Traffic Noise Impact Analyses Using a Screening
Methodology: Oregon DOT Experiences
• Presented by: Carole Newvine/Noise Specialist
Oregon Department of Transportation
• Presented at: Transportation Research Board ADC40 Transportation-Related Noise and Vibration 2013 Summer Meeting - Santa Fe New Mexico
1
![Page 2: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/2.jpg)
Outline
• OR DOT previous screening methodology
• New screening methodology
• Project experiences using screening – Local Gov’t – suburban setting
– Rural setting
– Protected forest land
2
![Page 3: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/3.jpg)
Previous Screening Methodology
prior to 23 CFR 772 update (2010)
Assumptions Receptor Distance: 15 meters from roadway CL Site Characteristics: Hard site, infinite flat roadway, no shielding Vehicle Speeds: 30, 40, 50, 60, 70, 80, 90, 100, 110, and 120 km/hr Traffic Characteristics: Peak Hour Traffic Volume (PHT) = 21% of ADT volume Truck Volume = 30% of PHT Volume (27% Heavy Trucks, 3% Medium Trucks) Study Year: 2015
3
![Page 4: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/4.jpg)
Previous Screening Methodology
prior to 23 CFR 772 update (2010)
Year Speed ADT 2015 30 km/hr 950
40 km/hr 600 50 km/hr 450 60 km/hr 300 70 km/hr 250 80 km/hr 200 90 km/hr 150 100 km/hr 140
110 km/hr 130 120 km/hr 110
Traffic volumes, speeds below would result in predicted noise levels of Leq 64 dBA at 15 meters (50 ft) from centerline.
4
![Page 5: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/5.jpg)
2013 Problem/Solution
• Oregon’s Type I projects in rural areas – project delivery impacted
• No provisions in Federal rule for programmatic streamlining
• Some states already had approval for screening methodologies
- Idaho
- Washington State
- Virginia
5
![Page 6: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/6.jpg)
ODOT Screening Methodology for Traffic Noise Impacts – March 2013
Applicability:
Type I projects where noise impacts are not anticipated or when there are impacts but no feasible abatement
6
![Page 7: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/7.jpg)
ODOT Screening Methodology – Highlights:
• Oregon’s screening methodology – mirrors WA, ID, VA methods
• TNM to estimate existing, design year traffic noise levels at selected distances from the roadway centerline – out to 1500 ft.
• Conservative results: assumes worst case conditions not actual roadway design or topography
• Technical report required
7
![Page 8: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/8.jpg)
ODOT Screening Methodology – Highlights Continued:
• Validation of the straight line model is not required
• Traffic data, vehicle speeds, actual receptor distances from the roadway for Build condition for NAC determination
• Compare Existing to Build to determine substantial increase impacts
8
![Page 9: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/9.jpg)
Complex Modeling Straight-line Modeling
9
![Page 10: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/10.jpg)
ODOT Screening Methodology Post Modeling
• If abatement appears feasible - detailed analysis required
• No abatement feasible (e.g., driveway access), a detailed noise analysis (full TNM modeling) is not required
• Noise monitoring may be required
• 23 CFR 772 requirements must still be met
10
![Page 11: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/11.jpg)
ODOT Screening Analysis for Traffic Noise Impacts – March 2013
Advantages: – Can be done in-house – Saves budget – Can be performed earlier in the project development cycle -
only limited design information needed
Disadvantages: – Limited use – conservative results – Can’t be used for analysis of alternatives – Inappropriate use
11
![Page 12: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/12.jpg)
Local Gov’t – Suburban Setting Freeman Road: Central Point
12
![Page 13: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/13.jpg)
Local Gov’t – Suburban Setting Freeman Road: Central Point
13
![Page 14: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/14.jpg)
Local Gov’t – Suburban Setting Freeman Road: Central Point
14
![Page 15: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/15.jpg)
Rural Setting
OR86: Baker County
15
![Page 16: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/16.jpg)
Rural Setting
OR86: Baker County
16
![Page 17: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/17.jpg)
Rural Setting
OR86: Baker County
17
![Page 18: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/18.jpg)
18
Protected Forest Land US26: Mt Hood Safety Project
![Page 19: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/19.jpg)
Protected Forest Land US26: Mt Hood Safety Project
Critical Viewpoint:
Laurel Hill. Existing Condition
Laurel Hill. Proposed Condition
19
![Page 20: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/20.jpg)
Protected Forest Land US26: Mt Hood Safety Project
Critical Viewpoint:
Mirror Lake. Existing Condition
Mirror Lake. Proposed Condition
20
![Page 21: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/21.jpg)
Protected Forest Land US26: Mt Hood Safety Project
Mirror Lake Trailhead (continued)
21
![Page 22: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/22.jpg)
Protected Forest Land US26: Mt Hood Safety Project
Critical Viewpoint: The Pioneer Bridle Trail at MP 51.30
The Pioneer Bridle Trail at MP 50.90
22
![Page 23: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/23.jpg)
Protected Forest Land US26: Mt Hood Safety Project
23
Critical Viewpoint: Map Curve.
![Page 24: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/24.jpg)
Suburban setting: Impacts with accessibility issues Rural setting: No impacts
USFS lands, 4(f): Impacts; access issues, Federal and County viewshed restrictions; exceeds cost criteria
24
Summary: Type I Projects – Screening Methodology
![Page 25: Traffic Noise Impact Analyses Using a Screening ... TRB13.pdf · Traffic Noise Impact Analyses Using a Screening Methodology: Oregon DOT Experiences ... ODOT Screening Methodology](https://reader031.fdocuments.us/reader031/viewer/2022021801/5b406add7f8b9aff118d41d3/html5/thumbnails/25.jpg)
Contact Information
Carole Newvine/ Noise Program Coordinator 503-986-3447 [email protected]
Natalie Liljenwall/Air and Noise Engineer 503-986-3456 [email protected]