Trans-Mediterranean Interconnection for Concentrating ...
Transcript of Trans-Mediterranean Interconnection for Concentrating ...
Folie 1
Trans-Mediterranean Interconnection for Concentrating Solar Power
Franz Trieb
Synergistic Supergrid Conference, London, January 19-21, 2010
Folie 2
Trans-Mediterranean High Voltage Direct Current Electricity Grid:Interstate Highways for Renewable Electricity in EUMENA
www.desertec.org
EUMENA:EuropeMiddle EastNorth Africa
Folie 3
Studies:
Assessment of the renewable energy potential forthe sustainable supply of electricity and water in 50 countries of Europe, the Middle East and North Africa taking into consideration the option of Concentrating Solar Power (CSP).
TRANS-CSPTRANS-CSPMED-CSPMED-CSP AQUA-CSPAQUA-CSP
www.dlr.de/tt/trans-csp
Folie 4
Portfolio of Energy Sources for Electricity:
Coal, Lignite Oil, Gas Nuclear Fission, Fusion Concentrating Solar Power (CSP) Geothermal Power (Hot Dry Rock) Biomass HydropowerWind Power PhotovoltaicWave / Tidal
ideally storedprimary energy
fluctuatingprimaryenergy
storable primaryenergy
Folie 5
• spinning reserve
• firm capacity,power on demand
• combined generation of process heat for cooling,industry, desalination, etc.
Fuel
Thermal Power Cycle (e.g. Steam
Turbine)
Process Heat
Electricity
Principle of a Conventional Thermal Power Plant
Concentrating Solar Collector Field (Mirrors)
Solar Heat
Thermal Energy Storage
• concentrated, easily storable solar thermalenergy as fuel saver
Principle of a Concentrating Solar Thermal Power Plant
Folie 6
ANDASOL, Guadix, SpainCapacity 2 x 50 MWelStorage 2 x 1000 MWhth
www.solarmillennium.de
Folie 7
Renewable Energy Technologies
Hydropower
Tides
Waves Wind PowerPhotovoltaic
Geothermal
ConcentratingSolar Power Biomass
http://www.erneuerbare-energien.de/inhalt/36983/35338/
Folie 8
Biomass (0-1)
Wind Energy (5-50)
Geothermal (0-1)
Hydropower (0-50)
Solar (10-250)
Max
Min
Electricity Yield in GWh/km²/y
Renewable Electricity Potential in Europe, Middle East & North Africa
Folie 9
0
2000
4000
6000
8000
10000
12000
14000
16000
Potentials Demand 2000 Demand 2050
Elec
trici
ty in
TW
h/y
SolarGeothermalHydroWindBiomassWave/TideDesalinationMENAEurope
Economic Renewable Electricity Potentials vs. Demand in EUMENA
> 630000
How Does a Sustainable Mix Look Like?
Folie 10
Criteria for Sustainable Electricity Supply:
Inexpensivelow cost no long term subsidies
Secure diversified and redundant supply power on demandinexhaustible resourcesavailable technology
Compatible low pollution climate protectionlow risks for health and environmentfair access
Folie 11
Electricity Supply in Europe (TRANS-CSP Scenario)
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2000 2010 2020 2030 2040 2050Year
Ele
ctric
ity[T
Wh/
y]
Import SolarPhotovoltaicsWindGeothermalHydropowerBiomassWave / TidalCSP PlantsOil GasCoalNuclear
www.dlr.de/tt/trans-csp
Folie 12
Electricity Supply in the Middle East & North Africa
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2000 2010 2020 2030 2040 2050
Year
Ele
ctric
ity[T
Wh/
y]
DesalinationExport SolarPhotovoltaicsWindGeothermalHydropowerBiomassWave / TidalCSP PlantsOil / GasCoalNuclear
www.dlr.de/tt/med-csp
Folie 13
Installed Capacity vs. Peak Load in EUMENA
0
400
800
1200
1600
2000
2400
2000 2010 2020 2030 2040 2050Year
Inst
alle
d C
apac
ity [G
W]
0
400
800
1200
1600
2000
2400 PhotovoltaicWind PowerGeothermalHydropowerBiomassTidal/WaveCSPOil & GasCoalNuclearFirm CapacityPeak Load
100 % availability plus 25 % reserve capacity
5000 h/a 2000 h/a
Import/ExportDesalination
www.dlr.de/tt/trans-csp
Folie 14
Firm Power Capacity based on Renewables and Fuel(no fossil or nuclear base load supply)
Hourly Model Germany 2050 (TRANS-CSP)
0
10
20
30
40
50
60
25.6. 26.6. 27.6. 28.6. 29.6. 30.6. 1.7.
Pow
er S
uppl
y[G
W]
Combined Heat & Power Domestic Renewables Solar ImportImport & Pump Storage Balancing Power (fossil) Surplus
Folie 15
Electricity Cost (Example Spain)
4.04.55.05.56.06.57.07.58.0
2000 2010 2020 2030 2040 2050Year
Ele
ctric
ityC
ost[
c/kW
h]
TRANS-CSP Mix BaU Mix 2000
€2000, Fuel Cost: IEA / WEO 2005, after 2020 CCS
Investment Phase Profit Phase
Folie 16
B
Break Even with differentload segments
0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
2010 2020 2030 2040 2050Year
Cost of CSP at DNI2400 kWh/m²/a
Average Costwithout CSP
Peak Load Cost
B1
Base Load Cost
B3
Medium Load CostB2
www.dlr.de/tt/csp-finance
Elec
tric
ityC
ost(
$ 201
0/k
Wh)
Folie 17(artist view created withGoogle Earth)
Energy, Water,Food, Labor and Income
for further300 Million People in MENA ?
Solar Power & Desalination Plants
HVDC Line
Conventional AC Grid
Folie 18
Solar Electricity Corridors to Europe: REACCESS
www.dlr.de/tt/csp-resources
Folie 19
High Voltage Direct Current Transmission in China
Voltage: ± 800.000 VoltPower: 6400 MegawattLength: 2070 kmSource: HydropowerLosses: 7%Setup Time: 2 years
http://www.abb.comhttp://www.siemens.com
Folie 20
Opportunities
Power on Demand by a Mix of Fluctuating and Balancing Sources
Increased Number of Sources and Supply Regions
Strategy is Based on Proven Technologies
Reduced Pollution and Climate Change
Optimal Land Use (1%) through Diversified Mix
Intrinsic Trend to Lower Cost and Lower Price Volatility
Conflict Prevention Solving Energy and Water Scarcity
Initiating EU-MENA (Energy) Partnership
Folie 21
Challenges
Requires New Structures and New Thinking (Change of Paradigm)
Requires Long-Term Financing Scheme for Large Infrastructure
Based on International Cooperation and Interdependencies
Higher Complexity than Using Ideally Stored Fossil Energy Sources
More Stakeholders Involved due to Decentralized Generation
Cultural and Political Differences in EUMENA
Lobby Groups Acting Against Each Other
Speed of Environmental Change and Conflict Potentials
Folie 22
Thank You!
www.dlr.de/desertec