in the electrical utility industry with New Brunswick Power. He spe-cializes in lightning protection and grounding system design.

CEATI 2017 /18 15

Transmission Underground CablesGroup OverviewThe Transmission Underground Cables Program facilitates an exchange of information on cable asset management. It also helps establish techniques and tools for improving installation, maintenance, and replacement procedures for fluid-filled and XLPE high voltage underground cable systems.

2017 Industry Conference:

Transition Joint Technology from HPFF to

XLPE CablesThis conference focused on transition joint technology and their use in managing the risk associated with the loss of supply of spare parts for HPFF systems. The conference sessions covered the following topics: Transition Joint Design Considerations, Utility Experience and Lessons Learned Using Transition Joints, Considerations for Install-ing XLPE Cables in Steel Pipes, and Technical Emergency Preparedness Strategy.

Transmission Cable Reference ManualThis is an inter-utility collaborative effort to compile existing information on practices and procedures related to underground transmission cable systems. This Manual is a reference for both novice and experienced engineers as it synthesizes specifications and procedures from numerous utilities. The Manual shall be detailed enough to describe what can be done for a given situation, as well as how it should be done.

The areas of focus include the design and installation of transmission cable systems. Volume 1 has been completed and covers preventive and corrective maintenance, diagnostic tests, and assessments. A second volume covering inspection and installation-related topics is now well advanced and is expected to be completed by the end of 2018. The final chapter on design and construction will be developed later as a separate project.

• Transmission Cable Reference Manual: Volume on Installation & Inspection

• Submarine Cable Operations and Maintenance Guidelines – Navigational Risk Assessment

• An Assessment of Various Underground Cable Diagnostic Techniques

• HV Cable Spares Management Guidelines• HPFF Joint Casings Corrosion Protection Aging

Tests

2017 Collaborative Projects

16 CEATI 2017/18

TUCIG CEATI has been a great place for me to learn about other utility practices and challenges and compare them versus my own. The teamwork that goes into problem solving has been of immense benefit to me and my company.

- Jeffrey LilesFlorida Power and Light

CEATI 2017 /18 17

• Developing a Maintenance Procedure for Surge Voltage Limiters and Associated Bonding System

• HPFF to XLPE Transition Splices – Insuring Quality Control in the Absence of Standards

• Maintenance Practices for XLPE Cables – Surge Voltage Limiters

• Guide to the Selection of Transmission Class XLPE Cables

• Guide to Advanced Diagnostic Test Techniques for XLPE, HPFF, and LPFF Cable Systems

• Cable Health Index Model and Software Analysis and Update

• White Paper on the Availability and Selection Criteria for Transition Splices

• State of the Art HV Cable Condition & Data Monitoring Technologies

2018 Collaborative Projects

Technical AdvisorSteve Haddock is a utility expert with over 34 years of experience in maintaining & managing transmis-sion lines and cables equipment. He brings a blend of knowledge

from field applications to senior level management positions within the electrical utility environment.

Topics & Issues

1. Strategies for Asset Management and Condition Assessment

2. Preventative and Corrective Maintenance Programs

3. Replacement Programs4. Assessment of Available Technologies and

Practices for Circuit Rating and Condition Monitoring Systems

5. Design & Construction of HV Underground Cable Systems

6. Means of Minimizing Environmental Impacts7. Worker Safety and Working in Proximity to Foreign

Utilities8. QA/QC – Factory Production, Inspection, and Test

Plans for Cable Systems 9. Training - Knowledge Transfer Techniques10. Utilizing HPFF Cable Pipes for XLPE Retrofit

Themes

• Asset Management & Life Extension• Advanced Diagnostic Techniques• Design and Installation Options

CEATI’s 2018 Transmission Conference - Cables Track will provide a forum to share information on best practices and emerging issues for working on trans-mission underground cable systems. Supported by CEATI’s Transmission Underground Cables Interest Group (TUCIG), the event will address and explore the latest in the development of tools, techniques, research, and experience to improve the design, installation, operation, and management of transmission underground cable systems.

Group Overview

Power System Planning & Operations

The Power System Planning & Operations Interest Group’s (PSPO) strategic direction is to enable the use of new and innovative technologies, including FACTS and HVDC, to enhance both existing and new transmission facilities while maintaining a high level of reliability. This includes exploring and developing tools and techniques for planning and operating transmission systems in a reliable, secure, and cost-effective manner.

2017 Workshop:

Resiliency Issues in Overhead Line Planning and Design

In October 2017, two of CEATI’s programs hosted a joint workshop which provided attendees with a better understanding of where the “National Resilience” effort is heading and its impact on the electric power industry.

Topics & Issues

1. System Adequacy, Reliability, Grid Capacity, and Security

2. Making best use of emerging and innovative technologies within the realm of PMUs, FACTS, and HVDC

3. Advances in simulation and modelling tools and techniques

4. Planning & operations practices in today’s regulatory and market environment

5. Planning and operations for power systems with increasing renewable generation and storage technologies

• NIST Lifeline Resiliency Project• Systems Resiliency to Disaster• Beyond N-1, A More Resilient Electric Power

Transmission Grid• Dynamic Reference Matrix for Management of High

Impact Low Frequency Risks & Basis for Technology Transfer

• Discussion on the Implementation of a Resiliency Program for Overhead Lines

• Station Hardening: Con Edison’s Response to Hurricane Sandy & Related Long-Term Improvements

• Understanding Resilience Issues from a Line Engineer’s Perspective

• EMP Mitigation: Systems and Components

Presentation Highlights

PMUs: New Applications and Disturbance Monitoring

This project aims to generate a repository of currently deployed PMU-based applications and to summarize their pur-pose, capabilities, grade (e.g. research, commercial), and whether they have been commercialized (i.e. readiness level). This effort will assist both planners and operators to understand applications’ capabilities as well as which applications have already been developed and which are still in the pipeline.

Impact on Transmission Operation and Reliability when Integrating DER

The objectives of this project are to identify the different major impacts on transmission grid operations when inte-grating DER resources. This project will increase transmission utilities’ and ISOs’ understanding of the issues and solu-tions needed for integrating DER into their grid operations.

Investigation, Control, and Mitigation of SSTI and SSCI Between HVDC Installations and Wind Turbines

or Turbine Generators

The objective of this project is to produce a guide on how to identify where SSTI and/or SSCI may be an issue, how to study and control them, as well as how to mitigate and/or protect against any adverse effects associated with these interactions. The main goal of the project is to improve the ability of HVDC equipment owners and others to identify, study, and mitigate the impacts of SSTI and SSCI associated with HVDC installations.

Highlighted Projects 2017

18 CEATI 2017/18

PSPO

• The role of planning coordinators and transmission planners in meeting requirements of NERC TPL-001-4

• Novel controls of PV solar farm during night and day to benefit utilities

• Lessons learned in AC / DC transmission line conversion studies performed for utilities

Recent PSPO Webinars

John Sabiston (BSc., P. Eng) is an electrical engineer with 35 years of power utility experience. He specializes in transmission system planning and participated on the Northeast Power Coordinating Council (NPCC) for 25 years.

Technical Advisor

Highlighted Projects 2018Commissioning and Maintenance Best Practices Guide for HVDC Lines and Converter Equipment

This project will generate a best practice guide to be used by utility personnel associated with the commissioning and maintenance of HVDC lines and converter equipment. The ultimate goal of the project is to improve utility personnel’s ability to install, own, operate, and maintain equipment associated with an HVDC system. The guide will assist with knowledge transfer when new personnel are assigned to HVDC operation and maintenance activities.

Planning and Operations of Power Systems with a Large Percentage of Renewable Generation

The objective of this project is to review and update the work carried out by the group in the 2007-08 on planning and operating power systems with a large percentage of renewable generation. The report will provide guidance to utility staff involved in both operating and planning the grid on managing the power system during periods of low or moderate demand with a significant amount of self-scheduling renewable generation on-line, much of which may be inverter-fed.

Best Practices for Compliance with NERC Standard TPL-001-004 “Transmission System Planning Performance

Requirement”

The objectives of this project are to review the requirements of NERC TPL-001-004 with respect to the interests of the PSPO Interest Group, as well as to summarize and identify best practices for utilities to accomplish the requirements of this standard most effectively. Also, this project may identify areas of opportunity to recommend favorable changes to this standard for improved efficiencies in Transmission Planning processes. The guidance provided should be struc-tured so that it is useful for utilities beyond NERC jurisdiction, who are facing similar regulatory demands, so that they can adopt similar approaches and strategies.

• Reliability & Security – Planning• Asset Management – Managing Transmission Line

Reliability and Performance• Reliability, Security & Safety in Line Design • Emergency Restoration (Catastrophic Failures) –

Lines, Network, Issues & Challenges

Topics:

CEATI 2017 /18 19

Infrastructure Protection & SecurityGroup OverviewThe Infrastructure Protection & Security Interest Group (IPSIG) is an international technical forum for utility engineers, operators, and both physical and cyber security experts in the fields of Power Generation, Transmission, and Distribution. This group facilitates the sharing of experiences among utilities and develops solutions to better secure utility assets from physical and cyber threats, while also filling a niche area that helps cyber and physical security specialists understand each other’s concerns and remedies.

Cyber Security: Program activities aim to evaluate cybersecurity standards and frameworks for communication and control networks, risk management, and regulatory compliance.Physical Security: Program activities aim to enhance the design and functioning of security operations for dams and powerhouses, substations, transmission/distribution assets, and RoWs.

Physical Security Maturity MatrixIPSIG’s participating utilities have recognized that physical and cyber security play an important role in electrical utility management and operations. The increasingly prevalent and severe physical and cyber security incidents affect organizations of all types. This demonstrates the need for electric utilities and related companies to continually evaluate and improve upon their security programs and procedures.

The Physical Security Maturity Matrix identifies the key attributes that should be addressed in order to create and maintain an effective physical security program within an electric utility. The matrix will help electricity organizations benchmark their security programs against others in the industry, allowing them the relative effectiveness of these programs and to justify enhancements or modifications. Alternatively, utilities can perform self-evaluations in order to identify weaknesses and areas for improvement.

2017 Highlighted ProjectKey Management

This project identifies the key management approaches currently being employed by IPSIG members and develops recommendations for “best practices” that can be applied to the full range of access control needs of electric utilities. Emphasis is placed on the integration of all tools (phys-ical and cyber) to effectively manage access control, which includes key fobs, cascading locks, and double authentication (depending on security needs).

Don Burlack (CISSP, CISM) has over 37 years of experience working within the telecommunications and electricity utility industries, with almost 30 of those directed towards computer science and cyber security. At SaskTel, he became the Senior Systems Security Director; at SaskPower, he held the position of Supervisor - Cyber Security; within the Technological Crimes Section of the RCMP he served as an Auxiliary Constable; and he has lead ethical hacking classes as an instructor for EC-Council.

Technical Advisor

20 CEATI 2017/18

IPSIG

• Playbook for Development of Security Risk Management Related Business Cases

• Managing Security around Renewables• Asset Management/ Replacement Strategies for

Security Assets• Managing Unmanned Aerial Vehicle Threats Within

Electricity Utilities• Safety of Utility Staff when Faced with Security

Threats• Insider Threats• Quantifying Loss Avoidance• Commissioning New Security Systems• Threat Vulnerability Risk Assessment –

Performance and Measurement• Intelligence-Driven Security• Intelligence Collection Techniques• Cloud Computing – Physical Security Perspective• Autonomous Botnets Detection in Industrial

Network • Meeting NERC CIP Standards Compliance within

the NIST Cybersecurity Framework• SCADA Communication Security Gap Analysis &

Recommendation • CRASHOVERRIDE Malware: Security Analysis &

Recommendation for the Industry Control System • Security Considerations Associated with OT/IT

Integration • Cyber Risk Preparedness Assessment

2018 Collaborative ProjectsCyber Security 101 Webinar Series

These webinars provide utility members with a resource that focuses on cybersecurity risk management basics as applied within electricity utilities. Targeting mostly non-cyber personnel, the webinar series distributes the information needed to support effective security risk management with-in utilities. The series discusses key functions within a Cyber and IT security risk management program with specific attention paid to the application of cyber security controls within electricity utility operations environments. The following five topics are discussed:

• Understanding & Protecting Cyber Assets• The Ins and Outs of Cyber Security Risk

Management • Building Blocks of Cyber Security Management &

Compliance• Care and Feeding of Cyber Security Controls

Within OT Environments • Cyber Security Incidents - Before, During & After

The Benefits of IPSIGIPSIG is known for its collaborative spirit and quick response time to other participants on Requests for Information (RFIs). Participants have recently provided peer-to-peer feedback on:

• Physical Security at Remote Locations• Company Documents on Security Policy• Using Yard Beams and Lasers to Protect Internal

Perimeters • Physical Security Standards• Substation Security• Emerging Technologies• Security Management Systems• Integration of Multiple Security Technologies

CEATI 2017 /18 21

Distribution Line Asset ManagementGroup OverviewThe Distribution Line Asset Management (DLAM) group focuses on improving distribution system reliability, maintenance and assessment of distribution assets, and new technologies and equipment that impact the grid. The mission of DLAM is to address best practices and processes regarding the management of distribution grid assets including planning, purchasing, installing, commissioning, maintaining, and operating the assets. The group is intended to assist utilities in maximizing the safety, reliability and efficiency of their electric distribution grid assets while minimizing cost and complying with applicable regulations, laws, and industry standards in both short and long-term timeframes.

2017 - T&D Asset Management Conference

This conference provided insight on how utilities and the industry are managing the condition of T&D lines. The strategies discussed included health indexing, risk assess-ment practices, work prioritization, condition assessment practices, new technologies, and data requirements.

Sessions

• Asset Management and the Importance of Managing Condition

• Condition Based Maintenance Strategies for T&D Lines, Highlighting the Benefits, Costs, and Risks

• How to Develop Health Indices & Assess the Likelihood of Failure

• Work Prioritization, Diagnostics, Risk Analysis, and Degradation Curves

• Condition Assessment for Various Components including Techniques and Technologies

• The Full Process Cycle from Data Collection to Use and the Creation of Gap Fillers for Failure Curve Models

• New Technologies and Industry Trends

Inspection Techniques for In-Service Indoor & Outdoor Distribution

Terminations This project documents the state of the art inspection techniques and emerging tech-nologies for inspecting in-service indoor and outdoor medium voltage terminations including separable insulated connectors such as elbows and loadbreaks. Utilities will have at their disposal information that will help them assess the risk of in-service termination failure. With this knowledge, utilities could move proactively to replace terminators before they fail, as well as improve system reliability.

Translating the Health Index into Probability of Failure for Distribution Assets

This initiative will develop a condition-based failure probability function on the basis of health index results for at least one distribution asset class. As part of delivering this primary objective, secondary objectives will also be completed including the research, development, and demonstration of approaches and procedures to be used by utilities in translating health index results into condition-based failure probability results.

2017 Highlighted Projects

• Translating the Health Index into Probability of Failure for Distribution Assets

• Application Guide and Hands-On Demonstration Workshop for Testing Based Condition Assessment of Medium Voltage Distribution Cables – Phase I

• Inspection Techniques for In-Service Indoor & Outdoor Distribution Terminations

• Survey of the Current State of Asset Management

• Big Data Analytics & Data Model for Asset Management in T&D Systems

• Grid Modernization Snapshot• Distribution System Health Indices:

A Simplified Methodology• Direct Buried Duct Vs. Concrete Encased

Duct Housing for Primary and Secondary Cable

2017 Collaborative Projects

22 CEATI 2017/18

Condition Based Maintenance Strategies for

Transmission & Distribution Lines

DLAM

• Technical Recommendations for Solar Distributed Energy Resource Interconnection Analysis

• Evaluation of Online Monitoring Technologies for Distribution Assets

• Wood Pole Refurbishment Technologies • Enhancing Connectivity of DGs by Control

Coordination of Smart Inverters• Framework for Deriving Failure Probability

Functions for Underground Cables• Voltage Induction on Pipelines Caused by Power

Line Harmonic Currents - Phase I• Detecting High Impedance Faults on Overhead

Distribution Systems• Utility Guide for Inspection and Maintenance of

Distribution Overhead Systems• Surveillance Methods for Inspection of Critical

Distribution Components• Impact on Worker Safety of Distributed Energy

Resources Connected to the Distribution Grid

2018 Collaborative ProjectsShortly after joining CEATI as a“working group member, our utility

- Jeff MochaDirector of Innovations

Oakville Hydro

was able to leverage CEATI’s reportson industry best practices to supportbusiness process enhancements. We’vealso found the working group meetingsto be a great opportunity to network,share experiences, and learn from ourpeers in the industry.”Technical Advisor

Eric Valois has close to 40 years of experience in the electrical utility industry. Having held leadership posi-tions at BC Hydro and various utilities in southwestern Ontario during the

last 20 years, he has direct experience in the planning, design, construction, operation, and maintenance of T&D systems.

Utility Guide For Inspection And Maintenance Of Distribution Overhead Systems

The objective of this project is to create an overhead distribution system inspection and maintenance guide that will help distribution utilities identify effective practices with respect to inspection and maintenance activities. It is

2017 Highlighted Projects

Detecting High Impedance Faults on Overhead

Distribution Systems

This project will help to understand the current state of the art for detecting high impedance faults on distribution systems and to explore new innovative techniques that may be em-ployed by Utilities to detect high impedance faults.

Wood Pole Refurbishment Technologies

The objective of this project is to review the utility practice, evaluate the cost effectiveness of the current wood pole refur-bishment technologies, and provide insight into potential fu-ture pole refurbishment technologies. The focus of this study is to establish the current utility practice with respect to the employment of pole refurbishment technologies in order to extend the life of wood poles. The study will also explore the cost justifications that utilities use to support the investment in wood pole refurbishment technologies.

Topics & Issues

• Improving Reliability of Distribution Equipment & Systems - Design- Distribution Emergency Management and Restoration of Assets to Service

• Maintenance & Assessment of Distribution Assets

• Technology & Equipment Impacting the Grid- Improving Safety of the Distribution System- Environmental Sustainability- Advanced Metering Infrastructure (Smart Meters)

expected that this guide will serve as a reference docu-ment to consult about best practices for inspection and maintenance activities.

CEATI 2017 /18 23

Power Quality & Advanced TechnologiesGroup OverviewThe Power Quality & Advanced Technologies (PQAT) Program provides a forum for collaboration among its members to assist them in providing consistent quality power for their customers. This includes collaboration on tools and methods to more quickly assess PQ events and conditions revealed through the automated analysis of PQ data. PQAT also provides opportunities to influence standards and share costs in doing high-quality cutting-edge studies and providing seminars, webinars, and literature on timely topics in power quality or other related areas in T&D systems, as well as on the customer side of the meter.

2017 Training Webinars and Information

Exchanges• Voltage Induction on Pipelines Caused by Power

Line Harmonic Currents• Prevention & Detection of High-Impedance Faults

and Distribution Apparatus Failures• Novel Controls of PV Solar Farm during Night and

Day to Benefit Utilities• Power Quality Monitoring Practices and Collection

& Utilization of PQ Data• Farm Equipment and Impulses on the Neutral• Detecting Second Fault on the Network System• AMI Analytics for Distribution Voltage Quality

Assessment • Capacitor Switching Analysis: Restrike,

Synchronous Closing, Reactive Power Balance• Monitoring Power Quality at a Large LDC• Electromagnetic Interference (EMI) Concerns with

Solar PV Farms

Guide for Variable Frequency Drive Installations

The handbook will provide utility personnel and their clients with a concise, easy to understand reference guide on the issues of installing a Variable Frequency Drive (VFD). The handbook will supply utilities with sufficient knowledge to properly specify, purchase and install the VFD per the VFD manufacturers’ recommendations, thus reducing or eliminating the potential of undesirable consequences. The knowledge found in this handbook will allow the user to significantly reduce their operating cost by preventing many of the issues affecting their power quality system.

Conducting Distribution and Customer Facility Ferroresonance Studies

The project will provide a guide for the modeling of ferroresonance events on distribution systems less than 25 kV, including typical circuit parameters, most notably transformers. The final report will include lessons learned from ferroresonance occurrences in distribution systems higher than 25 kV.

2017 Highlighted Projects

Dennis Hansen worked with PacifiCorp where he was principal engineer over Engineering Technical Services. In this role, he managed a group that handled a variety of issues for which engineering standards were marginal, emerging, or did not exist. This included distributed generation, energy storage devices, energy saving devices, audible noise, AC corrosion, stray voltage, and electrodynamic field effects.

Technical Advisor

24 CEATI 2017/18

PQAT

CEATI 2017 /18 25

• Statistical Methods for Aggregating, Characterizing, and Assessing Big Data from Distribution Networks

• Enhancing Connectivity of DGs by Control Coordination of Smart Inverters

• Voltage Induction on Pipelines Caused by Power Line Harmonic Currents

• Automated Waveform Characterization• International Power Quality Monitoring Project• Voltage Quality Publications for “Net-Zero”

Communities and “Microgrid” Systems

2018 Collaborative Projects

Topics & Issues

1. Customer Power Quality2. PQ Monitoring and Data Analytics3. PQ Impacts of DER Integration4. Transmission Power Quality

Statistical Methods for Aggregating, Characterizing, and Assessing Big Data from Distribution Networks

The main purpose of this project is to provide mathematical details about various statistical methods used for working with big data in engineering and operational applications. The information will be presented in a report with technical theory explanations, specific equations, methods for application, and supporting examples where applicable.

Enhancing Connectivity of DGs by Control Coordination of Smart Inverters

This project will encompass an in-depth review of the following aspects:• Enhancing DG connectivity with existing technologies• Enhancing DG connectivity with emerging smart inverter and energy storage technologies• Control coordination of Smart Inverters• Modeling, controller design, and study techniques• Case study of controller coordination of Smart Inverters in a realistic distribution system• Planning studies and field implementations of Smart Inverters for enhancing DG connectivity

Voltage Induction on Pipelines Caused by Power Line Harmonic Currents

The following will be completed: • Developing a simple and useful measurement-based method to screen/survey the severity of harmonic voltage

induction• Extending the 60Hz voltage induction assessment method to the harmonic currents• Preparing an educational style report to enable project sponsors to gain a solid understanding of the harmonic

voltage induction problem

2018 Highlighted Projects

Smart GridGroup Overview

The Smart Grid Program (SGP) is mainly concerned with technologies and system software (ADMS, OMS, DERMS, and SCADA) that are essential for modernized operation of the grid, including the related field sensors, ICT, and enterprise IT system integrations. Additionally, SG is concerned with the requirements for the future oper-ation of the grid, to enable the advancement and participation of customer-owned technologies on the edge of the grid, including all forms of distributed energy resources (DER), and to enable the advancement of Internet-connected technologies.

2nd Annual Smart Grid ConferenceThe 2017 conference focused on the meaning of a smart grid as a platform for users, services, and new technologies from both a utility’s and a customer’s perspective. The conference sessions covered technologies and devices at the edge of the grid, the possibilities of the Internet of Things, smart monitoring of the grid for automated operation in the presence of these new services, and the integration of utilities’ IT and OT.

Sessions

• The Distribution System as a Platform • Measuring and Sensing Technologies to Support Monitoring

of a Smart Grid• Customer-owned DER and Integration with the Grid• Customers, Services, & Internet of Things• The Integration of OT with IT

Interfacing DMS/OMS/SCADA Systems with Enterprise Business IT Systems for IT/OT Integration in Smart Grid

This project outlines the leading practices and techniques used to provide the pros and cons of the approaches along with the alternative methods used for IT-OT integration in DMS/OMS/SCADA projects. This project also helps members to understand the appropriate system architectures for their chosen smart grid applications and the potential areas for enhanced focus by using experience on these type of work.

Impact on Distribution Operations When Integrating DER

This project identifies various major impacts on distribution grid operations when integrating DER resources, as well as how to determine the most appropriate solutions and remedial measures to resolves said impacts. The proposed solutions involved system architecture, communications infrastructure, and automation technologies with the associated changes in the work process and product design. This work is intended to help utilities integrate DER into their distribution system operations and pave the way for future integration of additional smart grid applications that may emerge in the near future.

2017 Highlighted Projects

Topics & Issues1. Distribution Automation Deployment Strategy2. Faulted Circuit Indicator and Line Sensor

Application and Technology3. IT/OT Interface4. Customer Owned DER on the Edge of the Grid5. Internet Connected Technologies6. Networks Modeling and Data Governance7. Deployment of ICT

26 CEATI 2017/18

SG2018 Highlighted ProjectsExample Roadmaps for Improving Maturity of DER Management at Distribution Utilities

The contractor will work with a host utility to develop a utility-specific process and technology roadmap, leverag-ing the DER Operational Maturity Roadmap methodology developed in the 2017 “Impact on Distribution Operations When Integrating DER” project. The projects will help to define a technology architecture maturity roadmap that aligns with the overall DER operations capability and process maturity level. It is anticipated that the developed process and roadmap can be used as a guideline for other Smart Grid Program members.

Smart Grid Application of Faulted Circuit Indicators and Line Sensors

This project will provide a report that may be used by utilities so that they may determine the optimal application of Faulted Circuit Indicators and line sensors for their individual case. It will consider a number of factors including the smart grid applications that have been deployed and the information requirements of those applications. It will also consider the characteristics of a utility’s system.

The conference sessions will cover changing demands on a utility’s operation of the power system in the presence of new technologies and devices on the edge of the grid, the possibilities of internet enabled technologies, smart monitoring of the grid for automated operation in the presence of these new services and things, and the integration of a utility’s operating systems with enterprise IT systems.

• The Integration of Distributed Energy Resources with the Grid• Operating the Grid by Integrating IT with OT• Network Monitoring and Modeling for Smart Grid Automation

3rd Annual Smart Grid Conference

Sessions

Mr. John Fuerth has over 35 years of experience in the electric power industry, including almost 30 years in distribution system engineering and planning. With Hydro One, he led the development of tools for assessing proposed distributed generation (DER) connections to the distribution system, including system impact assessments and technical interconnection requirements.

Technical Advisor

CEATI 2017 /18 27

Protection & ControlGroup OverviewThe mission of the Protection and Control Program (P&CP) is to assist participating utilities in identifying the best prac-tices and processes for management of electrical power grids’ protective relaying and control systems over their entire life cycle. The group also focuses on developing solutions to protective relaying and control system issues as well as following up on the relevant technological developments and industry trends in order to promote optimization and innovative use of new protection and control technologies.

4th Annual Protection & Control ConferenceThe 4th Annual Protection and Control Conference, Protection Systems - Improvements and Evolution for the

Future Grids, focused on several areas of concern for power utilities including system performance, design and maintenance, digital relays and settings, information databases, integration of DGs and microgrids, new technologies, and generation-related topics. Sessions

• Optimizing Protection System Design, Maintenance, and Replacement Strategies

• Potential Use of Digital Relay Capabilities for “Smart Grid” Applications

• Improved Effectiveness of DG and Microgrid Integration• New Protection, Control, and Communication Systems

Technologies• Power Generators

Effective and Secure Protection Settings Data Management and Storage

This project identifies the best practices and data management systems that will enable the management of unified relay setting databases for the new and updated settings with associated drawings, commissioning, and test reports.

Guide for IEC 61850 Standard Applications

This project develops a comprehensive guide for applying the IEC 61850 standard in the design of new substations and an expansion and/or refurbishment of existing substations. This project also includes a methodology for quantifying the benefits of the new design attributes. In addition to the technical aspects of IEC 61850 application, the guide discusses the requirements and methodologies for the new protection and control systems testing, relay settings, and maintenance data management, as well as the requirements for protection and control staff training.

2017 Highlighted Projects

2017 Selected Training Webinars and Information Exchanges

Jerry Lepka’s career includes many years P&C, with Ontario Hydro (now Hydro One) as their District P&C Manager for the Toronto and Cherrywood Districts. He also spent several years in Ghana as a P&C Instructor and later on as the Director of the newly-formed Transmission System Division for the national power utility, Volta River Authority.

Technical Advisor

• Considerations for Remote Access to Control and Protection Systems of Small and Medium Size Hydro-Sites• High-Impedance Fault Detection – Present Technology and a Glimpse into the Future• Generator Fault Analysis and Case Studies• Power Grid Protection Systems - Duplicate Protections Design Practices• IEEE 1547 Standard for the Interconnection of Distributed Resources with Electric Power Systems• Standardizing Protective Relaying Setting and Design Philosophy

28 CEATI 2017/18

P&C2018 Highlighted ProjectsAnti-Islanding Techniques for Distribution Systems

The proposed project will help utilities gain a solid understanding of the available techniques and recent developments. It will enable sponsors to make an informed decision when designing protection schemes for distribution systems with DGs.

A Concept of Smart Substations

This project will provide utility engineers and customers with a comprehensive report to understand the new developments of protection and control devices and solutions, to get familiar with emerging technologies in substation automation including communication protocols and standards and to realize the role and importance of the “smart substation” concept in future power systems.

Detecting High Impedance Faults on Overhead Distribution Systems

This collaborative project will help with understanding the current state of the art for detecting high impedance faults on distribution systems and will explore new innovative techniques that may be employed by utilities to detect high impedance faults. This work will focus on determining the current state of detection of high impedance faults in overhead distribution systems and will include the detection of fallen conductor, conductor arcing, and phase to phase as well as phase to ground high impedance fault scenarios.

Generators Protection & Control Working

Group Potential Projects

This working group has three project definitions for further development:

• PSS tuning in the generator exciter• Hydraulic response - governor control systems and

turbine characteristics• New protection and control technologies – e.g.,

new turbine governors, excitation systems, etc.

Topics & Issues

1. Management of Protection Assets & Investment Strategies

2. Protective Relaying Maintenance Practices 3. Protection Systems Design - Standards & Utility

Practices4. Automation of Substations5. New and Emerging Protection Technologies

5th Annual Protection & Control Conference: Challenges in Maintaining Grid

Reliability in a Fast-Changing Power System LandscapeThe 5th Annual Protection and Control Conference will focus on several areas of concern for power utilities including: power system performance, protection systems design and maintenance, digital relays applications and settings, management and analytics of large information databases, enhanced integration of DGs and microgrids, new protection, control and communication technologies, and generator protection and control related topics.

Sessions

• Optimizing Protection System Design, Maintenance & Replacement Strategies

• Potential Use of Digital Relay Capabilities for “Smart Grid” Applications

• Improved Technologies & Techniques for DG and Microgrid Integration

• New Protection, Control & Communication Systems Technologies

• Protection & Control Matters for Power Generators

CEATI 2017 /18 29

Vegetation ManagementGroup OverviewThe Vegetation Management program brings industry professionals together to discuss and develop solutions for common industry issues, create networking opportunities, improve the management of vegetation, advance plan-ning techniques, and investigate the best use of technological innovations for vegetation management. The program provides vegetation managers with a cost-effective vehicle to share experiences and to address issues pertinent to their day-to-day operations, maintenance, and planning.

4th Annual Vegetation

Management Conference

The effective management of vegetation on transmission and distribution corridors is essential for providing a reliable supply of electricity and for ensuring public and worker safety. The focus of the 4th Annual Conference was on the various technologies, techniques, and equipment that are being developed or are currently available to Vegetation Managers.

Themes

• Public & Social Issues • Techniques & Products• Program Management

Vegetation Management Cost Benefit of Herbicide Use

This study compares the cost of maintaining vegetation on electric transmission right of way (ROW) corridors with and without the use of herbicides. Three case studies were used to compare the cost of Integrated Vegetation Management (IVM), which includes the use of herbicides to control incompatible trees to simply maintaining ROW vegetation by repeated cutting without the use of herbicides. Least cost economic analysis methods were used to determine the present value cost of each vegetation maintenance prescription over a 20-year evaluation period. This project convincingly demonstrates that a vegetation management strategy based on the principles of IVM (including the use of herbicides) is less costly than a strategy that does not use herbicides and relies simply on repeated mechanical and manual treatments.

Control of Weeds in Electrical Facilities such as Substations, Switchyards, Capacitor Stations, and Cable

Termination Sites

The purpose of this project is to develop two herbicide programs: one that utilizes products available in Canada, and one for the United States. These programs must be designed to reduce the development of resistance and should also include strategies to reduce reliance on herbicides, such as preventative measures and non-herbicide techniques.

2017 Highlighted Projects

Technical Advisor

Gwen Shrimpton (RPF, RPBio, MPM) is a Registered Professional Forester, Biologist, and holds a Masters in Pest Management. She has worked for BC Hydro for twenty years developing vegetation managementstrategies and standards.

30 CEATI 2017/18

VM2017 Training Webinars and Information

Exchanges

• UVM Regulatory Requirements - What the State and Provincial Regulators Think of UVM Oversight

• Debris Management to Reduce Fire Risk on Power Line Corridors

• Work Management Systems in Vegetation Management• Managing Vegetation as Environmental Assets: New

Paradigms for Utility Vegetation Management• Distribution Vegetation Maintenance Clearances• Which Herbicides are Being Used by Utilities and How

(Aerial, Foliar, Cut Stump Basal) and When They are Used• Tree Growth Regulators: How Many Utilities Use Them

and Are They Effective?• Work Management Systems

Topics & Issues

1. Environmental Issues2. Risk Quantification3. Regulatory Requirements and

Compliance 4. Vegetation Management Program

Optimization5. Adaptation Strategies for Changing

Forest and Tree Health6. Responsible Vegetation Management

Practices7. New Materials and Techniques8. Vegetation Management in Urban Areas

Integration of Tree Growth Regulators (TGR)’s into Utility Vegetation Management Programs

The project will identify and evaluate various strategies that may justify (economically and otherwise) the integration of tree growth regulator (TGR) treatments into distribution system line clearance vegetation management programs. Once potential strategies are identified, each will be used to develop representative case studies, which will subsequently be subjected to economic analysis.

Powerline Vegetation Management Best Practices within Boreal Forest Caribou Regions

Electrical utilities are expected to develop and maintain powerline RoWs in a manner that avoids or reduces impacts on caribou and caribou habitats. This project will help utilities identify and implement the most effective programs for boreal forest caribou regions. The document will specifically help justify the selection and, conversely, the avoidance of various mitigation techniques, management practices, and generally accepted industry practices in caribou regions. Conversely, electrical utilities can avoid being pressured into implementing those mitigations that are deemed to be non-effective and of no value.

The Cost-Efficiency of Integrated Vegetation Management (IVM)

The VMTF study of Vegetation Management Cost Benefit of Herbicide Use defined a business case for IVM using least cost analysis methods. This supplemental study would define a broader range of value-added benefits associated with IVM. The proposed study will clarify the many benefits of IVM beyond hard dollar cost savings, and help develop a convincing argument for more complete adoption of IVM across the ROW vegetation management industry.

2018 Highlighted Projects

5th Annual Vegetation Management Conference

The 5th Annual Vegetation Management Conference will focus on the various technologies, techniques, and equipment that are being developed or are currently available. The conference will also include a half-day live field demonstration of products from vendors.

CEATI 2017 /18 31

Strategic Asset ManagementGroup OverviewThe main objective of the Strategic Asset Management Program (SAMP) is to bring industry professionals together to identify, discuss, and develop solutions to common issues in Strategic Asset Management by creating a networking opportunity for utilities concerned with asset management application, optimization, and innovation. It also serves as a forum to identify knowledge gaps and to provide guidance on future collaborative projects.

1st Annual SAMP Conference: Strategic Asset Management Enhancement of

Effectiveness & ValueThis conference provided critical insight into the effectiveness and value of strategic asset management to electrical utilities. Strategic asset management is a holistic approach as it involves the application of asset management across the entire utility organization or business. Strategic asset management starts with the utility’s corporate strategy and mission, as a unified and coordinated approach across all technical and non-technical areas of the utility is what drives an integrated and value-based approach to Asset Management. This conference responded to the increasing pressures utilities are facing in meeting their regulatory requirements, addressing environmental and societal expectations, optimizing their performance, and for extracting as much value for customers and owners as possible from their asset infrastructure.

2017 Training Webinars and Information

Exchanges• Context of the Organization• From Asset Plans to Corporate Asset Management

Strategy• Planning: Asset Lifecycle Approach• Normalized Approach to Risk• Identification of Asset Management Issues that

Plague Us• Strategic Asset Management Investment

Optimization• Continuous Improvement

Topics & Issues

1. Context of the Organization2. Leadership3. Planning4. Support5. Operation 6. Performance Evaluation7. Improvement

SAMP’s explored program topics are organized within the framework of seven groups based on the structure of ISO 55001 Asset Management:

• Identify the value of Strategic Asset Management to utilities over standard asset management approaches

• Demonstrate that Strategic Asset Management starts from the utility corporate strategy and mission

• Develop Strategic Asset Management alignment across utility policies, processes, and procedures

• Encompass other business functions that are important to the full and proper application Strategic Asset Man-agement, such as corporate executives, human resources, information management, finance, material management and customer and stakeholder management

• Cover utility business objectives, practices, and risk management that drive asset investments & maintenance

• Collaborate with other CEATI Asset Management Programs

SAMP Objectives

32 CEATI 2017/18

SAMP

CEATI 2017 /18 33

• How to Implement Asset Management: Guidance Document

• Enterprise Risk Management: Creation of Heat Maps

• Optimized Data Model for Strategic Asset Management

• Asset Life Cycle Analysis (ALCA)• Quantifying the Non-Financial Impacts of

Asset Failures• Capital Investment to Reduce O&M• Best Practices for System-Wide Health

Analysis

2018 Collaborative Projects

Technical Advisor

David Curtis has been working in the electric utility industry in Ontario for over thirty-seven years primarily for Ontario Hydro and Hydro One. He has experience in Asset Management includ-ing Corporate Strategy Development, Risk Management, and Asset Planning.

How to Implement Asset Management: Guidance Document

This project will aim to create a pragmatic “how to” guidance document towards transforming the way organizations work with assets. This would include how to: demonstrate the value of Asset Management to your executive; assess your organization using available best practice; develop a roadmap/implementation plan; build your business case and change management plan; design and integrate your asset management system with other management systems; define and develop your approach to risk and an asset management risk framework; and define and develop your performance management framework at the right level within the organization.

2018 Highlighted Project

2018 Training Webinars and Information

Exchanges• Encouraging Effective Participation of the Front-line Field

Staff Under Strategic Asset Management • Big Data and Data Integrity • Ensuring Quality Products from our Suppliers and

Contracted Resources • Building a Qualified Workforce • Identifying the Next Strategic Asset Management Issues

that Plague Us • Developing Lower Level Asset Management Plans from a

Corporate Strategic Plan • How to Keep Pace with IT Developments • The Challenge of Asset Renewals • 2nd Annual SAMP Conference (October 2018)

This conference will bring subject matter experts from around the world to provide in-sights to conference members on the corporate perspective of asset management. In leading electric utilities, the leadership, direction and framework for the asset management system starts with the corporate strategy and involves all areas of the organization. In the various sessions of this conference, members will gain deeper understanding in the application of as-set management in the electric utility context.

Contact Information:Alex Mogilevsky

Manager, Transmission & Distribution

+1.514.866.5372

[email protected]