Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at...

18
Strictly Confidential Tram Project Board 19th December 2007 Transport Edinburgh Trams for Edinburgh Lothian Buses 1 CEC01483731_0001

Transcript of Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at...

Page 1: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Strictly Confidential

Tram Project Board

19th December 2007

Transport Edinburgh Trams for Edinburgh

Lothian Buses

1

CEC01483731_0001

Page 2: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Agenda

Price

Progress to closing contract

Programme

Employer's Requirements

Outstanding activities

Network Rail and other Third Parties

Governance

Funding

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

2

CEC01483731 0002

Page 3: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Strictly Confidential

INFRACO/ TRAMCO

Stewart McGarrity

Steven Bell

Geoff Gilbert

Transport Edinburgh Trams for Edinburgh

Lothian Buses

3

CEC01483731_0003

Page 4: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Price

Stewart McGarrity

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

4

CEC01483731_0004

Page 5: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Progress To Closing lnfraco Contract

Headlines of Deal agreed in Wiesbaden

• Based on

- BBS taking detailed design development risk

- Completion of Phase 1a by Feb 2011 (based on current

tie/TEL/CEC/BBS programme discussions)

- Employer's Requirements V3 and corresponding lnfraco compliance

matrix

- Contract negotiations as at 14/12/07

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

5

CEC01483731 0005

Page 6: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Progress To Closing lnfraco Contract

• Technical basis

- Employer's Requirements V3 and corresponding lnfraco

compliance matrix

- Stepped poles allowed in on street sections

- Catenary in off street sections (excluding NEL)

- VE includes for change to Edinburgh Park Viaduct column heads

(price and programme benefit)

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

6

CEC01483731 0006

Page 7: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Progress To Closing lnfraco Contract

Excludes

• Utilities diversions currently in MUDFA but which will transfer to

lnfraco

• Work in St Andrews Square outside track alignment

• Extra over cost of work in Forth Ports Estate

• Adverse ground conditions

• Bernard St streetscape works

• Frontage to frontage replacement in Leith Walk

• Changes at Edinburgh airport - diversion of Burnside Road

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

7

CEC01483731 0007

Page 8: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Progress To Closing lnfraco Contract

Why is this a good deal?

• Design development risk transferred to lnfraco from this point on

• Firms up previously provisional elements of structures, highways

and drainage

• Stronger commitment to VE

• Reduces risk to programme for closing a contract - no need to do

detailed measurement of provisional items

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

8

CEC01483731 0008

Page 9: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Progress To Closing lnfraco Contract Third Party Agreements

• Contain

- Design consultation/approval requirements

- Requirements to agree local CoCPs (FP, SRU, EAL,NEL)

- Approval of insurance levels

- Specific scope in certain instances

- Some constraints on delivery of work

- Requirement to take 'due cognisance of representations' from TPs

• Wewill

- Agree local CoCPs with TPs prior to contract award (with BBS)

- Tie will consult with TPs and gain agreement on levels of insurance

- Consult with TPs on closing out any other issues

• SOS will confirm to BBS that have consulted with TPs on designs where

required Transport Edinburgh Strictly Confidential Trams for Edinburgh

Lothian Buses

9

CEC01483731 0009

Page 10: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Programme

Methodology and sequence agreed by key stakeholders.

Current completion date 1 a 01 2011

- March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted

during August 2010 embargo).

Detailed Traffic Management Proposals being programmed

comprehensively learning from MUDFA experience.

- A8 Traffic Management solutions and phasing of guided bus way work being

concluded for off street section.

Key constraints included above:

- Design delay in line with sos V22 Program as MUDFA and sue completion.

- BBS critical resource constraints.

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

10

CEC01483731 0010

Page 11: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

._ ... T­¥.litMM:WliWld -­w.bl•AoadJunctio!l

__ .,, __ St AMhw S.,... .... .._ .......,,.._ ....__

___ ... __ W'l• ~R9tW .. __ ...., ...... ......... _ W21M~i WOl:l)ol~1i9ridoit - -o,t, ~ .. (dftPJt\.C...JI Edift,-"1.Ctft· Edlw\hrlt:SM ..,_ ... ..._ -~P¥\bl·~o,,tf ...... .,,..._ - -e.o;,­,,,~--,., ............ & .... Y4 BaiWDrbt R,t_ Wlll 8---... s1,~~ SiO Al.-swt Road &iduit WJ,'Wj ~ RNdAtilw.11 W11 t.btM)'!Wd TS Rte vt• ---­UfA~YbdllCll n ,e ~ °' Ui!h 8rndgt S?18 t....,~Ritt.Wlll S:hD~Rtt.Wll

-

-- -,.._ ---- ---

-... t.UlFA ~

Strictly Confidential

--

-

·--

Summary Programme

Sequencing Chart

Transport Edinburgh Trams for Edinburgh

Lothian Buses

11

CEC01483731 0011

Page 12: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Employer's Requirements

• BBS/ tie synchronisation due to be finally completed 20.12.07.

• No significant issues expected with SOS regarding this synchronisation and will be concluded as part of novation plan and agreement.

• Latest version also being checked/ verified for assisting with contract suite as part of DLA review.

• tie/ TEL/ Transdev/ BBS participation in facilitation on ER's.

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

12

CEC01483731 0012

Page 13: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Outstanding Activities

• Closure of critical CEC Documentation

• Further due diligence by BBS

• Novation details, prioritisation delivery

• SOS Design/ ER 3.1 alignment

• Completion of aligned BBS proposals

• Value Engineering

- Prioritise and fast track

- Establish risk provisions for post financial close

• Contract consistency checks (e.g. with ERs)

• Third Party agreements - particularly NR APA

• Other schedules and details

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

13

CEC01483731 0013

Page 14: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Strictly Confidential

Other Issues

Steven Bell

Stewart McGarrity

Transport Edinburgh Trams for Edinburgh

Lothian Buses

14

CEC01483731_0014

Page 15: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Network Rail and Third Party Agreements

• NR Property Agreement Suite

• Framework Agreement : One outstanding point to resolve with NR

(abi lity of CEC to use CPO)

• Lease Agreed

• Neighbour Agreement Agreed

• Bridge Agreement in progress (non critical to lnfraco Award)

• Operating Agreement in progress (non critical to lnfraco Award)

• APA approaching agreed form. Issues/points around indemnities

and LD's to resolve with NR. Aiming to conclude drafting mid Jan

• Full APA sign off suspensive on Depot & Station Change

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

15

CEC01483731 0015

Page 16: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Network Rail and Third Party Agreements

• Depot & Station Change proposals being progressed with NR and

TO Cs

• BBS are providing input to these proposals

• Working with NR to fast track these regulatory processes (Aiming to

have TOC consent by Financial Close)

• BAA Licence & Lease agreed: with CEC for sign off

• Forth Ports Heads of Terms concluded - SOS working to agreed

tramway/roads layout & full agreement drafting in progress (Aiming

to agree drafting by Financial Close)

• SRU Agreement being progressed with outstanding design matters

being resolved (Aiming to conclude agreement by Financial Close)

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

16

CEC01483731 0016

Page 17: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Governance - Operating Agreements and related matters

• tie Operating Agreement was appended in draft to the Council Report issued 17 December 2007. tie Board reviewed this draft on 18 December 2007, comments have been sent to CEC.

• To date we have had no workable draft of the TEL Operating Agreement, but we are preparing a draft for CEC to consider which will be issued to CEC by 21 December 2007

• We are also preparing an update of the governance paper which was included in the TPB papers on 7 December 2007 and which will include proposed delegation thresholds for all entities in the governance hierarchy, consistent with the Council Report

• It is critical that the model which emerges has a clear and singular character and that duplication of effort is avoided. The tie agreement, TEL agreement and all delegations must be coherent and consistent.

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

17

CEC01483731 0017

Page 18: Tram Project Board · 2017. 10. 19. · - March 201 1 (Feb 2011 if OHL and associated work at Picardy Place is permitted during August 2010 embargo). Detailed Traffic Management Proposals

Funding Letter

Stewart McGarrity

Strictly Confidential Transport Edinburgh Trams for Edinburgh

Lothian Buses

18

CEC01483731_0018