Traffic Engineering Report - eisdocs.dsdip.qld.gov.aueisdocs.dsdip.qld.gov.au/Abbot Point...
Transcript of Traffic Engineering Report - eisdocs.dsdip.qld.gov.aueisdocs.dsdip.qld.gov.au/Abbot Point...
TTM Consulting Pty Ltd
41 105 037 045 Brisbane | Gold Coast | Sunshine Coast Melbourne | Sydney | Singapore
PO Box 949
Maroochydore, QLD 4558
t (07) 5479 2455
f (07) 5479 3651
www.ttmgroup.com.au
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Abbot Point, Qld
Prepared for:
Adani Australia Company Pty Ltd
October 2015
Reference: 15BRT0361/Rep02
Traffic Engineering Report
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
i \\TTMFS01\Synergy Data\Synergy\Projects\15BRT\15BRT0361 Abbot Point T0 EIS\7 - Reports\TTM report 15BRT0361Trep151016 Final Adani comments - FINAL.docx
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
© 2015 - TTM Consulting Pty Ltd
ABN 65 010 868 621
Level 1, 129 Logan Road, Woolloongabba
PO Box 1310 Coorparoo QLD 4151
T: (07) 3327 9500 F: (07) 3327 9501 E: [email protected]
Document Status
Rev
No. Author
Reviewed / Approved Description Date
Name Signature
01 G Harris RV Jones Draft 25.09.2015
02 G Harris RV Jones
RPEQ: 8943
Final for Submission 16.10.2015
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
ii \\TTMFS01\Synergy Data\Synergy\Projects\15BRT\15BRT0361 Abbot Point T0 EIS\7 - Reports\TTM report 15BRT0361Trep151016 Final Adani comments - FINAL.docx
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table of Contents
Abbreviations and Acronyms vi
Executive Summary vii
1 Introduction 1
1.1 Project Overview 1
1.2 Investigation Process 2
1.3 References 2
1.4 Scope 2
1.5 Consultation 3
2 Project Profile 4
2.1 Project Description 4
2.2 Project Timeframes 4
2.3 Staffing Operation 6
2.3.1 Construction Workforce 6
2.3.2 T1 – Existing Staffing Model 7
2.3.3 T0 – Staffing Model 7
2.4 Heavy Vehicle Movements 8
2.5 Description of Proposed Vehicles 8
2.6 Site Access 9
2.7 Other Relevant Projects 9
3 Regional Context 11
3.1 Project Location 11
3.2 Existing and Proposed Port Infrastructure 11
3.3 Existing Road Network 11
3.3.1 Bruce Highway 11
3.3.2 Abbot Point Road 12
3.4 Major Structures 12
3.5 Public Transport and School Bus Routes 13
3.6 Future Road Improvement Projects 13
3.7 Rail Access 13
4 Development Traffic Generation and Distribution 14
4.1 Basis for Traffic Impact Analysis 14
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
iii \\TTMFS01\Synergy Data\Synergy\Projects\15BRT\15BRT0361 Abbot Point T0 EIS\7 - Reports\TTM report 15BRT0361Trep151016 Final Adani comments - FINAL.docx
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
4.2 Existing Operations: Traffic Demands 14
4.3 Construction Stage: Traffic Demands 14
4.3.1 Construction Stage: Heavy Vehicle Traffic Generation 14
4.3.2 Construction Stage: Workforce Traffic Generation 18
4.3.3 Construction Stage: Traffic Distribution 19
4.4 Operational Stage (Phase 1 and 2): Traffic Generation 21
4.4.1 Operational Traffic 21
4.4.2 Operational Stage: Traffic Distribution 22
4.5 Impacts of Decommissioning 23
4.6 Cumulative Traffic 23
4.7 Future Background Traffic 25
5 Traffic Operation Assessment 26
5.1 Introduction 26
5.2 Average Annual Daily Traffic (AADT) 26
5.3 Road Corridor Capacity Criteria 26
5.4 Bruce Highway Operational Performance 27
5.5 Proposed Haulage Route 28
6 Site Access Review 29
6.1 Introduction 29
6.2 Existing Intersection Layout 29
6.3 Accident Review 29
6.4 Sight Distance Review 29
6.5 Traffic Scenarios 30
6.6 Intersection Turn Warrant Review 33
6.7 Right and Left Turn Requirements 35
6.8 Intersection Capacity - Isolated 36
6.9 Intersection Capacity - Rail Impacts 37
6.10 Updated Traffic Capacity Assessment 42
6.11 Adjacent Bruce Highway Intersections 42
7 Road Pavement Impact Assessment 43
7.1 Existing ESA Pavement Loadings 43
7.2 Development Heavy Vehicle Generation & Impacts 43
7.3 Mitigation Review 44
8 Draft Road-use Management Plan (RMP) 45
8.1 Introduction 45
8.2 Draft RMP Policy Statement 45
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
iv \\TTMFS01\Synergy Data\Synergy\Projects\15BRT\15BRT0361 Abbot Point T0 EIS\7 - Reports\TTM report 15BRT0361Trep151016 Final Adani comments - FINAL.docx
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
8.3 Draft RMP Objectives 45
8.4 Draft RMP Implementation Strategy 45
8.4.1 Driver Fatigue Policies 46
8.4.2 Driver Behaviour Policies 46
8.4.3 Work Related Travel and Transport Policies 46
8.4.4 Over-dimension Vehicle Management 46
8.4.5 Road Safety Audit Review, Capacity & ALCAM Assessment 47
8.4.6 Road Noise Management 47
8.4.7 Dust Control Management 47
8.4.8 On-site Parking Management 47
8.4.9 Dangerous Goods Management 48
9 Rail Information 49
10 Conclusions and Recommendations 51
Table Index
Table 2.1: Existing and Proposed Projects Abbot Point 10
Table 3.1: Local Road Hierarchy 11
Table 4.1: Phase 1 Construction Vehicle Requirements (External to Site) 17
Table 4.2: Construction Staff Requirements (Phase 1) 19
Table 4.3: Construction Traffic Movements (Phase 1) 19
Table 4.3: Construction Traffic Distribution (Phase 1) 20
Table 4.4: Operational Site Traffic Generation (Phase 1 and 2) 22
Table 4.5: Operational Traffic Distribution (Phase 1 and 2) 23
Table 4.6: Design Background Traffic Growth on Bruce Highway 25
Table 5.1: Existing AADT Volumes on State-Controlled Roads 26
Table 5.2: Two Lane Rural Road Capacity – Rolling Terrain Two-Way Flow 26
Table 5.3: Maximum AADT’s for Various LOS on Two-Lane Two-Way Rural Roads 27
Table 5.4: Level of Service: Bruce Highway (Base Case) 27
Table 5.5: Construction (Phase 1) and Operation (Phase 1 and 2) Impact on Bruce Highway 28
Table 6.1: Accident Details within 500m of Bruce Highway/Abbot Point Road Intersection 29
Table 6.2: Anticipated Abbot Point Road Train Volumes and Crossing Times 38
Table 6.3: Sidra Queue Outputs: Bruce Hwy/Abbot Point Road/Rail crossing Intersections 39
Table 6.4: Recommendations Due to Queue Exceedance 40
Table 7.1: Construction Stage: Peak Daily ESA Generation (2018) 43
Table 7.2: Operational Stage: Peak Daily ESA Generation (2019) 43
Table 7.3: Bruce Highway Impact on Road Network: Construction Stage 43
Table 7.4: Bruce Highway Impact on Road Network: Operation Stage 44
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
v \\TTMFS01\Synergy Data\Synergy\Projects\15BRT\15BRT0361 Abbot Point T0 EIS\7 - Reports\TTM report 15BRT0361Trep151016 Final Adani comments - FINAL.docx
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 9.1: Base and Development Volumes on Abbot Point Road - Phase 1 Construction 49
Table 9.1: Base and Development Volumes on Abbot Point Road - Phase 1 & 2 Operation 50
Figure Index
Figure 2.1: Project Site Location and Regional Transport Network 5
Figure 2.2: Project Site Location and Regional Transport Network 9
Figure 3.1: Existing Road Network & Site Access 12
Figure 4.1: Estimated CCMP and NGBR 2016 Construction Peak Hour Volumes 24
Figure 4.2: Estimated CCMP and NGBR 2026 Operation Peak Hour Volumes 24
Figure 6.1: Bruce Hwy/Abbot Point Road: 2013 Base Traffic - Surveyed 30
Figure 6.2: Bruce Hwy/Abbot Point Road: 2018 Base Traffic (3% p.a. growth) 31
Figure 6.3: Bruce Hwy/Abbot Point Road: 2019 Base Traffic (3% p.a. growth) 31
Figure 6.4: Bruce Hwy/Abbot Point Road: 2029 Base Traffic (3% p.a. growth) 32
Figure 6.5: Bruce Hwy/Abbot Point Road: 2018 Base and Construction Traffic (Phase 1) 32
Figure 6.6: Bruce Hwy/Abbot Point Road: 2019 Base and Operations Traffic (Phase 1 & 2) 33
Figure 6.7: Bruce Hwy/Abbot Point Road: 2029 Base and Operations Traffic (Phase 1 & 2) 33
Figure 6.8: Turn Warrant Requirement: 2018 Construction Phase (Phase 1) 34
Figure 6.9: Turn Warrant Requirement: 2029 Operation Phase (Phase 1 and 2) 34
Figure 6.10: Rural CHR Turn Treatment from AUSTROADS GRD Part 4A 35
Figure 6.11: Rural AUL Turn Treatment from AUSTROADS GRD Part 4A 36
Figure 6.12: AUSTROADS GTM Chapter 3: Table 6.1 37
Figure 6.13: Sidra Network Layout 38
Figure 6.14: Anticipated Queuing on Bruce Highway and Abbot Point Road 40
Figure 6.15: Recommended Road Works 41
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
vi www.ttmgroup.com.au
T: (07) 3327 9500 F: (07) 3327 9501 E: [email protected]
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Abbreviations and Acronyms
AADT Average Annual Daily Traffic
AAPT Adani Abbot Point Terminal
ALCAM Australian Level Crossing Assessment Model
APSDA Abbot Point State Development Area
AUL Auxiliary Left Turn Lane
AV Articulated Vehicle
BIBO Bus In/Bus Out
CCMP Carmichael Coal Mine Project
CHR Channelised Right Turn Lane
DIDO Drive In/Drive Out
DTMR Queensland Department of Transport and Main Roads
EIS Environmental Impact Statement
EPBC Act Environment Protection and Biodiversity Conservation Act 1999 (Cth)
ESA Equivalent Standard Axles
FIFO Fly In/Fly Out
GARID Guidelines for Assessment of Road Impacts of Development
HV Heavy Vehicle
KM Kilometre
LOS Level of Service
MCU Material Change of Use
Mtpa Million tonnes per annum
NGBR North Galilee Basin Rail Project
NQBP North Queensland Bulk Ports
QR Queensland Rail
RMP Road User Management Plan
SDA State Development Area
SEQ South East Queensland
WRC Whitsunday Regional Council
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
vii www.ttmgroup.com.au
T: (07) 3327 9500 F: (07) 3327 9501 E: [email protected]
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Executive Summary
Adani Australia Company Pty Ltd (Adani), as Trustee of Adani Australia Holding Trust, is proposing to construct a Port Facilities development involving a terminal [Terminal 0 (T0)] with a throughput of 70 Million tonnes per annum (Mtpa) and ancillary services (the Project). The Project will be located in the Abbot Point State Development Area (APSDA) approximately 25km nort-west
of Bowen, Queensland.
The Port of Abbot Point currently supports existing coal infrastructure [Terminal 1(T1)] which is
owned (under a 99 year lease term) by Adani Abbot Point Terminal (AAPT). The arrangements
provide a provision for expansion of the facility in the future and as capacity requirements require
additional works. The T1 infrastructure will continue to operate once the T0 Project is operational.
The overall project will be delivered over two (2) phases, Phase 1 (throughput of 40 Mtpa) and Phase 2 (additional throughput of 30 Mtpa). The current State Development Area (SDA) application is for Phase 1 only; and as such this traffic and transport assessment excludes construction aspects related to Phase 2. To provide a robust assessment, Phase 1 and 2 are considered for operation of the Project.
This report investigates the road transport aspects associated with the proposed Project. The
report evaluates the developments traffic and transport impacts on the existing road network and
recommends appropriate measures to mitigate any significant traffic impacts from the Project.
The investigation has identified that the development traffic generated during the construction
stage will generally be low due to the shipping of major construction materials directly to site and
the use of buses to transport workers to and from their accommodation locations. The
investigation has further identified that the traffic generated during the operational stage is likely
to have a minor traffic impact due to the highly automated nature of the port facilities.
Mitigation measures are required due to the proximity of rail lines to the Bruce Highway along
Abbot Point Road. These measures include providing laybys between the rail lines to prevent
vehicles becoming stranded over these, and lengthening turn lanes on the Bruce Highway to
provide additional vehicle storage.
It is intended for a Road-user Management Plan (RMP) to be prepared at least 6 months prior to
the commencement of construction activities. This RMP will review and identify any road
capacity, safety and operational issues, which can be corrected through the implementation of
strategies or corrective actions. This RMP will ensure that no undesirable operational or safety
impact will occur on both the road and rail networks, with the RMP updated through monitoring,
auditing and reporting.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
1
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
1 Introduction
1.1 Project Overview
The Port of Abbot Point (Project site) is located approximately 25 km north-west of Bowen and is
Australia’s most northerly coal port. The Port of Abbot Point is of particular significance to both the
Commonwealth and the State, as there are few locations along Queensland’s eastern seaboard with
in-shore proximity to deep water.
The Port of Abbot Point supports an existing coal export terminal (T1) with capacity to export 50
Mtpa of product coal. Capacity at the port and rail which feeds the port was expanded to 50 Mtpa in
recent years.
The T0 Project is a new coal export terminal adjacent to the existing T1 and will be constructed over
two phases - Phase 1 and Phase 2. This assessment concentrates on Phase 1 with a separate
assessment to be conducted in the future for Phase 2. Development of Phase 1 is proposed to occur
over a 2 year period and will be timed to correspond with production outputs at the Adani
Carmichael Coal Mine being developed by Adani Mining Pty Ltd. The Project will allow for an initial
throughput of 40 Mtpa and an eventual maximum throughput of 70 Mtpa upon completion of Phase
2. This allows for potential increases in mine output efficiency and any other sources of coal to be
incorporated into the port’s capacity.
This traffic assessment has been prepared in response to an Information Request from the
Department of transport and Main Roads (DTMR) on the T0 Phase 1 SDA application for a Material
Change of Use (MCU) in the APSDA, being assessed by the Office of the Coordinator-General. This
assessment includes updated information with regard to timing of the Project, workforce and
accounts for other projects particularly the Carmichael Coal Mine Project (CCMP), North Galilee
Basin Rail Project (NGBR) and the Abbot Point Growth Gateway Project.
The assessment of traffic impacts for the Project was divided into two primary stages; construction
and operational. The construction stage focuses on Phase 1 and the operational stage focuses on the
combined Phase 1 and 2 information. The traffic assessment has been based on a continuous
construction schedule, over a 2 year period.
Adani lodged a referral for the T0 Project in 2011 (Referral No. 2011/6194) and received guidelines
for preparation of the Environmental Impact Statement (EIS). Adani submitted the Project (EIS) in
2013 under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) (for both
phases). Adani received approval from the Commonwealth Government (10 December 2013), under
Section 130 (1) and 133 of the EPBC Act, to construct and operate the T0 Project. The assessed and
approved EIS included an original Traffic and Transport Assessment (TTM 2013). This report is an
updated version of the original report and had been prepared for state approval requirements.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
2
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
1.2 Investigation Process
In addition to information provided by Adani, TTM undertook their own investigations to gather
relevant traffic data and have contacted DTMR to collate existing traffic and transport data for the
surrounding road network.
1.3 References
In preparing this report, the following guidelines and planning documents were referenced:
• AUSTROADS, 2009, 'Guide to Road Design' series;
• Department of Transport and Main Roads, 2015, 'Road Planning and Design Manual' 2nd
edition. Volume 3: Guide to Road Design';
• Department of Transport and Main Roads, 2006, 'Guidelines for Assessment of Road Impacts
of Development';
• Worley Parsons Consulting, 2015, 'Road Transport Impact Assessment: Abbot Point Growth
Gateway Project'; and
• Brown Consulting (QLD) Pty Ltd, 2013, 'Carmichael Coal Mine and Rail Project: Traffic Impact
Assessment'
• GHD, 2013, 'North Galilee Basin Rail Project: Environmental Impact Statement Chapter 2
Project Description'
• Calibre Consulting, 2015, 'Road Impact Assessment - Whitsunday Regional Council Road
Network: Carmichael Coal Mine and Rail Project'.
1.4 Scope
This report forms part of the overall SDA Application technical documentation and investigates the
traffic demands anticipated to be generated by the Project including a review of potential
development traffic impacts.
The scope of the transport aspects which have been investigated are as follows:
• Review of the existing road network in the vicinity of the Project;
• Review of the existing traffic volumes provided by DTMR for the road segments identified as
part of the potential haulage and transport routes for the Project;
• Review crash statistics provided by DTMR for all road segments relevant to the Project;
• Estimation of developmental traffic demand;
• Estimation of future traffic demand for scenarios with and without the influence of the
Project;
• Identification of likely impacts to the community resulting from the additional traffic. This
includes:
o locations where traffic and pavement impacts are likely to be significant;
o impacts on vehicle safety; and
o impacts on sensitive receivers within the community.
• Identification of possible mitigation measures required to address impacts on the road
network and pavement due to the increased traffic demand of the Project where necessary.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
3
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
1.5 Consultation
TTM has undertaken consultation with the Whitsunday Regional Council (WRC) and DTMR to acquire
information about school bus routes, accident data and traffic volume and intersection data. This
report has been updated and reviews:
• Traffic, safety and rail issues raised by DTMR in their Information Request, April 2013
• Traffic, safety and rail issues raised by DTMR via Office of the Coordinator-General in an
Information Request, May 2015
• Request by Office of the Coordinator-General to ensure consistency with the 'Road
Transport Impact Assessment, Abbot Point Growth Gateway Project' prepared by Worley
Parsons Consulting in August 2015
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
4
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
2 Project Profile
2.1 Project Description
Adani Australia Company Pty Ltd (Adani) is developing Terminal 0 to facilitate export of coal from the
Galilee Basin. The Project location in the context of the regional transport network is shown in Figure
2.1.
It is intended that the proposed Project (Phase 1) will consist of the following elements:
• One (1) rail receiving bottom dump station located in a single common concrete vault
situated on the proposed rail loop corridor;
• An inloading conveyor stream feeding coal to the stockyard;
• Stockyard consisting of one (1) bund with two (2) stockpile rows and stacker/reclaimers;
• Conveyor outloading stream consisting of conveyors, surge bins and sample plant;
• Onshore infrastructure including stockyard drains, sediment ponds, roads, stormwater
retention dams, administrative building, workshop, sewerage treatment plant, car park and
amenities block;
• An expansion of the existing Material Offloading Facility (MOF) so it can receive Roll-on Roll-
off (RORO) vessels (e.g. barges) and vehicles;
• Piled approach jetty structure extending approx. 2.75 km north north-east from the shore
line adjacent to the existing T1 port facility carrying the out loading stream of conveyors and
access road; and
• Piled wharf structure at the end of the jetty which consists of a single berth and one ship
loader.
Note: The marine component of T0 is excluded from the SDA application; however this assessment
has included traffic related implications from the entire Phase 1 development (marine and
terrestrial).
2.2 Project Timeframes
The project dates are not specifically programmed to retain flexibility in the development
timeframe. However, it is anticipated that the Project would take 24 months to construct (Phase 1
only).
To provide a conservative assessment of the traffic impacts of the development, a 24 month
construction program commencing in 2017 and finishing in 2019 has been used. As such, operations
of the T0 terminal are anticipated to commence in 2019 with a 10 year design horizon in 2029.
It is expected that the project will have an expected life greater than 50 years.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
5
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Figure 2.1: Project Site Location and Regional Transport Network
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
6
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
2.3 Staffing Operation
2.3.1 Construction Workforce
The works on site for both the construction and typical port operations will be based around a 24
hours a day, seven days a week operation. From a review of existing site operations it is considered
that the main workforce will be split into two main 12 hour shifts. The ‘day’ shift is likely to utilise
approximately 70% of staff, with the ‘night’ shift consisting of the remaining 30% of staff.
The applicant has advised that the construction workforce will peak at 1,200 staff around the middle
of the construction period. As such the assessment of traffic impacts during the construction period
will use this staffing level in the 2018 base year.
Two thirds of staff (approximately 800 persons) will utilise existing and temporary accommodation
facilities in the Merinda Township approximately 9km east of Abbot Point Road along the Bruce
Highway. The remaining workforce (400 persons) will be sourced from, or accommodated in, the
Bowen Township. Any temporary accommodation facilities used during the construction stage will
be subject to separate applications by state and local road authorities.
The construction workforce will typically consist of a mix of fly in / fly out (FIFO) staff who are likely
to reside near regional centres and drive in / drive out (DIDO) staff who reside in northern and
central Queensland. The FIFO/DIDO rotation is typical when working a seven days on/ seven days off
roster. However, this can vary based on individual worker requirements at the construction site. Bus
in / bus out (BIBO) may be considered in lieu of DIDO should the number of workers from central
and northern Queensland permit. Local residents, including local subcontractors, would be expected
to drive their private vehicles to designated bus stops for bussing to site.
It is expected that transport between the worker accommodation village and the site will
predominantly be via buses, with limited private transport. The transfer of shift staff by buses is a
general requirement of Occupational Health and Safety standards due to the length of shifts.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
7
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
2.3.2 T1 – Existing Staffing Model
The 2012 staffing of T1 (50 Mtpa capacity), at an operational throughput of 20 Mtpa, consisted of
184 total staff as shown in the table below.
The maintenance crew is currently structured to operate during day time hours only. Maintenance
employees form 2 teams, with each team working a 12 hour shift each day (6am-6pm), with a 7 days
on / 7 days off rotating roster.
The operating team is required to keep the terminal operating on a continuous 24 hour production
mode, to receive trains and load vessels. The operating crew includes both production and a
skeleton maintenance crew, primarily to manage system failures between 6pm to 6am (when the
main maintenance crew is off shift). The crew is broken up into 4 teams with each team working a
12 hour shift, on a 7 days on / 7 days off rotating roster.
Leave and other absences are covered by: providing overtime to off shift employees, moving
employees between work crews, employing contractors for specified period of time or by sourcing
casuals from local townships.
2.3.3 T0 – Staffing Model
Operational staff levels for the completed Phase 1 and 2 operations (70Mtpa) will be used to provide
a conservative assessment of traffic impacts during operations. At full operating capacity (70Mtpa),
anticipated staff levels are shown below.
EMPLOYMENT T1 Existing Staffing* T0 Staffing Phase 1 and 2
Staff 50 73
Production 9 15
Maintenance 15 25
Strategic Development 6 7
Administration 4 4
Commercial 7 10
Logistics 9 11
Wages 82 107
Production (incl. casuals) 45 58
Maintenance - Mechanical 21 30
Maintenance - Electrical 16 19
Apprentices 17 26
Total Employees 149 207
Contractors 35 29
Total Manning 184 236
* sourced from proponent
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
8
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
The main consideration to determining the structural change between the Project and the current
T1 staffing structure is that the Project will be highly automated, both operationally and logistically.
As a result, fewer staff will be required at full operation.
A total of 236 employees are planned to operate the terminal at a peak output of 70 Mtpa. At this
modelled manning level, the Project will be one of the most highly productive coal terminal
operations in the world, with productivity at 297,000 tonnes per employee per year. This high
productivity figure is based on achieving a high degree of automation throughout the operating site,
in addition to transparent communication and planning systems with the miners, rail providers and
vessel owners.
At full capacity, maintenance and operational crewing is planned to be structured for a continuous
24 hour operation to receive trains, load vessels, and execute continuous minor and major
maintenance tasks (both planned and unplanned), to keep the terminal operating at full capacity.
As a consequence, both operating and maintenance site teams will be broken up in to 4 equally sized
teams. Each team will work a 12 hour shift, on a 7 days on / 7 days off continuous rotating roster. In
addition to the above crews, there will also be a weekday permanent maintenance crew that will be
tasked to perform project work or support the day time shifts. This team will be drawn on to cover
manning gaps in the roster for holiday leave, sick leave and other absences.
As noted, on completion of the construction works it is anticipated that there will be a total of 236
workers employed to manage typical port operations. It is anticipated that the majority of workers
will stay in nearby residential township areas, such as Bowen, Proserpine and Ayr.
2.4 Heavy Vehicle Movements
All construction materials transported by the road network will access the site via the Bruce
Highway. The Bruce Highway will continue to provide heavy vehicle access to supply the site with
equipment, services and resources in undertaking port operations. The proposed access and haulage
routes will be discussed in further detail in Chapter 3.
2.5 Description of Proposed Vehicles
The site will be vehicles up to a 19m long AV in size for construction materials, which include buses
which transport workers between the site and their accommodation. This restriction on vehicle size
is due to the distance between the North Coast rail line and the Bruce Highway along Abbot Point
Road.
The designation type of over dimensional vehicles are those which exceed the following dimensions
when loaded:
• Width of 2.5m;
• Height of 4.6m; and
• Length of: 12.5m for a rigid truck and 19m for an articulated vehicle.
Each supplier or transporter provider will be required to obtain special permissions prior to
accessing the subject site. Special permissions will be required for any over dimensional vehicle to
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
9
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
access the subject site. Permits from DTMR, Aurizon, QR, Queensland Police and NQBP may be
required. Traffic control at the Bruce Highway/Abbot Point Road intersection and co-ordination with
train movements may also be required.
2.6 Site Access
The Port of Abbot Point site is currently accessed via the private port access road (Abbot Point Road)
which has direct access to the Bruce Highway. It is proposed that the Abbot Point Road will be used
as the primary staff, contractor, and heavy vehicle access for travel from the Bruce Highway. As the
construction activity is contained within the Port of Abbot Point site, it is anticipated that no roads
or accesses will have to be closed for any traffic management requirements. The site access (Bruce
Highway / Abbot Point Road intersection) is a typical T-intersection with left (110m long including
taper) and right (105m long including taper) turn lane treatments from the Bruce Highway.
Rail lines operated by Aurizon cross Abbot Point Road and are located approximately 30m and 110m
from the Bruce Highway. It is noted that the rail crossing 30m from the Bruce Highway is owned by
Queensland Rail (QR) but the crossing section (within 300m of the rail crossing) is the responsibility
of Aurizon.
An aerial image of the intersection and rail crossings is shown in Figure 2.2.
Figure 2.2: Project Site Location and Regional Transport Network
2.7 Other Relevant Projects
Given the high demand on Port services to satisfy the current and proposed coal mines, there are
other port construction and expansion activities occurring at Abbot Point. These other proponents
and their Projects are outlined in Table 2.1.
QR owned Rail
Aurizon
owned Rail
crossing
Abbot Point Road
Bruce Highway
Section of rail line owned
by QR but the
responsibility of Aurizon
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
10
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 2.1: Existing and Proposed Projects Abbot Point
Project Name Proponent Description Approval Status
T0 and associated
rail loop
Adani Adani T0 development, 70
Mtpa in two (2) phases
Approved by
Commonwealth, pending
State Approvals.
T1 (existing
operation)
Adani Adani existing 50 Mtpa coal
export terminal and
associated rail
Operational
T2 and associated
rail
BHP Billiton Coal export terminal including
onshore and offshore
infrastructure
No longer proceeding
T3 and associated
rail
GVK-Hancock 60 Mtpa expansion Approved by
Commonwealth
T0 / T2 / T3
Dredging
NQBP Combined dredging proposals Approved by
Commonwealth. New
dredging proposal under
Abbot Point Growth
Gateway Project
CCMP and NGBR Adani Coal Mine and Rail Project Approved. Currently under
State and Federal
Government review
Abbot Point
Growth Gateway
Department
of State
Development
Dredging and onshore
material placement in
previous T2 site
Currently under
assessment. Will supersede
T0 / T2 / T3 Dredging
above
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
11
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
3 Regional Context
3.1 Project Location
The Project is located at the Port of Abbot Point on the central coast of Queensland.
3.2 Existing and Proposed Port Infrastructure
The Project relates to the development of new port facilities, with all construction works intended to
be undertaken within the site boundary.
3.3 Existing Road Network
The external local roads in the vicinity of the site are administered by the WRC, with the DTMR
Controlled Bruce Highway providing the main route and connection into the site. Abbot Point Road
is maintained by the Port Authority (NQBP). The hierarchy and description of surrounding access and
external roads is provided in Table 3.1.
Table 3.1: Local Road Hierarchy
Road Authority Posted
Speed
Limit
Classification Carriageway
width
Description
Abbot Point
Road
NQBP 100kph* Access Road 7.0 m Fully sealed carriageway,
two lanes.
Bruce Highway DTMR 100kph National
Strategic
9.0 m Fully sealed carriageway,
two lanes plus shoulders.
*60kph at the intersection with Western Access Road
3.3.1 Bruce Highway
The Bruce Highway forms part of the Australian National Highway Network (AUSLINK) and is a major
north-south route along the Brisbane-Cairns corridor. The Bruce Highway is constructed as a divided
multi-lane road between Brisbane and Gympie. North of Gympie the Bruce Highway is essentially a
two lane rural highway with four-lane sections near regional centres. The Bruce Highway links the
regional centres of Rockhampton, Mackay and Townsville via Proserpine and Bowen.
This report will focus on the Bruce Highway corridor between Townsville, Bowen and Proserpine. It
is anticipated that the majority of traffic generated by the development will access these key areas.
This segment of highway has one lane in each direction with sealed shoulders on both sides. The
section of the Bruce Highway fronting Abbot Point Road has a posted speed limit of 100 kph and
carries approximately 3,000vpd. Other sections of the Bruce Highway between Proserpine and
Townsville carry between 2,500 and 8,000vpd.
There are limited public transport, walking and cycling facilities along this segment of Bruce
Highway, with no educational or child facilities having direct access to the Highway.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
12
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
3.3.2 Abbot Point Road
The Abbot Point Road will provide the main access route into the site and runs in a north south
direction connecting the main port facilities with the Bruce Highway to the south. The road has one
lane in each direction with sealed shoulders on both sides.
Figure 3.1: Existing Road Network & Site Access
3.4 Major Structures
There is separated road and rail bridge along the access route that crosses Saltwater Creek along
Abbot Point Road, which has been designed to cater for general port traffic demands. There are also
various bridge and culvert structures along the Bruce Highway corridor between Townsville, Bowen
and Proserpine. As noted, the Bruce Highway is a strategic highway and it is anticipated that the
associated structures will be able to cater for the anticipated development traffic demands.
Bruce Highway
Abbot Point Terminal
Abbot Point Road
Source: Nearmap
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
13
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
3.5 Public Transport and School Bus Routes
There are no formal school bus stops along the internal site access route or in the vicinity of the site.
There are, however, existing school bus services that utilise sections of the Bruce Highway, which
provides access to key townships along the corridor, with the school buses generally operating
between 7:30 am and 8:30 am; and 2:30 pm and 3:30pm.
3.6 Future Road Improvement Projects
The Queensland Transport and Roads Investment Program (QTRIP) 2015-2016 to 2018-2019’
document for the Mackay/Whitsunday Region outlines proposed road improvement projects on the
state controlled road network (SCRN) within the vicinity of the site. This document has been studied
to identify any improvement projects scheduled for roads relevant to the Project.
Approved projects in the vicinity of the subject site include intersection improvements at the Bruce
Highway/Lower Don Road intersection and replacement of the bridge at Sandy Gully (indicative
program to 2019).
Other works along the Bruce Highway between Proserpine and Townsville include intersection
improvements, installing roundabouts, adding lanes and other miscellaneous improvement.
3.7 Rail Access
The Queensland North Coast rail line provides connectivity between the major urban centres along
the coast, with stops at Mackay, Proserpine, Bowen, Home Hill, Ayr, Giru and Townsville. The
nearest train station to the site is located in Bowen; however, due to the limited rail services it is
unlikely that any staff or contractors will travel by train.
The Port of Abbot Point is currently served by heavy rail with connections to various inland coal
mines to the south of the site. There are future plans for upgrading the heavy rail access which is
intended to enhance the existing rail port capacity. As part of the port expansion works, it is
intended that a new internal rail loop will be constructed including coal and ancillary facilities.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
14
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
4 Development Traffic Generation and Distribution
4.1 Basis for Traffic Impact Analysis
In establishing the overall traffic demands, it is necessary to review the traffic associated with the
existing Port of Abbot Point facilities and the likely level of construction traffic activity. A final review
will be undertaken to determine the traffic associated with the port operation once the construction
works have been completed.
The assessment of traffic generation during the proposed development construction stage is split
into two vehicular categories. Staff categorisation is calculated based on the movement of workers
to and from the site and the number of associated trips generated. The second category includes
construction traffic predominantly consisting of heavy goods and oversized vehicles.
Construction of the Project will occur over a period up to 2 years. The primary tasks involved will be
the construction of the additional port facilities and infrastructure. The following provides a review
of the proposed traffic generation for existing operations, construction stage (Phase 1) and
completed works/operational stage (Phase 1 and 2).
4.2 Existing Operations: Traffic Demands
TTM undertook an intersection movement survey between 5am and 7pm on Tuesday 5th March
2013. The survey data is provided in Section 6.
The survey data indicate that Abbot Point Road carried 312 vehicles during this 14hr period. Thirty or
10% of these vehicles were service vehicles. Approximately 95% of the vehicles travelled to and from
the south. The peak entering movements occurred between 6:15 and 7:15am with 38% of all
entering vehicles (58 vehicles or 0.32vph/staff) during this time. Peak exiting movements occurred
between 4:15 and 5:15pm with 25% of all exiting movements (37 vehicles or 0.2vph/staff) during
this time.
As noted, there are 184 existing staff working at the Port of Abbot Point. It is anticipated that the
survey captured 85% of turn volumes at this intersection. As such, it is anticipated that standard Port
operations generate approximately 370vpd. This equates to an average of 2vpd per staff member.
Of all vehicles accessing Abbot Point Road, 30 or 10% were service vehicles. All deliveries were
received between 6am and 2pm. It is anticipated that deliveries would not be received outside these
hours except in critical circumstances or during maintenance periods.
4.3 Construction Stage: Traffic Demands
The following provides a breakdown of the likely traffic generated at the construction period (Phase
1).
4.3.1 Construction Stage: Heavy Vehicle Traffic Generation
This inventory is based on an understanding of general construction requirements, which are based
on the individual material transportation requirements. Site construction materials will be sourced
from various locations, with the following providing a summary of likely sourced materials locations:
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
15
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
• Local – within 100km of the site, includes: Ayr, Bowen, Collinsville and Proserpine;
• Regional – generally within 400km, such as Charters Towers, Mackay and Townsville;
• State – All areas of Qld;
• National – provided from within Australia, but outside Qld; and
• International – provided from outside Australia, with delivery most likely via the existing
port.
This demand assessment has made several assumptions in respect to the overall scope of works, as
follows:
• Supply of all construction materials for the Project, including:
� A rail connection from the existing track and/or a new rail connection from the
South west;
� Rail loops and train unloading facilities;
� Coal stockpile bunds and associated infrastructure;
� Conveyors from the coal terminal tranches to port facilities;
� Berthing and ship loading facilities;
� Land for lay down areas and support industries; and
� Site and common user infrastructure including but not limited to roads, phone,
electricity, water supply and storage and sewage treatment.
• Transportation of workers via bus between township camps and site during construction;
• Supply of all materials and replacement equipment to operate the site; and
• Local accommodation camp likely to be located near Bowen.
It is intended that sea transport will be used for most of the overseas manufactured items and
materials with road transport being used for most of the locally sourced materials and items. These
large components and modules are expected to use the existing MOF facility which was established
in 1982 for the original port development works, by upgrading through maintenance and
refurbishment.
At this stage of the development/design process there is limited information in relation to the
percentage break-down between sea and road transport. This percentage break-down depends on
what this comparison is to be based upon, i.e., mass/size of materials/items or time/number of trips
to transport the required items/materials. In a review of the mass/size of construction materials it is
considered that larger materials/operating equipment will be transported by sea, with smaller
typical construction materials/plant arriving by road. It is anticipated that this mass/size break-up
would probably be approximately 75% by sea and 25% by road.
A major part of the construction activity will be raising the ground level of the site, with infill
material likely to be sourced from the existing Abbot Point quarries along the Abbot Point Road and
material sourced as part of the Abbot Point Growth Gateway project. It is anticipated that
approximately 400,000m3 of infill material is required for the Phase 1 construction works of the
Project, with this material trucked from the existing quarries or the neighbouring onshore dredge
placement area. A further 900,000m3 will be required for the Phase 2 construction works. If
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
16
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
circumstances change and material is to be sourced from outside Abbot Point a further traffic
assessment will be completed.
TTM understand that the existing quarry operator will use a B-double set-up to transport the fill
material from the quarry to the site. This truck and trailer set-up will allow cartage of 35 tonnes of
material per trip. For the transport of 400,000m3 of fill it is calculated that there will be a
requirement for 17,400 internal truck trips/movements. Fill will predominately be gravel and less
permeable material, and a bulking factor of between 1.2 and 1.3 has been used to determine the
necessary truck trips. As the source of this fill is along Abbot Point Road, these movements will not
have pavement or traffic impacts on the Bruce Highway.
In assuming a construction time of six months to complete the earthworks for the Project, the
frequency of trucks taking fill material to the Project site from the quarry would be approximately 13
trucks per hour. This equates to one truck travelling along Abbot Point Road approximately every 5
minutes to and from the quarry. This calculation is based on 9 hours of actual travelling time for a 12
hour working day and a six day working week.
Note, this does not incorporate the likely use of material sourced as part of the development of the
adjacent Abbot Point Growth Gateway Project, and is therefore a conservative estimate of
movements along Abbot Point Road.
There will be a requirement for further materials, plant and equipment to be transported via the
external road network for the Project works. At the commencement of the on-site construction
activities, all contractor’s plant, equipment, temporary offices and amenities will be transported to
site via the road network. All locally sourced building materials such as ready mixed concrete,
precast concrete products (e.g. reinforced concrete stormwater pipes, manholes, reinforced
concrete box culverts, etc), steel reinforcement, etc will be transported by road.
Locally sourced hire equipment and plant such as cranes, concrete pumping trucks, earthmoving
plant and equipment, etc will either be transported or self-driven via the existing road network.
There will be several new buildings required for the Project and all materials to be incorporated in
these new building will be sourced locally and will be transported via the existing road network.
The largest vehicle accessible to the site is an AV. It is understood that the transport of many goods
which cannot be further divided into smaller components will require transport on over dimensional
type vehicles. Suppliers and transport providers will be required to obtain special permissions to
access the site from the Bruce Highway with any vehicle larger than an AV.
Table 4.1 provides a summary of the likely construction vehicle requirements (for Phase 1) external
to the site, with approximately 1,821 trucks movements covering the two year construction of the
site.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
17
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 4.1: Phase 1 Construction Vehicle Requirements (External to Site)
Plant/Materials Quantity Transport Arrangements Delivery
Vehicles
Origin
General Construction Equipment Requirements Mobile Cranes 2 2 (AV) Regional
Fork lifts 4 1 (AV) Local
Grader 3 3 (AV) Regional
Dozer 10 Stored on-site for construction
activities 10 (AV)
Regional
Excavators 10 Stored on-site for construction
activities 10 (AV)
Regional
Dump trucks 10
Standard size articulated tippers,
self-drive to site
Stored on-site for construction
activities
10 (AV)
Regional
Buildings/Storage Tanks Requirements
Workshops Constructed from base materials
(steel/concrete)
2 (AV) Regional
Stores 4 (AV) Regional
Workforce admin/muster Demountable offices (25m
2)
Footings
20 (AV)
5 (AV) State
Wash Facilities 3 (AV) Regional
Fuel/oil 2 tanks 2 (AV) Regional
Waste station 2 tanks 2 (AV) Regional
Hazardous materials 2 tanks 2 (AV) Local
Water tanks / treatment 3 tanks 3 (AV) Local
New Rail Loop Requirements
Rails Delivered by road 150 (AV) State
Sleepers Delivered by road 50 (AV) State
Base material 35 tonnes per truck and trailer 50 (AV) Local
Construction Materials Requirements
Internal access roads material,
Rock armour, quarry materials 25 tonnes per truck and trailer 500 (AV) Local
Concrete
For
footings,
retaining
walls
standard concrete truck 100(AV) Local
Road Pavement/Rock armour
Coal Handling Machinery Requirements
Buildings/structures
50 (AV) Regional
Coal handling facility structure Delivered by sea - International
Regular Service Vehicles Requirements
Potable water 2 per week
(208 LRV) Local
Fuel 1 per week
(104 LRV) Regional
General supplies (office, catering
and miscellaneous equipment)
3 per week
(312 SRV) Regional
Waste collection 2 per week
(208 MRV) Local
Internal Infrastructure
Sewerage pipes 2 (AV) Regional
Electricity wire/poles 2 (AV) Regional
Telecom line 2 (AV) Regional
Water pipes 2 (AV) Regional
Total 1,821
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
18
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
It is estimated that on average there will be 3 truck deliveries, or 6 total truck movements, per day,
based on 3 loaded and 3 unloaded trip movements, covering typical Phase 1 construction activities.
This level of activity may increase during specific construction operations which may peak at 6 truck
deliveries, or 12 total truck movements, per day based on 6 loaded and 6 unloaded trip movements.
It is assumed that all construction equipment/plant delivered to the site will be dedicated to
construction activities and will be located on-site for the duration of construction activities and not
transported to and from as required.
4.3.2 Construction Stage: Workforce Traffic Generation
The main factor influencing workforce traffic generation will be the general self-contained nature of
the site. The provision of internal equipment and facilities will allow the majority of employees to
stay within the vicinity of the site at most times during their shifts.
Considering the spatial nature of the development it is considered that employees will be sourced
primarily from South-East Queensland (SEQ) and would be accommodated in Merinda. Secondly,
staff would be sourced from the Bowen Township. It is therefore considered that the majority of
traffic generated by the development will generally travel to and from these areas. The sources of
staff traffic are expected to result in travel patterns similar to existing movements at the Bruce
Highway/Abbot Point Road intersection once sub-contractors are included.
At this initial development stage, the specific location of the accommodation village is yet to be
determined, however, it is likely to be located in the vicinity of the Merinda Township to the
south/east of the site. A separate application will be prepared for the accommodation village.
It is considered that the majority of worker movements from the accommodation village will be via
bus (40 person capacity) movements to the site, with further buses collecting workers at various
nearby airports. However, not all workers will travel by bus, with approximately 20% likely to reside
in nearby townships and use their private vehicles to access the site. There will also be a
requirement for sub-contractor workers and they are likely to use a private vehicle or hire car as
their primary method of transportation. Notwithstanding, local labour will be encouraged to also use
the project bus service to further reduce traffic generation and congestion on site.
The traffic generation also takes into account the expected roster and shift systems which would
result in staff movements shown in Table 4.2. Communal transport relates to buses which would
take up to 40 staff per bus. Private transport relates to cars/utility vehicles and it is anticipated
vehicle occupancy would be 1.5 persons per vehicle.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
19
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 4.2: Construction Staff Requirements (Phase 1)
Staff Percentage Number Communal Transport Private Transport
Total 100% 1,200 - -
Rostered on 70% 840 80% = 672 staff in 17
buses
20% = 168 staff in 112
cars
Day Shift 70% of rostered staff 588 80% = 470 staff in 12
buses
20% = 118 staff in 79 cars
Night Shift 30% of rostered staff 252 80% = 202 staff in 5 buses 20% = 50 staff in 33 cars
Buses identified for night shift would be the same buses used for day shift. As such a peak of 34 bus
movements per day is expected. Private vehicles however, would remain on-site for the duration of
the workers shift. As such it is expected that the site would generate up to 224 private vehicle
movements per day.
A summary of development traffic movements is shown in Table 4.3.
Table 4.3: Construction Traffic Movements (Phase 1)
Vehicle Type Daily AM peak PM peak
In Out In Out In Out
Service Vehicles 6 (loaded) 6 (unloaded) 2 (loaded) 2 (unloaded) 2 (loaded) 2 (unloaded)
Buses 17 (loaded) 17 (loaded) 12 (loaded) 5 (loaded) 5 (loaded) 12 (loaded)
Private Vehicles 112 112 79 33 33 79
Total 135vpd 135vpd 93vph 40vph 40vph 93vph
Traffic
Generation 270vpd 133vph 133vph
This is considered a worst case scenario as it assumes that shift workers, administrative staff and
sub-contractors all arrive and depart the site during the same peak hour, which is unlikely to occur.
4.3.3 Construction Stage: Traffic Distribution
The total daily traffic volume generated by the construction activity is expected to equate to 270
vehicle movements per day based on average construction operations. The primary source of staff
will be an accommodation village in Merinda, and the remaining staff from Bowen which are both
southeast along the Bruce Highway from Abbot Point Road. Only a small number of sub-contractors
and service vehicles are anticipated to come from the northwest of the site (Ayr). As such traffic
from the Project is expected to replicate surveyed traffic directions at the Bruce Highway/Abbot
Point Road intersection with 5% to the northwest and 95% to the southeast.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
20
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
TTM note that the construction and operation of an accommodation camp will be dealt separately
from this traffic assessment.
Further, indirect traffic will be generated by FIFO and DIDO activities. Once shifts are complete, the
workers will fly back to regional centres for leave periods. Staff and contractors based in SEQ and
other states are expected to fly to and from Townsville, Proserpine and Mackay airports. Staff from
central and northern Queensland are expected to drive to and from their residence. During a major
roster change it is expected that up to 30% of total staff numbers would leave their accommodation
with the same number entering their accommodation.
Up to 20% of service vehicles are expected to continue through Proserpine and travel further south
towards Brisbane. These movements are primarily expected to consist of long distance heavy vehicle
movements, servicing the site from major regional centres along the coast.
Approximately 30% of service vehicle trips will be from the north/west (Townsville, Ayr) with the
remaining 70% from Mackay and further southern Queensland destinations. These will consist of
material deliveries from local quarries and suppliers for materials.
Based on the above assessment of construction (non site staff) vehicle trips it is estimated that there
will be an average of 5 to 6 Heavy Goods Vehicles (HGV) trips per day to and from the site during the
construction stage. It is therefore estimated that there will be approximately 270 total daily vehicle
trips generated during the construction stage, with the majority of site workers using bus transport.
A summary of construction vehicle movements and distributions is shown in Table 4.3.
Table 4.3: Construction Traffic Distribution (Phase 1)
Vehicle
Type
AM peak (5:30-6:30am) Off peak (7:00am-5:00pm) PM peak (5:30-6:30pm)
North/west South/east North/west South/east North/west South/east
Service
vehicles
1 (loaded in)
1 (unloaded
out)
1 (loaded in)
1 (unloaded
out)
-
-
2 (loaded in)
2 (unloaded
out)
1 (loaded in)
1 (unloaded
out)
1 (loaded in)
1 (unloaded
out)
Buses -
-
12 (in)
5 (out)
-
-
-
-
-
-
5 (in)
12 (out)
Private
vehicle
4 (in)
2 (out)
75 (in)
31 (out)
-
-
-
-
2 (in)
4 (out)
31 (in)
75 (out)
Combined
movements
5 (in)
3 (out)
88 (in)
37 (out)
-
-
2 (in)
2 (out)
3 (in)
5 (out)
37 (in)
88 (out)
Traffic
Generation 133vph 4 vehicles 133vph
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
21
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
4.4 Operational Stage (Phase 1 and 2): Traffic Generation
The Project will be operational for greater than 50 years. The primary tasks involved will be
stockpiling coal from rail deliveries and processing coal for shipping export. The primary
requirements for service vehicles will be the supply of operating goods and maintenance of the rail
and port equipment plant.
4.4.1 Operational Traffic
For the duration of the operational life span of the port facility it is anticipated that the majority of
staff will stay in nearby residential areas, such as, Bowen, Proserpine and Ayr. All staff and service
vehicle movements will access the site via the Bruce Highway.
After future completion, a total of 236 employees are planned to operate the terminal at 70 Mtpa
output. It is intended that the port facility will be highly automated, both operationally and
logistically, with fewer staff required during operations.
The staff will continue to work on a 4 team basis over a 12 hour shift, on a 7 days on / 7 days off
rotating roster. On this basis it is anticipated that 59 staff cover each shift and arrive and depart
during the shift changes being 5:30am to 6:30am in the morning and 5:30pm to 6:30pm in the
evening.
It is therefore estimated that there are approximately 40 vehicles entering and exiting the site during
the shift changes, which is based on vehicle occupancy of 1.5 workers.
The port operation will continue to require constant servicing and will be supplied with daily
materials including: food and replacement maintenance equipment. As the existing port facility
generates 30 trucks per day with a near capacity of 50 Mtpa, it is anticipated that T0, with an output
of 70 Mtpa for Phase 1 and 2 operational works, the site would generate an average of 42 trucks per
day. The service vehicles will range in size from SRV to AV, with the smaller type service vehicles
providing the majority of daily service requirements.
Additional trips are expected which includes port operators, additional maintenance personal, rail
and port authorities and visitors among other purposes. An additional 50% loading of peak hour and
daily trips have been added to account for these miscellaneous trips.
Table 4.4 identifies all the likely traffic generation and heavy vehicle requirements during both Phase
1 (40Mtpa) and Phase 2 (70Mtpa) stages.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
22
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 4.4: Operational Site Traffic Generation (Phase 1 and 2)
Shift Phase 1 and 2 (70Mtpa)
Day Night
Total Workforce 236
Total Rostered Staff 118
Shift Staff 59 59
Staff Access:
• Bus
• Private
-
40
-
40
Peak Hour Staff Movements 80 vehicles per hour (vph)
Total peak hour traffic generation, service vehicles 12 (in/out)
Miscellaneous peak hour trips 40vph
Total peak hour traffic generation, including heavy vehicles 132vph (In/Out)
Daily Staff Movements 160 vehicles per day (vpd)
Daily service vehicle movements 42vpd (in /out)
Miscellaneous daily trips 100vpd
Total traffic generation – vehicles per day (vpd) 302vpd (In/Out)
4.4.2 Operational Stage: Traffic Distribution
As shown in Table 4.4, the daily traffic volume generated by the site is expected to equate to a total
of 302 daily vehicle movements for the combined operational stage of Phase 1 and 2. The number of
trips is in alignment to the surveyed traffic generation of existing T1 terminal.
These traffic volumes are expected to replicate existing traffic distributions at the Bruce
Highway/Abbot Point Road intersection as follows:
• 95% to the east/south along the Bruce Highway; and
• 5% to the north/west along the Bruce Highway.
Of the port generated heavy vehicle traffic, 30% is anticipated to be generated from the Townsville
area, with the remaining 70% from Mackay and further southern Queensland destinations. Table 4.5
shows the expected breakdown of traffic accessing the site in peak periods.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
23
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 4.5: Operational Traffic Distribution (Phase 1 and 2)
Vehicle Type AM peak (5:30-6:30am) Off peak (7:00am-5:00pm) PM peak (5:30-6:30pm)
North/west South/east North/west South/east North/west South/east
Service Vehicles
2 (loaded in)
2 (unloaded
out)
4 (loaded in)
4 (unloaded
out)
3 (loaded in)
3 (unloaded
out)
6 (loaded in)
6 (unloaded
out)
2 (loaded in)
2 (unloaded
out)
4 (loaded in)
4 (unloaded
out)
Staff 2 (in)
2 (out)
38 (in)
38 (out)
-
-
-
-
2 (in)
2 (out)
38 (in)
38 (out)
Miscellaneous 1 (in)
1 (out)
19 (in)
19 (out)
1 (in)
1 (out)
9 (in)
9 (out)
1 (in)
1 (out)
19 (in)
19 (out)
Combined
movements
5 (in)
5 (out)
61 (in)
61 (out)
4 (in)
4 (out)
15 (in)
15 (out)
5 (in)
5 (out)
61 (in)
61 (out)
Traffic
Generation 132vph 38 vehicles 132vph
4.5 Impacts of Decommissioning
It is assumed that the site will have an operational life span over 50 years, with no plans for any
decommissioning process.
However, if decommissioned, the Port will require several operations which will have an impact on
the local and state controlled network. This will include
• Removal of hazardous material;
• Decommissioning of buildings and structures;
• Removal of waste material;
• Environmental actions; and
• Removal of plant and machinery from site.
4.6 Cumulative Traffic
TTM have been requested to include traffic movements from other projects, specifically the CCMP,
NGBR and the APGGP.
TTM have reviewed the 'Road Impact Assessment - Whitsunday Regional Council Road Network:
Carmichael Coal Mine and Rail Project' (Calibre Consulting, 2015). TTM have estimated peak hour
volumes of the CCMP and NGBR based on daily volumes during the 2016 construction stage and
2026 operation stage. These daily volumes are provided as an Appendix in the Calibre Consulting
report.
The cumulative traffic impact assessment assumes the peak construction stage of the CCMP and
NGBR projects coincide with the construction of T0. This enables a conservative analysis as these
years are programmed as 2016 and 2018 respectively, and thus are unlikely to coincide in reality.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
24
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
To gain relevant peak hour traffic data for analysis of the CCMP and NGBR projects the following
estimations have been used:
• 40% of daily light vehicle volumes occur in the peak;
• 20% of daily heavy vehicle volumes occur in the peak;
• Peak hour traffic distributions are based on daily distributions
These estimated traffic volumes are shown in Figure 4.1 and Figure 4.2.
Figure 4.1: Estimated CCMP and NGBR 2016 Construction Peak Hour Volumes
Figure 4.2: Estimated CCMP and NGBR 2026 Operation Peak Hour Volumes
TTM have been advised that construction of T0 will not overlap with the APGGP and as such
consideration of cumulative traffic impacts of the APGGP do not need to be assessed.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
25
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
4.7 Future Background Traffic
Regional roads, including the Bruce Highway have seen a marked decrease in traffic since 2013, with
traffic volumes decreasing on average 20-30% p.a. to 2015. The AADT on the Bruce Highway south of
Abbot Point Road in 2011 was 3,585. The comparative 2014 AADT was 3,097. This results in a traffic
reduction of approximately 5% p.a. over this 3 year period. Conversely traffic volumes on the Bruce
Highway north of Abbot Point Road appear to have increased by 2.3% p.a. during this period.
TTM has applied a conservative 3% p.a. traffic growth for traffic volumes on the Bruce Highway.
Allocating a nominal date of 2018, peak construction in 2018, nominal commencement of operations
in 2019 and a 2029 design horizon, the cumulative traffic growth rates are provided in Table 4.6.
Table 4.6: Design Background Traffic Growth on Bruce Highway
Data set Base Data (year) 2018 (construction
peak)*
2019 (operations
commence)*
2029 (design
horizon)
Peak hour 2013 16% 19% 60%
Daily 2014 13% 16% 56%
*Note – Construction and operation dates are nominal and may change
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
26
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
5 Traffic Operation Assessment
5.1 Introduction
This chapter reviews the traffic operation and capacity performance of the Bruce Highway corridor
adjacent to the site including the Bruce Highway/ Abbot Point Road intersection.
5.2 Average Annual Daily Traffic (AADT)
Table 5.1 identifies the typical (2014) traffic volumes, sourced from DTMR, for the Bruce Highway at
the site frontage.
Table 5.1: Existing AADT Volumes on State-Controlled Roads
Road Section 2014 AADT HV Percentage
North of Abbot Point Road (10K WiM Site Guthalungra) 3,041 17%
South of Abbot Point Road (10K Little Goodbye Creek) 3,097 18%
5.3 Road Corridor Capacity Criteria
The AUSTROADS Guide to Traffic Engineering Practice - Part 2: Roadway Capacity indicates that two-
lane rural highways have a capacity of 2,800 passenger cars per hour total for both directions of
flow, under ideal conditions where there are no restrictive roadway, terrain or traffic conditions.
AUSTROADS defines level of service as a qualitative measure describing operational conditions
within a traffic stream. The term Level of Service (LOS) and its characteristics for rural roads is
defined in Table 5.2.
Table 5.2: Two Lane Rural Road Capacity – Rolling Terrain Two-Way Flow
LOS Description Rating
A Free, unrestrictive flow Very Good
B Mostly free flow, few disruptions Very Good
C Stable flow Good
D Mostly stable flow, some delays Acceptable
E Congested flow, delays common Bad
F Forced flow Bad Source: AUSTROADS Guide to Traffic Engineering Practice, Part 2
The volume and composition of traffic on a given road determines the level of interaction between
vehicles and is measured as its LOS. LOS decreases with increasing traffic volumes. LOS ‘A’, LOS B’,
LOS ‘C’ in a rural context are satisfactory, with a LOS ‘D’ satisfactory in some circumstances.
In cases where traffic, terrain or geometric data may not be precisely known, the AUSTROADS Guide
provides planning guidance on maximum AADT values that two-lane, two-way rural roads can
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
27
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
accommodate under various terrain conditions. Table 5.3 shows the values for various LOS for a
rural road in rolling terrain with varying ratios of design hour volume to AADT.
Table 5.3: Maximum AADT’s for Various LOS on Two-Lane Two-Way Rural Roads
Level of Service
Design Hour Volume to AADT
Ratio
A B C D E
0.10 1,100 2,800 5,200 8,000 14,800
0.11 1,000 2,500 4,700 7,200 13,500
0.12 900 2,300 4,400 6,600 12,300
0.13 900 2,100 4,000 6,100 11,400
0.14 800 1,480 3,700 5,700 10,600
0.15 700 1,800 3,500 5,300 9,900 (Source: AUSTROADS Guide to Traffic Engineering Practice, Part 2: Roadway Capacity, Table 3.9)
5.4 Bruce Highway Operational Performance
For a LOS ‘C’, the maximum AADT values range from 3,500 to 8,000 depending on the design hour
volume to AADT ratio. The peak hour volumes along the Bruce Highway corridor were observed to
be less than 10% (or 0.10) of the average daily traffic based on the traffic peak periods. As such the
design ratio of 0.10 will be used.
From Table 5.3 above, a maximum AADT of 5,200 to 8,000 is assumed for a LOS ‘C’. Comparing these
values with the average AADT levels along the Bruce Highway indicates that the existing road
corridor generally operates at LOS ‘C’, as shown in Table 5.4. As noted, the future year corridor
operation is based on a 3% background traffic growth and from the criteria noted in Table 5.4 will
generally operate at a LOS ‘D’ in 2029 (10 year post construction completion).
Table 5.4: Level of Service: Bruce Highway (Base Case)
Bruce Highway
Route
AADT LOS
2014 2018 2019 2029 2014 2018 2019 2029
North of Abbot Point
Road 3,041 3,423 3,525 4,738 C C C C
South of Abbot Point
Road To Merinda 3,097 3,486 3,590 4,825 C C C C
Merinda to Bowen 6,442 7,251 7,468 10,036 D D D E
Table 5.5 identifies the impact of development traffic on the Bruce Highway north and south of the
subject site. Where the impact is greater than 5%, the impact is quantified.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
28
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 5.5: Construction (Phase 1) and Operation (Phase 1 and 2) Impact on Bruce Highway
Section Year Base AADT Development
(vpd)
Base and
Development (vpd)
Percentage
Impact (%)
North of Abbot
Point Road
2018 3,423 20 3,443 <1
2019 3,525 28 3,553 <1
2029 4,738 28 4,766 <1
Abbot Point Road
to Merinda
2018 3,486 254 3,740 7.2 (LOS: C)
2019 3,590 274 3,760 7.6 (LOS: C)
2029 4,825 274 5,099 5.7 (LOS: C)
Merinda to
Bowen
2018 7,251 220 7,471 3.0
2019 7,468 274 7,742 3.7
2029 10,036 274 10,310 2.7
As shown in Table 5.5, the construction and operation of T0 is expected to have an assessable
impact on the Bruce Highway between Abbot Point Road and Merinda. The highest traffic volumes
on this road section are expected to occur in 2029 where the project impact of 5.7% is anticipated to
increase daily volumes to 5,099 during the operation (Phase 1 and 2). This section of the Bruce
Highway is expected to retain a Level of Service C.
The addition of traffic related to the CCMP and NGBR (180vpd) may increase the AADT on this
section of the Bruce Highway (Abbot Point Road to Merinda) to 5,279 in 2029. This section of the
Bruce Highway is still expected to retain a Level of Service C.
5.5 Proposed Haulage Route
The Bruce Highway is intended to be the main haulage route to the site and is considered to carry
the majority of the construction vehicles. Bowen Developmental Road to the south of Abbot Point
Road may carry construction vehicle traffic, however, the level of potential generated traffic is
considered negligible, with the majority of traffic using the Bruce Highway from both the north and
southern directions.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
29
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
6 Site Access Review
6.1 Introduction
This chapter reviews the adequacy of the Bruce Highway / Abbot Point Road intersection to
adequately cater for the predicted development traffic demands.
6.2 Existing Intersection Layout
The intersection layout is a typical priority 3-arm intersection with left and right turn treatments.
The intersection has good inter-visibility in all directions, with the following key traffic and geometric
attributes:
• A posted speed limit of 100km/hr;
• A 9 metre wide carriageway;
• An approximate 30 metre entry width for AV turning vehicles;
• Left turn lane provision being approximately 110m length. This design is considered
consistent with a short auxiliary left, AUL(S) turn treatment; and
• Right turn lane provision being approximately 105m in length treatments and shoulder
provisions. This design is generally consistent with a short channelised right, CHR(S) turn
treatment.
6.3 Accident Review
TTM have reviewed accident data on the Queensland Globe database. Within 500m of the Bruce
Highway/Abbot Point intersection, there were found to be four recorded accidents since 2001 with
details provided in Table 6.1.
Table 6.1: Accident Details within 500m of Bruce Highway/Abbot Point Road Intersection
Year Severity Crash Type Day/Night Wet/Dry
2001 Property Damage Single Vehicle Day Dry
2005 Property Damage Single Vehicle Day Dry
2007 Medical Treatment Single Vehicle Night Dry
2012 Hospitalisation Single Vehicle Night Dry
As shown in Table 6.1, all accidents occurred during dry conditions and involved single vehicles. On
average an accident occurred every 3 years. Given the severity, frequency and single vehicle nature
of the accidents, no further accident review is considered necessary.
6.4 Sight Distance Review
TTM have reviewed the intersection sight distance requirements with reference made to the
Austroads Guide to Road Design Part 4A: Unsignalised and Signalised Intersections requirements.
Intersection sight distance is considered adequate in all directions.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
30
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
6.5 Traffic Scenarios
TTM have considered the following scenarios for assessment:
• 2013 Base Case;
• 2018 Base and Construction Case (Phase 1);
• 2019 Base and Operations Case (Phase 1 and 2); and
• 2029 Base and Operations Case (Phase 1 and 2).
To provide a robust traffic assessment, through volumes and turn volumes will be used, even where
construction and operations traffic is not expected to coincide with these volumes. Development
traffic movements during the construction and operation stages are provided in Table 4.3 and Table
4.5. Base and estimated development volumes are shown in the following Figures 6.1 to 6.7.
Figure 6.1: Bruce Hwy/Abbot Point Road: 2013 Base Traffic - Surveyed
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
31
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Figure 6.2: Bruce Hwy/Abbot Point Road: 2018 Base Traffic (3% p.a. growth)
Figure 6.3: Bruce Hwy/Abbot Point Road: 2019 Base Traffic (3% p.a. growth)
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
32
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Figure 6.4: Bruce Hwy/Abbot Point Road: 2029 Base Traffic (3% p.a. growth)
Figure 6.5: Bruce Hwy/Abbot Point Road: 2018 Base and Construction Traffic (Phase 1)
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
33
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Figure 6.6: Bruce Hwy/Abbot Point Road: 2019 Base and Operations Traffic (Phase 1 & 2)
Figure 6.7: Bruce Hwy/Abbot Point Road: 2029 Base and Operations Traffic (Phase 1 & 2)
6.6 Intersection Turn Warrant Review
TTM has reviewed the turn warrant requirements as part of the overall intersection review with
reference made to the 'Guide to Road Design Part 4A: Unsignalised and Signalised intersections'
Figure 4.9A (AUSTROADS, 2009)
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
34
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
This assessment review considers the highest volumes in the Phase 1 Construction (2018) and the
Phase 1 and 2 Operations (2029) scenarios in Figure 6.8 and Figure 6.9 respectively.
Figure 6.8: Turn Warrant Requirement: 2018 Construction Phase (Phase 1)
Figure 6.9: Turn Warrant Requirement: 2029 Operation Phase (Phase 1 and 2)
Right Turn (AM)
Left Turn (AM)
Right Turn (AM)
Left Turn (AM)
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
35
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
6.7 Right and Left Turn Requirements
The AUSTROADS figures indicates that CHR and BAL treatments are required to cater for peak traffic
movements associated with the construction and operation stages. The existing AUL(S) treatment is
considered suitable based on this assessment. The right turn lane however should be upgraded to a
full length CHR to cater for development and background traffic.
A CHR treatment at this intersection should be designed in accordance with Figure 7.7 of the
AUSTROADS Guide to Road Design Part 4A: Unsignalised and Signalised Intersections. as shown in
Figure 6.10.
Figure 6.10: Rural CHR Turn Treatment from AUSTROADS GRD Part 4A
The diverge deceleration length (D) should be a minimum 185m long including a 35m long taper (T).
Storage length (S) is considered in the following section.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
36
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Should an AUL treatment be required, it should be designed in accordance with Figure 8.4 of the
AUSTROADS Guide to Road Design Part 4A: Unsignalised and Signalised Intersections. as shown in
Figure 6.11.
Figure 6.11: Rural AUL Turn Treatment from AUSTROADS GRD Part 4A
The diverge deceleration length (D) should be a minimum 185m long including a 35m long taper (T).
Whilst storage is typically not required for an AUL turn treatment, this will be discussed in the
following section.
6.8 Intersection Capacity - Isolated
In a review of the GARID Guidelines Criteria 3: Traffic Operation Assessment, traffic operation
impacts need to be considered for any section of a State Controlled Road (SCR) where the
construction or operational traffic generated by the development equals or exceeds 5% of the
existing AADT on the road section, intersection movements or turning movements.
As noted in Section 5.4, the development is expected to have an assessable impact on the Bruce
Highway between Abbot Point Road and Merinda in all cases assessed. However, this impact is
expected to be limited and is unlikely to worsen the performance of this road section with an
expected Level of Service C with and without construction or operations traffic.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
37
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 6.1 in the Guide to Traffic Management Part 3: Traffic Studies and Analysis is replicated in
Figure 6.12 and identifies uninterrupted flow conditions for which no further capacity assessment
would be required.
Figure 6.12: AUSTROADS GTM Chapter 3: Table 6.1
The highest traffic volumes at the Bruce Highway/Abbot Point Road intersection in the base,
construction and operation scenarios considered (Section 6.5) are predicted have less than 300vph
through movements along the Bruce Highway and less than 250vph turn movements in the AM and
PM peak hours. This level of traffic in accordance with the AUSTROADS Guide to Traffic Management
Chapter 13 is therefore unlikely to impact significantly on the intersection performance, with the
intersections operating under uninterrupted flow conditions with nominal delays and queuing. As
such Figure 6.12 defines that further capacity analysis of this intersection is unnecessary due to low
through and turn volumes.
TTM note that the majority of site worker activity will occur prior to the highway morning peak
period (before 8:00am) and after the highway evening peak period (after 5:00pm), with any
construction vehicle activity operating throughout the working day.
6.9 Intersection Capacity - Rail Impacts
The Bruce Highway/Abbot Point Road intersection is close to the North Coast rail line (approximately
20m) and Collinsville Newlands rail line (approximately 100m) crossings of Abbot Point Road. The
proximity of these rail crossings could lead to queuing at the Bruce Highway/Abbot Point Road
intersection. TTM have therefore undertaken a capacity assessment of the Bruce Highway/Abbot
Point intersection with the influence of the rail crossings.
This assessment has been undertaken as a network in Sidra Intersection analysis software Version
6.1.
A signalised T intersection was modelled with two phases, one allowing all movements with the
second phase allowing through movements only. This was modelled to account for the impact on
the intersection of a train using the North Coast rail line. Train movements and crossing times are
based on the ‘Road Transport Impact Assessment: APGGP’ (Worley Parsons Consulting, August
2015). This report indicates an average of 11 trains per day on this line with a crossing time of 1.9
minutes (114 seconds).
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
38
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
It is anticipated that a peak hour scenario could include two trains along this line. Therefore, the all
movements phase was 1,686 seconds, with the through movement only phase for 114 seconds.
The Collinsville-Newlands rail line was modelled as a pedestrian crossing. The Worley Parsons
Consulting report indicates that 32 trains (16 empty, 16 loaded) use this rail line per day. It is
anticipated that the trains are evenly distributed over a 24 hour day and as such, in the base and
construction scenarios include two trains in the peak times. This report identifies a crossing time of
5.1 minutes (306 seconds). Therefore, the through movement phase over this rail line will be 1,494
seconds and the train (pedestrian) phase will be 306 seconds.
Current and anticipated train numbers and delays are summarised in Table 6.2.
Table 6.2: Anticipated Abbot Point Road Train Volumes and Crossing Times
Rail Line Scenario Trains
per
Hour
Delay
per
Train
(sec)
Abbot Point Road
Green Phase (sec) Red Phase (sec)
North Coast All 2 114 1,686 114
Collinsville-Newlands All 2 306 1,494 306
The Sidra network layout is shown in Figure 6.13. The intersections are set 60m apart which is
consistent with the Abbot Point Road length between the clearances of the two rail crossings. Traffic
volumes, including heavy vehicles, are provided in Section 5.4. The two rail crossings are not
considered to be coordinated.
Figure 6.13: Sidra Network Layout
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
39
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Relevant queue lengths from the Sidra network are identified in Table 6.3. It is noted that the
queuing at the Bruce Highway intersection identified in this table is the combined 95th percentile
queue from left (from north) and right (from south) turning vehicles at this intersection. To provide a
conservative estimation of queue lengths, the number of vehicles queuing has been rounded up, and
one vehicle is considered to have 10m queue length given distance between vehicles and to account
for service vehicles.
Table 6.3: Sidra Queue Outputs: Bruce Hwy/Abbot Point Road/Rail crossing Intersections
Scenario Eastbound 95th %ile Queue (veh) Westbound 95th %ile Queue (veh)
Bruce
Hwy Int.
C-N line Total C-N line Bruce
Hwy Int.
Total
2013 AM Base 3.7 9.3 13.0 1.7 0.7 2.4
2018 AM Base 3.9 9.3 13.2 1.7 0.7 2.4
2018 AM Cons. 12.8 12.5 25.3 9.1 4.6 13.7
2019 AM Base 3.9 9.3 13.2 1.7 0.7 2.4
2019 AM Op. 15.8 13.4 29.2 26.9 13.4 40.3
2029 AM Base 4.0 9.3 13.3 1.7 0.7 2.4
2029 AM Op. 16.0 13.4 29.4 27.1 13.4 40.5
2013 PM Base 0.9 1.7 2.6 6.1 2.4 8.5
2018 PM Base 0.9 1.7 2.6 6.1 2.4 8.5
2018 PM Cons. 3.5 9.0 12.5 23.6 9.4 33.0
2019 PM Base 0.9 1.7 1.6 6.1 2.5 8.6
2019 PM Op. 10.7 13.5 24.2 33.8 13.6 47.4
2029 PM Base 1.1 1.7 2.8 6.1 2.4 8.5
2029 PM Op. 10.8 13.5 24.3 33.8 13.6 47.4
Longest Queue
(vehicles rounded)
16 14 30 34 14 48
Longest Queue (m) 160m 140m 300m 340m 140m 480m
As shown in Table 6.3, the longest queues are expected to be found during T0 operations. The clear
zone between the rail lines is approximately 60m and there is approximately 20m of queuing
available between the North Coast rail line and the Bruce Highway along Abbot Point Road. As such
there is approximately 80m of queuing along Abbot Point Road between the Collinsville Newlands
rail line and the Bruce Highway.
The anticipated queues are shown in Figure 6.14.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
40
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Figure 6.14: Anticipated Queuing on Bruce Highway and Abbot Point Road
In peak scenarios this available queue area is expected to be exceeded in the T0 construction and
operation stages. Due to this, improvements should be made to the intersection/rail crossings as
identified in Table 6.4.
Table 6.4: Recommendations Due to Queue Exceedance
Location Direction Queue (m) Recommendation
Available Expected
Between C-N and NC
rail line
Eastbound 60 140 Provide layby lanes on egress and
additional storage on Bruce Highway
turn lanes
Bruce Highway Turn
Lanes
Eastbound - 240
(300-60)
Increase storage provision on Bruce
Highway turn lanes
Between C-N and NC
rail line
Westbound 60 140 Provide layby lanes on egress
East of C-N rail line Westbound - 420 None
In the westbound and eastbound directions over the two rail crossings, there is potential for queuing
over the rail line. To avoid a vehicle stopped over either rail line, it is recommended that laybys are
provided between the rail line as shown in Figure 6.15.
60m
60m
420m
200m
40m
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
41
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Figure 6.15: Recommended Road Works
The laybys should be 35 to 40m long and 4m wide beyond the clearance zone of each crossing. This
should be sufficient to allow a 19m long semi-trailer to fully cross the rail line and merge back in into
downstream traffic at a low speed. The laybys should also be located a minimum 30m from the
Intersection and clear of the rail line to allow sufficient manoeuvring for multiple heavy vehicles.
As shown in Table 6.4 and Figure 6.15, turn lanes on the Bruce Highway should provide capacity for
a combined 240m. Providing storage on the AUL of 40m is sufficient to store two semi-trailer or four
smaller vehicles. Given the existing and future traffic distributions, this additional storage is
considered suitable. It is recommended that additional storage beyond between the Bruce Highway
and the North Coast rail line is provided by widening the roadway at this location. The widening
should be hatched to encourage it not to be used as a regular lane.
Providing storage on the CHR of 200m is expected to cater for up to 20 vehicles. This is consistent
with the 20 vehicle queue (200m) expected on this lane in the 2029 AM Base and Operation
scenario. With a peak of 16 vehicles (160m) expected based on the Sidra model, an existing 60m
provision between the rail lines, and existing storage of 20m between the North Coast rail line and
the Bruce Highway, lengthening storage lanes on the Bruce Highway will result in a total 320m of
storage to cater for the total of 300m storage required.
As this storage would be provided for queued (stationary) vehicles and the posted speed limit along
this section is 100kph, it is recommended that 1m painted medians are provided to separate through
and queued/turning traffic. The median would be provided for the full length of storage provided.
Increase AUL Length and
provide painted median
Increase CHR Length
and provide painted
medians either side
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
42
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
6.10 Updated Traffic Capacity Assessment
TTM note that an updated traffic capacity assessment will be undertaken as part of the RMP, which
will review in detail the traffic generated by the construction activities.
TTM have undertaken a Sidra analysis of the Bruce Highway/Abbot Point Road intersection to
determine how the intersection will perform considering existing and future train movements.
6.11 Adjacent Bruce Highway Intersections
As noted, it is anticipated that the construction and operational traffic volumes will generally have a
negligible traffic impact along the Bruce Highway corridor, due to the level of traffic on the Bruce
Highway during the development peak traffic periods. TTM do not envisage any further traffic
impacts at any further intersections along the Bruce Highway corridor.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
43
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
7 Road Pavement Impact Assessment This chapter will review the road pavement traffic impacts associated with the construction and
operational activities, with the Bruce Highway subject to additional heavy vehicle traffic due to site
operations.
7.1 Existing ESA Pavement Loadings
It is assumed that the average ESA on the Bruce Highway equates to 2.8 for heavy vehicle
classification. Traffic data gained from DTMR has established that the average percentage of heavy
vehicles on the Bruce Highway in the vicinity of Abbot Point Road are 17% (north) and 18% (south).
This equates to 517 heavy vehicles north of Abbot Point Road and 557 heavy vehicles south of Abbot
Point Road (Table 5.1).
7.2 Development Heavy Vehicle Generation & Impacts
The total heavy vehicle traffic from the site has been estimated in Chapter 4 of this report. This
identified that the site will generate 6 (12 total) larger type service vehicles and 17 (34 total) bus
trips per day during the construction stage. This will change to 21 (42 total) smaller type service
vehicles with no bus movements during the operational stage.
Heavy vehicle distribution by classification is expected to be geared towards the higher loads and
larger vehicles during the construction activity, with an average ESA of 3.0 per heavy vehicle. The
type of load and truck is anticipated to be smaller during the operational stage, with typical bus,
servicing and maintenance deliveries to the site having an average ESA of 2.2 per heavy vehicle.
Table 7.1 and Table 7.2 show the level of predicted generated heavy vehicle volumes and their
resultant ESA’s, with Table 7.3 and Table 7.4 showing the respective impacts.
Table 7.1: Construction Stage: Peak Daily ESA Generation (2018)
Road Trucks ESA Truck Truck
ESAs
Buses Average
ESA bus
Bus ESAs Daily ESAs
Bruce Highway 12 3.0 36 34 2.2 75 111
Table 7.2: Operational Stage: Peak Daily ESA Generation (2019)
Road Trucks ESA Truck Truck
ESAs
Buses Average
ESA bus
Bus ESAs Daily ESAs
Bruce Highway 42 2.2 92.4 - - - 93
Table 7.3: Bruce Highway Impact on Road Network: Construction Stage
Section 2018 AADT Existing Truck ESA Development ESA
% CV ESA ESA Impact
North of AB Road 3,423 17% 1,629 12 <1.0%
South of AB Road 3,486 18% 1,757 99 5.6%
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
44
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 7.4: Bruce Highway Impact on Road Network: Operation Stage
Section AADT Existing Truck ESA Development ESA
% CV ESA ESA Impact
North of AB Road 2019: 3,525 17% 1,678 31 1.8%
South of AB Road 2019: 3,590 18% 1,809 62 3.4%
North of AB Road 2029: 4,738 17% 2,255 31 1.4%
South of AB Road 2029: 4,825 18% 2,432 62 2.7%
7.3 Mitigation Review
By definition, operational pavement impacts due to the project are deemed to be insignificant as the
additional levels will be less than 5% of existing daily traffic levels on the majority of the SCR
network. The construction pavement impacts are anticipated to peak with a 5.6% impact. This
impact is only expected for the section of the Bruce Highway between Abbot Point Road and
Merinda, which is approximately a 12km long section.
It is noted that the construction period is expected to be 2 years. During the operations period,
servicing T0 is not anticipated to result in pavement impacts. In the context of an anticipated design
life of 20 years, a pavement impact of 5.6% over a two year period is predicted to have a minimal to
negligible impact on the pavement life of this section of the Bruce Highway.
TTM note that an updated pavement impact assessment will be undertaken as part of the RMP,
which will review in detail the traffic generated by construction activities.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
45
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
8 Draft Road-use Management Plan (RMP)
8.1 Introduction
It is intended that a RMP will be prepared at least 6 months prior to the commencement of
construction activities. The RMP will be a transforming document which evolves over time based on
project requirements and the road environment.
The purpose of a RMP is to identify appropriate protection objectives and associated
implementation strategies together with monitoring, auditing, reporting and corrective actions to be
adopted if an undesirable impact or unforeseen level of impact occurs.
It is noted that the RMP will be reviewed and periodically updated, if necessary, to reflect knowledge
gained during the detailed design process, construction and the course of operations. The following
provides an outline RMP, highlighting potential key policies and objectives:
8.2 Draft RMP Policy Statement
It is intended that the key RMP policy will be based on ‘minimising any impacts on the State
Controlled Road (SCR) and associated traffic generated by the Project, including the transportation
and handling of materials’.
8.3 Draft RMP Objectives
The following provides a summary on the key RMP objectives:
• To minimise the impact on the efficiency of the State Controlled Road Network;
• To ensure for safe operation of vehicles on and off the site; and
• To minimise any potential traffic-related complaints and incidents.
In order to meet these objectives the RMP will include the following:
• A summary of updated project traffic information and impact assessments;
• Review of mitigation strategies including time frames for approvals, permits and
implementation;
• Identification of roles and responsibilities of the working group, and the monitoring process
involved; and
• Development, Consultation and Implementation of Strategies and Policies.
8.4 Draft RMP Implementation Strategy
The RMP Strategies/Policies will be developed and implemented in consultation with key
stakeholders as to mitigate any road safety risks associated with the development traffic generation.
This will be for safer road conditions and driver behaviour on all roads accessing the Project.
It is anticipated that a working party will be established to review and sign off on the RMP which will
enable the proponent and its contractors to formally adopt and implement the RMP in relation to
any site vehicular transport requirements. The working party would likely consist of members from
DTMR Fitzroy Region, Council, local emergency services (Police, Fire and Ambulance authorities),
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
46
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
HVROPO including a representative from the local school bus committee. The RMP will be made
available to the public with key contact details provided. It is envisaged that this RMP will be
updated annually included a review by all members of the working party.
The RMP will include an updated traffic and pavement impact assessment based on the latest
information available. It is anticipated that these assessments will form the basis of financial
agreements between the proponent, DTMR regarding road upgrade, maintenance and rehabilitation
contributions.
The RMP once complete will provide more detailed information on each strategy/policy and may
incorporate additional strategies, however the following provides an outline of several key strategies
to be implemented and developed further:
8.4.1 Driver Fatigue Policies
The proposed development will result in an additional DIDO trips on the road network, where
fatigue is a significant factor. As such, it is recommended that the local Road Accident Action Group
(RAAG) is consulted with respect to local policy on fatigue. The construction industry as a whole
should participate in this forum to address the issue of fatigue and determine strategies for dealing
with fatigue for DIDO trips.
• Typical Strategies to minimise the impacts of driver fatigue include the following:
• Allowing DIDO staff to work shorter shifts at the start and end of their working period;
• Providing DIDO staff with an additional day or night of accommodation prior to commencing
work or driving home; and
• Sponsorship of rest zones and driver reviver stations.
8.4.2 Driver Behaviour Policies
This policy relates to DIDO workers, staff who drive private vehicles to site and contractors. This
policy will include requirements for these employees and contractors to drive in a safe manner when
in charge of a vehicle, with additional attention to any instance of public transport use (school bus
times), OD, heavy vehicle use and pedestrian and cyclist activity. This policy will also inform workers
of other strategies including their implementation, monitoring and reporting as to discourage use of
local roads that do not form part of the access route to the construction site.
8.4.3 Work Related Travel and Transport Policies
This policy relates to the use of communal transport, work access, and alternative travel modes
related to construction and operation of the project. This policy will include use targets and
strategies to increase communal transport use by staff and contractors, reduce the impact on the
local community and to deal with the movement of goods to and from site in a safe and responsible
manner.
8.4.4 Over-dimension Vehicle Management
As part of the construction and operation stages of the development it may necessary that some
indivisible components will be delivered by over-dimensional vehicles. Where vehicles larger than a
19m long AV are required to access the site, special permissions will be required. Suppliers and
transport provides will be required to liaise with the appropriate authorities for each instance.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
47
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
The proponent will liaise with the Heavy Vehicle Road Operations Program Office (HVROPO) in
Rockhampton regarding over dimensional use as early as possible. It is noted that a 6 month lead
time to organise permits and personnel is required by this office. The community will also be advised
of any over dimensional vehicle activity related to the construction and operation of the Project.
These strategies may include radio announcements and information via the internet, however the
RMP will identify all over dimensional and heavy vehicle movements as early as possible.
8.4.5 Road Safety Audit Review, Capacity & ALCAM Assessment
An independent Road Safety Audit (RSA) will be undertaken by an accredited auditor in relation to
the operation of the Abbot Point intersection. This audit will be undertaken prior to any construction
activity and will establish the existing road safety conditions and potential impacts associated with
the construction traffic.
The RSA will also review any school bus activity, however, due to the relatively secluded location of
the development and limited bus activity along the Bruce Highway, the level of development traffic
is considered to have a minor impact on any school or public transport operations along this
highway.
A further intersection analysis will be undertaken once the site construction vehicle activity and
programme has been updated/refined to determine the level of any development traffic impacts.
An ALCAM assessment will be undertaken once the site construction vehicle activity and programme
has been updated/refined. This ALCAM assessment will identify any potential mitigation measures
associated with the level crossing, which will be further discussed with both Aurizon, DTMR officials
including key stakeholders (Port Authority).
8.4.6 Road Noise Management
There are residential and sensitive noise receiving developments located immediately adjacent to
the Bruce Highway at the Ayr, Bowen and Proserpine townships. Typically, these residents are set-
back suitably to allow for rural highway traffic volumes and are set back from the highway.
Operationally, it will be communicated to truck drivers that they are expected to conduct
themselves with appropriate care towards local residents. This will include limiting the use of air
brakes in townships and near residences, restricting the movements of heavy vehicles to within
standard business hours when possible, and driving in a safe and responsible manner.
8.4.7 Dust Control Management
Internally, it is expected that all heavy vehicles leaving the site will be subject to a wash-down of
tyres to limit loose material being transported onto SCR network.
8.4.8 On-site Parking Management
It is recommended that parking on site be provided as follows:
• 1 space for every employee expected to drive to site during peak accumulation;
• On-site bus set-down facilities; and
• On-site standing and parking for service vehicles separate from private vehicle areas.
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
48
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
8.4.9 Dangerous Goods Management
All transportation of dangerous goods by road will be carried out in accordance with the licensing
and vehicles requirements set out by DTMR. This includes operational policies for the port
operators, its suppliers and sub-contractors that all drivers transporting dangerous goods are
adequately trained, hold valid licenses and that all vehicles are adequate for transportation of these
materials.
Typical dangerous goods expected to be transported to / from the site include:
• Fuel and oil;
• Flammable gas;
• Corrosive materials including solvents; and
• Chemical waste (including sewerage).
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
49
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
9 Rail Information It is understood that the appropriate rail authorities will undertake an ALCAM assessment of each
rail crossing on Abbot Point Road. This section is intended to provide sufficient information for rail
authorities to undertake this assessment.
The rail lines impacted are the North Coast rail line and the Collinsville Newlands rail line. Base traffic
is provided in Section 6.5. Development traffic is expected to be distributed as identified in Section
4. Project time frames are discussed in Section 2.2. Traffic volumes over the rail lines are not
expected to increase without development. As such traffic volumes along Abbot Point Road are not
expected to change in the base scenarios.
Table 9.1 and Table 9.2 identify base traffic volumes, CCMP and NGBR traffic volumes and traffic
volumes generated by the construction and operation of T0 respectively. The largest vehicle
anticipated to access the site is a 19m long AV. Any suppliers or transport providers requiring access
to the site with over-dimensional vehicles will require special permissions.
Table 9.1: Base and Development Volumes on Abbot Point Road - Phase 1 Construction
Scenario AM Peak (vph) PM Peak (vph) Estimated Daily (vpd)
LV HV Total LV HV Total LV HV Total
Base Eastbound 56 4 60 11 - 11 169 18 187
Base Westbound 10 1 11 40 - 40 169 11 180
Base Combined 66 5 71 51 - 51 338 29 367
2018 Eastbound Construction
(CCMP & NGBR) 3 4 7 3 4 7 18 17 35
2018 Westbound
Construction (CCMP & NGBR) 3 4 7 3 4 7 18 17 35
2018 Combined Construction
(CCMP & NGBR) 6 8 14 6 8 14 36 34 70
2018 Eastbound Construction
(T0) 79 14 93 33 7 40 112 23 135
2018 Westbound
Construction (T0) 33 7 40 79 14 93 112 23 135
2018 Combined Construction
(T0) 112 21 133 112 21 133 224 46 270
2018 Eastbound (Total) 138 22 160 47 11 58 299 58 357
2018 Westbound (Total) 46 12 58 122 18 140 299 51 350
2018 Combined (Total) 184 34 218 169 29 198 598 109 707
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
50
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
Table 9.1: Base and Development Volumes on Abbot Point Road - Phase 1 & 2 Operation
Scenario AM Peak (vph) PM Peak (vph) Estimated Daily (vpd)
LV HV Total LV HV Total LV HV Total
Base Eastbound 56 4 60 11 - 11 169 18 187
Base Westbound 10 1 11 40 - 40 169 11 180
Base Combined 66 5 71 51 - 51 338 29 367
2019+ Eastbound Operation
(CCMP & NGBR) 36 - 36 36 - 36 180 - 180
2019+ Westbound Operation
(CCMP & NGBR) 36 - 36 36 - 36 180 - 180
2019+ Combined Operation
(CCMP & NGBR) 72 - 72 72 - 72 360 - 360
2019+ Eastbound Operation
(T0) 60 6 66 60 6 66 130 21 151
2019+ Westbound Operation
(T0) 60 6 66 60 6 66 130 21 151
2019+ Combined Operation
(T0) 120 12 132 120 12 132 260 42 302
2019+ Eastbound Operation
(Total) 152 10 162 107 6 113 479 39 518
2019+ Westbound Operation
(Total) 106 7 113 136 6 142 479 32 511
2019+ Combined Operation
(Total) 258 17 275 243 12 255 958 71 1,029
© 2015 - TTM Consulting Pty Ltd Reference: 15BRT0361/02
51
Traffic and Transport Assessment
Abbot Point Terminal 0 Project
10 Conclusions and Recommendations From a traffic engineering perspective, the peak traffic impacts associated with the Project are
expected to be between 2017 and 2018 during the main on-site construction activity. On
completion, it is anticipated that T0 will employ approximately 250 workers to serve typical port
operations.
This traffic impact assessment has considered both the construction and operational stages of the
Project.
The level of likely worker activity has been assessed which has established that their traffic impacts
will be negligible due to the roster and shift patterns, with construction workers being generally
transported by bus.
A likely inventory of the heavy vehicles required during construction has been developed as
provided which is expected to generate up to 12 total loaded and unloaded heavy vehicle trips per
day. During the peak operational stage the site is expected to generate a further 42 total loaded and
unloaded heavy vehicle trips per day per day.
The key impact of development traffic relates to the interaction with adjacent rail lines. TTM have
indicated storage provisions on the Bruce Highway turn lanes to account for potential queuing back
from these rail lines.
The level of traffic generated by both the construction (Phase 1) and full operational stage (70 Mtpa
throughput in Phase 1 and 2) is therefore not expected to have a significant traffic impact on the
local or wider strategic road network.
Mitigation measures are required due to the proximity of rail lines to the Bruce Highway along Abbot
Point Road. These measures include providing laybys between the rail lines to prevent vehicles
becoming stranded, and lengthening turn lanes on the Bruce Highway to provide additional vehicle
storage.
It is intended for a RMP to be prepared as to identify any appropriate protection objectives and
associated implementation strategies, together with any monitoring, auditing, reporting and
corrective actions to be adopted. This RMP will ensure that any undesirable impact or unforeseen
level of impact is assessed/addressed on both the road and rail networks.